This document is a Statement of Work (SOW) for the fabrication and purchase of five (5) 40-foot shipping containers with interior components and hardware installed per drawing X202306165-1. The containers will be used for short and long-term storage of the A-10 Hogback Fixture at Hill Air Force Base.
The SOW outlines the requirements for the shipping containers, including quality specifications, delivery schedule, acceptance criteria, and technical drawing package availability. Contractors cannot make changes to the drawing or configuration without prior approval. The government will inspect each container upon delivery for full acceptance. Delivery must be coordinated with the Project Engineer and will be staggered over several months. The associated federal contract opportunity is solicitation FA822424Q0013 for the AMXG 571 (A-10) Ship Container w Storage Hardware for Hogback Fixture Storage.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Solicitation - FA822424Q0013.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Prepared by:
Preston Cox, 309TH AMXG/EN (Project Engineer) 5875 Southgate Ave, Hill AFB, UT 84056
Phone: 801-586-0702 Email: Preston.Cox.2@us.af.mil
Statement of Work AMXG A-10 X202306165-1 Shipping
Container with Storage Hardware.
For Hogback Fixture Storage
25 January 2024 mailto:Preston.Cox.2@us.af.mil
Figure 1 X202306165-1 Shipping Container with Storage Hardware
1. Purpose Fabricate and purchase all components of drawing X202306165-1 Shipping Container with Storage Hardware installed and assembled per drawing requirements. X202306165-1 Shipping Container with the installed components/hardware will be used for short and long-term storage of the A-10 Hogback Fixture P/N 160D110000-1 & -5 at Hill Air Force Base (HAFB).
2. Scope Supply 40’ shipping container (meeting quality requirements listed in section 4) with interior components and hardware installed per drawing X202306165-1.
3. Quantity Five (5) of Drawing X202306165-1, delivery quantities will be staggered (1,1, and 3. See section 7). All DATA Rights and Drawing packages are the sole property of the USAF/309 AMXG/EN.
4. Quality All items shall be clean of dirt, burrs, material shavings, cutting oil, etc. upon delivery and meet the requirements of X202306165-1 drawing and drawing notes.
a) 40’ Shipping Container can be either a high-cube or standard and must meet requirements for a “CARGO WORTHY” container, but do not require a current CSC plates/stickers or surveys.
5. Changes
Contractor cannot make changes to X202306165-1 drawing, scope, design, or configuration without prior approval from cognizant 309th AMXG Engineering. The Government Representative reserves the right to authorize and make changes to X202306165-1 drawing, scope, design, and configuration. After contract award the Government will not make any
Figure 2 X202306165-1 Shipping Container with Storage Hardware and Hogback Fixture Installed (fixture shown for reference only) drawing changes unless requested by the contractor and approved by cognizant 309th AMXG Engineering.
6. Acceptance Government shall inspect each X202306165-1 Shipping Container with Storage Hardware for full acceptance at time of delivery.
7. Delivery Schedule Exact delivery schedule can be negotiated after contract award but must meet the general scope as follows:
X202306165-1 Shipping Container with Storage Hardware shall be delivered in groups such as:
1st: One (1) X202306165-1 Shipping Container with Storage Hardware delivered 4 months or less after contract award.
2nd: One (1) X202306165-1 Shipping Container with Storage Hardware delivered 1-2 months or less after 1st delivery.
3rd: Three (3) X202306165-1 Shipping Container with Storage Hardware delivered 2-3 months or less after 2nd delivery and can be staggered.
Delivery must be coordinated in advance with Project Engineer:
Preston Cox 5875 Southgate Ave
HAFB, UT 84056
Phone: 801-586-0702 Email: Preston.Cox.2@us.af.mil
Delivery hours Monday through Friday 8:00 AM to 2:00 PM. Truck entry is through the Roy Gate.
Added delivery instructions will be supplied by the Project Engineer during delivery coordination.
8. Technical drawing package Government contracting officer will issue drawing package upon request. An e-drawings 3D model file of the assembly is also available. The e-drawings viewer can be downloaded free of charge from www.edrawingsviewer.com .
i. After award and upon request, additional 3D model files (STEP, IGES etc.) of selected component of the assembly will be available. Contact the Project Engineer.
9. Systems Requirement Review
Initial requirements review is required upon award of contract. Contractor shall establish a date and time for a review via telecom within 21 calendar days of contract award.
mailto:Preston.Cox.2@us.af.mil http://www.edrawingsviewer.com/
10. Warranty
Standard commercial warranty required in Federal Acquisition Regulation (FAR) clause 52.212-4.
11. Reference Images
IMAGE 1: SHOWS THE TRACKS ITEM #350 INSTALLED INSIDE THE 40’ CONTAINER, AND THE TRACK
WHEEL ASSEMBLY ITEM 250 ON THE TRACK.
IMAGE 2: SHOWS THE HOGBACK FIXTURE INSTALLED INSIDE THE 40’ CONTAINER
IMAGE 3: SHOWS THE HOGBACK FIXTURE INSTALLED INSIDE THE 40’ CONTAINER
File details come from the government source that posted it. Updated .