This statement of work outlines insulation services required for the chilled water piping system aboard the Coast Guard Cutter Sequoia. The contractor will insulate piping sizes ranging from 1/4 to 5 inches using Armaflex AP rubber or equivalent insulation with a 1 inch thickness. The insulation will be covered with brattice cloth and Sealfas jacket. In addition to insulating straight pipe runs, the contractor must insulate valves, fittings and flanges. The contractor must provide all materials, labor and equipment to complete the work, and check in daily with Coast Guard representatives. The period of performance is from December 3rd through 17th, 2024 at the Coast Guard Yard in Baltimore, Maryland. Bidders must visit the ship site on December 13th, 2023 and have experience installing this type of piping insulation.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 70Z04023Q60118Y00 RFQ.docx | DOCX document | |
| 225B-WLB-514-010.pdf | ||
| 225B-WLB-514-009.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
For
Chill Water Pipe Covering/Insulation Services
PR #2123403Y61A2699010
225’ CGC Hickory Yard POC: James Johnston, (410) 636-3095 Period of Performance: 3rd through 17h, 2024 Final period of performance will be determined by Yard POC.
Location: Coast Guard Yard, 2401 Hawkins Point Rd, Baltimore, MD
The Coast Guard requires contractor services for marine pipe cover / insulator services to occur at the Coast Guard Yard in Baltimore MD. The services required shall be performed on-board 225’ CGC Sequoia. The contractor services shall insulate the chilled water piping system using the Coast Guard drawing as references.
Insulation services will be required in various locations on-board the ship. Piping to be insulated will vary in size from ¼” to 5”. Type of insulation to be installed shall be Armaflex AP, rubber or equal to. Type of jacket to be installed is brattice cloth and sealfas over the Armaflex insulation. Required thickness of the insulation is ¾” (MIL-P-15280). The contractor will be required to insulate various irregular shaped items such as valves, fittings, and flanges. In addition, the contractor shall provide all materials, personal and equipment needed to perform all work as required.
Piping installation may not be 100% IAW the drawing, so a site survey will be required to ensure all pipe sizes and materials required. Contractor shall check in with the Ship’s superintendant, pipe shop foreman, or leader at the beginning of each workday. The Coast Guard Yard will provide chill water system drawings for insulating guidance. Contractor must have experience in installing Armaflex pipe insulation and brattice cloth with Sealfas. Workers must be trained and have experience in properly installing pipe insulation. Personal protective equipment must be worn at all times in accordance with OSHA standards.
A ship check on December 13th, 2023 at 2401 Hawkins Point Rd, Baltimore, MD 21226 is required for the bidding process. Site visit may be waved for vendors who previously installed this chill water insulation on board a 225.
Access to the Yard during the rental period is coordinated through the Yard POC. All personnel shall receive visitor’s passes and clearance from USCG Coast Guard Yard Security located at the Main Gate. List of personnel requiring access shall be provided to the Yard POC twenty-four (24) hours prior to requiring access. Personnel will be required to provide full name, picture I.D. (valid driver’s license preferred), and date of birth. For non-US citizen’s, a passport will be required. The following forms of IDS are authorized: CAC, Foreign Passport containing appropriate visas, TWIC, Green Cards, US Passport, or state Real ID.
No oral statement of any person other than the contracting officer shall in any manner or degree, modifies or otherwise affect the terms of this contract.