This document outlines requirements for architectural and engineering services to renovate a clinical community living center into a hospice unit at a Veterans Affairs medical campus in Murfreesboro, Tennessee. The project involves converting approximately 14,500 square feet of an outdated ward into a new hospice unit and constructing an additional 1,300 square feet to include a new dayroom, secure entry vestibule, and visitor restroom. Exterior improvements also include a covered patient drop-off area with circular driveway and five accessible parking spots. The selected A/E firm will provide design development, construction documents, cost estimates, and construction administration services. The design is to modernize outdated mechanical, electrical and control systems while meeting VA accessibility, safety, and energy efficiency standards. Submission requirements and a 355-day schedule are defined. The contract value is estimated at $13.5 million.

View the file

Other files

File Type Posted
36C77623R0162.docx DOCX document
PPQ - Murfreesboro CLC-Hopsice.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

August 12, 2023 Department of Veterans Affairs TVHS, Murfreesboro Campus Requirements for A/E Services Project 626-317 Renovate CLC – Hospice Unit

I. GENERAL SCOPE OF WORK

The consultant shall provide all necessary Architectural and Engineering (A/E) services as required to prepare complete contract drawings, specifications, observation/evaluation/technical reports, cost estimates, and services throughout construction to "Renovate CLC – Hospice Unit” at the historic York Campus of the VA Tennessee Valley Healthcare System (TVHS), located at 3400 Lebanon Pike, Murfreesboro, TN 37129. This project will renovate approximately 14,500 square feet to convert an outdated CLC ward to a new hospice unit, uniquely designed for patients who are terminally ill. This project will also construct approximately 1300 new square feet to include a new dayroom with porch, a secure entry vestibule, and a visitor restroom. Additionally, an accessible, covered patient drop off area with a circular driveway and 5 accessible parking spots will be constructed. Work includes, but is not limited to, professional design services of Architects, Mechanical, Plumbing, Industrial Hygiene (IH), Structural/Seismic, Electrical power and systems (such as communications, controls, security, fire protection/alarm).

II. STATEMENT OF PROJECT OBJECTIVES

The Department of Veterans Affairs (VA) intends to have the A/E fully survey, investigate, and document the existing spaces and utility systems, affected by renovations, to gain the knowledge and insight necessary to prepare accurate documents in a professional and competent manner. The project objectives are as follows:

A. Renovate existing ward for hospice care.

B. Increase and promote staff efficiency through more functional layouts.

C. Improve privacy and accessibility.

D. Convert semi-private rooms and shared restrooms to full private facilities to provide privacy and space for families to meet with their loved ones.

E. Build additional square footage for a new dayroom with porch, a secure entry vestibule, and a visitor restroom.

F. Improve exterior building entry and access, including a drop off area with a circular driveway and five accessible parking spots.

G. Improve the condition of the facility by partially correcting the following issues from the Facility Condition Assessment (FCA):

a. 203386 (Accessibility): Replace doorknobs with lever type on all floors.

b. 334339 (Accessibility): Staff Toilets, Lockers, and Showers are generally noncompliant throughout building; provide at least one complying toilet, locker, and shower for the floor.

c. 61566 (Windows): Windows are in poor condition. Poor seals let bugs in. No thermal break built into windows. No parts available to repair blinds. Seals failed. Replace all with alum fixed windows with insulated glass and integral blinds.

d. 400453 (Controls): The pumps and VAV boxes are pneumatically controlled, are obsolete, and should be replaced.

e. 400454 (AHU): Data/OIT closet(s) are exhausted only and do not have local temperature control or the ability to monitor remotely. Provide dedicated cooling to each data closet and integrate into building management system.

f. 334694 (Elec/Telecom Closets): Second floor electrical closet is warm. Provide ventilation.

H. Modernize systems so that they are scalable and capable of modern features such as the integration of various existing systems, equipment, and devices. Upgrade outdated electrical, controls, communications, and mechanical systems. All relevant systems including but not limited to Nurse Call/ Code Blue, telephone, PA, Fire Alarm, and Security shall meet current VA standards.

I. Improve reliability, monitoring, control, and energy efficiency, utilizing modern systems and features, such as non-priority native BACnet DDC controls, variable speed drives, energy optimization control, reset of discharge air temperature, optimal start/stop, occupied/unoccupied, occupancy sensing, lighting control, and economizer modes. Replace outdated pneumatic controls with DDC that will integrate into the frontend controls system. Install thermostats with resets, setback, and override controls. New automated control systems shall provide precise control of temperature and humidity, pressure relationships, and provide a quality care environment.

III. STATEMENT OF A/E TASKS

A. The A/E shall furnish all services for a complete design development including construction documents, and construction period services as specified in the subject contract.

a. Necessary site survey work and evaluation such as verifying existing conditions/pre-TAB (Test-Adjust-Balance), geotechnical surveys/report, verifying record drawings, and verifying and analyzing utility systems shall be accomplished in conjunction with the preparation of Design Development documents. A/E shall furnish documentation and drawings of these findings, and address deficiencies in the design process.

b. The complete site survey work shall include a thorough investigation of existing conditions, affected by renovations, to accurately document and convey space dimensions for measured drawings, all utilities for affected areas, and utilities that traverse through affected areas, typical construction type and variations, and finishes. This information provides the necessary base drawings for the Schematic Development phase of Design Development.

c. Utility system verification shall include, but not be limited to, the necessary testing, adjusting, and/or balancing of affected systems to ascertain the existing operating and performance conditions that will impact the design and construction process. Systems that are insufficient in capacity or are no longer supported by OEM (original equipment) parts shall be considered for expansion and/or replacement.

d. System verification shall include, but not be limited to, the necessary testing of affected systems to ascertain the existing operating and performance conditions that will impact the design and construction process. Systems that are insufficient in capacity or are no longer supported by OEM (original equipment) parts shall be considered for replacement.

e. Geotechnical surveys are required for new construction, buildings, building expansion, parking lots and drives.

B. The A/E shall provide cost estimation, project scheduling & phasing, bid period and construction period services as further described in the contract.

C. The A/E will provide an Interior Designer with a NCIDQ Certification to coordinate all aspects of the interior design. All finishes must be approved by the VA Interior Designer.

D. The A/E shall provide three (3) interior design color boards for VA review, discussion, and selection. The color boards will be updated and re-submitted with the final revision.

E. The A/E shall provide bid document preparation in quantities as specified in the contract.

F. The A/E shall provide professional design and construction period services utilizing individuals who are adequately knowledgeable of the various design disciplines as required by the project. Changes in personnel from those who are proposed in negotiations, interviews, kick-off meeting, and/or A/E submission forms must be approved in writing. Submit requested change to COR and CO a minimum of 14 days prior to said change. The registered individuals who will stamp the completed documents shall accomplish engineering design work.

G. The A/E will provide third party commissioning of all the systems constructed and/ or modified by the design of Renovate CLC – Hospice to include HVAC, Controls, Nurse call, Med-Gas, Phone, Fire Alarm, Security, and Data.

H. A/E shall design within funding limitations and coordinate cost control measures throughout the design. Primary, fundamental cost control alternatives shall be thoroughly explored in Design Development (DD’s) and cost control/review shall be a critical part of each submission, thoroughly discussed at each review. Any submission with an estimate exceeding the base construction budget shall initiate a gate review, in which the A/E must develop and submit cost control measures, then make the corrections to the package (estimate, drawings, specifications) to get within budget, to be released to the next submission phase. In the event of budgetary issues, additional A/E presentations/meetings will be required to correct the budget issues.

I. The A/E design and estimate shall identify viable deductive construction alternates (target 10% of the total construction budget). The A/E and their design team shall develop proposals to prioritize the bid deducts for construction. A/E shall review the proposals with the Contracting Officer’s Representative (COR) to finalize the deductive alternates.

J. The A/E is to incorporate into the design all adjacent spaces that are impacted by the project. It is in the scope to investigate all existing utilities that must be moved/ mitigated to accomplish the renovations to include all affected structure/finishes. The A/E is to also integrate HIPAA standards into the design and layout.

K. The design must ensure proper life safety, including egress, proper fire/smoke compartmentation, fire alarm, sprinkler system, etc. The A/E shall provide a separate stamped Life Safety Sheet for the entire area within the submitted drawings.

L. The A/E shall survey and evaluate the HVAC, electrical, plumbing systems, and mechanical rooms to ensure they will meet the requirements of the renovated space and meet VA design guide requirements without adversely affecting the surrounding areas. A/E will design new mechanical, electrical, and plumbing systems where need to meet VA standards. Utilize LED interior lighting with occupancy, and daylight sensors. A/E will pre-TAB (Test, Adjust, Balance) HVAC and exhaust in investigative service to establish a basis for the design and to make corrections to HVAC systems to get space to VA standards. A/E will place in construction documents that all HVAC will have a complete TAB performed by construction contractor. The design will allow for 10% growth on all major systems. Growth factors shall be separate from safety factors (in addition, compounded on top of safety factors). Design to ensure coverage to maximize patient safety.

M. A/E will coordinate with leading industry equipment manufacturers/vendor(s) to ensure proper layout and support of equipment per manufacturer’s requirements. However, design drawings and specifications shall be generic to promote fair and open competition.

N. Design shall be energy efficient per the TVHS Energy Conservation Project Requirements (see attachment) and Design Guide. Night/ Occupancy setbacks will be utilized where applicable to lighting and HVAC/ Exhaust.

O. A/E shall identify and design for the removal of all hazardous material.

a. Perform an asbestos survey to identify approximate quantities of ACM in type and location for complete abatement from the general limits of construction. Adjacent areas that are outside of these limits but are affected by construction for utility modifications or tie-ins shall limit abatement to the extent necessary to complete the utility work.

b. Lead-based paint may be encountered on some of the HVAC/piping/equipment. A/E will investigate and design for corrective action.

P. The A/E will provide expertise during testing of all systems constructed and/ or modified by the design, including but not limited to, HVAC startups, test-adjust-balance (TAB), Controls trending and adjustment, Nurse call, Medical Gas, Phone and Data.

Q. Data closets will be brought to VA EHRM specifications. Controls and HVAC will also be correctly integrated into the closets to control temperature and humidity.

R. A/E shall provide space planning for the project as part of SD1 and SD2. To perform the space planning, additional meetings will be required with the VA Planning Department, primary stakeholders, such as Hospice Care, and other affected secondary stakeholders, such as Security, Engineering, Environmental Management / Housekeeping, Information Technology, etc.

S. The A/E shall review the Contractor's requests for information and cost proposals for construction change orders when requested by the COR. The A/E's reply regarding his/her review of cost proposals and his/her recommendations shall include an independent breakdown of costs in detail, quantities, and unit prices and shall cover both additions and deductions of labor, materials, and equipment. The A/E shall also supply cost estimates as requested by the COR for Request for Proposals for anticipated changes.”

IV. BASIS FOR DESIGN

A. Department of Veterans Affairs standards and VA Office of Construction & Facilities Management Design Guides can be obtained from the Internet at http://www.cfm.va.gov/TIL/.

B. Design Criteria including manuals, guides, processes, and equipment lists are located at https://www.cfm.va.gov/til/criteria.asp C. Design shall conform to the latest 003C2B-DA-142 (06-01-14) Patient Safety in VHA Bathrooms http://www.cfm.va.gov/TIL/dAlert/dAlert142.pdf D. VA PG 18-13 Barrier Free Design Standard.

E. Comply with Nurse Call design guidance and requirements per NFPA 99, UL 1069 and facility standards. Discussions regarding new facility system/standard shall be addressed during Schematics. VA design guidance can be found on the TIL at https://www.cfm.va.gov/til/dManual/dmTelecomm.pdf. Design guides (PG18-12) shall also be reviewed to ensure compliance. https://www.cfm.va.gov/til/dGuide.asp F. The A/E shall design for a total construction budget of approximately $13.5 million. The planned budgetary amount will be provided during negotiations. The A/E design and estimate shall be within the total construction budget prior to viable deductive construction alternates. This will require individual estimates by clearly defined, easily deductible areas and/or portions of work. The A/E shall not plan to infringe upon the contingency as part of their cost control measures. The contingency includes changes and additional construction period work and is utilized/obligated the VA’s discretion, only when the CO and CORs are in agreement.

G. Comply with current federal, national, and international building codes and applicable state and local building codes and standards, as well as codes/standards from other recognized authoritative bodies. This includes, but is not limited to, authoritative bodies such as Associated Air Balance Council (AABC), American Concrete Institute (ACI), Acoustical and Insulating Materials Association (AIMA), American National Standards Institute (ANSI), American Society of Heating, Refrigeration, and Air-Conditioning Engineers (ASHRAE), American Society of Mechanical Engineers (ASME), American Society for Testing and Materials (ASTM), Gypsum Association (GA), International Building Code (IBC), National Electric Code (NEC), National Fire Protection Association (NFPA), National Environmental Balancing Bureau (NEBB), National Standard Plumbing Code (NSPC), Occupational Safety and Health Administration (OSHA), Sheet Metal and Air Conditioning Contractors’ National Association (SMACNA), Electronic Industry Alliance/ Telecommunications Industry Association (EIA/TIA), American Disabilities Act (ADA), American Barriers Act (ABA) and other applicable codes referenced in the VA design guidelines and Master Specifications. Designers shall indicate each applicable code with the current date, revision, version indicated on one sheet, including each applicable VA Guidelines / Standards. Submit this with the Schematic Design Submission and include with the drawing packages H. Comply with VA HVAC Design Guidelines at www.cfm.va.gov/til/dGuide/dgMH.pdf. Indoor air quality requirements must be met / maintained, such as pandemic readiness, outside air percentages, air changes / CFM, and humidity. Design shall maintain building envelopes to prevent moisture infiltration and possible mold growth.

I. Comply with VHA National Center for Patient Safety. http://www.patientsafety.va.gov/ J. Comply with H-18-8 Seismic Design Requirements and its adopted edition of the ICSSC RP Standards. https://www.cfm.va.gov/til/seismic.asp K. Comply with VA TIL, PG-18-3, Design and Construction Procedures for this Minor category project. http://www.cfm.va.gov/TIL/cPro.asp L. Comply with VA TIL, PG-18-15 for A/E Submission Requirements (attached). http://www.cfm.va.gov/til/aeDesSubReq.asp (Click Minor and NRM Projects).

M. Any deviation from project requirements, guidelines, standards, or specifications shall be requested in writing and approved by the VA. The deviation request shall include an item for which deviation is requested and the reason or basis for the deviation. Designer shall maintain as list of any approved deviations with their reasoning and resolution. Code sheets shall be updated as appropriate.

N. Comply with energy requirements. See TVHS Energy Requirements and Design Guide (attached) and ASHRAE 90.1-2010.

O. Ensure proper life safety and VA accessibility requirements. Code Analysis will be clearly defined on the Index Sheet of the Construction Documents.

P. Comply with the Physical Security Design Manuals for VA Facilities. This is a Mission Critical Facility. http://www.cfm.va.gov/til/spclRqmts.asp#PHS.

Q. The required stamp of the licensed architect(s) and engineers of record will be considered as certification of compliance with the contract requirements. The registered individuals who stamp the final construction bid documents shall be the same lead designers that accomplish the assessments, surveys, interviews, and design work. Assessments shall also be stamped.

R. The Certification and Accreditation (C&A) does not apply, a Security Accreditation Package is not required.

V. DETAILED SUBMISSION REQUIREMENTS

Program Guide PG-18-15 establishes the guidelines for the A/E submissions. The design shall be performed and submitted in accordance with VA A/E Submission Instructions for Minor and NRM Construction Program. Refer to (http://www.cfm.va.gov/til/aeDesSubReq.asp). These guidelines indicate a minimum level for submission compliance. Certain types of design may dictate more than the minimum to progress the design submissions/reviews and maintain the schedule. In some instances when critical decisions need to be made, adequate, relevant information must be provided timely for the design to progress to meet certain milestone dates. Questions regarding the applicability of specific requirements shall be resolved with the medical center staff, COR and Contracting Officer (CO) prior to any submission deadline. Where “days” are stated, this refers to “calendar” not “work” days.

At each submission, all drawings and support material shall be dated and appropriately labeled above the title block (the number of submissions shall be adjusted according to the project size and scope). In addition of full electronic version of required documents, hardcopies shall be submitted in quantities indicated:

Work Element
Copies
Duration (Calendar Days)

Notice of Award

Design Kick-off Meeting

7 days after Notice of Award

Schematic SD1 (Planning & Concept)
2+ QA & redlines
75 Days after Design kickoff

Government Review

7 Days after VA receipt of SD1

Schematic SD2
2+ QA & redlines
60 Days after VA acceptance of SD1

Government Review

7 Days after VA receipt of SD2

Design Development 1
2+ QA & redlines
45 Days after VA acceptance of SD2

Government Review

14 Days after VA receipt of DD1

Design Development 2
2+ QA & redlines
45 Days after VA acceptance of DD1

Government Review

7 Days after VA receipt of DD2

Construction Document 1
2+ QA & redlines
30 Days after VA acceptance of DD2

Government Review

7 Days after VA receipt of CD1

Construction Document 2
2+ QA & redlines
30 Days after VA acceptance of CD1

Government Review

7 Days after VA receipt of CD2

100% Final Bid Documents
3
7 Days after VA acceptance of CD2

Final Acceptance Review

7 Days after VA receipt of Final Bid Documents

Total Days Design Phase Schedule

355 Calendar Days

A. Solicitation Support Services (Option Line Item) shall be performed for the length of time between the time the option is exercised and award of the construction project.

B. Construction Period Services (Option Line Items) and Commissioning (Option Line Item) shall be performed for the length of time between the time the option(s) are exercised and acceptance of Construction Completion.

C. The VA has 365 calendar days from final acceptance of the design to exercise the option(s) for Solicitation Support Services, Commissioning and Construction Period Services.

D. VA submission review comments may be verbal, noted directly on review sets, or written list. The A/E shall be responsible for compiling & addressing review comments. A/E shall produce & distribute meeting notes or minutes for VA review immediately after each submission review meeting. The A/E is responsible for running the meetings in person (1-2 hours) at the VA Campus where work is being performed, reproduction of all meeting materials for review and producing the agenda, attendance, and full meeting minutes. A design meeting (with lead designers in person) will be required for each submission on site. Group space surveys shall follow each submission review and A/E shall follow with additional onsite investigative work (1-2 hours) to verify conditions and conduct following interviews.

E. A/E shall develop and execute a Quality Assurance (QA) plan that demonstrates the team approach and methodology for design review and improvements and code compliance, including fully documented comments / issues and resolutions / corrections. The QA process shall drive design review, improvement, and code compliance, including fully documented comments / issues and resolutions / corrections. The QA plan shall be submitted to the VA along with the project schedule and shall describe each QA task that will be taken during the development of the various design submission packages, including review of submissions. The design QA effort shall be led by a Senior Design Engineer and a Senior Architect and shall include Senior Designers for each trade. VA COR shall be invited to all QA meetings and reviews. Completion of each QA task shall be initialed and dated by the responsible QA team member. A 100% completed QA review shall be submitted with each A/E design submission, including the final construction bid document submission package. Cost review and cost control shall be part of each phase of the QA process and each design submission. The QA process shall produce deliverables included with each submission package, including but not limited to redline mark-ups and QA issue tracking sheets and a QA overview/narrative. QA teams shall review issues with the design team, so corrections are made prior to submission of each package. QA team shall be involved throughout design, installation, inspection, and testing. A final QA report shall include an overview/main narrative, designer certification letters of compliance for each discipline/trade, and final inspection list and tracking sheet of corrections.QA team leaders shall maintain a tracking sheet, mapping all code compliance issues from inception, review, and resolutions. Tracking sheet line-item activities shall include, date, issue, review and decision, responsible A/E designer and satisfactory resolution. Since the A/E is solely responsible for the design, ‘VA Directed’ shall not be an acceptable explanation of compliance or resolution. The QA team leaders shall simultaneously copy the VA COR and Contracting Officer when producing/conveying any QA work product, (correspondence, observation lists, tracking, etc.). Any issues shall be discussed in group meetings and resolved to the satisfaction of the designers and QA team, then incorporated into the upcoming design submission package.

F. Each submission will include, furnish electronic files in the latest version of Microsoft Office and/or AutoCAD 2020. PDFs of the specifications will also be furnished. Submit hard copies in the quantities identified in the schedule of all drawings (one of which will be half-sized), narratives, tests, and other work products. Construction shop drawings are not required to be completed in AutoCAD.

G. The 100% construction documents submission will include a full set of construction documents including all disciplines/packages and will be sealed and signed by the Architects and Engineers of Record.

H. Submission packages, including the final construction documents, must incorporate/address all VA comments from the earlier submission package reviews.

I. If submission packages, including the final construction documents. are not complete, the A/E must resubmit the package in its entirety.

J. Construction Specifications - Project specifications shall include specifications for all products, materials, equipment, methods, and systems shown on the construction drawings per standard professional practice and the resulting contract. The specification submitted for review shall include: The name of the manufacturer, the product name, model number, or other identification as appropriate to identify the product that will be used in the construction.

K. Final bid documents shall be reproduced as part of the contract. Two (2) full sets and two (2) half sets of the Construction Bid Documents are to be delivered to the COR. Electronic files of the Construction Bid Documents will be provided to the COR and CO.

L. Total time to accomplish Schematics, DDs, and CDs through final reproduced bid documents shall be 355 calendar days from the issuance of the Notice of Award. A/E shall prepare a schedule, including all design work, submissions, trips, reviews, demonstrations, testing, and other tasks/activities based upon their understanding of the design and their staffing workload.

VI. Solicitation Support Services (Option Item) A. Solicitation Support Services (Option Line Item): The A/E shall provide the following solicitation support services during the construction project’s solicitation phase:

a. Attend the pre-bid site visit, to include meeting and project walk-around.

Contractors are invited to the job site to visually inspect the construction site to accurately develop a construction bid package.

b. Answer any technical questions/requests for information (RFIs) received from contractors over the duration of the solicitation, including questions asked following the site visit.

B. Questions from contractors may come at multiple times and cover several questions over the course of the solicitation period. Technical question responses will be provided to the Contracting Officer, who will distribute the information via amendment to the solicitation.

Answers to RFIs will be required from the A/E within five (5) calendar days of the date the questions are sent to the A/E from either the project COR or CO. An alternate response period may be submitted for review, however, unless approved by the CO and COR, the A/E is required to comply with the five-calendar day requirement.

C. Throughout the solicitation period, the A/E shall provide addenda as necessary if required to revise specs and drawings.

D. In response to any technical questions and/or addenda issued during the solicitation period, the A/E shall provide any final revisions to the 100% Construction Documents as part of the construction contract. These documents shall be labeled Final Construction.

VII. CONSTRUCTION PERIOD SERVICE REQUIREMENTS (Option Items) A. Review of Submittals: A/E shall review all material submittals, shop drawings, test reports (as applicable), etc. Reviews shall be completed, and submittals returned to the VA COR within Seven (7) calendar days of the A/E's receipt of the submittal.

B. Review Analysis of Requests for Information (RFI), Change Orders, and Costs: The A/E shall review the Contractor's requests for information and cost proposals for construction change orders when requested by the COR. The A/E's reply regarding his/her review of cost proposals and his/her recommendations shall include an independent breakdown of costs in detail, quantities, and unit prices and shall cover both additions and deductions of labor, materials, and equipment. The A/E shall also supply cost estimates as requested by the COR for Request for Proposals for anticipated changes. The A/E shall provide a prompt response when contacted by the CO, or COR, to review and provide analysis of construction contractor requests for information; change orders; and resulting cost adjustments due to omissions, errors, ambiguities, etc. RFI response time shall be no more than five (5) calendar days.

C. Site Visits: A/E shall provide 40 site visits (1 designer onsite for 3 to 4 hours) during the construction period when requested by the CO, in addition to pre-bid site survey/conference, structural base and footing inspections, in-wall inspection, above ceiling inspection and final inspection of each phase. A site visit “unit” is defined as a visit to the site by one individual for any part of a day when requested by the CO or COR. Multiple “units” when more than one individual or an extended period is needed to inspect an area of work. Only registered architects and engineers familiar with the project may make these site visits. The CO has the prerogative to determine the professional discipline(s) required for each site visit. The A/E shall notify the COR of their presence on site to document the number of individuals who are making the site visit. The A/E shall observe the construction, advise the COR of any deviations or deficiencies, and recommend appropriate corrective actions.

D. The A/E, when requested, shall assist the CO and COR to interpret the construction documents and shall: (1) recommend any action(s) deemed suitable for the satisfactory execution of the construction work; (2) prepare any supplemental drawings, specifications or other documents that may be required to clarify or supplement the construction documents; and (3) assess the preparation of Construction Contract Modifications initiated by or through VA to be executed in accordance with the Construction Documents.

E. The A/E shall review the Contractor's requests for information and cost proposals for construction change orders when requested by the COR. The A/E's reply regarding his/her review of cost proposals and his/her recommendations shall include an independent breakdown of costs in detail, quantities, and unit prices and shall cover both additions and deductions of labor, materials, and equipment. The A/E shall also supply cost estimates as requested by the COR for Request for Proposals for anticipated changes.

F. "Record Drawings" Requirement: A/E shall revise the solicitation documents if necessary and provide a complete set of all drawings showing actual, completed construction, and reflecting any changes incorporated in the work on hard (bond) copy and on electronic media. Electronic media drawings shall be in AutoCAD 2020 and always electronically stamped. A/E shall load and demonstrate full AutoCAD compatibility at VA site. Compatibility means that data can be accessed directly by the target system without translation or processing of data files. Problems shall be corrected to the satisfaction of VA. Final electronic media specifications shall be in Microsoft Word 2016 and Adobe PDF.

VIII. MATERIALS TO BE FURNISHED TO THE A/E BY VA

The following items will be furnished to the selected A/E:

A. Available electronic media of the station site plans and building floor plans. The station does not have electronic versions of utilities (mechanical, electrical, plumbing, etc.). The accuracy of drawings is not guaranteed and shall be used for general information only. Actual conditions shall be field verified by the A/E.

B. Utility and structural drawings will be made available to A/E at the TVHS Projects Section. A/E is to view drawings needed and may remove (same business day sign-out) to make copies at an offsite location.

C. The TVHS Energy Conservation Project Requirements and Design Guide D. Facility Condition Assessment report E. Hospice Unit space programming plan (VA SEPS) will be provided during negotiations with the selected A/E. This A/E is responsible for reviewing the space programming, discussing issues and adjustments, resolving issues as part of schematics.

IX. ATTACHMENTS

A. Attachment 1: TVHS Energy Requirements and Design Guide - Sep 2014 B. Attachment 2: PG 18-15 AE Submission Requirements