- FSH BLDG 4055 Repair Vertical Stack Doors
- Solicitation number
- FA301624Q5022
About this file
This statement of work and related federal contract opportunity outline requirements for repairing overhead doors at Joint Base San Antonio-Fort Sam Houston in 2024. The statement of work requires contractors to assess and repair five vertical stack blast doors and electrical function boxes, including inspecting and troubleshooting all operating components, replacing parts as needed, inspecting and repairing door seals, and coordinating work with the base. Contractors must complete the work within 60 days of the project start date using qualified skilled technicians while following all applicable safety standards. Interested parties must respond to the related sources sought notice questionnaire by March 12, 2024 to be considered for the pre-solicitation opportunity issued by the Department of the Air Force Air Education and Training Command. The solicitation number is FA301624Q5022 for repairs at building 4055.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sources Sought Notice- Repair Vertical Door 6 March 2024.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ABBREVIATED STATEMENT OF WORK
FOR
Repair Overhead Doors Joint Base San Antonio - Fort Sam Houston
NAME OF INSTALLATION:
Joint Base San Antonio - Fort Sam Houston
PROJECT MANAGER: Gabriel Talamantes
PART 1 – SCOPE OF WORK:
1.1 GENERAL: The work to be performed under this contract and in accordance with this Statement of Work shall consist of furnishing all necessary parts, labor, tools, transportation, supplies, supervision, equipment, materials, and incidentals necessary for providing all work shown in the statement of work, and all applicable codes, regulations, standards, and criteria in effect the date project is awarded. All commercial installation/repairs must be performed by qualified skilled/licensed technicians.
1.2 PROJECT DESCRIPTION: Contractor shall provide all labor, materials, to perform full functional repair of vertical lift stack doors and electric door openers.
• The following components must be accomplished: Contractor shall assess the current condition of (5) vertical stack blast doors and electrical function box.
• Service Required:
o Main focus are doors inoperable #7, #13, #26, #27, and #34. These doors shall be full rehabilitated to functioning state. The doors shall be inspected/troubleshooted of all operating components. i.e., motor operation, lubrication, door adjustment, electrical box/components, operator motor, photo eyes, cables, pulley, wenches, all hardware, all door lift components, weather sealant/stripping, etc.
o All motors shall be inspected for proper function and security to mount and belts. Some belts to motors are loose. Belts shall be tightened or replaced if unserviceable.
NOTE: There will be no modification done to the building. NO drilling or cutting. All work will be removed and replace parts.
o Doors #1 - #28 shall be inspected for proper top and bottom sealant. Doors shall be properly sealed from outside weather.
o Coordinate with Lackland AFB Civil Engineer Operation Planning office ahead of time. Par (1.5.2) o Contractor shall always utilize all proper Personal Protective Equipment (PPE) for this project. If using lifts contractors shall use proper fall protections according to OSHA Regulation 1910.28/1910.29. AFOSH DAFMAN 91-203 Chapter 13.6 Fall Protection Plan.
o Contractor shall haul all project waste off government property.
o Upon completion of project, contractor shall call Civil Engineer Project Manager (PM) and
Facility Manager (FM) for inspection.
o Upon final inspection, contractor is responsible for removing all tools, trash, equipment, and personnel off government installation.
o Provide specialized equipment at Contractor cost.
1.3 LOCATION: Building 4055 on 2566 Wilson Way, Joint Base San Antonio-Fort Sam Houston, TX.
1.4 WORK AND MECHANICS: The work for this project shall be executed in the best and most craftsman-like manner, by qualified and efficient mechanics/tradesmen, skilled in their respective trades. Only certified journeymen in each respective trade, or apprentices under the direct supervision of certified journeymen, shall be permitted to install and/or supervise installation for this project. Individual trade work for this project shall be performed and quality maintained by the applicable trade only. The Contractor shall assure that all trades coordinate their work with that of other trades. The Contractor shall coordinate and perform all operations in a manner that will result in a professional and expeditiously completed project. The work shall be in strict accordance with prevailing industry standards and manufacturer’s instructions. Work and materials shall comply with this Statement of Work and the editions in effect at the time of this solicitation for all applicable criteria, regulations, guidelines, and codes, all of which are made a part thereof.
1.5 WORKING CONDITIONS: All Contractor operated/owned vehicles, equipment, tools, etc., shall be stored as prescribed in paragraph 1.11. DELIVERY, STORAGE, AND PARKING. Applicable traffic control signage where required by the contract shall remain overnight. There shall be no power outage in excess of 8 hours.
SHOWERS, LARISSA C Amn BR USAF AETC 502 CONS/JBKAA Date of award ? How many days after it ?
SHOWERS, LARISSA C Amn BR USAF AETC 502 CONS/JBKAA Please specify POP
TALAMANTES, GABRIEL CIV USAF AETC 502 CES/CEOER
Par. 1.5.3 I mention the contract shall complete within 60 days once project start date.
1.5.1 WORK SCHEDULE: Working hours for the Contractor will normally be between the hours of 7:00 a.m. and 5:00 p.m. excluding Saturdays, Sundays, and Federal holidays. The Contractor shall be allotted ten (10) working days to coordinate project listed in Section 1.2., Project Description.
New Year's Day Martin Luther King Jr's Birthday President’s Day Memorial Day Juneteenth Independence Day Labor Day Columbus Day Veterans' Day Thanksgiving Day Christmas Day
1.5.2 WORK AREA ACCESS: The Contractor shall coordinate with the designated Planning Technician, Mr.
Gabriel Talamantes (210) 808-0154 gabriel.talamantes.1@us.af.mil, or the Planning Section Lead, Mr. Victor Reyna at (210) 808-0010 victor.reyna@us.af.mil.
1.5.3 PROJECT SCHEDULE PLAN: Contractor shall send a progress schedule plan of start date and completion date 7-14 days after contract has been awarded. Contractor shall complete project within 60 days of project start date.
1.6 SAFETY: All Contractor operations shall be conducted and performed in accordance with Department of Labor, OSHA requirements found in 29 CFR 1910 (1910.146 and 1910.147) and 29 CFR 1926, and Air Force Occupational Safety & Health (AFOSH) AFOSH standards including 91-25. The Contractor shall also ensure that all work is performed in accordance with project identified national standards, military manuals, instructions, pamphlets, standards, and handbooks, and with the edition in effect on the date of this solicitation of the Corps of Engineers (COE) Safety Manual 385-1-1.
1.6.1 All companies who conduct business within the state of Texas must, in accordance with Texas Worker’s Compensation laws (Texas House Bill 62), have an approved company safety policy and an Accident Prevention Plan.
The plan, approved by the Texas Worker’s Compensation Commission (TWCC), shall be submitted For Information Only (FIO) in accordance with paragraph, SUBMITTALS. In addition to meeting the TWCC requirements; the plan must also include the requirements of COE Safety Manual 385-1-1.
1.6.2 Resolution of Department of Labor citations for violations of Occupational Safety and Health Standards is a Contractor responsibility and shall provide for no basis of a claim against the Government.
1.7 PROTECTION OF GOVERNMENT PROPERTY: The Contractor shall use reasonable care to avoid damaging existing buildings, equipment, and vegetation on the Government installation. If the Contractor fails to use reasonable care and causes damage to any of this property, the Contractor shall replace or repair the damage at no expense to the Government. If the Contractor fails or refuses to make such repair or replacement, the Contractor shall be liable for the cost, which may be deducted from the contract price.
1.8 SITE MAINTENANCE AND CLEANUP:
1.8.1 SITE MAINTENANCE: The Contractor shall protect adjacent property, buildings and their contents from dust, dirt, or other materials. Work areas shall be maintained in a neat, clean, and safe condition and shall, at a minimum, be cleaned at the end of each shift. All streets and roadways in/or adjacent to the site shall remain free of project generated trash and debris at all times.
SHOWERS, LARISSA C Amn BR USAF AETC 502 CONS/JBKAA 10 or 5 working days ? Please clarify.
SHOWERS, LARISSA C Amn BR USAF AETC 502 CONS/JBKAA Provide emails as well
1.8.2 DAILY CLEANING: The Contractor shall keep the site free from debris at all times and shall perform daily cleaning of all areas.
1.8.3 CLEANUP: The Contractor shall collect any, and all trash, debris, refuse, garbage, etc., that is generated and place it in appropriate containers with lids or approved covers on a periodic basis or as directed by the Structures Shop Supervisor. The aforementioned materials shall be hauled from the site by appropriate means on a daily basis, unless otherwise approved by the designated Planning Technician. Disposal shall be outside the limits of Government property. Disposal shall be by sanitary landfill or other approved methods and shall conform to all local, state, and federal guidelines, criteria, and regulations. Upon completion of the work, the Contractor shall leave the work site and storage area(s) in a clean, neat, and workmanlike condition satisfactory to the Structural Shop Supervisor.
1.10 WARRANTY: The Contractor shall identify all items being installed that are guaranteed or under warranty for more than a one-year period and provide validated copies of the manufacturer’s warranty. All warranty information shall be filed by the Contractor in the Government’s name. All warranties shall be identified by product with a listing of the name and address of the company and the expiration date of the guarantee or warranty.
The contractor shall guarantee all materials and workmanship for a period of one year from the date of project completion and shall within that period correct all defects in materials/workmanship within twenty-four (24) hours of being notified. Correction of all defects under this warranty shall be at the expense of the contractor.
1.11 DELIVERY, STORAGE, AND PARKING: All equipment delivered and stored shall be protected from the weather, humidity and temperature variation, dirt and dust, and any other contaminants.
1.11.1 CONTRACTOR STORAGE: The Planning Section Lead and/or designated Planning Technician shall designate Contractor storage and parking area.
1.11.2 STORAGE AREAS: Contractor shall coordinate with Project Manager for assigned storage area/space. All project storage areas shall be kept free of debris, leaks, stains, or splashes and kept in a neat, clean, and safe condition.
Any contamination of the storage area by a hazardous substance shall be immediately remediated by the Contractor.
1.12.4 BASE FIRE REGULATIONS: The Contractor shall comply with Base Fire Regulations as set forth in the latest edition of GAFB Instruction 32-2001, titled “Base Fire Protection Program”. The Contractor shall use no explosives in performing the work. All work shall be in strict compliance with NFPA-101.
1.13 REMOVAL: Items to be included in the removal shall include but not be limited to the careful removal and disposition of materials. The Contractor shall, before commencement of any work, carefully survey the existing site to determine the extent of the work. The Contractor shall take all necessary precautions to ensure against damage to existing work to remain in place, or to remain the property of the Government. Any damage to the aforementioned shall be repaired or replaced by the Contractor at no additional cost to the Government. The Contractor shall be responsible for the proper disposal of all materials, meeting all rules pertaining to the disposal of such products.
PART 2 – ENVIRONMENTAL REQUIREMENTS:
2.1 REFERENCES TO MATERIALS, MANUFACTURERS, AND PRODUCTS: Materials and equipment shall be the standard products of a manufacturer regularly engaged in the manufacture of the products and shall essentially duplicate items that have been in satisfactory use for at least 2 years prior to bid opening. Equipment shall be supported by a service organization that is, in the opinion of the Planning Section Lead, reasonably convenient to the site.
2.1.1 VERIFICATION OF DIMENSIONS AND CONDITIONS: The Contractor shall visit the premises to become thoroughly familiar with details of the work and working conditions, field verify all dimensions and advise the Planning Section Lead of any discrepancies before starting the work.
PART 3 – ADDITIONAL INFORMATION:
3.1 GENERAL: All work shall be installed as shown and in accordance with commercial door operator installation procedures, unless otherwise specified. All dimensions are shown for information only. Contractor shall field verify all dimensions and site conditions. The Contractor shall provide all labor, materials, tools and equipment required to perform all dismantling, repairs, and re-installation as listed in this statement of work.
3.2 OPERATIONAL SYSTEMS: The Contractor shall insure that all work is performed in accordance with the criteria herein and demonstrate to the requester/agent a successful function check.
3.3 INSPECTION AND ACCEPTANCE: A representative from 502 CES will conduct daily inspections of work progress. A final inspection of completed work will be conducted by the project manager, contractor and designated 502 CES personnel. All discrepancies identified during inspections shall be corrected prior to final payment.
3.4 MANUALS: The Contractor shall provide all applicable manufacturers recommendations and operating instructions to the designated Planning Technician or Planning Section Lead.
END OF STATEMENT OF WORK