SOW_5G SA Lab Netwk Expansion.pdf
PDF 659 KB Posted
- Attached to
- 5G SA Lab Network Expansion Federal contract opportunity
- Solicitation number
- NB671000-22-01668
View the file
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
St at em en t o f W or k
Statement of Work: 5G SA Lab Network Expansion 1 Last Saved: 8/15/2022 9:49 AM Double-click on for further assistance.
Use this Statement of Work document to purchase an item and/or item-related services.
TITLE: 5G SA Lab Network Expansion Requesting Lab/Division/Group: Public Safety Communications Research Laboratory, Division 671 Requisition Number: NB671000-22-01668
Statement of Need The Public Safety Communications Research (PSCR) Division of the National Institute of Standards and Technology (NIST) is in the process of expanding its Long Term Evolution (4G LTE ) lab network toward the 5G Stand Alone (SA) network architecture. The aim of the expansion is to support PSCR core research projects in assisting public safety first responders fulfilling their missions.
Having the Polaris 5G SA and 5G Non-Standalone (NSA) virtual EPCs and Nokia 4G LTE radio network (RAN) units already in the lab, it is logical that the PSCR lab would expand the network with 5G SA new radio (NR) gNB elements to achieve the 5G SA network architecture. Since the existing 4G LTE RAN units are Nokia specific the new 5G SA gNBs, new 5G Airscale Baseband cards and to-be-upgraded 4G LTE units and associated software shall be Nokia’s manufactured and supplied products to meet compatibility requirements with existing Nokia products in the lab.
More specifically, this expansion effort will include new software, software upgrades and new hardware elements for the Nokia Airscale Baseband unit, and software upgrades for 4G LTE eNB radio units, new 5G sub-6 GHz and millimeter wave (mmW) NR gNB units. Besides the hardware components, the procurement shall include all the related operating software and updates, all necessary wiring including RF and fiber optic cables and connectors, installation and configuration, integration and technical support, training, warranty and maintenance for the installed elements. NIST will provide 48 VDC and 120 VAC power sources and related circuit breakers. All new and ugraded items shall be compatible with the latest 3GPP release for 5G SA network at the time of installation and configuration, or at the minimum 3GPP Release 15 or newer.
Items and/or item-related services Section Requirements Related Information Items/Service (required)
Upgrade existing Airscale Baseband 473095A/96A/98A to support 5G SA operation
One (1) AWEWA n260 mRRH
5G BBU cards
AC power version. Shall be configured initially 5G NSA and reconfigured to 5G SA whenever the support is first available.
em en t o f W
Statement of Work: 5G SA Lab Network Expansion 2
One (1) AWHQE n78 mRRH One (1) AHCE n5 mRRH End-to-End project management.
Software upgrades for existing 4G LTE RAN units to be identified at a later date.
4G/5G Radio Site Survey, Planning, Databuild, Deployment, Acceptance
4G/5G Radio SW Support - Bronze (8-5) SLA + 4G/5G SW Upgrade
4G/5G Radio HW Support – Next Business Day
(NB)
☐ See attached document for detailed specifications
DC power version DC power version Upgrades shall include revised or new SCF files for the 4G LTE RAN units.
All deliverable, operational and related software shall be compatible with the latest 3GPP Release for 5G SA, at the minimum 3GPP Release 15 or newer.
The Contractor is responsible for providing all wiring including RF cables and connectors, fiber optic cables and connectors for the installation. NIST will provide fiber optic cable between two physical rooms if needed. Utilizing the 48VDC and 120 VAC power sources and the available patch panels, routers and switches in the lab the Contractor shall provide all elements that are needed for connections among the installed units.
Shipping & Delivery ☐ N/A
Delivery information by item ☒ Phased delivery is acceptable ☐ Software on USB / disk required ☒ Software electronic delivery acceptable Email address for software delivery
Software deployment via electronic delivery is acceptable, if applicable. Shipping & Delivery cost for the hardware to the NIST site in Boulder CO is to be included in the submission.
Installation ☐ N/A
On-site installation and services shall be provided by the Contractor. The Contractor is responsible for the installation of the hardware and ensuring that all components are able to power up. The Contractor shall configure, commission and integrate all the acquired equipment to PSCR lab 5G SA core network and 5G NSA core network.
Installation shall include, at a minimum, Installation will take place between 8:30 AM and 5:00 PM Mountain Standard Time, Monday through Friday (except Federal Holidays).
NIST Boulder Site is located at:
325 Broadway, Boulder, CO 80305 em en t o f W
Statement of Work: 5G SA Lab Network Expansion 3 uncrating/unpacking of all materials, installation and configuration of all of the acquired equipment, demonstration of specifications, and removal of all trash. The acquired equipment shall operate to manufacturer’s specifications upon installation.
☒ Site visit recommended
Additional information on Security, Safety, and Vehicle Registration in:
6700X-Upgrade 4G LTE RAN to 5G SA-General-Information.docx.
Delivery of all units shall take place earlier but no later than 20 weeks after receipt of purchase order.
Installation and configuration shall take place earlier but no later than 12 weeks after delivery of units.
Inspection and Acceptance ☐ N/A
The Contractor shall demonstrate that all units are operational according to the manufacturer’s specifications. The deliverable and installed equipment shall be configured and integrated with the PSCR Lab Polaris 5G SA EPC and 5G NSA EPC emulators in collaboration with NIST and Polaris personnel for the overall integration effort. NIST will inspect and perform basic operation to ensure that the requirements have been met. NIST shall not sign off on the acceptance until an end-to-end call with a commercial handsets/UE, i.e., originating and terminating calls between two handsets via the network, has been completed on the installed and integrated system.
☒ Government acceptance expected to take longer than 7 days
Enter related information here
Warranty
Extended Warranty Required If you require an Extended Manufacturer Warranty, describe the warranty requirements.
Period Length:One year
The agreement shall cover all parts, labor and travel (if required).
The warranty shall commence upon successful completion of delivery, installation, deployment and demonstration of all required specifications.
☐ Option Period 1 ☐ Option Period 2 ☐ Option Period 3 ☐ Option Period 4
Training ☐ N/A
Training of NIST personnel on the software features and basic operation of the equipment.
Training shall take place earlier but no later than 4 weeks after successful installation and configuration and acceptance.
Maintenance
☐ N/A
Maintenance requirements to be covered by standard warranty, and standard support ☐See attached document for detailed maintenance specifications Period Length: One year
☐ Option Period 1 ☐ Option Period 2 ☐ Option Period 3 ☐ Option Period 4 em en t o f W
Statement of Work: 5G SA Lab Network Expansion 4
Repair
No repairs included outside of warranty period.
Describe your repair requirements.
Period Length: Ex. month, 6 month, year etc.
When NIST reports a hardware failure the Contractor shall send NIST a unit replacement within NBD. NIST shall send back the broken unit for repair.
☐ Option Period 1 ☐ Option Period 2 ☐ Option Period 3 ☐ Option Period 4
Government Furnished Material / Equipment ☐ N/A
Access to NIST/PSCR lab 5G SA and 5G NSA cores/emulated cores/virtual cores
Enter related information here
Travel ☐ N/A
Describe any travel requirements Vendor: To the maximum extent possible, include as part of appropriate sections above (maintenance, repair, etc.).
Otherwise, it will be a separate line item, reimbursable per the Federal Travel Regulation.
Enter related information here