This document is a Statement of Work (SOW) for appliance procurement issued by the Camp Perry Joint Training Center (CPJTC), located in Port Clinton, Ohio, for Phase 4 of a project involving new cottages and bungalows. The procurement involves supplying and installing 5 refrigerators and 5 stoves (2 ADA-compliant and 3 standard) across Cottage 611 and Bungalows 612-615, with specific requirements for white, Energy Star-qualified appliances featuring top freezer refrigerators and electric stoves with specific design considerations. The project requires all appliances to be fully assembled and installed prior to August 30, 2025, with contractors responsible for coordinating closely with CPJTC, maintaining work area cleanliness, ensuring material security, and providing a minimum one-year written warranty.
The SOW indicates that potential bidders must submit detailed proposals with pictures of proposed items for pre-approval by the CPJTC Business Administrator, with approvals required at least 24 hours before bid closure. Interested parties can arrange site visits and obtain additional information by contacting Debbie Paul at the provided contact information. While specific pricing details are not included in the document, the procurement appears to be a targeted, specific appliance replacement project with clear technical specifications and accessibility requirements for a military training facility.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFP - Appliances Point Project Phase 4.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
FURNITURE PROCUREMENT FOR POINT PROJECT PHASE 4
CAMP PERRY JOINT TRAINING CENTER
DIVISION 1 – GENERAL
SECTION 01001 – STATEMENT OF WORK FOR Appliance Procurement for New Cottage and Bungalows at The Camp Perry Training Post.
SW-1 SCOPE
The work shall be defined as all materials and labor to provide a complete project herein defined as Appliance Procurement for the New Cottage and Bungalows at the Camp Perry Joint Training Center, Port Clinton, Ohio.
SW-2 SITE OF WORK
The site of the proposed work is located at the Camp Perry Joint Training Center, approximately 5 miles west of Port Clinton, Ohio located in Ottawa County. The new cottage and bungalows are located west of BLDG 600 on Scorpion Road.
SW-3 WORK TO BE ACCOMPLISHED
The work to be accomplished includes, but is not limited to the following items:
1) Contractor is responsible for supplying all material and labor to make a complete package for the Cottage and Bungalow Appliances in accordance with this statement of work. These appliances must be installed prior to August 30, 2025.
2) Demolition:
a) N/A
3) Contractor will provide the following, fully assembled and installed:
Total Units:
| Refrigerators | 5 |
| Stoves (regular) | 2 |
| Stoves (ADA) | 3 |
A) Cottage 611:
· 21.9 cu ft white refrigerator with top freezer, with automatic defrost for fridge and freezer. Shelves must have spillproof glass. Unit shall be Energy Star qualified. No ice maker. An example of a desirable model would be GE Model#GTS22KGNRWW
· Stove for ADA use with the knobs on the front like Frigidaire Model # FCFE3062AW -30” glass top, 5 burners, 5.3 cubic foot slide in electric, in white with self-cleaning oven. Knobs can’t be on the top back, must be on the front for wheelchair-bound people to be able to reach.
B) Bungalow 612:
· 21.9 cu ft white refrigerator with top freezer, with automatic defrost for fridge and freezer. Shelves must have spillproof glass. Unit shall be Energy Star qualified. No ice maker. An example of a desirable model would be GE Model#GTS22KGNRWW
· Stove for ADA use with the knobs on the front like Frigidaire Model # FCFE3062AW -30” glass top, 5 burners, 5.3 cubic foot slide in electric, in white with self-cleaning oven. Knobs can’t be on the top back, must be on the front for wheelchair-bound people to be able to reach.
C) Bungalow 613:
· 21.9 cu ft white refrigerator with top freezer, with automatic defrost for fridge and freezer. Shelves must have spillproof glass. Unit shall be Energy Star qualified. No ice maker. An example of a desirable model would be GE Model#GTS22KGNRWW
· Stove like Frigidaire Model # FCRE3062AW - 30” wide, white smooth top stove with oven. 5.3 cubic foot min. capacity, 4-5 elements, electronic controls, self- cleaning oven. Energy Star, coordinating with the refrigerator.
D) Bungalow 614:
· 21.9 cu ft white refrigerator with top freezer, with automatic defrost for fridge and freezer. Shelves must have spillproof glass. Unit shall be Energy Star qualified. No ice maker. An example of a desirable model would be GE Model#GTS22KGNRWW
· Stove like Frigidaire Model # FCRE3062AW - 30” wide, white smooth top stove with oven. 5.3 cubic foot min. capacity, 4-5 elements, electronic controls, self- cleaning oven. Energy Star, coordinating with the refrigerator.
E) Bungalow 615:
· 21.9 cu ft white refrigerator with top freezer, with automatic defrost for fridge and freezer. Shelves must have spillproof glass. Unit shall be Energy Star qualified. No ice maker. An example of a desirable model would be GE Model#GTS22KGNRWW
· Stove for ADA use with the knobs on the front like Frigidaire Model # FCFE3062AW -30” glass top, 5 burners, 5.3 cubic foot slide in electric, in white with self-cleaning oven. Knobs can’t be on the top back, must be on the front for wheelchair-bound people to be able to reach.
4) All approved equals will be submitted to The Business Administrator (CPJTC) for approval NTL 24 hours prior to bid close to allow for spec comparison and approval. Decision will be provided to contractor in writing.
5) Any submittals for materials, type and color must be approved by CPJTC prior to commencement of project. Please provide pictures of each item proposed.
6) Contractor is responsible for leaving the work area in a clean and workable condition on a daily basis throughout delivery, set up and installation.
7) Contractor is responsible for the security of all materials on site.
8) Contactor will need to coordinate closely with the CPJTC to schedule work so it doesn’t interfere with CPJTC Scheduling.
9) Provide minimum 1 year written warranty, after owner acceptance of completed work.
SECTION 01001-1
SW-4 SITE VISITATION
PRE-BID SITE VISITATION IS WELCOME FOR THIS PROJECT.
SECTION 01001-2
SW-5 POINT OF CONTACT
Questions concerning this Statement of Work and site visits should be arranged through:
Debbie Paul at 614-336-6215 deborah.m.paul4.nfg@army.mil
Camp Perry Joint Training Center Conference Center and Lodging 1000 Lawrence Rd. BLDG 600 Port Clinton, Ohio 43452-9578
Monday-Friday: 8:00 a.m. - 4:00 p.m. (excluding State Holidays)
Phase 4 Furniture July 25 2025 Page 2 of 2