This is a Statement of Work (SOW) for canvas awning replacement and aluminum frame maintenance on the USCGC ISAAC MAYO, a Fast Response Cutter operated by the United States Coast Guard. The work encompasses removal of existing canvas covers and lacing from awnings on the 01 Deck and Fantail, visual inspection of all awning support structures and mounting hardware with documented discrepancies and repair proposals, cleaning of existing aluminum awning frames using chemical and/or mechanical methods to remove corrosion, application of outdoor protectant coating to exposed aluminum, and installation of new color-matched canvas awnings with lacing and required mounting hardware. The contractor must provide all protective coverings to seal work areas against contamination, furnish all access equipment including ladders, scaffolding, or man lifts, and return all affected vessel components to original condition upon completion. The work is scheduled to occur during the vessel's inport availability from June 27 to July 18 at USCG Sector Key West, 100 Trumbo Point Road, Key West, Florida 33040, with point of contact ENS Genevieve Brewer.

The related federal contract opportunity indicates the USCG intends to award this work on a sole-source basis to Pipe Dreams under FAR 13.106-1(b)(1) and FAR 6.302-1 due to the highly customized nature of the FRC awnings, lack of government data rights, design complexity requiring precise measurements with significant boat-to-boat variations, and the determination that reverse-engineering would substantially duplicate costs. The contract will be issued as a firm-fixed-price purchase order. References include Coast Guard Drawing 154 WPC-613-201 (Rigging & Covers) and Surface Forces Logistics Center Standard Specifications 0000 (General Requirements), 0740 (Welding and Allied Processes), and 6310 (Preservation of Ship Structures).

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Canvas Awning Replacement Clean, Inspect, and Coat Aluminum Frame On CGC ISAAC MAYO

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to renew the canvas awnings on the 01 Deck and the Fantail. In addition, to inspect, clean and coat the installed aluminum frame. This work is to be performed on the Coast Guard Cutter Isaac Mayo during their scheduled inport period.

1.2 Government-furnished property.

None

2. REFERENCES

2.1 Coast Guard Drawings.

Coast Guard Drawing 154 WPC-613-201, Rev C, Rigging & Covers A&D

2.2 Coast Guard Publications.

· Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements

· Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and Allied Processes

· Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures

2.3 Other References.

None

3. REQUIREMENTS

3.1 General.

3.1.1 CIR. None.

3.1.2 Tech Rep. Not applicable

3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.

3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Any disturbed mounting hardware shall be replaced with new. Known interferences include, but are not limited to the following:

· GPS/Radio Antennas

· Screen Panels

3.1.5 Ladders, Scaffolding, Man Lift. The contractor shall provide all required equipment for access to the awnings for removal and installation.

3.1.6 Canvas Removal. The contractor shall remove existing canvas covers and lacing and remove from property for disposal.

3.1.7 Awning Frame Inspection. The contractor shall conduct a visual inspection of all awning support structures and mounting hardware. Any discrepancies shall be documented and a proposed repair plan provided via CFR to KO. Any disturbed mounting hardware shall be replaced with new.

3.1.8 Awning Piping Cleaning and Protectant Application. The contractor shall remove all visible corrosion from existing awning frame using chemical and/or mechanical methods and coat the exposed aluminum with an outdoor protectant. Any chemical applied shall have current SDS provided for ships records.

3.1.9 Awning Installation. The contractor shall install new color matched to existing awning, lacing and any required mounting hardware. Canvas shall be tensioned to ensure a tight application.

4. NOTES

4.1 This Scope of Work was generated by:

USCGC ISAAC MAYO

100 Trumbo Pt. Rd.

Key West, FL, 33040

(305) 432-7419

4.2 The following are the U.S. Coast Guard vessels that the work is to be performed on and the availability for installation:

4.2.1

USCGC ISAAC MAYO

100 Trumbo Pt. Rd.

Key West, FL, 33040

(305) 432-7419

· Expected installation dates are during the vessel’s inport availability, 27JUN-18JUL.

· POC: ENS Genevieve Brewer

· Work Location: USCG Sector Key West, 100 Trumbo Pt. Road, Key West, FL 33040.

Scope of Work