SOW - 532 Spindles Re-build.docx

DOCX document 95 KB Posted

Attached to
Spindle Repair Federal contract opportunity
Solicitation number
FA822723QSPIN
Issued by
Department of the Air Force Materiel Command Air Force Sustainment Center

View the file

Other files for this federal contract opportunity

Other files attached to Spindle Repair, newest first.
File Type Posted
Sources Sought - Spindle Repair.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK (SOW)

CMXG 532nd Spindle Re-build

U.S AIR FORCE

309TH COMMODITIES MAINTENANCE GROUP (cmxg)

1/27/2023 CMXG 532nd Spindle Re-build i

TABLE OF CONTENTS

1SCOPE1
2BASIC SERVICES1
3GENERAL SERVICES1
3.1GOVERNMENT FURNISHED PROPERTY (GFP)1
4APPENDIX2
Appendix A – ACRONYM AND ABBREVIATION LIST3

SCOPE

This Statement of Work (SOW) defines the Spindle Re-build. The contractor shall provide all labor, supplies, tooling, and equipment required to rebuild and refurbish spindles back to original manufacturer specifications. The services shall be performed at the contractor’s facility in support of the 309 Commodities Maintenance Group (CMXG) located at Hill Air Force Base (AFB), Utah.

BASIC SERVICES

The Government will ship the Government Furnished Property (GFP) to the Contractor’s facility.

The Contractor shall perform a visual check for the current state functionality and evaluate how extensive of any overhaul the spindles will need. Then the contractor shall overhaul back to manufacturers operating requirements.

The overhaul process will be documented on a Process Completion Certification for every component (CDRL A001). The contractor shall provide a written document for the processed components; this document certifies completion of each spindle being refurbished back to the original manufacturing specifications.

GENERAL SERVICES

0. GOVERNMENT FURNISHED PROPERTY (GFP)

GFP will be issued via hand receipt to the contractor. The contractor shall safeguard all GFP placed into the contractor’s care.

The contractor is responsible for returning all GFP to the Government after repair is complete at the destination specified in the contract, FOB destination unless directed otherwise in writing by the CO.

Appendix A – ACRONYM AND ABBREVIATION LIST

Acronym/Abbreviation Definition

AFBAir Force Base
CMXGCommodities Maintenance Group
COContracting Officer
GFPGovernment Furnished Property
HAFBHill Air Force Base
IAWIn Accordance With
NGNorthrop Grumman
NLTNo Later Than
SOWStatement of Work
TACMTinker Aircraft Commodities Management