SOW_Annex outlets_2024.pdf
PDF 734 KB Posted
- Solicitation number
- 12905B24Q0086
About this file
This document is a Statement of Work (SOW) for the Annex Building Electrical and Data Outlet Installation project located at the USDA-ARS DKI U.S. Pacific Basin Agricultural Research Center in Hilo, Hawaii.
The SOW requires the contractor to provide all labor, materials, and services necessary to install 14 new electrical outlets and 43 new data outlets in the Annex Building. The work must adhere to federal, state, and local code requirements as well as industry standards. The contract is a firm-fixed-price construction contract with a period of performance of 90 calendar days from the notice to proceed. The project is set aside for small businesses under NAICS code 238210. The government will issue a Request for Quotation (RFQ) under Solicitation Number 12905B24Q0086 on or around May 06, 2024. Interested offerors must be registered in the System for Award Management (SAM).
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
United States Department of Agriculture Agricultural Research Service
Statement of Work
ANNEX BUILDING ELECTRICAL
AND DATA OUTLET INSTALLATION
USDA-ARS DKI U.S. Pacific Basin Agricultural Research Center 64 Nowelo Street, Hilo, Hawaii 96720
STATEMENT OF WORK
1.0 CONTRACT PROJECT:
a. Project Title:
Annex Building Electric and Data Outlet Installation
b. Project Location:
USDA-ARS-DKI
Pacific Basin Agricultural Research Center
2.0 PROJECT CONTACT PERSONS:
a. CONTRACTING OFFICER (CO):
RESEARCH PROGRAM REPRESENTATIVES (RPR):
Nicholas C. Manoukis Research Leader USDA-Agricultural Research Service Daniel K. Inouye U.S. Pacific Basin Agricultural Research Center Tropical Crop and Commodity Protection Research Unit 64 Nowelo Street, Hilo HI 96720 Phone: (808) 895-0686 or (301) 646-8038 E-mail: nicholas.manoukis@usda.gov
b. ADMINISTRATIVE OFFICER (AO):
Carlee Wehrsig Administrative Officer USDA-Agricultural Research Service Daniel K. Inouye U.S. Pacific Basin Agricultural Research Center 64 Nowelo Street, Hilo HI 96720 Phone: (808) 932-2116 E-mail: carlee.wehrsig@usda.gov mailto:nicholas.manoukis@usda.gov mailto:carlee.wehrsig@usda.gov
c. LOCATION CONTRACTING OFFICER REPRESENTATIVE (COR):
Pernell Hanoa Facilities Manager Daniel K. Inouye U.S. Pacific Basin Agricultural Research Center USDA-Agricultural Research Service 64 Nowelo Street, Hilo, HI 96720 Phone: (808) 959-4356 Cell: (808) 896-4523 E-mail: pernell.hanoa@ars.usda.gov
d. AREA SAFETY AND HEALTH MANAGER (ASHM)
Scott Geib PhD Research Entomologist USDA-ARS Pacific Basin Agricultural Research Center 64 Nowelo Street, Hilo HI 96720 Phone: (808) 959-4335 E-mail: scott.geib@usda.gov
e. REAL PROPERTY MANAGEMENT:
Christa Meier Realty Specialist/Lease Contracting Officer USDA-ARS Pacific West Area Phone: (510) 559-6124 Email: christa.meier@usda.gov
f. ENGINEERING PROJECT MANAGER (EPM)
Carolyn Williams Facilities, Safety and Real Property Branch USDA-ARS Pacific West Area Phone: (510) 207-2929 Email: carolyn.williams@usda gov
3.0 SCOPE OF WORK: The contractor shall provide all professional services necessary for the accomplishment of the contract project and such required service shall be in accordance with the requirements as described herein and on attached contract documents.
3.1 Background: The USDA-ARS DKI US PBARC Tropical Crop and Commodity Protection Research Unit requires the labor and materials to install (14) new electrical outlets and (43) new data outlets in the Annex Building at 64 Nowelo Street in Hilo, Hawaii.
3.2 Contractor shall provide the labor and materials to install (14) new electrical outlets and mailto:pernell.hanoa@ars.usda.gov mailto:scott.geib@usda.gov mailto:christa.meier@usda.gov mailto:carolyn.williams@usda%20gov
(43) new data outlets, based on the attached drawing and specifications below:
a. Standard 4" sq. (Electric) and 4-11/16" sq. (Data) galvanize box and EMT conduit shall be used for new electric and data outlets and shall be a surface mount type installation.
b. (13) new electrical 120 volts outlets. Connected to nearest existing plug circuit.
c. (1) new electrical 120 volts outlet on a dedicated circuit. Connected to nearest existing panel.
d. Identify all circuits and label panel.
e. Total of (43) new data outlets with (2) Cat 6 cable drops each (Total of 86 Cat 6 drops).
f. Each outlet shall be box and 3/4" EMT conduit stubbed up into ceiling space with (2) Cat 6 cables homerun back to existing IT cabinet located at front entrance.
g. Wiring shall be self-supported by existing framing members.
h. Final termination at communication outlet end only.
i. Contractor shall remove all excess material from site.
4.0 PROJECT REQUIREMENTS:
a. The Contractor will work with site personnel to ensure project is accomplished in a timely manner.
b. Unless otherwise specified, all materials shall be new as specified and both workmanship and material shall be of good quality.
c. The Contractor’s work shall adhere to the criteria stated within these project requirements, drawings, and specifications. All construction and services shall comply with applicable federal, state, and local code requirements as well as current industry standards, (ie: EPA, ASTM, GSA, AASHTO, etc.) and health and safety codes, in effect at the time of contract award.
d. All work to meet all pertinent Unified Facilities Guide Specifications (UFGS) and ARS 242.1M standards. UFGS available at http://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs. ARS 242.1M available at https://www.afm.ars.usda.gov/ppweb/pps-and-manuals/.
e. This project falls under the DAVIS BACON Wage Act.
http://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs http://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs https://www.afm.ars.usda.gov/ppweb/pps-and-manuals/
4.1 Background & Site Description: This project is located at the USDA-ARS DKI US PBARC facility at 64 Nowelo St. in Hilo, Hawaii. Electrical and data outlet installations in the Annex Building.
4.2 Bid Schedule:
Item Description
Base Item Provide materials, labor, equipment, and all associated services necessary to complete project.
4.3 Description of Work:
a. The Contractor will provide a turn-key project satisfying all Local, State, and Federal requirements.
b. The Contractor will provide all the necessary materials and labor per Section 3.0 and properly dispose of all material being replaced.
c. Contractor is responsible for any damage to adjacent equipment and miscellaneous objects that may become damaged during installation of the fencing. The Contractor is responsible for making repairs to meet or exceed conditions prior to damage.
d. The Contractor is responsible for visiting the site prior to submitting a bid to observe existing conditions. No compensation will be provided for conditions that would be visible during an on-site visit for persons experienced performing this type of work.
4.4 Government Furnished Equipment\Services
a. The Government does not anticipate the need in this project, but the Government will be available to assist with the identification/location of utilities as necessary.
b. The Government will furnish a reasonable amount of electricity and water.
5.0 GENERAL REQUIREMENTS:
5.1 Permits: Where governing regulations and imposed codes and standards require notices, permits, licenses, inspections, tests, and similar items or actions to lawfully proceed with the required work, the Contractor shall obtain items and take those actions in accordance with the regulations of the governing authority. The costs of such permits, licenses, inspections, etc., are the obligation of the Contractor.
5.2 Existing Installations / Demolition: Contractor shall modify existing installations as needed to accommodate the new installation. Contractor shall coordinate modification of existing installations with Owner. All disturbances of existing systems shall be thoroughly coordinated with the Owner to prevent disturbances that might jeopardize on-going operations and research. Owner reserves the right to retain any equipment / materials removed as part of the scope of work. Contractor shall coordinate any equipment / materials to be retained with Owner prior to starting demolition operations. Contractor shall legally dispose all any materials removed that will not be retained.
5.3 Installation: It shall be the responsibility of the Contractor to complete work in accordance with Federal, State, and Local Code Standards. Additional procedures and materials may be required than is indicated herein. If any item specified herein conflicts with the applicable codes and recommendations, the Contractor shall bring it to the attention of the Contracting Officer Representative for immediate resolution.
5.4 Submittals: Provide manufacturer’s descriptive literature/shop drawings for all materials to the COR for review. The descriptive literature shall be annotated/ highlighted to show its conformance with contract requirements. Submittals are required for new materials and will be stamped and/or signed by the general contractor prior to submission to the Government. Contractor is responsible for any costs incurred for equipment ordered without prior approval.
5.5 Quality Control: The work performed under this contract shall be subject to continuous audit by the COR. Quality control is the exclusive responsibility of the Contractor.
5.6 Protection of Work and Property/Safety Requirements:
a. Contractor shall furnish a Site Specific Safety Plan (SSSP) or Accident Prevention
Plan (APP) 10 days after contract award. SSSP / APP shall be approved by the Government before construction work commences.
b. The Contractor shall protect the work, the site, and all existing property and structures within the limits of the construction activities or that may be affected thereby until acceptance of the work. Any damage to property shall be repaired at the Contractor’s expense, to pre-damaged condition to the satisfaction of the COR.
c. Safety and health matters, as they relate to the work, are the exclusive responsibility of the Contractor. The Contractor shall furnish, erect, and maintain barricades, warning lights, signs, guards, or take other precautions as may be required by law or local authorities of the protection and security.
d. Contractor is responsible for verifying location of any underground utility and is responsible for any damaged caused to such utilities.
5.7 Temporary Facilities:
a. Temporary utilities (water and electricity) may be furnished to the Contractor by the Government, if so requested. The Contractor shall maintain and protect all such utilities during construction and shall repair or replace any items damaged through its own negligence.
b. Should the Contractor require any power or utility shutdowns during construction, the
Contractor shall obtain approval for such shutdown from the COR 21 working days prior to the need.
5.8 Materials and Equipment:
a. The material and equipment to be furnished under these contract documents shall be the standard products of manufacturers regularly engaged in the production of such materials and equipment and shall be the manufacturer’s latest standard design.
b. All materials and equipment to be incorporated in the work shall be handled and stored by the manufacturer, fabricator, supplies, and Contractor before during and after shipment in a manner to prevent any injury, theft or damage of any kind to the materials and equipment. All materials and equipment furnished by the Contractor shall be subject to inspection and approval by the CO/COR.
c. Government will not furnish any labor or equipment to unload or move materials or supplies.
5.9 Cleanup: The construction site shall be always kept clean and free of debris. Disposal of the old equipment is required. Restore areas disturbed as nearly as possible to the original appearance and condition. Upon completion of the project, and prior to final inspection, the Contractor shall remove from the premises all unused material, trash, and debris resulting from the work to the satisfaction of the COR.
5.10 Warranty:
a. Submit data concerning the standard one-year warranty for workmanship, including the warranty periods (dates), and warranty contacts with names, addresses and telephone numbers.
b. Extended Equipment/Product Warranties: Obtain and furnish to the Contracting Officer all written warranties for equipment/products that have extended warranties (warranty periods exceeding the standard one-year warranty) furnished under the contract. The warranty period shall begin on the same date as project acceptance and shall continue for the full/product warranty period. The warranties shall be fully executed and delivered to the Contracting Officer prior to final acceptance of the facility.
5.11 Final Payment/Contract Closeout: The following documents are REQUIRED PRIOR TO FINAL PAYMENT (other documents may also be required):
a. General contractors minimum one (1) year warranty on work.
b. Operation and Maintenance Data
c. Release of liens.
d. Final Invoice
6.0 PROJECT SCHEDULE: The Contract time for this project is 90 calendar days from Notice to Proceed.
Attachment
Map for electrical and data outlet installation.
| STATEMENT OF WORK |
| 3.0 SCOPE OF WORK: The contractor shall provide all professional services necessary for the accomplishment of the contract project and such required service shall be in accordance with the requirements as described herein and on attached contract docu... |
| 4.1 Background & Site Description: This project is located at the USDA-ARS DKI US PBARC facility at 64 Nowelo St. in Hilo, Hawaii. Electrical and data outlet installations in the Annex Building. |
| 4.2 Bid Schedule: |
| 4.3 Description of Work: |
| 4.4 Government Furnished Equipment\Services |
| 5.0 GENERAL REQUIREMENTS: |
| 5.6 Protection of Work and Property/Safety Requirements: |
| 5.7 Temporary Facilities: |
| 5.8 Materials and Equipment: |
| 5.10 Warranty: |