This document is a Statement of Work (SOW) for moving a 100 KW generator at the Dale Bumpers National Rice Research Center (DBNRRC) in Stuttgart, Arkansas. The SOW outlines the scope of work, including providing equipment to move the generator, installing it at a new location approximately 75 feet away, disconnecting and reconnecting the electrical and natural gas services, and constructing a concrete pad for the generator.

The SOW also includes requirements for the contractor, such as verifying site conditions, managing the project, minimizing impact on DBNRRC operations, and providing daily progress reports. The contractor must follow applicable codes and standards, utilize bio-based products, and submit a site-specific safety plan. A government representative will inspect and approve the work. The project must be completed within 90 days of the notice to proceed.

View the file

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

United States Department of Agriculture Agricultural Research Service

STATEMENT OF WORK

Move 100Kw Generator

Dale Bumper National Rice Research Center

(DBNRRC)

2890 Highway 130 E Stuttgart, AR 72160

Prepared by Robert Ideker

July 30, 2024

Statement of Work USDA, Agricultural Research Service

Scope Statement

This is for moving a 100Kw generator and rerouting the electrical service. Contractor will provide all labor and materials for the installation of conduit and wiring to facilitate the moving of the generator approximately 75 FT at the Dale Bumpers National Rice Research Center (DBNRRC) 2890 AR – 130 East, Stuttgart Arkansas 72160.

The quote will be presented in MS Word format and the cost breakdown/analysis will be presented in MS Excel.

The contractor shall include all services and field labor, equipment necessary to remove and install new chiller.

Applicable Codes and Standards apply and are not limited to the following:

ANSI - American National Standards Institute.

ASME - American Society of Mechanical Engineers.

NEC - National Electrical Code, NFPA 72.

OSHA - Occupational Safety and Health Administration ADA – Americans with Disabilities Act

All work must meet ARS 242.1M “ARS Facilities Design Standards” for the defined scope of this project in addition to meeting all Local, State and Federal codes, and latest IBC codes.

The document may be found at https://www.afm.ars.usda.gov/ppweb/pdf/242-01m.pdf.

Project Objectives The project consists of the following elements:

1. Provide equipment to move the 100Kw generator to the new location.

2. Provide all labor and materials for installing the generator in the new location approximately 75FT.

3. Contractor will be responsible for removing and replacing a fence at the new location of the generator.

4. Disconnect and reconnect the generator to the electrical service.

5. All exterior new conduits must be rigid, and all connections must be made with weatherproof fittings.

6. Contractor will be responsible for installation of 2” and ¾” EMT conduit from inside the electrical room to outside wall.

https://www.afm.ars.usda.gov/ppweb/pdf/242-01m.pdf

7. Contractor will supply and install all weatherproof junction boxes.

8. Contractor will provide a 5’ x 10’ concrete slab for the generator, the slab must be at least 4” inches thick and have rebar and wire reinforcement.

9. Reroute the natural gas supply to the generator at the new location.

10. This is a turnkey job.

Site Visit

Contractors are encouraged to visit the site and be escorted by a government representative to confirm locations, dimensions, and conditions of the project before a quote is submitted. The site visit shall be for the purpose of observing first-hand any conditions relevant to the completion of this project. No consideration will be given to claims based on lack of knowledge of existing conditions, except where Contract Documents make definite provisions for adjustment in cost or extension due to existing conditions not readily foreseeable.

Contractor must be registered in System for Award Management, (SAM), prior to submitting a quote. Registration can be completed at www.sam.gov/portal/public/SAM

Utilization of Bio-Based Products

The contractor shall utilize products and material based from bio- based materials as applicable, (e.g. bio-based greases; bio-based hydraulic fluids, bio-based absorbents), to the maximum extent possible without jeopardizing the intended end use of detracting from the overall quality delivered to the end user. All supplies and materials shall be of a type and quality that conform to the applicable Federal Specifications and Standards. All supplies and materials to be used in the performance of work described herein are subject to the approval of the Contracting Officer Representative (COR). Products can be found at:

www.biopreferred.gov

Safety

The contractor will submit a Site Safety Specific Plan/Accident Prevention Plan in industry recognizable format to the Contracting Officer within 14 days of contract award.

Contractor shall furnish a Site-Specific Safety Plan (SSSP) and the Government shall review the SSSP prior to the start any construction activities. SSSP shall be in typically accepted industry format.

http://www.sam.gov/portal/public/SAM http://www.biopreferred.gov/

Base

Contractor shall perform the work as specified in the Statement of Work.

All quotes shall be in unlocked MS Word format and all cost shall be detailed and presented in unlocked MS Excel format with formulas working.

All quotes shall be in unlocked MS Word format and all cost shall be detailed and presented in unlocked MS Excel format with formulas working.

Contractor Responsibilities

The project has a base to be performed per the following specifications:

1. Contractor will verify all dimensions and existing site conditions prior to beginning work.

2. Contractor shall keep work area clean daily and take measures to control debris while work is being performed.

3. Contractor is required to manage the project and consult with the Government prior to beginning all work phases.

4. Contractor shall perform work in a manner that minimizes the impact of the work on Government operations, research, and functions.

5. All work must be performed in such a manner as to not adversely affect daily operations of the facility and its workers.

6. Contractor will provide daily reports of work performed to the COR.

7. Contractor shall remove and dispose of all construction related materials from all work areas daily and remove these waste materials from the site on a weekly basis.

8. Contractor must have a superintendent on the jobsite when crews are performing the installation work.

9. Contactor will provide their own restroom facility.

10. Contractor to include commissioning of the new system, and controls tie-in to the existing building automation system (BAS).

Material / Submittals:

The material for the entire work shall include but are not limited to those detailed above necessary to successfully complete the project and deliver a functioning system as required. Submittals on all material used on this project shall be submitted to the EPM, Site RL, and Contracting Specialist as noted in this document. Electronic submittals are acceptable otherwise three written submittals are required.

Installation Procedure:

Contractor will verify all dimensions and site conditions prior to beginning work.

Contractor is required to provide labor, specified material, equipment, and other tools required to perform the job fully and completely. No Government equipment will be available for use by the contractor. The contractor shall always be responsible for protecting his work and ensuring the safety of his crew and ARS employees. Upon completion of the project, the contractor shall remove from the premises all accumulated materials and rubbish caused by the project. Premises shall be left in a clean, orderly, and acceptable condition.

Damage to Property:

Any damage to the Government buildings, utilities, etc. caused as the result of the contractor’s activities shall be repaired or replaced to the satisfaction of the Government.

Inspection and Acceptance:

A government representative shall inspect and approve the work performed on this project. The Contractor shall schedule inspection a minimum of 10 days in advance, in writing, to the Contracting Officer.

Project Schedule:

The completion of this project shall not exceed 90 days from date of notice to proceed. A request for time extension must be submitted to the Contracting Specialist in writing.

Each request must include specific and detailed reasons in support of the schedule alteration.

Work Hours:

Contractor work hours shall be Monday through Friday, seven (7) A.M. to four (4) P.M.

with the exception of Government holidays. Any changes to work schedule shall be submitted to Contacting Officer for written approval prior to schedule change.

Project Contacts

RESEARCH LEADER (RL)

Dr. Yulin Jia Phone: 870-672-6129

USDA, ARS, SEA

2890 HWY 130 East Stuttgart, AR, 72160 Email: Jia.yulin@usda.gov

ADMINSTRATIVE OFFICER (AO)

Raeann Braithwaite Phone: 870-672-8254

USDA, ARS, SEA

2955 Highway 130 East Stuttgart, AR 72160 Email: Raeann.braithwaite@usda.gov

CONTRACTING OFFICER Representative (COR)

Robert Ideker Phone: 870-672-8266

USDA, ARS, SEA

2955 Highway 130 East Email: Robert.Ideker@usda.gov Stuttgart, AR 72160

ENGINEERING PROJECT MANAGER (EPM) & (CO)

Everett Wilson Phone: 720-618-0703 USDA, ARS, SEA Facilities 3550 Main Street, #5121 Houston TX 77002 Email: everett.wilson@usda.gov

AREA SAFETY AND HEALTH MANAGER (ASHM)

Joel Ledbetter (SNARC) Phone: 870-672-8255

USDA, ARS, SEA

2890 HWY 130 East Stuttgart, AR 72160-0287 Email: joel.ledbetter@usda.gov mailto:Jia.yulin@usda.gov mailto:Raeann.braithwaite@usda.gov mailto:Robert.Ideker@usda.gov mailto:everett.wilson@usda.gov mailto:joel.ledbetter@usda.gov

CONTRACTING OFFICER (CO)

Robert Ideker Phone: 662-686-5414

USDA, ARS, SEA

141 Experiment Station Rd. Email: jessica.pacheco@usda.gov Stoneville, MS 38776 mailto:Robert.Ideker@usda.gov

United States Department of Agriculture
Agricultural Research Service
Scope Statement
Applicable Codes and Standards apply and are not limited to the following:
Site Visit
Utilization of Bio-Based Products
Safety
Base
Contractor Responsibilities
Material / Submittals:
Installation Procedure:
Damage to Property:
Inspection and Acceptance:
Project Schedule:
Work Hours:

Project Contacts