About this file

This document is a Statement of Work (SOW) for replacing the batteries in an Eaton 93E Uninterruptable Power Supply (UPS) and Eaton 93E 30 External Battery Cabinet (EBC) used by the Alaska Fire Service. The objective is to replace the end-of-life batteries to maintain the operational capabilities of the UPS, which provides uninterruptible power to the agency's server room. The SOW specifies the requirements for new Eaton batteries compatible with the existing UPS and EBC, and the delivery location at the Alaska Fire Service facility in Fort Wainwright, Alaska. The related federal contract opportunity is solicitation number 140L0224Q0038, issued by the Department of the Interior Bureau of Land Management Alaska Region for the AFS UPS Replacement Batteries requirement.

View the file

Other files

File Type Posted
UPS-93E-30-30-Config-SN_0002.JPG JPG image
93E-External_Battery_Cabinet_Battery_Type_0002.JPG JPG image
Additional_Information_0002.PNG PNG image
UPS-93E-30-30-Battery_Type_0002.JPG JPG image
Sol_140L0224Q0038_Amd_0002.pdf PDF
93E-External_Battery_Cabinet-Config-SN_0002.JPG JPG image
EatonUPS_Pics_0001.zip ZIP file
Sol_140L0224Q0038_Amd_0001.pdf PDF
Sol_140L0224Q0038.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 5

Statement of Work

1.0 Background

The Alaska Fire Service has one Eaton 93E Uninterruptable Power Supply (UPS) and one Eaton 93E 30 External Battery Cabinet (EBC). We want to replace the batteries in both units.

Pictures of the current installation are attached.

2.0 Objective

The batteries have reached end of life and must be replaced with new batteries to maintain the operational capabilities of the unit, which provides uninterruptable power to the Alaska Fire Service server room.

The new batteries will be installed by an Eaton technician on the next service visit.

3.0 Requirements

Replacement batteries for one Eaton 93E UPS and one Eaton 93E 30EBC.

4.0 Deliverables

New Eaton batteries that are compatible with the existing Eaton UPS and EBC onsite.

Delivery location:

Alaska Fire Service, BLM 1544 Gaffney Road Fort Wainwright, Alaska 99703

5.0 Contacts

Bill Beach, NAK-IT Section Chief, Zone 3 Bureau of Land Management (BLM) HQ-563 Branch Zone 3 Alaska Fire Service, BLM - Northern Alaska IT (NAK-IT) Staff P.O. Box 35005 Fort Wainwright, Alaska 99703 Phone: 907-356-5592 e-mail: bbeach@blm.gov mlstewart Reviewed

Attachment 5

SOW Checklist

YES NO

1. Does the scope of work accurately reflect the requirements?

X

2. Does your background explain the rationale for the project?

3. Will your background help a potential contractor prepare a sound technical proposal?

4. Does the objective emphasize what is most important to the agency?

5. Is your breakdown of objectives accurate and logical?

6. Will the contractor understand your agency’s need?

7. Have you checked your facts?

8. Are your requirements realistic, definite, and nonrestrictive?

9. Do your requirements satisfy the minimum needs of your agency?

10. Is each requirement capable of being inspected or verified?

11. Are your references necessary, available, and timely?

12. Are the modes of transmittal or delivery realistic?

13. Will your inspections, reports, and tests provide an accurate gauge of quality?

14. Are all report, inspection, and test procedures clearly defined?

If you have checked any “No’s,” continue work on the SOW until you answer “Yes” to all the questions.