Project # 523A5-21-002 Replace Fuel Pumps, Brockton Statement of Work (Design) Scope of Work Provide all professional architectural and engineering (A/E) services necessary to develop complete drawings, specifications, cost estimates, design analysis and narrative reports, construction schedules, project phasing plans, investigations, environmental assessments and coordination efforts, site visits and construction period services associated with removing and replacing failed gasoline and diesel fuel pump stations/systems at Veterans Affairs’ Medical Center (VAMC), 940 Belmont Street, Brockton, MA. The intent of this project is to replace corroded and failed gasoline and diesel fuel pump systems to correct deficiencies similar to the West Roxbury Campus efforts (design and construction documents to be provided for reference). Conduct preliminary project scope meetings and site survey investigations to develop the necessary elements for conceptual layout schemes with proposed alternatives consistent with the VA’s project team goals as prioritized during preliminary project meetings, field surveys and studies.
The intents of this project are to include, but are not be limited to:
· Remove existing gasoline and diesel pumps and all utilities/tanks associated with it, including but not limited to containment, fuel piping, concrete slab, system appurtenances, soil and associated utilities. Environmental protection and restoration design for this area.
· Design for new ballistic hardened combined diesel and gasoline fueling station. Review and propose the optimal design layout and location(s) on campus with drive through ability and ease of snow removal and tank fill-up for VA review and approval. Consider above ground and below ground containment options to present to the VA design team.
· Design elements shall consider the New England environment and climate: canopy/cover; antistatic design; corrosion protection, environmental protection, heaters and exterior radiant heated slab/concrete to avoid freezing/icing.
· Fire protection, suppression, alarm, detection, fire extinguishers, chemical/wet/dry suppression systems are all to be reviewed and considered for the appropriate systems to be included
· Design includes Environmental Assessment and coordination with Brockton Conservation Commission (BCC) and BCC’s subconsultants for environmental impacts, Wet Land/Buffer Zone coordination, clearing of trees/vegetation, Notice of Intent, NEPA CATEX, permits, etc.
· Soil investigation/borings/samples and monitoring for UST removal work
· Topographical surveys.
· Meet VA standards for security and anti-theft measures. This may or may not include safety bollards, cameras, emergency call stations, fencing, PACS and other security requirements.
· Modify/upgrade/replace/ existing utilities that are affected by this work. Include necessary new utilities and tie-ins to include but not be limited to fire alarm, fire suppression, storm drain/catch basins/drainage, electrical normal and emergency power, lighting, mechanical/plumbing/HVAC/ventilation, steam, condensate, and other necessary utilities.
· Review existing electrical system and upgrade as needed for new equipment including emergency power
· Incorporate Infection control measures, Lead and asbestos abatement, Lighting, Signage, Landscape, Controls, Energy and Patient safety features
· Accessibility requirements (ADA, Uniform Federal Accessibility Standards, Massachusetts
· Architectural Access Board Regulations, Architectural Barriers Act)
· At completion of construction, update the WebGIS portal with as-built information
Design work will include, but not be limited to: demolition, excavation, pavement, civil, landscaping, soil investigation/borings/samples, environmental assessment and coordination, utilities, fuel pumps, canopy/cover, security, life safety, underground utility investigations/alterations/relocations, meet the requirements of ASHRAE 90.1 Energy Standard for Buildings (latest edition); environmental impact statements, notification, design and permitting as required by VA, Massachusetts Department of Environmental Protection, and the Environmental Protection Agency.
All personnel will be required to obtain PIV Badging prior to accessing the medical center site.
Any CDs used to store and communicate VA data files will be required to be encrypted and scanned for viruses by the VA.
File Sharing sites established by the contractor will require a request for Outbound Firewall Waiver and a MOU/ISA between the VA and the contractor if data is stored on the contractor’s network.
2.
Description of Work — 2.1 General: Conduct preliminary meetings and site survey investigations to define the necessary elements of the project scope of work fulfilling the goals of the VA’s project team (Engineering Service), and presentation of preliminary layout plans with proposed alternatives to the User Group. Based on User Group meetings and site surveys, prepare a detailed project plan description report pertinent to the project requirements within the constraints of the construction budget consistent with the VA’s project team goals. Through the course of the design phase, it will be necessary to interface with Medical Center staff to ascertain the details of the scope through a series of meetings and periodic submissions of documents. All design submission requirements shall be in accordance to Open ended A/E Contract and conform to the latest editions of all VA criteria/standards/regulations/design guides, etc. (VA’s Office of Construction & Facilities Management web site: http://www.cfm.va.gov ), in addition to Commonwealth of Massachusetts state codes and regulations and national codes and regulations.
2.2 Implementation: Engage the services of all consultants in each discipline deemed to be necessary to fulfill the requirements of the project plan. Each discipline shall document and investigate the relevant existing conditions found, identify/investigate/review the availability of existing building information, and field verify all essential elements pertinent to their discipline. Site investigations shall measure, photograph, video tape, and document the conditions of areas to be renovated and/or impacted. Provide the necessary investigation/inspection/testing/metering of existing utilities to ensure their adequacy for this project.
The A/E shall visit the project site to investigate the information shown on the Government Furnished drawings, record (as built) drawings and other planning documents which are part of this contract. This information is the best available, but the Government does not guarantee its accuracy or completeness. The A/E's investigation of field conditions shall be performed in a competent professional manner in accordance with the Architectural Design Manual PG18-10. It is the A/E's responsibility to research the existing Government documents, determine those that are applicable to the project and request copies from the Government; the Government will not perform a search of Government documents to determine the information that the A/E may need during design.
2.3 Project Development: The A/E shall provide all services required to prepare documents and reports for the subject project consistent with the VA’s project team goals as prioritized during preliminary project meetings, field surveys and studies. The A/E shall determine existing conditions, severity of deficiencies, if any previous deficiencies have been corrected and to identify any conditions which may have previously been unreported. Cost estimates shall be prepared to reflect the cost of replacing the component in a standalone project (i.e., not as part of another project) and all cost for this replacement including but not limited to asbestos removal, required phasing, special field conditions and/or temporary equipment needed during the construction. The completed report shall then be submitted for approval to the Project Engineer.
2.4 Project Design: Based on the approved design development the A/E shall provide all services required to prepare plans, specifications, and other supporting documents necessary to correct the identified deficiencies in priority order. The approved cost estimate and available project funding will be used to determine the amount of deficiencies which will be correct under this project. A complete design including but not limited to determination and evaluation of existing conditions, necessary engineering calculation, necessary design work, independent fire safety/life safety review, IH Services, quantity and cost estimates, bid schedule, construction cost estimates, a proposed construction schedule, design analyses and calculations, a design documentation report, engineering considerations and options report shall be developed for this project.
2.5 Asbestos: The proper identification Asbestos to determine construction costs associated with Comprehensive Strategy & Report phase of this project are considered part of this project. To extent possible existing Asbestos Assessment of the facility will be made available to the A/E. Additionally proper asbestos abatement design and IH monitoring services required during construction to correct the deficiencies selected for the construction design portion of this project shall also be provided by the A/E.
3.
General Description of Services —
A/E shall provide the services indicated in this Statement of Work, Supplement A, Supplement B and Supplement C. These services will be provided in distinct phases:
Conceptual – Preliminary User Group Meetings & Field Surveys
30% Submittal – Schematics
90% Submittal – “CD” Construction Documents
100% Submittal – Bid [Final] Documents
Construction Period Services
Project Close Out Submittal – “As-Built” Construction Documents
3.1 Drawings: The drawings, specifications, and all other submittal items will be prepared using English units of measure.
3.1.1 General: The A/E shall prepare drawings in a manner that clearly and adequately delineates the work to be accomplished by the construction contractor. Design documents will be sufficiently detailed to permit construction contractors to submit responsive bids without visiting the project site. The cover sheet will be signed and stamped by principal of the firm who is a registered Architect or Professional Engineer. All drawings will be created using AutoCAD and National CAD standards. These CAD standards are available on the Internet at the VA’s Office of Construction & Facilities Management web site: http://www.cfm.va.gov .
3.1.2 CAD Files: One CAD (*.DWG) file shall be used per drawing (sheet) applying the VA’s CAD layering and disk labeling protocols. All files shall be IBM compatible and furnished on high quality CD-R disks. Provide in accordance with Supplement “B” sets of drawings (AutoCAD). The computerized version, format and media of the computer disks and files shall be specified and verified by the VA Project Engineer at the time each submission is due (XRF, DXF and ZIP files are not acceptable). Provide durable high-quality plastic storage boxes at each submission for long term archiving of the disks.
3.1.3 Format: All drawings and sketches will be provided in both hard copy and electronic file format. Full-sized drawings shall be developed as “E” sized sheets (30 inches by 42 inches at the trim line) and shall utilize the standard VA title block. Fonts shall be standard AutoCAD, and drawings must be fully compatible with AutoCAD 2019. Drawing file names must relate to the VA project name, discipline and subject as approved by the VA Project Engineer. Drawings shall utilize world coordinate system with standard cross hairs. Each drawing shall have a separate drawing file. Adobe Acrobat PDF files for each AutoCAD file shall be provided.
3.1.4 Fire/Life Safety Review: An independent fire safety and life safety review shall be accomplished at each design submission. Include the cost and coordination for a fire/safety review.
3.2 Specifications … 3.2.1 General: The A/E shall utilize the latest edition of VA Master Specifications as revised and provided by the facility supplemented by the VA Office of Construction and Facilities Management Master Specifications as needed. The VA retains no responsibility for the development or preparation of any specification. While it is recognized that certain Divisions and/or Sections will require significant input from the VA, the A/E retains overall responsibility for these Sections.
3.2.2 Electronic Files: All files shall be IBM compatible and furnished on high quality CD-R disks. Provide in accordance with Supplement “B” sets of specifications (MS Word). The computerized version, format and media of the computer disks and files shall be specified and verified by the VA Project Engineer at the time each submission is due (ZIP files are not acceptable). Provide durable high quality plastic storage boxes at each submission for long term archiving of the disks.
3.2.3 Outline Specifications: The A/E shall develop an outline specification listing the proposed guide specifications and the A/E prepared sections that will be used for the project. The outline specification will list the guide specification number and title for each proposed section. Sections shall be arranged within their respective divisions, in numerical order. New specification sections, developed by the A/E, will be numbered to fall in their respective division at a logical location.
3.2.4 Editing Specifications: The A/E must thoroughly edit and adapt the Specifications to satisfy the project requirements and provide a complete set of construction specifications. The A/E shall notify the VA in writing should there be instances where there are no appropriate Master Specifications available for use. At the VA’s direction the required specifications will be prepared by the A/E. These specifications shall list the essential features, functions, and other factors to clearly indicate the type and quantity of items/work required. All specifications will be prepared by listing parameters and requirements that can be met by several manufacturers. The use of trade names may be used to establish the standard of quality to be met.
3.2.5 Construction Contractor Submittal Register: The specifications require the construction contractor to submit shop drawings, samples, manufacturer’s data, certificates, test reports, and other items to the Government. The A/E shall prepare a complete listing of construction contractor submittal requirements on an Excel Spreadsheet. The spreadsheet shall have a separate line for each required submittal and separate columns for Division, Section, and type of submittal (catalog cut, sample, etc). The register shall be incorporated with the specifications.
3.3 Quantity and Cost Estimates …
3.3.1 Format: The A/E shall prepare quantity computations, cost estimates, and construction cost estimates for this project. All construction cost estimates shall conform to the requirements contained in VA Manual for Preparation of Cost Estimates (latest edition). Manual is available on the Internet at the VA’s Office of Construction & Facilities Management web site: http://www.cfm.va.gov .
3.3.2 Cost Estimate Submittal: Cost estimates shall be submitted in 2 hard copies and in electronic form. THE A/E IS RESPONSIBLE FOR ESTABLISHING INTERNAL CONTROLS FOR KEEPING THE PRJOJECT DESIGN WITHIN PROJECTED CONSTRUCTION FUNDING. THE A/E WILL BE REQUIRED TO REVISE DESIGN AND RESUBMIT COST ESTIMATES AS NECESSARY (AT NO COST TO THE VA) SHOULD COST ESTIMATES EXCEED CONSTRUCTION FUNDING.
3.4 Phasing and Construction Schedules…
3.4.1 Schedules: The A/E shall prepare a proposed schedule for construction that is consistent with the project construction cost estimate. During development of this schedule, due consideration will be given to standard construction practices, durations of tasks, the sequence of construction, procurement of materials, climatic conditions, etc. It is planned that areas in and adjacent to the proposed construction area shall be occupied during construction. The A/E shall develop a phasing plan that addresses this fact and assures smooth implementation of required construction. Special attention will be required to develop a design that can be phased as to allow work to be performed while all services remain in operation and can reasonably maintain day to day operations.
3.4.2 Schedule Format: The construction schedules shall be horizontal bar charts that: a) identify the major construction activities required to perform the work; b) identify the duration of each of the major construction activities; c) identify the critical path network to achieve the work.
3.5 Design Analysis (DA): The A/E shall develop a DA that addresses general project parameters, functional and technical requirements, existing conditions, design objectives, design assumptions, product literature, calculations applicable to the project’s design. Design/Construction Alternatives, existing physical limitation and their impact shall also be included in the DA.
3.6 Quality Control …
3.6.1.
Quality Control Plan: The A/E shall prepare a Quality Control Plan (QCP) which includes the following as a minimum:
· Identification and discussion of all organizational and technical interfaces
· Design team members and their areas of responsibility
· Team members responsible for checking the design
· Team members responsible for checking the electronic files
· Team members responsible for reviewing and submitting the required VA Design Alerts and Quality Alerts
· Project Schedule showing key milestones and review periods
3.6.1.1.
VA Design Alerts and VA Quality Alerts can be found on the internet at the VA’s Office of Construction & Facilities Management web site: http://www.cfm.va.gov .
3.6.2.
Quality Assurance: The A/E is responsible for developing and performing quality assurance reviews of all work to confirm that proper criteria, regulations, laws, codes, principles and professional procedures have been used. This includes work performed by subcontractors. The VA shall review all project submissions but this review is general in nature and should not be considered as part of the A/E’s Quality Control Plan and/or Quality Assurance.
3.6.3 Quality Certification: The A/E shall certify at each submission in writing that he/she has performed quality assurance reviews of that submission.
3.7 Site Visits, Meetings/Conferences, and Discussions …
3.7.1.
Site Visits: The A/E shall perform design site visits as required to accomplish the scope of this project. The purpose of these visits is further define project requirements, observe and evaluate existing field conditions, review any existing documentation, conduct required design meetings, and to gather supplemental site data necessary for performing the design. Reports summarizing the conditions observed, personnel contacted, and data gathered during the visits shall be prepared and included in the Design Development Documentation.
3.7.2.
Design Review Conferences: Design review conferences shall conduct shortly following the issuance of each review Submission. Refer to Supplement B for the proposed schedule, but will typically take place two weeks after the submission date. Design review conferences for the Schematics, Design Development and Construction Document Development phase shall include the A/E Project Manager/Senior Designer. These conferences shall take place at the facilities where the work is being performed.
3.7.3 Site Visit and Meeting Minutes: The A/E shall take notes and prepare minutes for all site visits, meetings and conferences attended. Minutes will be prepared in typed form, signed by the A/E Project Manager, and furnished to project engineer within seven calendar days after the meeting/conference for concurrence and distribution to attendees. Copies of all meeting/conference minutes will be included in each Submission.
3.8 Responsibility after Design Completion: The A/E is required to support the VA should errors or omissions in the documents create problems in bidding or administering the contract for construction. As needed, the A/E will clarify the design intent and correct any errors or omissions in the original documents. The corrections shall be done in a timely manner at no additional cost to the Government. The A/E shall incorporate amendment changes on the original drawings and/or CAD drawings when requested to do so after the bidding process at no extra cost to the Government. In addition, the A/E shall incorporate amendment changes on the submittal registers and submit on a CD labeled with the project title, location, and construction contract number. Also, during the bidding period, the A/E is required to assist in answering all bidders’ inquiries pertaining to the design. If clarifications are required, the A/E will prepare the required amendment. The A/E, however, shall not receive or respond to any direct inquiries from contractors.
3.9 A/E Services during Construction – Construction Period Administration (CPA):
CPA Services shall include, but are not limited to:
· review and approval of construction submittals covering products that have been listed within the contract documents and contractor substitutions, manufacturer’s data/performance sheets, samples, shop drawings, schedules, phasing plans;
· compatibility analyses of different materials and recommendations associated with acceptance or rejection of alternate materials and products;
· responses to Request for Information (RFI);
· change order review and recommendations;
· preparation of cost estimates to Request for Proposal (RFP);
· cost/time/impact estimates and recommendations relevant to design omissions and construction plan deviations.
· site visits as required and/or requested by the VA Project Engineer for inspection of ongoing construction including final tests and inspections; documentation of all necessary site visits to the VA Project Engineer within one (1) week after the visit;
· verification of as-built conditions from contractor supplied marked up prints;
· preparation of as-built documents in accordance with Supplement “B” which the VA will retain permanently;
· IH services associated with any asbestos or lead abatement identified in the project.
The Government may issue a change order for the A/E to provide additional services to such as review of value engineering change proposals, preparation of design modifications, or other similar services during construction.
Electronic Construction Submittals:
· The A/E shall have the capability to electronically review and process construction submittals including digitally signing the Material Approval Submittal. A PDF writer (such as Adobe Reader/Writer or Pro V Nuance, etc.) is required by the A/E in order to process electronic construction submittals.
· The A/E shall provide and manage a file transfer protocol (ftp) site or file share site for the processing of electronic submittals. This file management site shall be set-up to allow the contractor to electronically submit the construction submittals, allow the A/E to review and process the submittals and allow the VA to review and process the submittals.
4.
Incorporated References — The following documents form a part of this contract to the extent referenced are included in the A/E Scope of Work. Design requirements identified in these documents are part of the A/E Required Services. National Codes, Standards and other requirements referenced in these documents also become part of the A/E Required Services. Design Copies of these may be found on the internet at the VA’s Office of Construction & Facilities Management web site: http://www.cfm.va.gov .
Supplement “A” (attached)
Supplement “B” - A/E Submissions of Design Review Materials (attached)
Supplement “C” - A/E Minimum Submission Requirements (attached)
Asbestos Abatement Design Manual (by referenced)
Construction Standards (H-18-3); latest revision (by reference)
Master Specifications (PG-18-1); as revised by facility supplemented with PG-18-1 as needed (by reference)
DVA National CAD Standard Application Guide (by reference)
DVA National CAD Standards & Detail (PG-18-4); latest revision (by reference)
Volume 1 Architectural; latest revision
Volume 2 Site Engineering & Landscaping; latest revision
Volume 3 Mechanical Engineering; latest revision
Section 1 Plumbing & Sanitary
Section 2 HVAC
Section 3 Steam Generation & Distribution
Volume 4 Electrical; latest revision
DVA Special Design Criteria; HVAC, Mechanical, Plumbing, Electrical, Structural, et al (by reference)
National Standard Plumbing Code (NAPHCC) (by reference)
National Electrical Code; latest revision (by reference)
Handicapped Standards; latest revision (by reference)
NFPA; latest revision (by reference)
Applicable VA Design Guides (by reference)
Applicable VA Design Alerts (by reference)
Applicable VA Design Manuals (by reference)
Applicable VA Quality Alerts (by reference)
Applicable VA Equipment Guide Lists (by referenced)
VA Equipment Reference Manual PG-18-6 (by referenced)
A/E Contract Procedures (by reference)
A/E Architectural Review Checklist (by reference)
A/E HVAC Review Checklist (by reference)
A/E Plumbing Review Checklist (by reference)
A/E Electrical Review Checklist (by reference)
A/E Coordination Drawing Checklist (by reference)
Manual for Preparation of Cost Estimates (by reference)
Applicable VA Energy Conservation & Sustainability Program requirements (by reference)
Preparation and Issuance of Construction Solicitation Contract Documents Manual (by reference)
A/E Submission Instructions for Minor and NRM Construction Program (PG-18-15) (by reference)
Barrier Free Design Standard PG-18-13
Minimum Requirements for A/E Submissions PG-18-15
Environmental Planning Guidance PG-18-17
Physical Security Design Manual
Sustainable Design
5.
Design Budget —
5.1 A/E is responsible to develop a design that can be built within budget and function as intended without change orders. The design must be based on the reality of existing site conditions and not solely on “As-Built” drawings. The A/E as part of their site investigation is responsible for confirming all existing conditions that may affect the project construction.
5.2 Cost Estimating: A/E shall be responsible, as part of the Quality Assurance Plan, to develop procedures for tracking estimated construction costs throughout the project design. Cost estimates submitted as part of the submission requirements shall not be used as the sole method of meeting this requirement. The A/E shall notify the Project Engineer when estimated construction costs exceed the construction budget. The A/E shall be responsible for proposing alternates to bring the project cost estimate within the construction budget. A/E shall modify design elements as necessary to keep the project cost estimate within the construction funding level. These changes shall be made at no additional cost to the Government.
5.3 Construction Budget: $990,000 5.4 Deduct Alternates: Shall be utilized in the best interest of the Government for market condition variations to maximize the use of available Government funds. The Government shall select the proposed alternates from the A/E recommendations. Deduct Alternates shall not be used to bring the projected project costs within construction funding. These alternates are designed to assure a contract award and are in addition to the requirement to have a project design and estimate at or below construction funding. The A/E shall incorporate deduct alternates totaling at least 20% of the construction estimate into the project. The deduct alternates shall be clearly identified in the specifications General Requirements section and on the drawings.
5.5 Add Alternates: Shall not be used.
6.
Design Phases —
6.1 Conceptual with Alternatives: Refer to Supplement A and B. Working with the VA Medical Center’s project team (Project Engineer and User Group) the A/E shall propose conceptual needs and requirements with proposed alternatives for the planned scope of work. This task is an iterative process requiring multiple proposals and revisions developed during site meetings.
6.2 Schematics: Refer to Supplement C. A/E shall develop specific design needs and requirements with proposed alternatives. These documents are to be developed from the documents, meeting minutes and recommendations made during the conceptual phase. Any existing utilities and/or equipment which are to be incorporated into the project design shall be reviewed and evaluated to assure that they are indeed there and are in sufficient quantity and condition to do so. Documents for this task define project requirements based on the planned scope of work. All required functional requirements shall be identified and incorporated into the project. All Architectural and Engineering requirements shall be identified and incorporated into the project. A/E shall provide an evaluation of the coordination of the drawings between disciplines; identification of errors, omissions or conflicts found within or between drawings and specifications.
6.3 Design Development: Refer to Supplement C. Any existing utilities and/or equipment which are to be incorporated into the project design shall be further reviewed and evaluated to assure that they are indeed there and are in sufficient quantity and condition to do so. Documents for this task define project requirements based on the approved scope of work. These documents are to be developed from the documents, meeting minutes and recommendations made during the schematics phase. All required functional requirements shall be identified and incorporated into the project. All Architectural and Engineering requirements shall be identified and incorporated into the project. A/E shall provide an evaluation of the coordination of the drawings between disciplines; identification of errors, omissions or conflicts found within or between drawings and specifications. A/E shall provide an evaluation of schedule to meet operating plan, project phasing and market conditions which may affect bidding. It is expected that at the completion of this phase marks the completion of the data gathering portion of the project. The A/E shall have obtained all information required (including site visits) to proceed directly the preparation of Construction Documents.
6.4 Construction Documents: Refer to Supplement C. The A/E shall develop complete drawings and specifications and other documents necessary for the bidding and construction of this project. These documents are to be developed from the documents, meeting minutes and recommendations made during the design development phase. A/E shall perform an evaluation of the coordination of the drawings between disciplines; identification of errors, omissions or conflicts found within or between drawings and specifications. A/E shall provide an evaluation of schedule to meet operating plan Invitation for Bids and Award dates, project phasing, and market conditions which may affect bidding.
6.5 Special Remarks: Cost estimates shall incorporate construction related issues which include but are not limited to materials, systems and construction techniques. Design documents review, analyses and recommendation of cost estimates covering labor, materials, equipment, general conditions and requirements developed for the project. Estimates shall allow for incorporation of review comments, which are within the Statement of Work.
7.
Submittals and Performance Schedule — 7.1 Deliver Submission Documents to the VA Boston Healthcare Project Engineer (MS-138P). The performance period will be project specific and will be specified with each scope of work. Review of material with the VA will take place approximately 14 days after submission.
7.2 Submission Materials and Schedules: Refer to Supplement B. Reproduction, mailing and delivery time is inclusive to the stated durations.
7.3 Government Review and Comment Resolution: The VA will review all submittals identified under this contract for functional and aesthetic relationship. VA review of the A/E’s work shall not be construed by either party to relieve the A/E from any requirements of this scope of work. The A/E will be responsible for taking minutes from submission review meetings and submitting them to the project engineer for concurrence within 7 days of the meeting. Both parties will discuss these comments, if necessary, and attempt to resolve any unsettled issues that may arise from the review. Time for reproduction and mailing is inclusive to the stated durations.
7.4 The A/E may choose to perform work, at its own risk, during the Government review and comment resolution period, however, comments resulting from that review must be incorporated into the design prior to the next submittal. In the event a subsequent design phase is not authorized, the A/E shall incorporate all available review comments into the design to complete the current phase.
7.5 Construction Execution:
Construction Documents to Bidders Date: To Be Determined (TBD)
Bid Opening Date: TBD
Actual Construction Contract Award: TBD
Anticipated Construction Duration: TBD
Construction Completion Date: TBD
8.
Authorized Changes — The A/E shall only accept instructions and/or directions from the assigned Project Engineer. Changes in the project scope of work must be authorized by the VA Contracting Officer.
9. Timely Response - As time is of the essence, particularly during the construction phase, the A/E shall promptly review and approve, disapprove or take other appropriate action upon all the VA requests. The A/E shall submit recommendations on all shop drawings and other submittals and other requests within fifteen (15) calendar days after receipt.
‑ ‑ ‑ E N D ‑ ‑ ‑