SOW Battery Installation Redacted.pdf

PDF 266 KB Posted

Attached to
Sodium Battery Installation for KAFB Building 498 - 2nd solicitation
Solicitation number
FA9401-25-Q-0022b
Issued by

About this file

This is a Statement of Work (SOW) for sodium battery installation at Building 498, Kirtland Air Force Base, New Mexico, prepared by the 377 MSG/SCXP. The contractor must remove and dispose of existing lead-acid batteries and install a new 12-module sodium nickel battery system with ethernet remote monitoring capabilities. The sodium batteries must meet specific requirements including 4,500 cycles (80% depth of discharge), battery energy density of 100-120Wh/kg and 150-190Wh/lt, shelf life exceeding 20 years, temperature immunity from -40°C to +60°C, and 48 volts with 1200-amp hours of DC power. Additional specifications include no gas emissions, no flammable materials, 100% recyclable materials, and manufacture date within 12 months of the performance period.

The project also requires removing existing power inverters and installing new modular power inverters (one 200-amp and one 100-amp) plus 27 new 20-amp dual locking power outlets throughout the facility. Contractor personnel must be escorted at all times in the controlled area and coordinate site access 72 hours in advance. The contractor must provide a one-year warranty on all work and materials, conduct system testing using AF747 forms, and schedule final acceptance with 377 MSG/SCXP. Work hours are Monday-Friday 0700-1600, though mission requirements may necessitate after-hours work coordinated 10 calendar days in advance. All work must comply with applicable standards including AFI 91-203, NFPA 70, and Kirtland AFB Communication Division specifications.

View the file

Other files

File Type Posted
bldg 498 2nd solicitation.pdf PDF
Base Access and Building Locations.pdf PDF
Vendor Questions and Answers.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK (SOW)

For Sodium Battery Installation for KAFB COMM

Building 498

Kirtland AFB, NM

Prepared By

377 MSG/SCXP

Table of Contents Table of Contents

1.0 SCOPE

2.0 REQUIREMENTS

2.1 GENERAL REQUIREMENTS

2.1.1 Safety Requirements

2.1.1.1 Site Coordination

2.1.1.2 Accident/Incident Reporting and Investigation

2.1.1.3 Work Area(s)

2.1.2 Security Requirements

2.1.2.1 Security Clearances

2.1.3 Environmental Management

2.1.4 Contractor Personnel

2.1.4.1 Project Management

2.1.4.2 Site Point of Contact (POC)

2.1.5 Warranty

2.2 SPECIFIC REQUIREMENTS

2.2.1 New Battery and Electrical Equipment Material Requirements for building 498

2.2 Grounding

2.2.3 Installation

2.2.4 Building 498 Battery and Electrical Equipment Work Requirements

2.2.5 Service Outages

2.2.6 Configuration Management. N/A

2.2.7 Test and Acceptance/Installation Test Plan

2.2.8 Final Acceptance

3.0 GENERAL INFORMATION……………………………………………………………….7

3.1 Period of Performance

3.2 Place of Performance

3.3 Hours of Operation

4.0 APPENDICES

4.1 Appendix A. APPLICABLE STANDARDS

4.2 Appendix B. LIST OF DELIVERABLES

1.0 SCOPE.

This SOW defines the requirement for the Contractor to remove and dispose of existing lead-acid batteries and the purchase and install new sodium nickel battery modules for communication building 498. Provide Ethernet remote monitoring capabilities. Additional electrical power infrastructure, supporting critical backup power from the batteries, is to be provided and installed by the Contractor. This will consist of removal and disposal of the existing power inverters, installation of new 200-amp and 100-amp modular power inverters to replace the removed power inverters, and installation of 27 new 20-amp dual locking electric outlets within the area of the newly installed equipment. The Contractor shall provide all equipment, tools, materials, supplies, transportation, labor, supervision, management, and other incidentals necessary to meet the requirements as stated in this SOW.

2.0 REQUIREMENTS.

2.1 GENERAL REQUIREMENTS.

2.1.1 Safety Requirements.

2.1.1.1 Site Coordination.

The Contractor shall coordinate with 377 MSG Communication Division personnel (377 MSG/SCXP) for base and facility access.

2.1.1.2 Accident/Incident Reporting and Investigation.

The Contractor shall record and report all available facts relating to each instance of injury to the Base Safety Office. The Contractor shall secure the scene of any accident and wreckage until released by the accident investigative authority through the Base POC. If the Government elects to conduct an investigation of the incident, the Contractor shall cooperate fully and assist the Government personnel until the investigation is completed.

2.1.1.3 Work Area(s).

At day’s end, the Contractor shall remove all debris and surplus materials from the work place. Safety barriers shall be in place to protect unfinished work site at the end of the day.

All materials and debris shall be removed before project completion.

2.1.2 Security Requirements.

2.1.2.1 Site Access Requirements.

The contractor shall be required to work in controlled areas (Building 498) where contractor employees must be escorted at all times. The contractor shall process a Site Access Letter (377 MSG/SC PM). This letter shall identify the names, numbers, driver’s license numbers and state of issue, and birth date of the personnel who will performing on this SOW for required background check by Kirtland AFB Security Forces. During project implementation, the Contractor shall coordinate access to secure areas at least 3 days (72 hours) in advance with the 377 MSG/SC PM. It is the Government's responsibility to provide escorts.

The contractor’s management will ensure that all employees, to include any sub-contractor employees, performing work on this effort receive an Operations Security (OPSEC) Awareness Briefing/Training prior to starting work on this effort and the briefing/training must be accomplished prior to entering the work site on day one of the work effort. The government (i.e., Contracting Officer, Unit Security Assistant, Unit OPSEC Coordinator, or 377 Air Base Wing OPSEC/Signature Manager (377 ABW/SMO)), can provide a tailored lesson plan for use by the contractor’s management to ensure training requirements are met. It is critical that contractor employees fully understand the importance of not discussing work details associated with this work effort, such as: actions or activities observed, the statement of work, as-built or other drawings, etc., in public or outside of the worksite. The contractor’s management will track all training by employee name and date the training was provided using a spreadsheet or similar document, such as a sign-in roster, and provide a copy to the assigned Contracting Officer

2.1.3 Environmental Management.

The Contractor shall comply with the most stringent environmental federal, state, and local laws and regulations; and Air Force policies, instructions, and plans. The federal Government is not exempt from compliance with environmental regulations. The Contractor shall maintain an awareness of changing environmental regulatory requirements to avoid environmental deficiencies for activities on Kirtland AFB, NM. The Contractor shall ensure their Sub-contractors comply with these specifications.

2.1.4 Contractor Personnel.

2.1.4.1 Project Management.

The Contractor shall provide a Project Manager (PM) and alternate(s) responsible for contract performance and continuity.

2.1.4.2 Site Point of Contact (POC).

The Contractor shall designate the Contractor's on-site team leader and alternate(s) as the Site POC for individual projects in their Site Visit Request Letter. The Site POC or alternate(s) shall be on site during duty hours until project completion. The Site POC shall be the interface for all work site communications with the Government, including quality, safety, and discrepancy matters.

2.1.5 Warranty.

The Contractor shall provide a one-year warranty or manufacturer’s standard commercial warranty, whichever is longer. This warranty shall include a one-year workmanship warranty. The warranty period shall start from the date of system and/or project acceptance.

The Contractor shall provide written procedures and required information for warranty services at or prior to site acceptance.

2.2 SPECIFIC REQUIREMENTS.

2.2.1 New Battery and Electrical Equipment Material Requirements for building 498 The Contractor shall Engineer, Furnish, Install and Test (EFI&T) a new 12 module sodium nickel battery system in building 498.

New batteries must meet the following requirements-

• Cycling Capability: 4.500 cycles (80% DOD)

• Battery energy density 100÷120Wh/kg, 150-190Wh/lt

• Shelf life (> 20 years)

• Temperature Immunity (-40 ÷ +60°C)

• No gas emissions

• No flammable materials

• No fire/water flood reaction

• 100% recyclable

• NO pollution materials

• NO gas emissions

• Battery system must be 48 volts and 1200-amp hours of DC power

The Contractor shall Engineer, Inform, Furnish, and Install (EIFI) ethernet enabled remote monitoring capabilities for the batteries that are to be installed. Upon completion of engineering the solution for this requirement, informing the 377 MSG/SCXP of the details for the solution. Examples for details include but are not limited to: any hardware/software requirements, real-time information capabilities, maintenance requirements, recurring costs, training requirements, and network configuration/capability requirements. Upon approval of the solution by the 377 MSG/SCXP, the furnishing and installation of the solution can be performed by the Contractor. The 377 MSG/SCXP reserves the right to omit this requirement should they decide it is necessary for satisfying the other requirements provided in this Statement of Work.

The Contractor shall Engineer, Furnish, Install and Test (EFI&T) one new rack mountable 200-amp capable modular power inverter and one new rack mountable 100-amp capable modular power inverter. These will support the 27 new 20-amp dual power outlets that are to be Engineer, Furnish, Install and Test (EFI&T) by the Contractor.

2.2.2 Delivery and Transport Requirements

Building 498, location of installation, does not have space available for storage of the required materials should there be a gap of time between material delivery and installation. It is recommended that should there be a gap of time between material delivery and installation, the contractor make use of storage separate from the building to protect the materials and accumulate them in preparation of installation. Examples of this could be: utilization of building warehouse on base, leased storage container, off-base storage facility.

Building physical address:

Building 498 is not equipped with a loading dock for material delivery. It is recommended that the contractor take this into account due to the size and weight of the materials involved both for installation and removal. Vehicles such as a liftgate equipped box truck could be utilized for delivery of the materials to building 498. Such a vehicle could also be utilized by the contractor for the removal and disposal of existing materials such as the lead-acid battery strings and their shelves.

2.2.3 Grounding.

Contractor shall reuse existing grounding hardware to properly bond/ground battery modules.

Contractor will provide any hardware required to meet bonding/grounding standards.

2.2.4 Installation.

2.2.5 Building 498 Battery and Electrical Equipment Work Requirements

• The Contractor shall purchase 12 new sodium nickel battery modules as specified above, an appropriate network rack for mounting the modules (if required), and any required Ethernet reporting module. Manufacture date of batteries shall be within 12 months of Period of Performance PoP.

• Remove the 6 existing lead-acid battery strings (composed of 24 cells each) and hardware and install new batteries, rack, and network module in its place.

• Connect all batteries in parallel to the existing DC power distribution cabinet. Should the 6 existing connections not be sufficient due to the new batteries and racks, removal and providing/installation of new connections are to be performed by the Contractor.

• Dispose of the removed lead-acid battery strings and hardware in accordance with any applicable federal and state laws.

• Provide and install one new modular power inverter equipped for a 200-amp load within the vault room of building 498 to support 20 new 20-amp dual locking power outlets, and one new modular power inverter equipped for a 100-amp load within the open telecom room of building 498 to support 7 new 20-amp dual locking power outlets.

• Remove and dispose of two old, existing power inverters in accordance with any applicable federal and state laws.

• Provide and install the required total of 27 new 20-amp dual locking power outlets throughout the cabinets located in the facility housing the batteries, power distribution cabinet, and inverters. These outlets are to match the Kirtland AFB Comm Division Specs for telecommunication equipment cabinets. Outlets are to be directly supported by the inverters for circuits.

• Should existing electrical distribution equipment be insufficient for the support of the newly installed power outlets’ circuits, provide, engineer, and install electrical distribution equipment.

• The provided floorplan at the end of this Scope of Work can be used as reference by the contractor for evaluation and planning. Measurements in the floorplan are estimates.

2.2.6 Service Outages.

The Project Manager will need to coordinate with affected units before the installation can begin. The Contractor shall be responsible for preventing any unscheduled interruptions of communications capabilities that are properly identified. The Contractor shall coordinate cutover with the site POC at least 10 calendar days in advance.

2.2.7 Configuration Management. N/A

2.2.8 Test and Acceptance/Installation Test Plan.

The Contractor shall test the system to demonstrate its proper performance to the Government quality assurance representative. These tests shall be accomplished prior to the system being placed into service. The Contractor shall populate the testing and results within an AF747 form as a deliverable.

2.2.9 Final Acceptance.

The Contractor shall schedule a final project walk-through with 377 MSG/SCXP. Signatures on an AF747 form will be collected from the Contractor and the 377 MSG/SC to complete acceptance.

3.0 GENERAL INFORMATION.

3.1 Period of Performance.

The period of performance for the project shall be determined based on the proposed schedule and actual contract award date.

3.2 Place of Performance.

The place of performance is Kirtland AFB, NM.

3.3 Hours of Operation.

The Contractor shall routinely work during normal duty hours of M-F between 0700 - 1600.

However, mission requirements may necessitate work outside normal hours (nights and/or weekends), especially if existing service must be interrupted. Any site work requested by the Contractor to be performed outside of normal duty hours shall be coordinated with the 377 MSG/SCXP PM at least 10 calendar days in advance.

4.0 APPENDICES.

4.1 Appendix A. APPLICABLE STANDARDS.

AFI 91-203 – Air Force Consolidated Occupational Safety Instruction ANSI-J-STD-607–A Commercial Building Grounding (Earthing) and Bonding Requirements for Telecommunications RUS Bulletin 1751F-801 – Electrical Protection Fundamentals RUS Bulletin 1753F-201 (PC-4) – RUS Standard for Acceptance Tests and Measurements of Telecommunications Plant NFPA 70 - National Electric Code Kirtland AFB Comm Division Specs 06 Sept 2023

4.2 Appendix B. LIST OF DELIVERABLES.

All deliverables are subject to Government acceptance and approval. They shall meet professional standards and the requirements set forth in this SOW. All deliverables shall be produced using recommended software tools/versions as accepted by the Government. The Contractor shall submit the following deliverables:

AF747 form

Building 498 Floorplan: