SOW 58301_TAB_0324_420_Miranda_Davit_anl_Inspct_Rpir.docx

DOCX document 46 KB Posted

Attached to
USCGC HEALY PORT & STARBOARD MIRANDA DAVIT REPAIR
Solicitation number
70Z08526Q024372
Issued by

About this file

This is a Statement of Work (SOW) for inspection and repair services on the Port and Starboard Miranda Davits aboard USCGC Healy. The contractor must provide comprehensive inspection, testing, and corrective maintenance services for both davit systems, including operational and load testing, component disassembly, inspection, repair, and reassembly. Work is scheduled for April 30 – May 8, 2026, at Vigor Drydock in Portland, Oregon. Evaluation criteria include cost, technical expertise, and past performance related to Miranda Davits. Contractors must submit resumes and applicable past performance documentation to the contracting officer before the solicitation closes on April 30, 2026.

The contractor must furnish a certified Technical Representative from Palfinger Marine to oversee all critical work phases and provide manufacturer's proprietary information, software, and tools. The contractor supplies all tools, materials, and equipment including testing equipment (dynameter and water bags) and specified replacement parts (disc brake linings, oil seals, filter breathers, return filters, and winch O-rings). Required work includes operating and servicing the entire system per standards, inspecting and lubricating wire ropes, performing hydraulic system integrity checks with fluid analysis, inspecting structural and mechanical components, examining electrical and control systems, conducting touch-up coating repairs, fabricating test load label plates, and performing final operational and weight testing. The solicitation is a Request for Quotations (RFQ 70Z08526Q024372) issued as a small business set-aside under NAICS code 336611 with a small business size standard of 1,250 employees, using simplified acquisition procedures on a firm-fixed-price basis.

View the file

Other files

File Type Posted
This is a combined synopsis solicitation 70Z08526Q024372.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Scope of Work CGC Healy Port & Starboard Miranda Davit Inspect and Repair

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to inspect, test and conduct corrective maintenance for the Port and STBD Miranda Davits.

1.2. Evaluation Criteria: contractor will be evaluated based on the following criteria: cost, technical expertise and past performances relating to the Miranda Davit.

1.3. Solicitation requirements: Contractor must submit a resume and a list of applicable past performances to the contracting officer (KO) before the solicitation period ends.

1.4 Government-furnished property.

None

2. REFERENCES

2.1 For any listed references to be distributed, the contractor must be registered in the Joint Certification Program (JCP) through Defense Logistics Agency (DLA) and provide your JCP number and expiration date to the listed point of contact (POC) for this work.

Coast Guard Publications Coast Guard Technical Publication 4668, MIRANDA DAVIT - MODEL MRT 3900 - Installation, operation and maintenance manual Coast Guard Technical Publication LR-H5-0008-V1 DAVIT WINCH & HPU, RESCUE BOAT (RHIB) – TYPE MRT 3900-BH7800-961045-1 – VOLUME 1 Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and Allied Processes Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), 2022, Auxiliary Machinery Systems Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ships Structures

Other References

NAVSEA S9583-AR-MMC-010, VOL 1, Davit, Winch & HPU, Rescue Boat (RHIB)

3. REQUIREMENTS

3.1 General.

Planned Period of Performance: 30 Apr – 8 May 2026 Location: Vigor Drydock, 5555 N Channel Ave, Portland, OR 97217

3.1.2 Technical Representative. The Contractor must provide the services of a certified Tech Rep from Palfinger Marine to accomplish the following tasks on site:

Provide manufacturer's proprietary information, software, and tools pertinent to the equipment/system.

Assist with proper repair methods, and ensure compliance with manufacturer's procedures and standards during disassembly, inspection, repair, modification, calibration, and reassembly of the equipment/system.

3.1.2.1 The Technical Representative must be present for all critical phases of the work such as operational and load testing, disassembly and reassembly stages for removal, inspection, renewing or repairing, installing, testing and calibrating each davit’s components.

3.1.3 Protective measures. The Contractor must furnish and install suitable covering to seal off and protect all non-affected surfaces/equipment and spaces in the vicinity of the work area against contamination during the performance of work. Upon completion of work, remove protective material and inspect for the presence of contamination. Clean all equipment and spaces, contaminated due to improper protection, to original condition of cleanliness.

3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences).

3.1.5 Tools and Materials. The Contractor is responsible for providing all tools and materials including eight testing equipment like dynameter, and water bags.

3.1.6 Contractor Furnished Equipment: Contractor must provide the following parts:

Part
Part Number
Quantity
DISC BRAKE LINING
DVP0001
2
LINING, BRAKE SHOE
WIN0001
2
OIL SEAL
OLS0001
2
OIL SEAL
OLS0010
2
OIL SEAL
OLS1250
2
BE WINCH ORING
RM1145-30
2
FILTER BREATHER
SES3-40-S80
2
RETURN FILTER
RF-070-G10-B
2

3.2 Operate and inspect. “Operate and Inspect” the entire system in accordance with paragraph 3.2.1 of SFLC Std Spec 5000. Submit CFR.

3.3 Service and Inspect. “Service and Inspect” the entire system in accordance with paragraph 3.2.2 of SFLC Std Spec 5000 and perform the weekly, six weekly and annually maintenance tasks as specified in CG Tech Pub 4668 Chapter 6. Ensure centrifugal Clutch/brakes are opened and inspected. Submit a CIR documenting results of all inspections and any recommended repairs.

3.4 Groom and Lubricate. After completion of all maintenance and repair work groom and lubricate the entire system in accordance with paragraph 3.2.6 of SFLC Std Spec 5000 and Tech Pub Remove, clean, lubricate and reinstall all cradle rollers to ensure all roll freely during final weight test

3.5. Inspect and lubricate Wire Ropes. The Contractor must remove the existing fore, center, and aft falls and the center wire ropes. Reinstall wire ropes after inspection and lubrication.

3.5.1 Inspect entire length of wires for kinks, broken strands, corrosion, and any abnormal condition. Measure wire rope diameter in six or more places to determine if diameter has been reduced below the allowable limits as listed in Table 1 below. Submit CIR of inspection results and recommendations.

TABLE 1 - WIRE ROPE DIAMETER

NOMINAL ROPE DIAMETER
MAX ALLOWABLE DIAMETER REDUCTION
9/16" to 3/4"
3/64"

3.5.2 Pressure lubricate the wire ropes with approved wire rope lubricant. The pressure lube system must include a groove cleaner and a scraper.

3.6 Touch-up and minor coating repairs. The Contractor must perform touch-up preservation of the boat davits and foundations. Repair all areas where corrosion is evident. Follow the requirements of SFLC Std Spec 6310. Paragraph 3.1.13. After coating repairs, apply one full cosmetic coat of paint to all davit painted surfaces. Match existing colors. Do not paint over unpainted surfaces and labels. Ensure personnel performing preservation are qualified.

Note Careless painting is one of the most common sources of trouble with davits.

3.7 Label Plate. Fabricate and install a label plate indicating test loads and test date information for the system in accordance with paragraph B2.9 (Label plates) of appendix B of SFLC Std Spec 5000.

3.9.1 Hydraulic System Integrity

3.9.1.1 Hydraulic Fluid Analysis: Conduct a semi-annual sampling of the hydraulic oil from system reservoirs. The sample should be tested for cleanliness/particulate count (target no dirtier than ISO 4406 Code 18/16/13) and water content (not to exceed 0.05% by weight).

3.9.1.2 Component Inspection: Inspect all hydraulic system components, including: Hoses and fittings for any signs of leakage or abrasion. Pumps and motors, checking for loose fasteners, joint leaks, seal leaks, or loss of pressure.

Valves for improper operation, correct relief valve set pressures, and evidence of sticking spools. Cylinders for seal leakage, scored rods, and any deformed joints.

3.9.2 Structural and Mechanical Components

3.9.2.1 Structural Member Inspection: Inspect all accessible structural members to identify any deformed, cracked, or corroded sections.

3.9.2.2 Fastener Inspection: Check for and tighten any loose bolts and rivets on the davit structure and foundation.

3.9.2.3 Wear Component Inspection: Inspect the following parts for signs of wear, cracks, or distortion: Sheaves and drums. Pins, linings, pawls, and ratchets.

3.9.2.4 Hook Inspection and Maintenance: Perform a detailed visual inspection of hooks for any cracking, bending, or distortion. Conduct quarterly hook maintenance: flush with fresh water, visually inspect, and lubricate moving parts with silicon spray (grease should not be used). Determine if the SOLAS hooks are due for the mandatory Five-Year Service and Inspection, which requires forwarding to a factory-authorized service center for NDT analysis and pull testing.

3.9.3 Electrical, Control, and Safety Systems

3.9.3.1 Electrical Apparatus Inspection: Inspect electrical components, including controller contactors, limit switches, and pushbutton stations, for any signs of pitting, corrosion, or deterioration.

3.9.3.2 Sensor and Indicator Verification: Inspect all sensors and indicators over their full operational range to verify there are no significant inaccuracies.

4.1 Final Operational and/or weight test. After completion of all other work, perform the operational and weight testing specified in Appendix B of SFLC Std Spec 5000. Submit a CFR to the contracting officer.

4.2. Points of Contact:

Igor Guerrero – Asset Manager – igor.guerrero@uscg.mil

Martin Joshua – Port Engineer - Joshua.A.Martin@uscg.mil

Trey Thunborg – Engineer Officer - Trey.A.Thunborg@uscg.mil

5. NOTES

This section is not applicable to this work item.

File details come from the government source that posted it. Updated .