SOW Attachment 1 - PG 18-15 Vol C - AE Submission Instr.pdf
PDF 235 KB Posted
- Solicitation number
- 36C77621R0130
About this file
This announcement is a request for Standard Form 330 Architect-Engineer Qualifications packages for a design contract. The Veterans Health Administration Program Contracting Activity Central is seeking sources for a firm-fixed price design contract to provide Architect-Engineering services for the Construct Addition And Renovations To Joint Ambulatory Care Center project located in Pensacola, Florida. The scope of work includes investigative and feasibility design, schematic design, design development, construction documents, bid documents, specifications, calculations, cost estimates, narratives, solicitation support, and construction period services. Submissions are due by July 6, 2021. A two-phase evaluation process will be followed to shortlist firms for interview presentations, with the highest rated firm to be selected for negotiations. The contract has a 100% SDVOSB set-aside and is valued between $10-20 million.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Mod to Previous Pre-Sol 2 - 36C77621R0130.docx | DOCX document | |
| Mod to Previous Pre-Sol 1 - 36C77621R0130.docx | DOCX document | |
| PPQ - Pensacola JACC.docx | DOCX document | |
| Final SOW - Pensacola JACC Minor Design.pdf | ||
| SOW Attachment 3 - Proposed Layout Drawings 2-18-2021.pdf | ||
| SOW Attachment 2 - AE CPM Schedule Specs.pdf | ||
| Request for SF 330s 36C77621R0130.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Program Guide, PG-18-15, Volume C Nov 2008
Department of Veterans Affairs
VA Medical Center Projects
A/E Submission Instructions for Minor and NRM Construction Program:
Schematics Design Development Construction Documents
Program Guide, PG-18-15, Volume C Page i May 2006
Department of Veterans Affairs Washington, DC 20420
FOREWORD
This document states the minimum requirements for each submission in the production of VA Schematics, Design Development, and Construction Documents for Minor and NRM Construction Program for Medical Center Projects. It will give VA reviewers and the A/E a clear understanding of what is required of the A/E at each stage of design.
This document does not relieve the A/E firms of their professional responsibility to produce a correct, complete, and fully coordinated set of construction documents.
Lloyd H. Siegel William W. Graham Director, Facilities Quality Office (Acting) Director, Engineering Management and Field Support Office
Program Guide, PG-18-15, Volume C 1 November 2008
A/E SUBMISSION INSTRUCTIONS FOR
MINOR AND NRM CONSTRUCTION PROGRAM
MEDICAL CENTER PROJECTS
Table-of-Contents
I. GENERAL
A. INTRODUCTION
B. A/E RESPONSIBILITIES
C. SUBMISSION POLICY
D. QUALITY ASSURANCE/QUALITY CONTROL
E. ADDITIONAL SERVICES
F. CRITICAL PATH METHOD
II. SUBMISSIONS
A. SITE DEVELOPMENT
B. ARCHITECTURAL
C. FIRE PROTECTION
D. INTERIOR DESIGN
E. STRUCTURAL
F. PLUMBING
G. SANITARY
H. HVAC
I. ELECTRICAL
J. EQUIPMENT
K. SPACE PLANNING
L. CRITICAL PATH METHOD (CPM)
M. ESTIMATING
N. SPECIFICATIONS
O. FINAL BID DOCUMENTS
III. DISTRIBUTION OF A/E MATERIAL
A. SYMBOL IDENTIFICATION OF CONTRACT DRAWINGS
B. GENERAL NOTES
Program Guide, PG-18-15, Volume C 2
A/E SUBMISSION INSTRUCTIONS FOR
MINOR AND NRM CONSTRUCTION PROGRAM
MEDICAL CENTER PROJECTS
I. GENERAL
A. INTRODUCTION
1. This document contains information and minimal submission requirements for contract documents specified in the A/E contract. If the A/E determines that additional information is vital and necessary for the project’s success, the information shall also be included during the submission process at the appropriate phase as agreed to by VA.
2. The Department of Veterans Affairs (VA) is procuring a contract with an Architect/Engineer (A/E) for a project that will require a submittal at all phases of the design process: Schematics, Design Development, and Construction Documents.
3. Coordinate all activities with the VA Medical Center (VAMC). Hold informal meetings (upon mutual consent of the VA and the A/E) at the VAMC to discuss the design and related issues. Continue to expand contacts by telephone, rough sketch studies and other means of communication with the purpose of finalizing a general design approach to be followed.
4. Final approved Schematic documents shall be the basis for the development of the Design Development phase. Likewise, final approved Design Development documents shall be the basis for the development of the Construction Documents phase. The VAMC must approve any changes from each set of documents before the A/E proceeds to the next phase.
5. VA will review all submittals for functional and aesthetic relationships. However, no further functional decisions are anticipated after the Design Development phase.
6. Provide a design narrative/analysis for each technical discipline (e.g., architectural, mechanical, fire protection, etc.) which describes the intent of each discipline with schematic and/or design development submission.
7. Provide computations and sizing calculations for electrical, mechanical (HVAC, plumbing, and steam), sanitary, structural and fire protection designs. For computerized calculations, submit complete and clear documentation of computer programs, interpretation of input/output, and description of program procedures.
8. Provide individually packaged drawings for each submission to each unit specified in the "Distribution of A/E Materials" section.
Program Guide, PG-18-15, Volume C 3
9. Submit a complete set of final approved drawings incorporating all revisions, within 30 days after completion of the Schematics and Design Development stages.
10. At each review stage, the VA’s technical reviewer, a value-engineering consultant, or a construction manager will perform a value engineering review.
11. Submit all completed documents in the following format(s):
a. Design Submittals, Complete PDF Binder.
b. Bid Documents (Drawings), PDF Binder(s) of each construction trade & Autodesk AutoCAD 2020 .dwg files organized in folders as appropriate.
c. Specifications, Complete PDF Binder(s), Individual Word Document files (filenames are to include the specification section number as well as the title of the specification).
d. Completed BIM Model, Autodesk Revit 2020.
e. Renderings, lossless PNG.
All files are to be provided to VA organized on a DVD(s). Submit any special instructions on the use of the DVD(s) in a PDF located in the root directory on the disk(s).
In addition to the above, submit physical copies of all documents as required by the agreement and as indicated in this document.
B. A/E RESPONSIBILITIES:
1. Contract documents shall meet or exceed the requirements of this document.
2. The A/E is responsible for producing a complete set of drawings, design narrative/analysis, calculations, sample boards, and specifications in accordance with professional standard practices and VA criteria. Each A/E discipline shall receive a copy of their respective VA design manuals, standard details, construction standards, and VA National CAD Standard Application Guide. The AE is responsible for obtaining the NCS.
3. A/E shall conduct coordination meetings between A/E technical disciplines before submitting material for each VA review and provide minutes of the meetings to VAMC.
4. A/E shall adhere to the approved Memorandum of Agreement (MOA).
5. A/E shall provide a checklist of all submittals, certifications, tests, and inspections required per drawing and specification section.
6. In addition, the A/E shall conduct interim fire protection installation inspections and witness final fire protection equipment testing.
C. SUBMISSION POLICY:
1. There is a Schematic* submission, a Design Development (DD**) submission, and a Construction Document (CD***) submission indicated in this guide. The VAMC may alter the submission requirements depending upon the complexity of the project by adding or deleting certain reviews. Where additional reviews might be required, the
Program Guide, PG-18-15, Volume C 4
VAMC will issue, at their discretion, a detailed “Statement of Task” or supplemental instructions to the A/E, which would be provided at the time of solicitation for a fee proposal.
2. At each submission, the A/E shall date all material and present the designs on VA standard size drawings that are appropriately labeled, "SCHEMATIC
SUBMISSION", “DESIGN DEVELOPMENT SUBMISSION”, OR “CONSTRUCTION
DOCUMENT SUBMISSION”, in large block letters above or beside the VA standard drawing title block. In each submission, the A/E shall incorporate the corrections, adjustments, and changes made by VA at the previous review.
D. QUALITY ASSURANCE/QUALITY CONTROL (QA/QC):
In an effort to reduce construction change orders due to design errors and omissions, the Office of Facilities Management has initiated a Quality Assurance/Quality Control program. The A/E shall develop, execute, and demonstrate that the project plans and specifications have gone through a rigorous review and coordination effort.
The requirements are as follows:
1. Fee Proposal: Provide an outline of the actions that your firm will take during the design process along with an associated fee.
2. Two Weeks after Receipt of the Notice of Award: Submit a detailed QA/QC Plan describing each step that will be taken during the development of the various phases of design. Each step should have an appropriate space where a senior member of the firm can initial and date when the action has been completed.
3. 100% Submittal: Submit the completed QA/QC Plan along with the latest marked-up documents (plans, specifications, etc.) necessary to ensure that a thorough review and coordination have been completed.
E. ADDITIONAL SERVICES:
If additional services (i.e. surveys, soil borings, asbestos surveys, water flow testing, or lead surveys), are necessary to be performed by consultants, submit criteria for the work to be performed to the VAMC Contracting Officer as soon as possible. Upon approval of the criteria, submit proposals and qualifications of at least three firms being considered for the work in accordance with the contract procedures (CP1) of the contract, together with a proposal from the recommended firm and a brief justification for its selection, for VA approval. A/E should submit survey information for the Schematic Review.
F. CRITICAL PATH METHOD PHASING MEETINGS
A. If required and prior to submission of Schematic material, the A/E shall meet with the VAMC’s Project Manager to discuss and outline phasing requirements for the
Program Guide, PG-18-15, Volume C 5 project. These phasing requirements shall describe the general sequence of the project work, estimated project duration, and what Government constraints will exist that will influence the Contractor's approach to the construction project. The A/E shall be responsible for recording the phasing requirements.
B. Submit a phasing narrative and phasing plans (on reduced size plans) within two weeks after each phasing meeting to the VAMC Project Manager. VA will review these submission(s) and return comments to the A/E within two weeks of receipt. The A/E will then use this information in preparing their schematic, design development, and construction document submissions.
II. SUBMISSIONS
A. SITE DEVELOPMENT: Submit the following:
Site Development: Schematics* DD** CD***
Narrative Analysis of site Circulation study at new parking areas Phasing analysis Parking analysis (existing and new) Development concept showing proposed new construction locations
Landscape drawings with plant groupings
Existing Topographic, utility, and landscape surveys of all new areas of construction and their impact(s) of surrounding/adjacent areas
Demolition plan indicated all existing structures and features which are to be removed or reworked
Layout plan showing location of existing:
Building and structures Roads Fire Access New parking areas showing indicating field spaces plus:
New accessible spaces New van spaces
New Mechanical and electrical equipment on grade
Program Guide, PG-18-15, Volume C 6
Site Development: Schematics* DD** CD***
Indicate future expansion Indicate Service area(s) Entrances and exits Walks Drop Inlets Contractor's staging area Paving joint patterns as applicable Grading plan showing:
Existing contours at new parking areas
Proposed contours at new parking areas to confirm adequate drainage
Spot elevations at new site elements i.e. parking areas, curbs, walks, etc.
Rim and invert elevations at new storm drainage fixtures (new parking areas)
Erosion and sediment control measures at all areas of new work
Planting plan at new parking areas showing:
List of plant material Limits of new irrigation required Site details Parking and landscape details Site Signage plan and schedule Specifications
Program Guide, PG-18-15, Volume C 7
* Submit site and landscape plans at an appropriate scale to show all work involved.
** Submit site and landscape plans at same scale as topographic/utility survey incorporating all of the revisions required by comments from schematics.
*** Submit fully dimensioned, complete, and coordinated site and landscape plans incorporating all revisions required by comments from the design development phase.
Program Guide, PG-18-15, Volume C 8
B. ARCHITECTURAL: Submit or show the following:
Architectural: Schematics* DD** CD***
Location of:
Rooms1 Doors Corridor(s) Basic column grid/sizes Expansion and seismic joints Electrical closets Information Technology and telephone closets
Mechanical spaces Stair(s) Floor Plans/Drawings:
All floor new and renovated floor areas and their relationship to existing spaces
Roof plan(s) Reflected ceiling2 Equipment floor plans 1:50 (1/4 inch) scale3
Demolition plans4 Room names and numbers5 Program net/designed net Exterior dimensions/total existing and additional building gross area(s)
Size and shape of all departmental functions and services6,7
Exterior building elevations8 Finish floor elevations9 Door locations, sizes, and swings Wall thickness and chase walls Handrail location/dimensions Fixed equipment Equipment elevations and details Plumbing fixtures Wheelchair accessible facilities Wall sections10 Building sections11 Finish grades at new interior and exterior floor areas.
Fire and smoke rated partitions
Program Guide, PG-18-15, Volume C 9
Architectural: Schematics* DD** CD***
Fire extinguisher cabinets Spray-on fire proofing (see fire protection)
Construction details12 Drafting symbols, abbreviations, and general notes
Door and window schedules Interior details, elevations, sections Finish schedule13 Graphics and signage Interior Color Renderings
* Submit, as a minimum, a single line layout for at a scale not less than 1:100 (1/8 inch). A scale of 1:200 (1/16 inch) is acceptable for architectural floor layout if an entire floor cannot be shown on one sheet. Submit a complete double line layout of areas of critical importance, at a scale of 1:50 (1/4 inch) including equipment.
** Submit minimum 1:100 (1/8 inch) scale floor plans, new and renovated, incorporating all of the revisions required by comments from schematics.
*** Submit fully dimensioned, complete, and coordinated 1:100 (1/8 inch) scale floor plans, incorporating all revisions required by comments from the design development phase.
B. NOTES:
1. Use lines between spaces to indicate the centerline of the partition (for schematics only).
2. Indicate ceiling mounted equipment, lighting fixtures, air diffusers, registers, tracks, furr-downs, and other significant elements.
3. Identify all equipment for each room. Indicate and coordinate all equipment with the Equipment Guide List (Program Guide 7610) and Activated Equipment List. Use VA standard symbols and notation to distinguish between contractor-furnished and installed (CC), VA-furnished contractor-installed (VC), VA-furnished and installed (VV), VA-furnished with construction funds [VC(CF) and VV(CF)], and relocated (R) equipment.
Equipment floor plans are not required for the offices, consultation rooms, classrooms, conference rooms, and waiting rooms within the above departments. Draw equipment details which are necessary for major decisions, though complete detailing is not required for this submittal.
4. Indicate existing finish schedule and notes on plan.
Program Guide, PG-18-15, Volume C 10
5. Label as required for schematic drawings. Coordinate new room numbering with medical center.
6. Use the same names on drawings as those used in the space program. Provide area figures in fractional form, e.g., 400/390. Indicate space provided, but not called for in the space program, as: -/390.
7. Label each service or activity listed in the Project Scope Data of the Design Program and indicate boundaries with a distinctive line. Include the activity code number (see Handbook 7610).
8. If the project requires exterior work, show all facades indicating massing, proposed fenestration and the building relationship to adjacent structures and the finish grade.
Show all significant building materials, including their colors, any proposed roof top mechanical equipment, architectural screens, skylights, and stacks on the elevation drawings. If building is designed for future expansion (vertical and/or horizontal), delineate elevations with and without the future expansion. If project is an addition, show elevations of the existing building in sufficient detail to illustrate the relationship between the new and existing in terms of scale, material, and detail.
9. Define the relationship of the finish ground floor to finish grade at all entrances.
10. Indicate construction including fire resistance rating, building materials and systems, and proposed sill and head heights of openings. Indicate both new and renovated areas on form provided by VA.
11. Define building configuration. Draw sections at the same scale as floor plans, normally 1:100 (1/8 inch). Where new construction abuts an existing structure, indicate in the section how the new floor elevations align with existing.
12. Indicate new building components and systems, such as window design, roofing system, building "skin", and any special architectural elements for the project. Complete detailing of miscellaneous items is not required for this submission.
13. Indicate all building systems, materials, and future expansion, as applicable.
Program Guide, PG-18-15, Volume C 11
C. FIRE PROTECTION: Submit the following:
Fire Protection: Schematics* DD** CD***
Fire protection narrative:1 Fire and smoke separation Fire sprinkler/standpipe system Size of fire pumps Water supply available/max.
demand
Water flow testing results Fire alarm systems2
Base loop system for interface of new construction
Size of air handling unit Exit paths from each zone Distances to stairs Occupancy of each area Exit calculations for each floor Smoke control features Floor Plans/Drawings:3 & 4 Sprinkler zones Fire alarm zones Smoke zones Building water supply Interior sprinkler supply lines Standpipes Fire extinguisher cabinets Fireproofing of structural members Sprinkler/standpipe riser supply piping
Termination of sprinkler main and inspector test drains
Sprinkler alarm valves Waterflow and tamper switches Sprinkler system fire department connections
Sprinkler design hazards per
NFPA 13
Exit signs and emergency lighting Occupied areas not protected by automatic sprinklers
Calculations
Program Guide, PG-18-15, Volume C 12
Estimated capacities for proposed air handling units in cubic meters (cubic feet) per minute
Location of and integration of new with existing:
Fire alarm system Annunciator panels Pull stations Flow switches Audio-visual devices Smoke detectors Duct smoke detectors Smoke dampers Fire dampers Fire alarm risers5 Exit signs Emergency lighting Fire sprinklers Standpipes Fire hydrants Fire pumps Post indicator valves Sectional valves Fire extinguisher cabinets Electromagnetic door hold open devices
Wall sections indicating fire resistive ratings
Excavation plan signage Door and window schedule with fire rating or fire rated glazing
Zoning of each fire alarm initiating device
Details:
Fire pump system (capacity and pressure)
Elevation and isometric view of fire pump
Stairwell sign Annunciator panel Interconnection of fire alarm system with:
Smoke dampers
Program Guide, PG-18-15, Volume C 13
Air handlers Elevator controls Kitchen fire extinguishing and fire pump system
HVAC system with smoke duct detectors
Single line riser diagram for fire alarm system
(1/8 inch). Submit a complete double line layout of areas of critical importance, at a scale of 1:50 (1/4 inch) including equipment.
** Submit minimum 1:100 (1/8 inch) scale floor plans, new and renovated, incorporating all of the revisions required by comments from schematics.
*** Submit fully dimensioned, complete, and coordinated 1:100 (1/8 inch) scale
C. NOTES:
1. Indicate NFPA 220 and UBC fire resistive rating of the building, NFPA 101 occupancy type, and fire protection code analysis to access compliance with NFPA 101.
2. Determine type, features, age, reliability, compliance with present day codes, capacity, zoning, supervision, control panel and power supplies, initiating devices and circuits, and auxiliary functions for existing fire alarm system. Indicate manufacturer, model number, voltage, and wiring style of existing alarm systems and devices. Provide recommendations for the proposed fire alarm work.
3. Provide information to meet JCAHO requirements; e.g. location of all fire rated barriers, smoke barriers, exit signs, fire extinguishers, manual pull stations, smoke detectors, and sprinkler flow switches. Show all interim life safety measures such as temporary systems Fire Alarm, Sprinkler, and Smoke.
4. At DD Submission, add room names, room numbers, door locations and swings, smoke and fire rated partitions, sprinkler/standpipe risers to floor plans. Add location of all valves (post indicator, sectional) and backflow preventer as provided.
Program Guide, PG-18-15, Volume C 14
5. Show new equipment and/or the necessary changes involved if modification to the existing system is required. Include any recommendations where certain requirements of VA criteria might be waived, in order to allow the existing equipment to be reused.
Program Guide, PG-18-15, Volume C 15
D. INTERIOR DESIGN: Submit the following:
Interior Design: Schematics* DD** CD***
Written interior design concept1 Illustrate overall design solution2 Material and finish samples Sketches Design solution for interior spaces:
Perspectives Plans Details Elevations Sections Wayfinding Floor patterns Wall patterns Lighting Signage Handrails Bumper guards Specification section 09050 Finish schedule Exterior colors and materials Sample boards for interior and exterior materials, products, and finishes
Edited carpet and wallcovering specifications
Keyed Finish plans Interior design details, elevations, and sections scale of 1:50 (1/4 inch) including equipment.
** Submit minimum 1:100 (1/8 inch) scale floor plans, new and renovated, incorporating all of the revisions required by comments from schematics.
*** Submit fully dimensioned, complete, and coordinated 1:100 (1/8 inch) scale
D. NOTES:
Program Guide, PG-18-15, Volume C 16
1. Provide a document of data collected in interior design programming. Include collection and analysis of data from the VAMC project coordinator and interior designer.
Data includes, but is not limited to the following: existing interior and exterior design and materials, light, safety, patient profile, customer’s “vision” or desired image, public vs.
private spaces, complete signage package, goals of customer, relationship to existing facilities, future expansion/renovation plans, regional influences, etc.
2. Discuss and illustrate the overall design solution for the primary areas of the project using marked-up floor plans, loose sketches, and material and finish samples. Use broad categories of materials, finishes, color palettes, patterns, textures, and scales.
Separately group all major neutral background materials and finishes that will be used and discuss how they will be integrated with all other materials and finishes on the project. Include all primary and secondary corridors, typical patient and toilet rooms, lobbies, atriums, eating spaces, chapels, waiting rooms, and exam rooms. Show the relationship among departments and functions, and between public and private spaces.
Program Guide, PG-18-15, Volume C 17
E. STRUCTURAL: Submit the following:
Structural: Schematics* DD** CD***
Investigation of existing structural system to ensure feasibility6
Three alternative structural systems for typical bays1
Supporting calculations2 Cost estimates for each system3 Recommend preferred system Column locations Shear load resisting elements4 Structural plans6 Sections Details Size/location of:
Columns Beams Lateral load resisting elements Load bearing walls Slabs Foundations Elevations Schedules General notes Subsurface investigation report Estimated quantity of rock Specifications
* Submit, as a minimum, a single line layout for at a scale not less than 1:100 (1/8 inch). Submit a complete double line layout of areas of critical importance, at a scale of 1:50 (1/4 inch) including equipment.
** Submit minimum 1:100 (1/8 inch) scale floor plans, new and renovated, incorporating all of the revisions required by comments from schematics.
*** Submit fully dimensioned, complete, and coordinated 1:100 (1/8 inch) scale
E. NOTES:
1. When only one structural system is possible due to other project requirements, include an explanatory statement and submit only that structural system.
Program Guide, PG-18-15, Volume C 18
2. Include vertical and lateral load design for CD submission.
3. Include foundation and fireproofing where required.
4. Indicate existing utilities and structures within, adjacent, or contiguous to the new construction.
5. Upon approval of the subsurface investigation criteria, submit qualifications of at least three consultants being considered for the work together with the proposal of the consultant recommended as most qualified.
6. If there is only a CD submission, provide a Structural Engineering Analysis Submission within six weeks from the notice of award including sketches, calculations, and cost estimates of three alternative structural systems for typical bays, boring location plan for subsurface investigation, and consultant qualifications. For vertical expansion projects, analyze existing structure for structural feasibility.
Program Guide, PG-18-15, Volume C 19
F. PLUMBING: Submit the following:
Plumbing: Schematics* DD** CD***
Narrative:
Existing plumbing systems to be used and necessary modifications
New plumbing systems Floor Plans/Drawings:
Room names Identify
Existing plumbing fixtures w/VA numbering system
New plumbing fixtures w/VA numbering system
Existing equipment New equipment New medical gas outlets New instrument air outlets New laboratory gas outlets Plumbing piping
Size of pipe Equipment schedule Fire & smoke partitions Demolition plans Riser diagrams Legend, notes, and details Location and size of sprinkler riser, standpipes, and fire pumps (see fire protection)
Location of emergency eyewash and shower equipment
Calculations (equipment & piping) List of Required Contract
Contract Specifications
(1/8 inch).
** Submit minimum 1:100 (1/8 inch) scale floor plans, new and renovated, incorporating all of the revisions required by comments from schematics phase.
*** Submit fully dimensioned, complete, and coordinated 1:100 (1/8 inch) scale
Program Guide, PG-18-15, Volume C 20 development phase. Submit a complete double line layout of areas of critical importance, at a scale of 1:50 (1/4 inch).
Program Guide, PG-18-15, Volume C 21
G. SANITARY: Submit the following:
Sanitary: Schematics* DD** CD***
Narrative:
Existing sanitary systems:
underground water, sanitary sewers, storm sewers, & fuel gas with sources, disposal methods, storage pressures, condition, etc.
New sanitary systems Provide water analysis & expected yield if well required
Utility Plans/Drawings showing existing and new sanitary systems as required:
Size of pipes Invert elevations of sewers Locate/size
Pumps Storage facilities Treatment equipment Fire hydrants Sectional and post indicator valves
Backflow preventer Areas of new irrigation system if applicable.
Profiles of sanitary & storm sewers if new.
Demolition Plans Legend, notes, and details Point of connection to sprinkler system Calculations List of specifications Contract Specifications
* Submit utility drawings at same scale as provided for Site Development drawings.
** Submit utility drawings at same scale as provided for Site Development drawings, incorporating all of the revisions required by comments from the schematics phase.
*** Submit utility drawings at same scale as provided for Site Development drawings, incorporating all of the revisions required by comments from the design
Program Guide, PG-18-15, Volume C 22 development phase. Submit legend, notes, and details at a scale not less than 1:100 (1/8 inch).
Program Guide, PG-18-15, Volume C 23
H. HVAC: Submit the following:
HVAC: Schematics* DD** CD***
Description of HVAC systems Equipment for each functional space Life cycle cost analysis1 Tentative location/sizes:
Mechanical equipment room(s) Principal vertical shafts Block layout of equipment Louvers:2 Outside air Exhaust air Relief air Engineering calculations3 Selection of HVAC equipment Catalog cutsheets of equipment Room by room heating and cooling loads
Zone by zone heating & cooling loads Building block heating & cooling loads Tabulation of steam consumption Psychometric chart for air handling unit Coil entering and leaving conditions Fan motor heat gains Consumption of humidification loads Sound/acoustic analysis Room-by-room air balance charts4 Chilled water plant:5 Quantity and type of chillers Capacity in tons of refrigeration Electrical equipment Heating system:
Total heating load Domestic hot water load Humidification load Equipment steam demand Zoning of heating system
HVAC floor plan:6
Program Guide, PG-18-15, Volume C 24
Main supply, return and exhaust ductwork
Volume dampers Fire and smoke partitions Fire and smoke dampers Smoke detectors Automatic control dampers Air quantities for each room Air inlets/outlets Rises and drops in ductwork Expansion loops Anchors Vales Drip assemblies Balancing fittings Interconnection of HVAC equipment with fire protection equipment (see fire protection)
Plan/section of mechanical equipment rooms
Schematic flow and riser diagrams7 Schematic control diagrams8 HVAC demolition drawings Phasing plan Equipment schedule Seismic bracing VA symbols and abbreviation Selection of Pumps Fans Sizing and selection of Expansion tanks Steam to hot water convertor Heat exchangers Sound analysis Complete selection data Outside chilled water and condenser water distribution9
Standard detail drawings Automatic temperature control drawings10
Program Guide, PG-18-15, Volume C 25
HVAC specifications
(1/8 inch). Submit a complete double line layout of areas of critical importance, at a scale of 1:50 (1/4 inch) including equipment.
** Submit minimum 1:100 (1/8 inch) scale floor plans, new and renovated, incorporating all of the revisions required by comments from schematics.
*** Submit fully dimensioned, complete, and coordinated 1:100 (1/8 inch) scale
H. NOTES:
1. Provide specific design recommendations and full back-up data. Include the heating and cooling capacities of each functional area and the block cooling and heating loads for each new and/or existing building.
2. The locations of these louvers must not allow short circuiting of air from emergency generator exhaust or truck waiting and loading dock areas into air intake etc. Consider factors affecting louver location such as visibility, historical considerations, wind direction, nuisance, and health hazard odors (from emergency generator or truck exhausts).
3. Include room-by-room, peak zone-by-zone, and building block heating and cooling loads. Provide a tabulation of steam consumption based on data from all sources. Show correlation between each HVAC zone boundary and architectural floor area correlation between the architectural room numbers and abbreviated/coded room numbers used with computer input data sheets.
4. Show supply, return, exhaust, make-up, and transfer quantities with intended pressure relationships, i.e. positive, negative, or zero with respect to adjoining spaces.
5. Provide pertinent data on accessories such as pumps and cooling tower etc. Show the extent of the outside chilled water and condenser water piping. Clearly show how the piping will be laid in tunnels, trenches, or by direct burial.
6. Show ceiling clearances, at locations where ducts cross each other, by providing 1:50 (1/4 inch) scale local sections. Show all ductwork and piping 150 mm (6 inch) and larger in double line. Show separate floor plans for air distribution and piping unless waived by VA. Show clearances required for access and maintenance with coil and tube pull.
Program Guide, PG-18-15, Volume C 26
7. Show typical air handling systems and all hydronic systems with existing capacities and new estimated loads. Verify actual operating conditions and capacities of HVAC systems prior to design.
8. Show control devices, such as, thermostats, humidistats, flow control valves, dampers, freezestats, operating and high limit sensors for all air systems and fluids, smoke dampers, duct detectors etc. Provide a written description of the sequence of operation on the floor plans. Detail the scope of work involved with the Central Engineering Center (ECC) and address if enough spare capacity is available or a new ECC is required. Show a point schedule for analog/digital input/output to be included in
ECC.
9. Show pipe sizes and insulation with plans, profile, sections, details, and all accessories, such as, anchors, expansion loops/joints, valves, manholes, capped and flanged connections, interface between the new and existing work (if any). Clearly indicate interferences (if any) with the existing utilities and/or landscape elements on outside piping layout drawings. Show rerouting any utilities, cuttings of roads, pavements, trees, etc., and the extent of new and demolition work. Outside utility drawings shall be based on the study of the latest site drawings, discussions with engineering personnel, and actual site inspection of the existing utility.
10. Show all duct detectors, control valves/dampers static pressure sensors, differential pressure control assemblies, etc., whose actual physical location is critical for the intended sequence of operation on floor plans.
Program Guide, PG-18-15, Volume C 27
I. ELECTRICAL: Submit the following:
Electrical: Schematics* DD** CD***
Narratives:
Design1 Life cycle analysis for electrical systems
Location and size of:
Electrical equipment2 Electric closets3 Telephone closets3 Signal closets3 Electrical distribution equipment Drawings showing:
Electrical plot plan of existing and proposed underground power (including manholes)
Telephone systems Signal inter-building systems Proposed electrical system4 Electric symbols Lighting fixture schedule Emergency Life Safety Equipment
(see fire protection)
Symbols, note, abbreviations List of specialty areas Method of short-circuit calculations Method of voltage drop and demand calculations
Utility company correspondence Utility company requirements Load calculations for normal & emergency use
Drawings:
Lighting layouts Power layouts Signal layouts Specialty area layouts Demolition plans Riser diagrams Branch circuit wiring (typ.)
Program Guide, PG-18-15, Volume C 28
Electrical: Schematics* DD** CD***
Location and size of:
Primary distribution switchgear/switchboard
Engine-generator sets Substation/pad-mounted transformer
Manholes Location of smoke dampers and duct smoke detectors
Interconnection of electrical control equipment with HVAC equipment
Smoke partitions and fire alarm zones Fire alarm and signal riser diagrams
Calculations for emergency generator(s)
Phasing scheme Electrical details scale of 1:50 (1/4 inch) including equipment.
** Submit minimum 1:100 (1/8 inch) scale floor plans, new and renovated, incorporating all of the revisions required by comments from schematics.
*** Submit fully dimensioned, complete, and coordinated 1:100 (1/8 inch) scale
I. NOTES:
1. Include basic assumptions, points of interconnection, impact of new construction to existing electrical distribution system, current demand loading (high voltage switchgear and primary feeder), and projected load of new construction. Propose various feasible electrical systems for project and provide advantages/disadvantages.
2. Include means and clearances for installation, maintenance, and removal/replacement of equipment.
3. Electrical, signal and telephone closets must stack vertically.
Program Guide, PG-18-15, Volume C 29
4. Include high voltage and low voltage switchgear, transformers and low voltage main and/or distribution panels, branch panels and methods of feeding 277/480 volt and 120/208 volt normal and emergency panels.
Program Guide, PG-18-15, Volume C 30
J. EQUIPMENT: Submit the following:
Equipment: Schematics* DD** CD***
Equipment (on architectural drawing) Activation Equipment List (Excel format)
(1/8 inch). Submit a complete double line layout of areas of critical importance, at a scale of 1:50 (1/4 inch) including equipment.
** Submit minimum 1:100 (1/8 inch) scale floor plans, new and renovated, incorporating all of the revisions required by comments from schematics.
*** Submit fully dimensioned, complete, and coordinated 1:100 (1/8 inch) scale floor plans, incorporating all revisions required by comments from the design
K. SPACE PLANNING
Schematics DD CD
Space-Accounting Summary Table 1 2 3
K. NOTES:
1. Provide a tabular table with columns entitled Departmental Function, H-7610 Requirements, Approved Space Program [Net Square Meters (Net Square Feet)], Variance Between H-7610 and Approved Space Program, Departmental Conversion Factor, Planned Departmental Gross Square Meters (Feet); column totals; and a Total Project Net to Gross Factor. Also, list separately the area required for additions to the program, unassigned space, major circulation (inter-departmental corridors, stairs, elevators), major mechanical and electrical spaces, exterior walls, connecting corridors to other buildings, space for future mechanical system expansion, and similar special requirements.
2. Update table. Justify in writing substantial deviations from the approved space program.
3. Update table.
L. CRITICAL PATH METHOD (CPM): Submit the following:
Critical Path Method (CPM)j: Schematics DD CD
Program Guide, PG-18-15, Volume C 31
Phasing Narrative Phasing Plans (on reduced site plans) Phasing Diagram Phases (marked on full size drawing) Written list of systems1 Phasing Diagram (drawn on Phasing Plan)1
CPM Phasing Plans (full size contract drawings)2
L. NOTES:
1. Include temporary system by phase and separate by technical discipline.
2. One drawing may reflect several reduced site plans.
M. ESTIMATING: Submit the following:
Estimating: Schematics DD CD
Cost estimate in compliance with Manual for Preparation of Estimates (separate estimates for new construction and alteration work)
Level "A" Summary Sheets for building Level "A" Summary Sheets for sitework Building gross area computation (new) Building gross area computation (alteration work)
Project Data Sheet 1 Project Data Sheet 1 and 2 Asbestos abatement Detailed estimate take-off sheets Level "B" Summary Sheets for buildings
Level "B" Summary Sheets for sitework Supplement A to SF 252 Detail Market Analysis
Program Guide, PG-18-15, Volume C 32
N. SPECIFICATIONS
Schematics DD CD
Specifications (All Disciplines) 1, 2. & 3 4 & 5
1. Submit for all technical disciplines the original VA Master Specification section drafts marked-up with pencil showing the editing for the project. Clearly identify modifications, deletions and insertions. Assure the specification drafts have been edited and tailored in their application to represent accurate coordination between drawings and specifications.
2. When no VA Master Construction Specification exists for a "unit of work", prepare the specification section consistent with VA Master Construction Specifications format.
a. Use generic or non-proprietary specifications describing the minimal acceptable product criteria level where no "Standard" exists to define quality and workmanship levels.
b. Use applicable "Standards" to define quality and workmanship when these publications exist. List complete designation and title of each publication used in Part 1; follow format in VA Master Construction Specifications for Applicable Publications.
c. Do not use proprietary specifications or systems that restrict competition unless authorization in writing has been received from the VA Project Manager for such proprietary specification. See the Federal Acquisition Regulation (FAR) Part 10, Part 14, and Part 36.
d. Do not use trade names or manufacturers brand names, except as previously noted.
e. When a deviation is requested, define and specify the minimum acceptable levels of essential criteria in descriptive, physical, functional, or performance requirements.
4. Type specifications in final format and content including any desk copy changes made by the VAMC staff at the previous review. Submit a complete set of the typed specifications for review. Include one set of full size final drawings of all disciplines, fully coordinated.
5. Return all draft specifications reviewed at DD review to aid the final bid document review. These draft specifications will later be returned to the A/E.
O. FINAL BID DOCUMENTS
a. Place the seal of the Registered Architect, Registered Landscape Architect, and Professional Engineer responsible for the design and the VAMC Project Director’s
Program Guide, PG-18-15, Volume C 33 signature on the Construction Documents. A stamp of the VAMC Project Director’s signature will be furnished.
b. Submit updated Department Ratio Chart of Final Bid stage to the VAMC Project
Manager.
Program Guide, PG-18-15, Volume C 34
III. DISTRIBUTION OF A/E MATERIAL
A. SYMBOL IDENTIFICATION OF CONTRACT DRAWINGS
AS - Architectural Drawings (Numbered Only)
ES - Electrical Drawings
FA - Fire Protection Drawings
MH - Heating, Ventilating, and Air Conditioning Drawings
PL - Plumbing Drawings
GS - Site Development and Environmental Drawings
CU - Sanitary and Irrigation Drawings
SS - Structural Drawings
B. GENERAL NOTES
1. Bond prints shall be full-sized.
2. Bind all drawings into sets in the order of their above classification symbol.
3. All submitted specifications shall be original, unbound, and marked-up VA Master
Specifications. Where no VA Master Specification is available, submit a developed specification.
4. Submit all materials, packaged, and clearly marked by discipline, to the VA’s
Contracting Officer. However, where a small amount of material is submitted, the drawings may be packaged together for all disciplines as long as the drawings are separated and tagged with the discipline name. Other material may also be consolidated provided they are labeled and can easily be identified and separated.
5. Material provided unbound will be returned to the A/E. All resubmission costs will be the responsibility of the A/E
Program Guide, PG-18-15, Volume C 35
Distribution of A/E Material
Schematic Submission:
VA Medical Center (VAMC) Appropriate Network Office* 3 complete sets 1 complete set
Design Development Submission:
VA Medical Center (VAMC) Appropriate Network Office* 3 complete sets 1 complete set
Construction Documents Submission:
VA Medical Center (VAMC) Appropriate Network Office* 3 complete sets 1 complete set
*Network Office will coordinate the necessary review with the responsible safety and fire protection person in their network.