This is a Statement of Work (SOW) for the procurement of a Pulsed Field Ablation (PFA) system for non-clinical research use by the U.S. Food and Drug Administration (FDA). The FDA seeks one complete, off-the-shelf PFA system that is FDA-approved or cleared for clinical use in the United States for treating atrial fibrillation or other cardiac arrhythmias. The system must include a PFA generator, five compatible clinical PFA catheters, all required accessories, cables, connectors, software, licenses, product documentation, training, warranty coverage, and technical support. The PFA generator must produce a bipolar, biphasic pulsed electric field waveform suitable for cardiac ablation research, be compatible with standard 115-120 volt, 60 hertz single-phase building power, and either be cart-mounted or tabletop in form factor. The contractor must deliver to 10903 New Hampshire Avenue, Silver Spring, Maryland 20993 within 60 days after receipt of order on an FOB Destination basis, with all packing, shipping, transportation, insurance, and delivery costs included.

The contractor is responsible for on-site installation, including unpacking, assembly, connection, configuration, and manufacturer-standard startup and operational verification before acceptance. The contractor must provide a minimum of one instructor-led training session (in person or virtually) within fifteen business days after government acceptance for three to four end-users, covering system components, setup, startup and shutdown, catheter connection, standard operation, safety precautions, routine troubleshooting, cleaning, storage, and technical support procedures. The manufacturer's standard commercial warranty must cover all durable components for a minimum of twelve months from the date of government acceptance, including troubleshooting and repair or replacement of defective components. Technical support by telephone and email must be provided during the warranty period, with response times, escalation procedures, and on-site support availability identified in the quotation. The contractor must provide complete electronic documentation at delivery including Instructions for Use, operator manuals, setup instructions, safety information, packing lists, component inventories, FDA authorization documentation, warranty documentation, technical-support contact information, software and licensing documentation, and preventive maintenance instructions. Expired catheters may be accepted solely for non-clinical research use if they are unused, unopened, in intact original packaging, and free from recall. The contractor must identify any external equipment, third-party hardware, software, subscriptions, licenses, disposables, or facility requirements necessary for operation but not included in the quoted price, as well as provide peer-reviewed literature, clinical data, or manufacturer test data addressing hemolysis associated with the proposed system. Government points of contact include Contracting Officer Iris Johnson at (301) 796-3353 and Iris.Johnson1@FDA.hhs.gov, with the Contracting Officer's Representative to be identified at time of award.

View the file

Other files

File Type Posted
SSN_CDRH-2026-134633.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOW Pulsed Field Ablation (PFA)

ALP CDRH-2026-134633 1

Pulsed Field Ablation System - Statement of Work

STATEMENT OF WORK (SOW)

Procurement of a Pulsed Field Ablation (PFA) System for Non-Clinical Research Use

1. Background The U.S. Food and Drug Administration (FDA) requires a clinical Pulsed Field Ablation (PFA) system for use in a non-clinical research environment. The system will support FDA research activities related to cardiac ablation technologies. The PFA system must be FDA-approved or cleared for clinical use in the United States and capable of operating in a research laboratory setting.

2. Objective The objective of this acquisition is to obtain a complete, off-the-shelf PFA system that enables FDA researchers to conduct non-clinical research involving cardiac ablation technologies. The system shall include the generator, compatible catheters, required accessories and cables, documentation, training, warranty coverage, and technical support necessary for safe and effective operation.

3. Scope The Contractor shall furnish and deliver one (1) complete PFA system, including a PFA generator, five (5) compatible clinical PFA catheters, and all accessories, cables, connectors, software, licenses, and other components required for the system to operate in the Government's non-clinical research environment. The Contractor shall also provide product documentation, training, warranty coverage, and technical support as specified in this SOW.

The Contractor shall identify in its quotation any external equipment, third-party hardware, software, subscriptions, licenses, disposables, or facility requirements that are necessary for full operation but are not included in the quoted price.

4. Minimum Technical Requirements

4.1 Regulatory Compliance

4.1.1 The proposed PFA system shall be FDA-approved or cleared for clinical use in the

United States for the treatment of atrial fibrillation or other cardiac arrhythmias.

4.1.2 The Contractor shall provide, with its quotation, documentary evidence of the applicable FDA authorization, including the PMA approval number, 510(k) clearance number, De Novo classification number, or other applicable FDA authorization number.

4.1.3 The Contractor shall provide the current product labeling and Instructions for Use associated with the proposed system.

4.2 Equipment Condition and Commercial Availability

4.2.1 The PFA generator and all durable system components shall be new, unused, current production equipment unless otherwise authorized in writing by the Contracting Officer.

ALP CDRH-2026-134633 2

4.2.2 The system shall be an off-the-shelf commercial product that is readily available for delivery within the required delivery period stated in the contract.

4.2.3 The Contractor shall identify the manufacturer, system name, model number, and configuration of the proposed equipment in its quotation.

4.3 PFA Generator

4.3.1 The PFA generator shall produce a bipolar, biphasic pulsed electric field waveform suitable for cardiac ablation research.

4.3.2 The Contractor shall state in its quotation whether the user can alter pulse parameters from the standard manufacturer waveform. The response shall identify each user-adjustable parameter and the available adjustment range, when applicable.

4.3.3 The PFA generator shall be compatible with standard building main power of 115- 120 volts, 60 hertz, single phase.

4.3.4 The PFA generator may be cart-mounted or tabletop in form factor.

4.3.5 The Contractor shall identify any required environmental, electrical, ventilation, network, or space requirements in its quotation.

4.4 Catheters

4.4.1 The Contractor shall provide five (5) unused clinical PFA catheters that are compatible with the proposed PFA generator.

4.4.2 Expired catheters may be accepted solely for non-clinical research use, provided each catheter is unused, unopened, in intact original packaging, free from recall, and clearly identified as not intended for clinical use.

4.4.3 The Contractor shall confirm in its quotation that compatible catheters are commercially available for separate purchase after award and shall identify the applicable catheter model number(s).

4.5 Accessories, Cables, Software, and Components

4.5.1 The Contractor shall provide all accessories and cables necessary to operate the

PFA system in a non-clinical research environment, including power cables, interface cables, connectors, adapters, and other required components.

4.5.2 The Contractor shall provide a complete component list with its quotation and again at delivery. The list shall identify each included item by manufacturer, model or part number, quantity, and purpose.

4.5.3 The Contractor shall identify any clinical deployment sheaths or other procedure-specific accessories that are not required for operation in the Government's non-clinical research environment.

4.5.4 Any software or license required for full system operation shall be included in the quoted price. The Contractor shall identify whether each license is perpetual, term-based, subscription-based, or otherwise restricted.

4.6 Non-Clinical Research Compatibility

4.6.1 The proposed system shall be suitable for use in a non-clinical research environment.

ALP CDRH-2026-134633 3

4.6.2 The Contractor shall describe in its quotation any configuration changes, software settings, accessories, interfaces, or other modifications necessary to enable non-clinical research use. Any required modification shall be included in the quoted price unless specifically identified as Government-furnished.

4.7 Clinical Safety Profile

4.7.1 The proposed PFA system shall demonstrate a non-hemolytic or low-hemolytic clinical safety profile.

4.7.2 The Contractor shall provide, with its quotation, peer-reviewed literature, clinical data, or manufacturer test data that addresses hemolysis associated with the proposed PFA system, catheter, and waveform configuration.

5. Documentation Requirements The Contractor shall provide the following documentation in electronic format at the time of delivery, unless an earlier submission is specified:

• Current Instructions for Use (IFU), operator manuals, setup instructions, and safety information.

• A complete packing list and component inventory identifying all delivered items.

• Applicable FDA approval or clearance documentation.

• Manufacturer warranty documentation and technical-support contact information.

• Software and licensing documentation, when applicable.

• Recommended preventive maintenance, cleaning, storage, calibration, and troubleshooting instructions.

• Any documentation required to safely operate the system in a non-clinical research environment.

6. Delivery, Installation, and Scheduling

6.1 Delivery Location: 10903 New Hampshire Avenue, Silver Spring, MD 20993.

6.2 Required Delivery: 60 days after receipt of order.

6.3 Delivery shall be FOB Destination unless otherwise stated in the resulting contract.

The Contractor shall be responsible for all packing, shipping, transportation, insurance, and delivery costs.

6.4 The Contractor shall coordinate the delivery date and time with the Government Technical Point of Contact at least five (5) business days before delivery. The Contractor shall not deliver equipment without receiving scheduling confirmation from the Government.

6.5 The Contractor shall provide on-site installation of the PFA system. Installation shall include unpacking, assembly, connection, configuration, and manufacturer-standard startup and operational verification. The Contractor shall ensure the system is fully installed, operational, and ready for Government use before acceptance.

6.6 The Contractor shall remove all packing materials and debris generated by delivery and installation unless the Government requests that specific packaging be retained.

ALP CDRH-2026-134633 4

7. Inspection and Acceptance

7.1 Inspection and acceptance will be performed by the Government at the delivery location identified in the contract.

7.2 The Government will inspect the delivered items to verify that:

• The manufacturer, model, configuration, quantities, and condition conform to the contract.

• The generator, catheters, accessories, cables, connectors, software, and documentation have been delivered.

• The system powers on and completes the manufacturer-standard startup or self-test, when applicable.

• The delivered catheters are compatible with the proposed generator and meet the packaging and condition requirements of this SOW.

• Required installation and configuration have been completed when applicable.

• No visible shipping damage, missing components, or material defects are present.

7.3 Government acceptance will occur after the Government verifies that the system and all required deliverables conform to the contract. Acceptance does not waive latent defects, warranty rights, or other contractual remedies.

7.4 Acceptance Testing. Following installation, the Contractor shall perform manufacturer-standard startup and operational verification of the PFA system. The Contractor shall demonstrate that the system powers on, successfully completes applicable self-diagnostic checks, connects with the required accessories and components, and operates in accordance with the manufacturer’s specifications.

Government acceptance shall occur after verification that all required components have been delivered, the system has been properly installed and is operational, required documentation has been provided, and any identified deficiencies have been corrected.

Acceptance testing shall not require use on human or animal subjects, performance of a research-specific ablation procedure, or consumption of single-use catheters unless expressly required by the resulting contract.

8. Training

8.1 The Contractor shall provide a minimum of one (1) instructor-led training session, conducted either in person or virtually, to educate FDA users on system setup and operation.

8.2 Training shall cover, at a minimum, system components, setup, startup and shutdown, catheter connection, standard operation, safety precautions, routine troubleshooting, cleaning, storage, and available technical-support procedures.

8.3 The Contractor shall provide electronic training materials to the Government.

8.4 Training shall be completed within fifteen (15) business days after Government acceptance unless the parties agree to another date in writing for 3-4 end-users

9. Warranty and Technical Support

9.1 The Contractor shall provide the manufacturer's standard commercial warranty for the PFA generator and all durable components. The warranty period shall be no less than twelve (12) months beginning on the date of Government acceptance.

ALP CDRH-2026-134633 5

9.2 Warranty coverage shall include troubleshooting and repair or replacement of defective components in accordance with the manufacturer's standard warranty terms. The Contractor shall provide the warranty terms with its quotation.

9.3 The Contractor shall provide technical support by telephone and email during the warranty period. The Contractor shall identify support hours, contact methods, response times, escalation procedures, and the availability of on-site support in its quotation.

9.4 The Contractor shall describe the availability and terms of technical support, maintenance, repairs, software updates, and replacement parts after expiration of the warranty. Post-warranty support is not included unless separately ordered by the Government.

10. Contractor Responsibilities

• Provide all personnel, equipment, materials, transportation, tools, and supervision necessary to satisfy this SOW.

• Coordinate delivery, installation, training, and support activities with the authorized

Government POC.

• Ensure personnel performing on-site work comply with applicable FDA facility access, safety, and security requirements.

• Promptly notify the Contracting Officer and Government Technical POC of any actual or anticipated delay, missing component, discontinued item, recall, safety notice, or other issue that may affect performance.

• Do not substitute equipment, catheters, components, or configurations without prior written authorization from the Contracting Officer.

11. Government Responsibilities

• Provide access to the designated delivery and installation location during approved hours.

• Provide standard building electrical power meeting the requirement stated in this SOW.

• Coordinate facility access and identify applicable receiving, safety, and security procedures.

• Inspect delivered items and provide acceptance or identify nonconforming items within a reasonable period.

• Make appropriate personnel available for scheduled training.

12. Government Points of Contact The Government will identify the following points of contact in the resulting solicitation or contract:

Role Name Email Telephone

Contracting Officer Iris Johnson Iris.Johnson1@FDA.hhs.gov (301) 796-3353

Contracting Officer's Representative

(COR)

Will be given at the time of award.

ALP CDRH-2026-134633 6

12.1 The Contracting Officer is the only individual authorized to modify the contract, change the scope or price, authorize substitutions, waive requirements, or otherwise bind the Government.

12.2 The Contracting Officer's Representative or Technical POC may provide technical direction and coordinate performance within the existing scope but may not change contractual terms, authorize additional work, or obligate Government funds.

12.3 The Contractor shall immediately notify the Contracting Officer if it believes any Government communication constitutes a change to the contract or requires work outside the existing scope.

13. Government Operating Hours and Closures

13.1 Normal Facility Hours.

13.2 Unless specifically authorized in writing, the Contractor shall not schedule delivery, installation, training, or other on-site activity on Saturdays, Sundays, Federal holidays, or days when the FDA facility is closed.

13.3 Government closure days may include Federal holidays, weather-related closures, emergency closures, building closures, or other administrative closures announced by the Government.

13.4 When a closure prevents a previously scheduled delivery, installation, training, or service activity, the Contractor shall coordinate with the Government POC to reschedule the activity at no additional cost to the Government.

13.5 A Government closure does not, by itself, authorize an increase in contract price or an extension of the delivery schedule. Any adjustment to the contract must be approved in writing by the Contracting Officer.

13.6 The Contractor shall verify facility status with the Government POC before dispatching personnel or equipment when severe weather, emergency conditions, or other potential closures may affect access.

14. Changes, Deviations, and Substitutions The Contractor shall not deviate from the requirements of this SOW or provide substitute equipment, catheters, components, software, or services without prior written approval from the Contracting Officer. Proposed deviations or substitutions shall be submitted in writing and shall describe the reason for the request, the effect on performance, compatibility, regulatory status, delivery, warranty, and price.

15. Final Requirement This SOW establishes the Government's minimum requirements for the procurement of a PFA system for FDA non-clinical research use. The Contractor shall provide a complete and fully functional system that conforms to all requirements of the resulting contract.

1. Background
2. Objective
3. Scope
4. Minimum Technical Requirements
4.1 Regulatory Compliance
4.2 Equipment Condition and Commercial Availability
4.3 PFA Generator
4.4 Catheters
4.5 Accessories, Cables, Software, and Components
4.6 Non-Clinical Research Compatibility
4.7 Clinical Safety Profile
5. Documentation Requirements
6. Delivery, Installation, and Scheduling
7. Inspection and Acceptance
8. Training
9. Warranty and Technical Support
10. Contractor Responsibilities
11. Government Responsibilities
12. Government Points of Contact
13. Government Operating Hours and Closures
14. Changes, Deviations, and Substitutions
15. Final Requirement