SOW B1575 Tank Inspection FINAL 6_Jul_22.pdf

PDF 195 KB Posted

Attached to
Clean and Inspect Building 1575 Underground Storage Tank, Scott AFB, IL
Solicitation number
FA440722Q0006
Issued by

View the file

Other files

File Type Posted
COMBO Underground Storage Tank Clean.pdf PDF
WD 2015_5075 Rev 22 07_12_2022.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

Clean and Inspect B1575 Underground Storage Tank

Scott Air Force Base, IL 6 July 2022

1. BACKGROUND: Bldg.1575 diesel steel underground storage tank (UST) has been in service for over 30 years without any in depth tank inspection to include cleaning. After taking a fuel sample, it was determined that the fuel in the tank was severely degraded and the amount of contaminates in the fuel was too great to be cleaned utilizing in-house fuel polishing equipment. It was determined that the fuel and tank needs to be cleaned and thoroughly inspected.

2. OBJECTIVE: The fuel in the tank must be cleaned to remove entrained contaminates, the tank thoroughly cleaned, and internally inspected using ultra-sonic thickness testing (UTT) technology. The contractor shall provide all tools, supplies, equipment, labor, and management to meet the requirements of the objective in a manner that will ensure its serviceability and operability.

3. PROJECT SCOPE: The following work will be accomplished.

A. Contractor shall be licensed with the State of Illinois Fire Marshal to conduct

Internal Tank Inspections, to include International Code Council Certificate for UST inspection, and must obtain all required permits.

B. Tank Access, Fuel Transfer and Filtering

i. Disassemble piping, valves, and tank monitoring equipment above man way in order to access tank interior.

ii. Supply an 8,000-gallon tank in order to hold the remaining product from the UST during tank cleaning and inspection process.

iii. Once the cleaning and inspection has been completed, the fuel from the tank will be processed through a filtering and de-watering equipment before being placed back in to the tank.

• Contractor shall provide before and after fuel samples to prove fuel filtering effectiveness.

iv. Reassemble piping, valves, and tank monitoring equipment above man way.

v. Upon completion, ensure tank is in full working order and meets all safety and environmental specifications for USTs.

C. Internal Cleaning

i. Personnel will transfer remaining fuel to the holding tank and work from the open man way and remove as much residual product as they can utilizing a vacuum system.

ii. Waste product will be properly disposed in adherence to local, state and federal guidelines.

iii. The tank will be ventilated in order to create an acceptable environment for confined space entry per Occupational Safety and Health Act (OSHA) Confined Space standard 29 CFR 1910.147.

iv. Personnel will enter the tank and remove remaining product.

v. Personnel will apply absorbent to the tank floors and remove remaining residual product.

vi. The remaining waste and absorbent will be properly disposed in adherence to local, state and federal guidelines.

vii. Pictures will be taken upon completion of cleaning the tank and photos will be provided to the government for their records.

D. Tank Inspection

i. The tank will continue to be ventilated in order to maintain an acceptable environment for confined space entry per OSHA Confined Space standard

29 CFR 1910.147.

ii. An inspector will enter the tank to conduct a visual tank inspection in accordance with the American Petroleum Institute (API) 1631 / Steel Tank Institute (STI) standard . This inspection shall include a visual inspection of the tank’s interior surfaces observing for any indication or evidence of leaks;

shell distortions; settlement; corrosion.

iii. All of the tank welds will be visually inspected.

iv. The inspector will conduct Ultrasonic Thickness Testing (UTT) on the tank walls to determine if there are any metal integrity issues or potential metal loss.

v. If the tank has an internal lining, the lining will be visually inspected looking for cracks, tears and disbondment in accordance with Illinois code Title 41 Section 175.500 b Interior Lining and Lining Inspection of USTs.

vi. A final report will be provided of the condition and recommendations for improvement of the tank.

4. SPECIFICATIONS: Work shall be performed in strict accordance with these contract general specifications, as well as all applicable local, state, and national Building and Life Safety Codes and American Society for Testing and Materials (ASTM) specifications.

Safety issues must adhere to all applicable Occupational Safety and Health Act (OSHA) regulations and International Mechanical Code (IMC).

5. GENERAL CONDITIONS:

A. Contractor shall be completed within the agreed upon PoP as stated within the contract issued by the Contracting Officer.

B. Contractor shall brief all Sub-Contractors on all safety and fire prevention regulations, emphasizing the requirement to obtain a daily AF Form 592, Welding, Cutting, and Brazing Permit, when welding, cutting, or brazing operations are to occur under this delivery order. The AF Form 592 can be obtained from and approved by 375 CES.

C. All documents related to the disposal of non-hazardous and/or hazardous material must be supplied to 375 CONS and 375 CES. The Contractor must obtain the proper approval documents from 375 CES to ensure all materials leaving Scott Air Force Base can be tracked and accounted for, in accordance with all governing laws.

D. Under the 1992 Clean Air Act, all products used in executing this project must not be related to the Class I Ozone Depleting Chemicals (ODCs) identified in Air Force Policy. The following products are considered Class I ODCs: CFC-11, CFC-12, CFC-113, CFC-114, CFC-115, Halon 1211, Halon 1301, Halon 2402, CFC-13, CFC-111, CFC-112, CFC-211, CFC-212, CFC-213, CFC-214, CFC-

215, CFC-216, CFC-217, Carbon tetrachloride, and Methyl Chloroform.

6. Government Furnished Utilities: The Contractor may have use of government electrical and water supplies that, in nearly all cases, are available at each site. If the Contractor needs additional utilities, special connectors, etc., the Contractor will need to provide these at their own expense.

7. Government Furnished Equipment: There is no government furnished equipment provided for this SOW. The Contractor is responsible for all tools, training, supplies, materials, labor, vehicles, etc.

8. Accomplishment of Work: The work areas of the existing building and lot will be in occupied and unoccupied areas. The Contractor must ensure that all access to the existing building remain clear for occupants and emergency access at all times during the construction period. All temporary closures, barriers, and protective procedures shall be coordinated with the Project Manager or Inspector. All work can be accomplished during non-standard business hours to accomplish work by deadline.

9. Protection of Building Property: The Contractor shall protect from damage all building property located in or adjacent to the building and shall repair, replace or otherwise be held liable for all such damage. Building properties include but are not limited to, furniture, vehicles, or items of supplies. Exercise control measures of all dust and toxic fumes associated with construction operations, in order to prevent hazards or illness to base and Contractor personnel.

10. Cleanup: The Contractor shall cleanup each work site at the end of each work day to the satisfaction of the Project Manager. Upon completion of each work day, the area shall be left in a neat and completely acceptable condition free of any excess debris. Contractor must always recycle materials, such as, but not limited to cardboard and paper. The Contractor will use whatever means necessary to store all recyclable materials and is responsible for turning in recyclable materials to an off Base Recycling Center.

11. Waste Management:

A. The contractor is responsible for the analysis, characterization, proper handling and disposal of regulated waste, including but not limited to hazardous waste generated by their operation. Management shall be in accordance with Title 22 of the Illinois Code of Regulations and the Scott AFB Hazardous Waste Management Plan. If regulated wastes are generated, the contractor shall properly contain the waste and it will be government’s responsibility to properly dispose. The contractor shall anticipate 375 CES/CEI audits to ensure their hazardous waste program is compliant with requirements.

B. Under no circumstances shall the contractor remove any waste from Scott Air Force Base without ensuring complete and full compliance with all applicable existing environmental laws and regulations. All shipments must be prepared in accordance with Department of Transportation Regulations (40 CFR 172).

C. Prior to removing, transporting or disposing of any waste from the base, the contractor shall forward waste manifests, land disposal restrictions, waste profiles, laboratory analyses, and safety data sheets to 375th CES/CEIE to obtain a review, approval, and/or signature as required. The 375 CES/CEIE shall receive all final manifests signed by the approved disposal facility. Hazardous waste treatment is not permitted on Scott AFB unless approved and monitored by 375th

CES/CEIE.

12. Notification of Environmental Spills:

A. If the contractor spills or releases any hazardous substance that contacts or has the potential to contact water, soil or any drain (sanitary or storm) the contractor shall call 911 (256-4911 utilizing telephone on base) then 375 CES/CEIE immediately.

The contractor shall be liable for reimbursement of containment and environmental clean-up of the spill or release of such substance.

B. Spill Response. The contractor shall be responsible for the clean-up and disposal of all spilled materials. This includes all materials used to contain and absorb the spill. Spilled material must be cleaned-up promptly and reported to 375 CES/CEIE. Spills of HAZMAT or hazardous waste shall be managed in accordance with the current 375 CES Wing Integrated Contingency Plan for Scott AFB. Disposal of wastes generated from spill clean-up shall be the contractor's responsibility and will follow protocol outlined in Section 9.3.3. The contractor shall be liable for reimbursement of containment and environmental clean-up of the spills.

C. Training. The contractor is responsible to train their employees regarding Environmental and Hazardous Materials Handling. The contractor is also required to have and maintain Safety Data Sheets (SDS) for all materials used by the contractor in accordance with federal and state laws. A copy of all SDSs shall be supplied to 375 CES/CEIE prior to field activities.

13. Fire Safety: The contractor shall obtain a burning permit from the Scott AFB Fire

Department building 460, (256-5130) prior to welding, burning or cutting operations each day they anticipate performing this type of work. All welding and burning operations necessary for the completion of the OWS shall be accomplished in strict compliance with fire safety and applicable standards. The contractor shall provide and maintain fire extinguishers in accordance with NFPA standards during all welding and burning operations.

14. General Requirements:

A. Contractor Consent to Background Checks: The contractor and, as applicable, subcontractor shall not employ persons for work on this contract if such employee is identified as a potential threat to the health, safety, security, general well-being or operational mission of the installation and its population, nor shall the contractor or subcontractor employ persons under this contract who have an outstanding criminal warrant as identified by Law Enforcement Agency Data System (LEADS) through the National Crime Information Center. LEADS checks will verify if a person is wanted by local, state, and federal agencies. All contractor and subcontractor personnel must consent to LEADS background checks. Contractor and subcontractor personnel who do not consent to an LEADS check will be denied access to the installation. Information required to conduct an LEADS check includes: full name, driver’s license number, and/or social security number, date of birth of the person entering the installation, and completion of a background check questionnaire. The contractor shall provide this information using the Scott AFB Form 21, Contractors Consent for Background Check, and shall submit it in conjunction with the contractor’s request for either base or vehicle passes. Completion of a successful LEADS check does not invalidate the requirement for an escort when contractor or subcontractor personnel are working within controlled or restricted areas. All identifying credentials will be compliant with the REAL ID Act. Contractors shall ensure their employees and those of their subcontracts have the proper credentials allowing them to work in the United States. Persons later found to be undocumented or illegal aliens will be remanded to the proper authorities. The contractor shall not be entitled to any compensation for delays or expenses associated with complying with the provisions of this clause. Furthermore, nothing in this clause shall excuse the contractor from proceeding with the contract as required.

B. Badges: The contractor is required to provide identification badges for their employees. All contractor personnel shall wear these badges while on duty on the government site. Badges are required to identify the individual, company name, and be clearly and distinctly marked as contractor. Size, color, style, etc. are to be mutually agreed to by contractor and government. The contractor’s identification badge will not be used as an entry requirement for installation entry or into any government designated controlled or restricted area. All DBIDS cards/passes will be turned in to the Dixon Visitor Control Center upon expiration of pass and/or completion of contract.

C. Contractor Registration of Vehicles on Scott AFB: All contractor or contractor employees’ vehicles used for the performance of this contract shall comply with all local, state and federal regulations. Additionally any pass shall be surrendered to Security Forces upon demand to positively identify a person’s need to be on Scott AFB.

D. Access to Installation during Force Protection Conditions (FPCONs):

Contractors will be assigned a mission essential designation IAW requirements contained in SAFBI 31-101/Installation Security Instruction. Only the installation commander or the unit commander requesting contract support will assign the mission essential designation.

E. AT Level 1 training for Contractors: AFI 10-245-O published on 07 Dec 20 states 100% of contractors will complete AT Level I (Antiterrorism Awareness).

This is also a federal law under 48 CFR § 252.204-7004 that all contractors that work on federally funded projects will have this training. The new AFI states:

i. Contracting Squadron (CONS) Commanders:

(1) Coordinate performance work statement (PWS)/statement of work (SOW) and modifications with the installation Antiterrorism Officer/Antiterrorism Program Manager (ATO/ATPM) to ensure AT considerations and measures are included in all applicable contracts and that all AT standards are in compliance. (T-1).

(2) Coordinate with the installation ATO/ATPM to ensure Level I - AT Awareness Training is completed by all contractors within 30 days of requiring access, and annually thereafter. (T-3). Coordination for training should be done by the requiring unit after contract award.

(3) Work with ATO/ATPM to coordinate AT-specific contracting measures for inclusion in the installation‘s AT Plan. (T-2).

(4) Coordinate necessary background investigations for contractors with the installation information protection office and work with the ATO/ATPM to develop mitigation measures that limit the potential for terrorist and insider threats posed by contractors while on the installation. (T-1)

(5) Incorporate required AT clauses, related supplements, and local AT measures as part of requirements for DoD contracts, as described in Standard

18. (T-0)

F. Property Protection: Property protection for facility where the contractors’ primary work center is located will be the responsibility of the local facility manager and local Government Security Manager, or their duly authorized representative IAW AFI 31-101, Integrated Defense and command/local directives. The contractor shall safeguard all government-owned equipment and materials in his/her possession or use.

G. Safeguarding Classified or Unclassified Information: The contractor shall meet Air Force standards for storing, processing, and handling classified information and systems. Additionally, all resources (e.g. maps, publication/instructions, photos) provided by the government to assist the contractor in the performance of their contract will be surrendered upon termination of employment or the end of the contract performance period.

H. Non-Disclosure Agreements: To safeguard information, the contractor shall enter into non-disclosure agreements with the responsible local security manager.

I. Privacy Act: Work on this project requires that personnel have access to Privacy Information. Personnel shall adhere to the Privacy Act, Title 5 of the U.S. Code, Section 552a and applicable agency rules and regulations.

J. Contractors Working in Controlled or Restricted Areas: The unit requesting contract support will provide escort (s) for contractors’ at all times when within a controlled area. Contractors shall not escort other contractor employees within controlled or restricted areas. In addition, contractors shall fulfill, maintain, and comply with all security requirements IAW AFI 31-101, Integrated Defense, and command/local directives.

K. Access to Government Facilities with Controlled or Restricted Areas: The contractor shall comply with security regulations imposed by the installation commander and/or the agency responsible for the project location. Due to specific mission requirements inherent in the nature of controlled or restricted areas on Scott AFB, the government may direct the contractor to leave the controlled or restricted areas at any given time.

L. Contractors Responsibilities while Working within Controlled or Restricted Areas: Only contractor personnel with proper authority and qualifications shall enter a controlled or restricted area. Certain facilities require the issuance of an AF Form 1199CD. The government, at any time, may revoke the AF Form 1199CD.

The procedures for the issuance of an AF Form 1199CD are contained in SABFI 31- 1 Integrated Defense/Antiterrorism Plan. Contractors shall not escort other contractor employees within controlled or restricted areas. Upon completion of the contract, all 1199CDs will be turned into the sponsor and in turn delivered to 375th SFS/S5B, Line Badges. In addition, contractors shall fulfill, maintain, and comply with all security requirements contained in SABFI 31-1 Integrated Defense / Antiterrorism Plan.

M. Access to Government Facilities with Controlled or Restricted Areas for Replacement Contractors: The unit requesting contract support will continuously escort replacement contractors, not initially possessing the proper clearances and requiring entry to controlled or restricted areas. Replacement contractors shall submit paperwork within 30 days of being assigned to obtain an approved security clearance or favorable review. Replacement contractor personnel shall obtain a security clearance prior to working with, or having direct access to, classified material. In addition, replacement contractor personnel shall obtain a “Favorable review” prior to having access to a Controlled Area. The above information shall be submitted to 375 AMW/IP.

15. Non-Personal Services and/or Inherently Governmental Services: The Government will neither supervise contractor employees nor control the method by which the contractor performs the required tasks. It shall be the responsibility of the contractor to manage its employees and to guard against any actions that are of the nature of personal services, or give the perception of personal services. If the contractor feels that any actions constitute, or are perceived to constitute personal services, it shall be the contractor's responsibility to notify the contracting officer immediately. These services shall not be used to perform work of a policy/decision making or management nature, (e.g., inherently governmental functions). All decisions relative to programs supported by the contractor shall be the sole responsibility of the Government.

16. PROJECT MANAGER: The 375th Civil Engineer Squadron Project Manager for this project is William Sarocco, 618-256-2683. The Project Manager is the point of contact for all matters of design and, unless a construction inspector is designated, construction. For matters going to terms and conditions of the contract with the Government, the 375th Contracting Squadron’s designated official is the point of contact.

B. Tank Access, Fuel Transfer and Filtering
C. Internal Cleaning
D. Tank Inspection
5. GENERAL CONDITIONS: