This document is a Scope of Work (SOW) for base security fencing at the United States Coast Guard Base Galveston, located at 3000 Fort Point Road in Galveston, Texas. The project requires a contractor to install approximately 490 feet of security fencing, including a new fence line 10 feet from the jetty rocks, tied into the existing property line fence, and securely attached to the waterfront break wall. The fencing must include a double gate with an 8-10 foot opening near the boat ramp, equipped with a locking latch, and topped with security wire.

The contractor will be responsible for providing all labor, materials, and equipment, using new materials and ensuring United States Coast Guard standards for quality and safety are met. Key requirements include conducting a field investigation to identify utility locations, maintaining a clean work area, protecting adjacent areas during installation, and providing construction signage. Contractors must be registered in the System for Award Management (SAM) with an active DUNS number, comply with OSHA safety standards, and follow specific notification and site access procedures. The project will involve working between 7:00 AM and 2:00 PM, Monday through Thursday, with prior notification and approval from the Contracting Officer's Representative (COR) and Facility Engineer.

View the file

Other files

File Type Posted
Attachment B (INSTRUCTIONS).pdf PDF
70Z02925QNEWO0036_0_US.pdf PDF
Attachment A.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF HOMELAND SECURITY

UNITED STATES COAST GUARD

BASE GALVESTON

Scope of Work

FOR

Base Security Fencing

AT

USCG Base Galveston 3000 Fort Point Road, Galveston, TX 77550

Base Galveston Initial Date

Contracting Officer (KO)

CWO Jesus Guevara FE Deputy Department Head

LT Jordan Groff FE Department Head

Table of Contents

1. GENERAL

1.1 GENERAL REQUIREMENTS

1.2 LOCATION

1.3 POINTS OF CONTACT

1.4 SITE INVESTIGATION

1.5 CONTRACTOR SECURITY REQUIREMENTS PROJECT SYNOPSIS

2. SCOPE OF SERVICES

2.1 FIELD INVESTIGATION

2.2 DESCRIPTION OF WORK TO BE COMPLETED

3. PROPOSAL SUBMITALS

3.1 SITE VISIT REPORT

3.2 ESTIMATE

3.3 SUBMISSION

4. CONSTRUCTION NOTIFICATIONS

4.1 NOTIFICATIONS

4.2 RECYCLING AND DISPOSAL OF REFUSE

4.3 SAFETY

4.4 TEMPORARY FACILITIES STORAGE

4.5 SANITARY FACILITIES

4.6 WATER AND ELECTRICITY

4.7 REFERENCE DRAWING

4.8 CONTRACTING REQUIREMENTS

5. COAST GUARD PROCUREMENT SELECTION

4.1 BID PROCEDURES

4.2 QUESTIONS

6. REFERENCE DOCUMENTS AND PHOTOS

1. GENERAL

1.1 GENERAL REQUIRMENTS

The United States Coast Guard is accepting quotes for qualified individuals or firms to Provide all labor, materials, and equipment necessary to install security fencing between existing property line and the break-wall. Prior to submitting a quote, it is mandatory to examine the Performance Work Statement (PWS), and it is highly recommended to visit the facility to take field measurements, evaluations, etc., and become familiar with existing conditions under which the work will be performed.

1.2 LOCATION:

Project site is located at U.S. Base Galveston 3000 Fort Point RD. Galveston, TX. 77550.

1.3 POINT OF CONTACT:

A. Facility Engineer

a. CWO Jesus Guevara (936) 232-2390

b. Mr. Timothy Florez Adams: (409) 766-4856 / (832) 221-9278

B. COR

a.

1.4 SITE INVESTIGATION

Investigate the site per FAR 52.236-3 to ascertain the general and local conditions which can affect the work or its cost. Contact Mr. Tim Florez for site access. Perform all on-site work between the hours of 7:00 AM and 2:00 PM, Monday through Thursday (Federal Holidays excluded), unless otherwise approved by the COR and the Facility Engineer (FE).

1.5 CONTRACTOR SECURITY REQUIREMENTS:

For this affected Coast Guard facility/property, the Contractor shall provide a list of all on-site personnel, including sub-contractors and suppliers, to the Facilities Engineer. The contractor shall update this list when changes occur. Contractor personnel not listed may be denied access to the Coast Guard facility. Contractor personnel will be restricted to designated working areas.

Any personnel violating this policy may lose access to the Coast Guard facility. Contractor personnel shall have photo identification at all times while working on Coast Guard facilities.

Contractors shall provide the POC in 1.3 with 24 hours of advance notice of every delivery to the site (e.g., concrete, lumber, parts, etc.) and provide the company name, delivery person, and phone number of the firm(s) making deliveries. All vehicle access to government property requires vehicle registration and proof of liability insurance. Otherwise access to the Coast Guard facility may be denied.

2. SCOPE OF SERVICES

2.1 FIELD INVESTIGATION

Contractor will conduct a thorough field investigation for the project. Inspection shall identify and document existing site conditions, specifically the location of all utilities (i.e., electric, water, sewer, gas etc.) or shared systems (Example: HVAC, Fire Suppression, Network) to identify any conditions that may be affected by work.

2.2 DESCRIPTION OF WORK TO BE COMPLETED

The Contractor to supply all plant, labor, materials, and equipment:

• All materials, supplies, and equipment (MSE) must be new. The Contractor shall not re-use any existing MSE, unless directed to by the SOW.

• Provide supervision to ensure United States Coast Guard Standards are met for Quality and

Safety.

• Maintain a clean working area.

• Protect adjacent areas during security fencing installation.

• Provide signage to clearly indicate the area is under construction.

• Install approximately 490 feet of security fence line with security wire on top.

• New security fence line is to be installed 10’ feet from the jetty rocks (shoreline / riprap materials) and is to be securely tied into existing property line fence on the north side of Base property and securely attached to the waterfront break wall to prevent any access from water side. Near the boat ramp, new fencing to be built with 1 access point for a double gate with an

8’ to 10’ feet opening for access to jetty rocks for property maintenance. Double Gates must have a locking latch (Double Gate Latch or better) for securing.

• Apply high performance materials (posts, poles and fencing) and hardware for attaching fencing to posts and gates.

• Section 6 of this SOW displays the area of security fencing to be constructed.

3. PROPOSAL SUBMITALS

3.1 SITE VISIT REPORT: One after each visit:

a) Personnel attending and local personnel involved.

b) Discussions held.

c) Observations and issues

d) Proposed solution

3.2 Estimated Costs:

Material Shipping if applicable Labor to include estimated time of completion.

3.3 SUBMISSION:

Contractor shall make the following submittals as a minimum, to the Contracting Officer specified on the cover sheet.

The contractor is required to provide verbal progress reports daily for the period of project duration. The progress report shall cover all work completed during the day and shall present the work to be accomplished during the subsequent period. This report shall also identify any problems that arose and a statement explaining how the problem was resolved. This report shall also identify any problems that have arisen but have not been completely resolved and provide an explanation.

4. CONSTRUCTION NOTIFICATIONS

4.1 NOTIFICATIONS:

The Contractor shall notify the COR in writing (or email) five (5) business days in advance of the date they intend to commence work, and five (5) business days prior to the date that work will be ready for final inspection.

4.2 RECYCLING AND DISPOSAL OF REFUSE:

Refuse, excess or waste materials resulting from construction operations shall become the property of the Contractor and shall be recycled and/or disposed of off Government property. All disposals shall be done in accordance with federal, state, and local laws and regulations.

4.3 SAFETY:

During the execution of this contract, the Contractor shall conform to the rules and regulations as set forth by OSHA Safety and Health Standards, 29 CFR 1926 is a National Code within OSHA that applies across the board. Texas is a “home run” state where the local municipality controls the building codes. The city of Galveston has a code, “Standard Construction Specifications - Standard Construction Specifications | Galveston, TX - Official Website (galvestontx.gov)”.

When the standards differ, the more restrictive standard shall apply. The contractor shall provide barriers, temporary fencing, trench covers, etc. wherever work could cause injury to workers, visitors, Coast Guard personnel, or dependents. An Accident Prevention Plan shall be submitted by the contractor prior to any commencement of work.

https://www.galvestontx.gov/504/Standard-Construction-Specifications

4.4 TEMPORARY FACILITIES STORAGE:

The location for exterior stock piling or lay down area of materials will be available on base with location to be determined by COR and Facilities Engineer depending on size. The Contractor shall be responsible for protecting materials stockpiled against weather, damage, theft, and other risks of loss. The Coast Guard assumes no responsibility for material or equipment left in the storage area.

4.5 SANITARY FACILITIES:

Toilet facilities are available for use, pending the status of the COVID Pandemic, it may be required that all contractors to wear face masks while entering and transiting the interior of buildings or when social distancing can’t be maintained with other government or contractor personnel. Additionally, good personal hygiene is required, and handwashing is required to prevent the potential spread, to include, but not limited of the COVID virus.

4.6 WATER AND ELECTRICITY:

Limited water and standard 110v electricity are available. The utility connections and disconnections of machinery or equipment shall be the responsibility of the Contractor.

Personnel using extension cords to bring power from another location for construction, maintenance, remodeling, etc., shall employ portable ground fault circuit interrupters (GFCIs), even if connecting to building wiring. Use of portable generators is authorized at contractor expense to power portable equipment, if required to provide power other than standard building supplied power sources.

4.7 REFERENCE DRAWING:

Contractor shall field verify all information provided. Drawings are provided and available onsite, as well as the pictures attached. The pictures are of what we are requesting repairs and are to provide a view of entire system as a whole for full visibility.

4.8 CONTRACTING REQUIREMENTS:

All contractors must be registered in SAM (System for Award Management -https://sam.gov/content/home) and have an active DUNS number.

5. COAST GUARD PROCUREMENT SELECTION

5.1 BID PROCEDURES:

The Coast Guard, through its Contracting Officer, will invite bids for construction, and will award and administer the contract. Once solicitation is released, communication with prospective bidders unless specifically directed by the Coast Guard Contracting Officer shall be made to Facilities or COR until awarded.

5.2 QUESTIONS:

The Contraction Officer will answer any questions posed by prospective bidders or Contractors.

All such inquiries, problems, etc., shall be transmitted with appropriate comments and opinions to the Contracting Officer who will reply.

6. REFERENCE DOCUMENTS AND PHOTOS

Fencing Path-

Existing Property Line Fencing –

Break Wall Area –