USCGC POLAR STAR CASING REPAIR REQUEST
Solicitation number
70Z08525Q0030311
Issued by

About this file

This is a Statement of Work (SOW) for boiler inspection and repair services for the USCGC POLAR STAR, a United States Coast Guard vessel. The solicitation is a small business set-aside (NAICS Code 336611) for a firm-fixed-price contract requiring a contractor to locate and repair a crack in the #2 boiler fire side casing. The work will be performed at USCG Base Seattle from September 29 to October 17, 2025, with the contractor required to provide a qualified technical representative (City of Seattle Grade Two Steam engineer or equivalent credential) to oversee equipment removal, inspection, and repair.

Key requirements include locating the boiler crack using smoke testing or non-destructive evaluation techniques, repairing the crack through welding (up to 2 square feet of casing material), and renewing insulation and sheathing. The contractor must submit documentation including technical representative qualifications, gas-free certificates, and a chain of custody record for waste disposal. The solicitation requires quotations to be submitted by 0800 Pacific Time on September 3, 2025, with Coast Guard personnel responsible for operational testing of the boiler before and after the repair work.

View the file

Other files

File Type Posted
This is a combined synopsis solicitation CGC POLAR STAR.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

General Requirements

1. SCOPE

1.1 Intent. This standard specification invokes general requirements for conducting vessel repairs performed by commercial contractors for Coast Guard vessels.

2. REFERENCES

COAST GUARD DRAWINGS

None

COAST GUARD PUBLICATIONS

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and Allied Processes Surface Forces Logistics Center Standard Specification 5550 (SFLC Std Spec 5550), 2022, Fire Prevention and Response

OTHER REFERENCES

None

3. REQUIREMENTS

3.1 General. The Contractor must conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability. The requirement of this WI applies to all work under the scope of this contract, whether explicitly stated in all following work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.

3.2 Welding and brazing requirements. The Contractor must perform all welding and allied processes, and NDE in accordance with SFLC Std Spec 0740.

3.3 Fire Prevention Specification. The Contractor must submit a Fire Prevention Plan in accordance with paragraph 3.1 of SFLC Standard Spec 5550

3.4 Materials. The Contractor must obtain all the materials required to complete this job except for the Government-furnished Property shown in Paragraph 1.2 of Work Item 1, if any specified.

3.5 Period of Performance. The period of performance for this requirement starts on 29 September 2025 and ends on 17 October 2025.

3.6 Location. The Contractor must perform this work while the USCGC POLAR STAR is alongside the pier at USCG Base Seattle - 1519 Alaskan Way S, Seattle, WA, 98134. The Contractor must provide full name, date of birth, and driver’s license number of contractors, subcontractors, and technical representatives to the designated USCG representative at least 48 hours prior to arriving on-site. The Contractor does not require access to designated restricted and/or controlled access spaces on the ship in execution of this work.

3.7 Release of References. For any listed references to be distributed, the contractor must be registered in the Joint Certification Program (JCP) through Defense Logistics Agency (DLA) and provide your JCP number and expiration date to the listed point of contact (POC) for this work.

3.8 Solicitation Period Site-Visit. The Contractor can perform a ship check during the solicitation period of this requirement. The Contractor must contact the designated points of contact (POC) at least 48 hours prior to requested access for USCG to process. The POC for a site visit is listed in Paragraph 3.11. Access prior to award cannot be guaranteed and depends on the availability of the POCs and the Contractor providing request documentation needed for access. USCG is not responsible for any costs associated with the Contractor’s site visit.

3.9 Documentation for Contractor’s Proposal. The Contractor must include at least the following in their proposal for this requirement: basic information (name, company name, contact details, the date, Unique Entity ID), company overview, past performance (if applicable), technical representative certifications and qualifications, and signature of the authorized person.

3.10 Points of Contact. The USCG Technical POCs for this requirement include but are not limited to the following:

3.10.1 SFLC-LREPL Asset Manager, LT Mikael Axelsson, Mikael.J.Axelsson@uscg.mil

3.10.2 USCGC POLAR STAR Engineer Officer, LT Joshua Herring, Joshua.C.Herring@uscg.mil

3.10.3 USCGC POLAR STAR Assistant Engineer Officer, LT Andrea Harris, Andrea.M.Harris@uscg.mil

#2 Boiler, Inspect and Repair

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to investigate and repair a leak in the #2 boiler fire side casing. See Figure 1 for nameplate information.

1.2 Government-furnished property.

None

2. REFERENCES

Coast Guard Drawings Coast Guard Drawing 400 WAGB 103-003, Rev AM, Booklet of General Plans (POLAR STAR) Coast Guard Drawing 400 WAGB 5101-007, Rev 1, SDW 350M Marine Auxiliary Boiler Bare Boiler Design Arrangement

Coast Guard Publications

Coast Guard Technical Publication (TP) 2035, SWBS 517, Section A, Rev -, Auxiliary Boiler Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and Allied Processes Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures

Other References None

3. REQUIREMENTS

3.1 General.

3.1.1 CIR.

None.

3.1.2 Tech Rep. The Contractor must provide the services of a City of Seattle Grade Two Steam engineer or a USCG-issued 2nd Assistant Engineer Steam Merchant Mariner Credential (Limited Horsepower or Unlimited Horsepower) or the Original Equipment Manufacturer or an equivalent credential to the Seattle Steam engineer/Steam Merchant Mariner Credential to accomplish the following tasks – on site:

· Oversee the removal and re-installation of equipment, insulation and casing

· Oversee the inspection and repair of the crack

3.1.2.2 Submit the name and résumé of the Tech Rep to the designated USCG representative in the solicitation proposal for this work.

3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).

3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences) including, but not limited to the following:

Insulation

· Sheathing

3.1.5. Residual Fluids. The Contractor must dispose of residual fluids in compliance with all applicable Federal, state, and local laws, ordinances, regulations and SFLC Standard Specification 0000. Notify the designated USCG Technical POC(s) (in writing) at least 5 days prior to removal of wastes and fluids. Document a complete chain of custody record of the removed contents and generated wastes, from the vessel to the point of final destination or delivery. Submit document to the designated USCG Technical POC(s) upon completion of work.

note Coast Guard personnel will operate all shipboard machinery and equipment note Operational testing of the boiler will take 4 hours

3.2. Operational Test, Initial. Prior to commencement of work, the Contractor must witness Coast Guard personnel perform an initial operational test of all items or shipboard devices to be disturbed, used, repaired, or altered, to demonstrate existing operational condition. Submit a CFR.

3.2.1 The boiler must be tested as part of the initial test in addition to other disturbed items.

3.3 Boiler Crack Location. There is a crack in the boiler casing (highlighted as #14 ga steel in Figure 2) somewhere near the forward casing for the water drum of Boiler #2. The Contractor must locate this crack. See Figures 2 and 3 for the scope of the interference removal.

3.3.1. Upon completion of crack repair, all the insulation and sheathing material must be renewed or re-installed. Welding must be done in accordance with SFLC Std Spec 0740

3.3.2. The Contractor must NOT weld or damage the pressure-containing components of the water drum in any way.

3.3.3. The Contractor may use smoke testing or any of the NDE techniques highlighted in SFLC Std Spec 0740 to locate this crack. Submit a CFR when the Contractor finds the crack describing its size and location or when the entire area has been searched and no crack was found.

3.3.3.1 If one method (smoke or NDE) does not locate the crack, then the other method must be used.

3.3.3.1.1. If VT is used as the form of NDE then another form of NDE must be attempted in addition to smoke until the crack is found.

3.3.4. The blower fan may be used to assist in crack location, but the boiler may NOT be fired without insulation.

3.3.5. The area between the red circles of Figure 3 represents the MINIMUM amount of sheathing removal to find this crack. The maximum amount of removal is shown in the green rectangle. The maximum area of sheathing and insulation removal is nine square feet.

3.3.6. The material of the outer sheathing is unknown. For bidding purposes, assume it could be either mild steel from 3/16th inches thick to 3/8th inches thick or 14 gauge Type 304 Stainless.

3.4 Crack Repair. The Contractor must repair the crack by welding it in accordance with SFLC Std Spec 0740. Conduct NDE in accordance with SFLC Standard Spec 0740 and submit a CFR.

3.4.1. For bidding purposes, assume that the crack will require the cropping and renewal of up to 2 square feet of casing material. The material is unknown, but for bidding purposes, assume it could be either mild steel from 3/16th inches thick to 3/8th inches thick or 14 gauge Type 304 Stainless.

3.4.2 The Contractor must clean the crack area sufficiently to conduct the weld repair.

3.4.3. The Contractor must provide gas free certificates, marine chemist certification documentation, and fire watch in accordance with Paragraph 3.3 of SFLC Std Spec 0000. The Contractor must produce the documentation required in Paragraph 3.3.1.2.3. upon request.

3.5. Operational Test, Final. Upon completion of work, the Contractor must witness Coast Guard personnel perform a final operational test of all items or shipboard devices to be disturbed, used, repaired, or altered, to demonstrate existing operational condition. Submit a CFR.

3.5.1 The boiler must be tested as part of the initial test in addition to other disturbed items.

3.6 Touch-up preservation, general. The Contractor must prepare and coat all new and disturbed exterior and interior surfaces, as applicable, to match existing adjacent surfaces in accordance with SFLC Std Spec 6310, paragraph 3.1.13 (Touch-ups and minor coating repairs). Use “Machinery, Steel, Operating Temperatures Over 200oF” in Appendix B.

4. NOTES

Figure 1. Nameplate for boilr

Figure 2. Cross Section of boiler showing the 14 ga stainless liner with a crack

Figure 3. minimum Outer casing and insulation removal circled in red with maximum in green rectangle image1.png image2.png image3.png