SOW_Appendix_A_-_ARHO_Overoll_Phasing.pdf

PDF 4 MB Posted

Attached to
Z-Resin Bound Aggregate Vaccum, Clean, Urethane seal
Solicitation number
140D0424Q0978
Issued by

About this file

This document appears to be an appendix titled "SOW_Appendix_A_-_ARHO_Overoll_Phasing.pdf" that outlines the phasing plan for cleaning and over-rolling the resin bound aggregate at the NPS Arlington House, The Robert E. Lee Memorial. The project will be divided into 3 phases, with each phase involving cleaning and over-rolling the aggregate, as well as patching, over a 1-2 day period, followed by a 24-hour curing period. The total area of resin bound aggregate that requires this treatment is approximately 25,000 SF, and the contractor shall also provide 1,000 SF of full depth repairs. The project will be managed by the Department of the Interior Departmental Offices Interior Business Center.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PHASE 3

PHASE 3

Clean & Over-Roll + patching: Day 4 Curing: 24 hours

PHASE 2

PHASE 2

Clean & Over-Roll + patching: Day 2-3

PHASE 1

Clean & Over-Roll + patching: Day 1