This document is a Statement of Work (SOW) for the painting and striping of select parking lots at the Cape Cod National Seashore in Wellfleet, Massachusetts.
The SOW outlines the scope of work, which includes providing all labor, materials, tools, and equipment to paint centerlines, fog lines, parking delineation lines, arrows, stop bars, and crosswalks on the paved parking lots. The contractor is responsible for verifying all measurements and dimensions, as well as minimizing disturbance to the site. The work must be performed according to applicable local, state, and federal codes and regulations. Requirements include environmental protection, safety protocols, and proper disposal of waste and debris. The period of performance includes material submittals within 48 hours and proposed completed work with documentation within 14 days after the notice to proceed. The SOW provides an appendix with estimated quantities and dimensions for three parking lot locations - Truro Highland Lighthouse Public Lot, Marconi Area Trails in Wellfleet, and Herring Cove Beach in Provincetown.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P4324R0050_Amd_0001.pdf | ||
| Sol_140P4324R0050.pdf | ||
| DOL_Wage_Determination.pdf | ||
| B08_Attachment_3_Vol_I_PastPerf.docx | DOCX document | |
| B08_Attachment_4__Limitation_on_Subcontracting_Report_Template.xlsx | XLSX spreadsheet | |
| B08_Attachment_5_Construction_Contract_Administration.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
Painting and Striping of Cape Cod National Seashore Parking Lots
CAPE COD NATIONAL SEASHORE
WELLFLEET, MA
Scope of Work
This project includes preventative cyclic maintenance to select Cape Cod National Seashore’s paved parking lots. Project is for the painting to have visible centerlines, fog lines, parking delineation lines, arrows, stop bars and crosswalks.
The Contractor shall provide all labor, materials, tools, and equipment required to complete this work. All ancillary work, cutting and /or removal of existing work necessary for the installation of new work shall be done as required as part of this contract.
The contractor shall minimize disturbance to the site to the greatest extent possible unless directed otherwise.
All work performed under this contract shall be done in accordance with applicable local, State, and Federal codes, bylaws, and ordinances in effect at the time of this work.
Measurements Estimated dimensions and quantities are provided as a guide only. The contractor is responsible for verifying all measurements and dimensions. The contractor shall take all measurements for quantities of materials and note existing conditions for the installation of new work.
Site Examination It is the responsibility of the Contractor to examine the work site to confirm existing conditions and required quantities prior to submitting a proposal on this project.
PAVEMENT MARKINGS
A. General: Before opening a pavement surface to traffic, remove all conflicting pavement.
markings by sandblasting or other methods that do not damage the surface or texture of the pavement. Make the removal pattern uneven so it does not perpetuate the outline of the removed pavement markings. Lightly coat sandblasted or removal areas on asphalt surfaces with emulsified asphalt.
Parking Lines and Arrows are to be in White Paint for Road surfaces, Center Lines will need to be in Yellow.
Parking space and center lines need to be 4 inches wide.
Where existing and final pavement marking locations are identical, stake the limits of all.
existing pavement markings (no-passing zones, edge stripes, etc.) before any pavement work.
Upon completion of the final surface course, establish line limits for the new pavement for approval before marking. Establish markings according to the MUTCD. In curve widening areas, apply the pavement edge markings at the edge of the traveled way and the centerline.
markings midway between the pavement lines.
Remove loose particles, dirt, tar, grease, and other deleterious material from the surface to be.
marked.
Remove temporary pavement markings the same day permanent pavement markings are applied. Apply markings to a clean, dry surface.
according to the MUTCD.
At least 7 days before applying pavement markings, furnish a written copy of the marking.
manufacturer's recommendations for use. A field demonstration may be required to verify the adequacy of recommendations.
Legends and symbols shall be installed per the dimensions shown on the exhibits or the latest.
edition of the Manual of Uniform Traffic Control Devices (MUTCD).
Ship marking material in appropriate containers plainly marked with the following.
information, as appropriate, for the material being furnished:
1. Manufacturer's name and address.
2. Name of product.
3. Lot/batch numbers.
4. Color.
5. Net mass and volume of contents.
6. Date of manufacture.
7. Date of expiration.
8. Statement of contents (if mixing of components is required);
9. Mixing proportions and instructions; and Safety information.
10. Apply pavement markings in the direction of traffic according to the manufacturers.
recommendations. Apply all markings to provide a clean-cut, uniform, and workmanlike.
appearance by day and night.
Make lines 4 inches wide. Make broken lines 10 feet long with 30-foot gaps. Make dotted.
lines 2 feet long with 4-foot gaps. Separate double lines with a 4-inch space.
Protect marked areas from traffic until the markings are dried to no-tracking condition.
Remove all tracking marks, spilled marking material, markings in unauthorized areas, and defective markings.
Quality Assurance, Safety and Environmental Protection Requirements, Permits and Approvals
The Contractor shall clearly mark and delineate the limits of work activities, access routes, staging areas for approval prior to starting any on-site activities. Equipment shall not be allowed to operate outside the limits of work or to disturb existing vegetation.
The Contractor shall maintain project areas in neat, orderly and safe condition at all times. Contractor shall provide containers for collection and disposal of waste and trash resulting from work. Contractor shall keep dust and dirt pollution to a minimum. Contractor shall be responsible for storage of all materials and equipment; the Park COR and / or Project Inspector must approve contractor’s use of any space on the site in advance.
During the execution of this contract, the Contractor shall conform to the rules and regulations as set forth by the Occupational Safety and Health Administration’s Safety and Health Standards. The contractor shall provide barriers, signage, etc. wherever work could cause injury to workers or visitors.
No radios or smoking (including vaping) will be allowed on the job site. Hardhat use must conform to safety rules and regulations.
The Contractor shall provide and maintain environmental protection during the life of the Contract to control pollution, runoff, or to correct conditions that develop during construction.
Construction equipment shall be kept in good repair, without leaks of hydraulic or lubricating fluids. Contractor must visually inspect all equipment prior to commencing work every day and at the mid-point in the workday for leaks. If such leaks or drips do occur, they shall be cleaned up immediately. Drip pans shall be utilized when vehicles are parked. Confine equipment maintenance to one location. Control runoff in this area to prevent contamination of soils and water. No equipment repair will be allowed on the site.
Equipment shall not be allowed to operate outside the limits of work or to disturb existing vegetation. It is the contractor’s responsibility to ensure that any disturbance or damage done during this project to the existing utilities, landscape, building or government materials, shall be repaired or restored to its original condition by the contractor at contractor’s expense to the government’s satisfaction prior to completion of the job. Restore all disturbed areas, repairing or replacing damaged plants, grasses, and other vegetation, at no additional expense to the Government, to pre-project conditions. Provide temporary barriers to protect existing vegetation.
All debris and removed material is the property of the contractor and is to be recycled or legally disposed of in a manner that is consistent with local and state regulations.
No work shall take place on holidays or weekends. All work areas shall be secured and safe after work hours, on weekends and holidays.
The work shall conform to all applicable state and local codes and shall be made in a neat and workmanlike manner, in accordance with the best practice of the trade. Requirements of the following entities shall be considered minimum:
· Massachusetts General Laws and Department of Environmental Protection regulations and statutes
· Occupational Safety and Health Administration (OSHA)
· National Institute for Occupational Safety and Health (NIOSH).
Workmanship The Contractor is responsible for appropriate Quality Control and workmanship shall be the best of their respective kinds and in full accordance with applicable codes.
When a manufacturer or a standard uses subjective words, e.g., should, could, may, etc., these words shall mean shall, will, required, etc. When the word recommended is used, it shall mean required. When there is a conflict between general and specific provisions, the specific shall govern.
Upon Notice to Proceed, Contractor shall make steady and uninterrupted progress toward the completion of the work of this contract.
Clean-Up After completion of the work, construction debris, excess material and equipment shall be removed from the site and legally disposed of. The work areas shall be left broom clean.
Period of Performance Material Submittals – Due within 48 hours (or 2 business days) of Notice to Proceed.
Proposed completed work with all documentation submittals – 14 days after date of the Notice to Proceed.
Appendix A: Base Location:
Truro Highland Lighthouse Public Lot 2 Bus parking lines 88 lineal feet 3 Cross hatches 74 lineal feet 29 regular Parking spots for 700 lineal feet 2 Handicap spots at 20 lineal feet w/to HC Logos Highland House Parking 4 Cross Hatches 90 lineal feet 17 Parking Spots 340 Lineal feet 10 Parking for 200 feet Five Parallel spots for 150 Lineal feet 4 handicap w/ Logos 9 lineal feet For a total of 1682 lineal feet Option One Location Wellfleet Parking Lots:
Marconi Area Trails Parking lot 8 Traffic Arrows Walkway Crosshatch 152 lineal feet 1130 lineal feet of parking line Option Two Location Provincetown Parking Lots:
Herring Cove Beach (South) 16- 10-foot X 3 foot yellow speed bumps 15 Traffic Arrows 10 Handicap spaces w/logos 2 cross hatch walkways 334 Lineal feet Yellow center line at 145 lineal feet Bike lane a 310 lineal feet.
Total Lineal 8160 lineal feet for 336 parking spaces
Base Location Highland Light Parking Area Truro Map
Option 1 Marconi Area Trails Wellfleet Parking Option 2 Herring Cove Parking Provincetown Lot image1.png image2.png image3.png