STATEMENT OF OBJECTIVES (SOO)

for Fiber Optic Cable to DSL Locations Joint Base McGuire-Dix-Lakehurst, NJ

23 June 2020

Prepared By

38 ES/ENII

4064 Hilltop Road

Tinker AFB OK 73145-2713

SOO – DSL Facilities Fiber Optic Cable, Joint Base MDL, New Jersey 23 June 2019 Page | 28 Table of Contents

1.0SCOPE6
2.0REQUIREMENTS6
2.1GENERAL REQUIREMENTS6
2.1.1Safety Requirements6
2.1.2Site Coordination6
2.1.2.1Cultural Resources6
2.1.2.2Confined Space6
2.1.2.3Accident/Incident Reporting and Investigation6
2.1.2.4Airfield Driving Reserved6
2.1.2.5Work Area(s)6
2.1.2.6Traffic control7
2.1.3Security Requirements7
2.1.3.1Security Clearances7
2.1.3.2Country Clearances Reserved7
2.1.4Environmental Compliance7
2.1.5Permits7
2.1.6Cultural Resources8
2.1.7Integrated Process Team (IPT)8
2.1.8Quality Assurance8
2.1.9Contractor Personnel8
2.1.9.1Project Management8
2.1.9.2Site Point of Contact (POC)8
2.1.9.3Personnel Requirements9
2.1.9.4Minimum Contractor Qualifications9
2.1.10Warranty9
2.1.11Manuals and Practices9
2.1.12Contractor Manpower Reporting Application (eCMRA)9
2.2SPECIFIC REQUIREMENTS9
2.2.1Equipment Cabinets10
2.2.1.1Grounding and Bonding10
2.2.1.2A.C. Power10
2.2.1.3Bushings10
2.2.2Outside Plant Requirements10
2.2.2.1Existing Maintenance Holes10
2.2.2.2Measurements10
2.2.2.3Underground Utilities Markings11
2.2.2.4Closures for Cable Splicing in Maintenance Holes11
2.2.2.5Splice Connectors.11
2.2.2.6Labeling11
2.2.2.7Shield Bonding Connectors.11
2.2.2.8Cable Tags11
2.2.2.9Cable Terminations12
2.2.2.9.1Cable Shields N/A12
2.2.2.9.2Backboards12
2.2.2.10FOC Maintenance Loop12
2.2.2.11New Maintenance Holes/Hand-holes12
2.2.2.11.1Cable Racks and Cable Rack Supports13
2.2.2.11.2Grounding13
2.2.2.12Underground Conduit System13
2.2.2.12.1Composition13
2.2.2.12.2Installation13
2.2.2.12.3Bends and Sealing14
2.2.2.12.4Utility Separation14
2.2.2.12.5Spacers and Tracer Wire14
2.2.2.12.6Warning Tape14
2.2.2.12.7Entrance Conduits into Existing Maintenance Holes14
2.2.2.12.8Excavation/Building Penetrations15
2.2.2.12.9Conduit Bends or Sweeps15
2.2.2.12.10Pulling Tape15
2.2.3Outside Plant Installation15
2.2.3.1McGuire15
2.2.3.1.1EBs 2704 and 2706 Visitor Quarters, EB 3700 United Communities15
2.2.3.1.1.1Infrastructure Installation15
2.2.3.1.1.1.1Manholes/Hand-holes15
2.2.3.1.1.1.2Duct bank Infrastructure16
2.2.3.1.1.1.3Entry Conduit Infrastructure17
2.2.3.1.1.1.4Geotextile Inner-duct (Max Cell)18
2.2.3.1.1.2Fiber Optic Cable Installation19
2.2.3.1.2EB 1922 Fuels Pump House22
2.2.3.1.2.1Infrastructure Installation22
2.2.3.1.2.1.1Manholes/Hand-holes22
2.2.3.1.2.1.2Duct bank Infrastructure23
2.2.3.1.2.1.3Entry Conduit Infrastructure23
2.2.3.1.2.1.4Geotextile Inner-duct (Max Cell)23
2.2.3.1.2.2Fiber Optic Cable Installation24
2.2.4Project Residue25
2.2.5Site Restoration25
2.2.6Service Outages25
2.2.7Configuration Management Reserved25
2.2.8Identification/Marking25
2.2.9Installation Schedules25
2.2.10Weekly Status Reports25
2.2.11Drawings26
2.2.11.1As-Built Drawings26
2.2.11.2Butterfly Drawings26
2.2.11.3Geospatial Deliverables26
2.2.12Test and Acceptance/Installation Test Plan26
2.2.12.1Testing26
2.2.12.2In-progress Testing27
2.2.12.2.1Excavations27
2.2.12.2.2Splices27
2.2.12.2.3Fiber Optic Tests27
2.2.12.2.4Optical Attenuation27
2.2.12.2.5Distance27
2.2.13Acceptance/Installation Test Report27
2.2.14Final Acceptance27
2.2.14.1Training Plan Reserved27
3.0GENERAL INFORMATION27
3.1Period of Performance27
3.2Place of Performance28
3.3Hours of Operation28
3.4Holidays/Down Days28
3.5Base Support28
4.0APPENDICES29
4.1Appendix A: APPLICABLE STANDARDS.29
5.0Attachment 1: Project Sketches30

SCOPE

This Statement of Objectives (SOO) defines the requirements for the Contractor to engineer, furnish, install and test (EFI&T) required manhole/duct-bank infrastructure and fiber optic cable to replace current copper connectivity to four facilities at Joint Base McGuire-Dix-Lakehurst (JBMDL), New Jersey.

2.0 REQUIREMENTS

GENERAL REQUIREMENTS

2.1.1 Safety Requirements

The contractor shall remain in compliance with all Federal, State, county, and base security and safety laws, regulations, policies, and requirements.

2.1.2 Site Coordination

The Contractor shall meet with the base safety officer immediately upon arrival on site for review of the specific safety requirements prior to installation.

2.1.2.1 Cultural Resources

The contractor shall coordinate with JB MDL Cultural Resources Manager before proceeding for a review of any potential impacts to cultural resources.

2.1.2.2 Confined Space

The Contractors and Sub-contractors entering spaces on JBMDL, NJ are responsible for the safety of their personnel and for their own permit space program as outlined in AFI 91-203. All confined space operations must be coordinated with the Base Safety Office prior to start of work. The primary Contractor is responsible for all Sub-contractor confined space operations.

2.1.2.3 Accident/Incident Reporting and Investigation

The Contractor shall record and report all available facts relating to each instance of injury to either Contractor or Government personnel to the 87CS/SCX Project Manager and the Base Safety Office unless otherwise stated in the SOO. The Contractor shall secure the scene of any accident and wreckage until released by the accident investigative authority through the Base POC (87 SFS). If the Government elects to conduct an investigation of the incident, the Contractor shall cooperate fully and assist the Government personnel until the investigation is completed.

2.1.2.4 Airfield Driving Reserved

2.1.2.5 Work Area(s)

At day’s end (16:30), the Contractor shall remove all debris and surplus materials from the work place. Safety barriers shall be in place to protect unfinished work site at the end of the day. All open holes or trenches shall be completely enclosed by flexible orange construction safety fencing, or other safety barriers, at the end of the work day. Equipment and materials required to complete the work effort may remain on site as long as they are organized/stored in a manner that does not cause a safety hazard. The contractor shall co-ordinate with the 87CS to ensure that any locking manhole covers are put back in place at the end of each workday.

2.1.2.6 Traffic control

In the event base vehicular traffic is to be disrupted by trenching or horizontal directional boring, the Contractor shall notify the 87 CS/SCX PM NLT 10 calendar days in advance to inform base Security Forces and Emergency Services personnel of the planned disruptions.

2.1.3 Security Requirements

The Contractor shall process and provide a Site Visit Request Letter to 87 CS/SCX within 5 calendar days after contract award. This letter shall identify the names (as shown on the driver’s license), driver’s license numbers and state of issue, and birth date of the personnel who will be performing work under this SOO. This information is required to grant access to the base. If required by the base, the Contractor shall provide identification badges for their employees. All Contractor personnel shall wear these badges while on duty on the Government site. The badges shall identify the individual, company name, and be clearly and distinctly marked as Contractor and be in accordance with base regulations.

2.1.3.1 Security Clearances

Stated work and associated products shall be performed at the UNCLASSIFIED level. However, some of this work may take place in secure areas where Contractor employees must be escorted at all times. The Contractor must coordinate access to secure areas at least five (5) calendar days ahead of time. It is the Government’s responsibility to provide escorts.

2.1.3.2 Country Clearances Reserved

2.1.4 Environmental Compliance

The Contractor shall comply with the most stringent environmental federal, state, and local laws and regulations; and Air Force policies, instructions, and plans. The Federal Government is not exempt from compliance with environmental regulations. The Contractors are responsible to know and follow all applicable Federal, State, Local and Air Force regulations for environmental protection, including waste disposal, sewer discharge, air emissions, and storm water requirements. The contractor shall maintain an awareness of changing environmental regulatory requirements to avoid environmental deficiencies for activities on JBMDL. The Prime Contractor shall ensure that their subcontractors (if any) comply with these specifications.

2.1.5 Permits

The Contractor shall be responsible to coordinate, complete and process all permits required to complete the installation prior to any trenching, horizontal directional boring or modifications to a facility, maintenance hole or hand-hole. For example:

· Digging permit, AF Form 103 shall be submitted through BCE 14 calendar days in advance of digging activities. The Contractor is responsible for maintaining all markings and for ensuring AF Form 103 remains current.

· Confine space entry permit, AF Form 1024 shall be coordinated through base safety office. The Contractor shall be prepared to provide proof of their Confined Space Training Program along with the AF Form 1024 to base safety.

· Base Civil Engineering Work Clearance Request, AF Form 332 shall be submitted through BCE 14 calendar days in advance of planned work.

All utility markings, flags, etc. shall be maintained by the contractor after the responsible work center/shop identifies/locates them and ensure that the AF Form 103 remains current. The contractor shall take precautions to protect existing infrastructure. If a utility is severed or damaged due to neglect or if attributed to the fault of the contractor, then the contractor shall repair and return the utility back to the same condition it was in prior to the damage.

2.1.6 Integrated Process Team (IPT)

The Contractor shall chair a weekly IPT meeting that includes Contractor representatives, the Government Contracting Officer (CO), the CSI-B, the System Engineer(s), the Government Project Manager, and other base personnel as required. The Contractor shall provide an agenda NLT 1 working day prior to the scheduled meetings. The Contractor shall provide worldwide “Meet Me” teleconference capability for the duration of the project. The purpose of the IPT meeting is to discuss project progress, problems being encountered, and other information necessary/beneficial to ensure success and timely completion of contract requirements. The Contractor shall record meeting minutes and distribute to the attendees NLT 1 working day after each meeting.

2.1.7 Quality Assurance

The Contractor shall provide Quality Assurance Support for the entire life of the project. The Contractor’s quality assurance evaluator shall assist the Government representative in performing random spot checks and system acceptance tests. The Contractor shall be responsible for identifying system and outside plant deficiencies and/or discrepancies throughout the life of the project. A weekly report (soft copy) shall be submitted indicating progress/status and listing any deficiencies/discrepancies found and actions to correct them.

2.1.8 Contractor Personnel

2.1.8.1 Project Management

The Contractor shall provide a Project Manager (PM) and alternate(s) responsible for contract performance and continuity. The Contractor shall identify the Project Manager’s or alternate's range of authority to act for the Contractor relating to daily contract operation.

2.1.8.2 Site Point of Contact (POC)

The Contractor shall designate the Contractor's on-site team leader and alternate(s) as the Site POC for individual projects in their Site Visit Request Letter. The Site POC or alternate(s) shall be on site during duty hours for the duration of the project, up to and until final acceptance by the Government PM and shall oversee all facets of the installation tasks. The Site POC shall be the interface for all work site communications with the Government, including quality, safety, and discrepancy matters.

2.1.8.3 Personnel Requirements

The Project Manager, Site POC, and respective alternate(s) shall be able to read, write, speak, and understand English and shall be on site to coordinate permits, clearances, and receive shipments/material related to the task order.

2.1.8.4 Minimum Contractor Qualifications

All work shall be performed by an experienced Telecommunications Contractor. The Contractor shall have a minimum of 3 years of experience in Telecommunications Systems installations.

2.1.9 Warranty

The Contractor shall provide a one year warranty or manufacturer’s standard commercial warranty, whichever is longer. This warranty shall include a one year workmanship warranty. The warranty period shall start from the date of system and/or project acceptance. The Contractor shall provide written procedures and required information for warranty services at or prior to site acceptance.

2.1.10 Manuals and Practices

The Contractor shall provide the latest version of operation, installation, and maintenance manuals and practices/users guide for each system installed as provided by the original manufacturer with all new equipment.

2.1.11 Contractor Manpower Reporting Application (eCMRA)

The contractor shall report ALL contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract via a secure data collection site. The contractor is required to completely fill in all required data fields using the following web address http://www.ecmra.mil.

Reporting inputs will be for the labor executed during the period of performance during each Government fiscal year (FY), which runs October 1 through September 30. While inputs may be reported any time during the FY, all data shall be reported no later than October 31 of each calendar year. Contractors may direct questions to the ECMRA help desk.

SPECIFIC REQUIREMENTS

As indicated in this SOO and attached sketches the Contractor shall EFI&T the fiber optic cable and additional duct bank infrastructure required to upgrade and enhance fiber optic cable connectivity from the nearest Information Transfer Building (ITB) to provide service to McGuire Edge Buildings (EBs) 1922 (Fuels Pump House), 2704 and 2706 (Visiting Quarters), 3700 (United Communities) at JBMDL, New Jersey.

The Contractor shall provide all equipment, tools, materials, supplies, transportation, labor, supervision, management, and other incidentals necessary to meet the requirements as stated in this SOO. The Contractor shall comply with the current TIA telecommunication installation and testing commercial standard and base installation standards. All equipment, supplies, and materials provided shall be new and not refurbished.

2.1.12 Equipment Cabinets

All new equipment cabinets shall be lockable and compatible with existing lockable cabinets. Coordinate with the 87CS to ensure a common lock/key in all cabinets matching existing locks/keys. Equipment cabinets shall have sufficient ventilation, cable pathway access, and space to allow for maintenance and operation of the equipment. Consideration must be given to wall mounted cabinets to ensure the long term ability of the cabinet to be mounted, to stay attached to the wall and for the required clearances to service all cabling and equipment installed with the cabinet. Rail settings within cabinets must be secured, be in a level condition and be positioned so all installed hardware and cables interfacing the hardware do not obstruct the closing of doors when door is in its final position. Existing/previously installed cabinets shall be re-used to the maximum extent possible.

2.1.12.1 Grounding and Bonding

All new and existing racks/cabinets housing equipment for this project, as well as all ladder rack/and cable tray shall be bonded and grounded to the Equipotential Ground Plane IAW Mil-Std-188-124B and Mil-HDBK-419A, Volumes I and II. All Equipment racks and cabinet rails shall be Telecommunications style rails that are unpainted and have drilled and tapped mounting holes IAW DISN Implementation Standards, Ch. 2.7.20 to 2.7.26. Equipment cabinets shall be capable of containing any standard equipment shelves for communications equipment per the current revision of EIA/ECA-310. The Contractor shall test any new or extended ground at the cabinet/rack and at the new grounding/bonding points. The government reserves the right to test and validate newly installed grounds to ensure they meet compliance.

2.1.12.2 A.C. Power

Each new equipment cabinet shall have a dedicated 110/120 20A power circuit originating from an existing breaker panel. All electrical work shall be labeled at the circuit panel with room and rack identification and at the equipment end with panel and circuit information. All electrical component work shall be performed in compliance with the NEC, UL Listing, and all local, base, state, and federal codes, requirements and regulations.

2.1.12.3 Bushings

All penetrations into the rack/cabinet must be reamed, filed and have an installed bushing or grommet material. No exposed metal edges shall come in contact with telecommunication cabling.

2.1.13 Outside Plant Requirements

As indicated in this SOO and attached sketches the Contractor shall EFI&T the infrastructure and fiber optic cable required to provide the fiber optic cable connectivity to the four affected DSL sites at JBMDL, NJ.

2.1.13.1 Existing Maintenance Holes

The Contractor shall pump out water as required into the storm drain system. Water may be drained through the pavement or grass area where a storm drain is not available. If necessary, the Contractor shall be responsible for removing mud, debris, etc. from maintenance holes/hand-holes to the extent necessary for the Contractor to perform work in the space.

2.1.13.2 Measurements

Any distances provided in this SOO are approximations and should NOT be used for ordering materials or determining duct lengths.

2.1.13.3 Underground Utilities Markings

The Contractor shall coordinate with base agencies to ensure markings are placed over existing base infrastructure prior to digging or horizontal directional boring and shall take precautions to protect existing infrastructure. The Contractor is responsible for repair of any damage caused during installation when the infrastructure is clearly marked. The Contractor is responsible for maintaining all markings and for ensuring AF Form 103 (Dig Permit) remains current.

2.1.13.4 Closures for Cable Splicing in Maintenance Holes

Intermediate cable splices shall be minimized and consist of fusion splices in a high quality re-enterable splice case. Only splice closures intended for underground applications shall be used in the underground system. The Contractor shall use standard re-enterable fiber splice closures. The closures shall have adequate strength to protect the splice and maintain cable shield electrical continuity in the below ground environment. The Government quality inspector shall have the opportunity to inspect the inside of the splice case before closure pressure testing and encapsulation is performed.

2.1.13.5 Splice Connectors.

All fiber splicing shall be performed in accordance with RUS Bulletin 1735F-401, Standards for Splicing Copper and Fiber Cable. The fusion splice method shall be used for all splicing and terminations of fiber optic cable.

2.1.13.6 Labeling

The Contractor shall label all equipment and cables they install and cables identified for re-use in accordance with TIA-606-B and as directed by the base communications organization. New ducts shall be permanently labeled on the wall of each building/manhole indicating the connecting building/maintenance hole at the other end of the duct (for example, “To MH-200”). The cover of all new fiber optic distributions (FODPs) shall be labeled to conform to the system used by local maintenance personnel to identify FODPs that terminate fiber. If the FODP manufacturer has not identified the sequence in which the ports are counted, the Contractor shall provide designation labels/strips to identify the sequence in which the ports are counted.

Example:FODP 1901
FO 1901-1922, XX-YY

Note: The same information shall appear on the Contractor’s completed As-Built-Drawings.

2.1.13.7 Shield Bonding Connectors.

Shield bonding connectors, bond bars, braids, ribbons, clamps, etc., shall be provided to maintain cable shield continuity at splices and at ground connections. Bonding connectors shall be provided IAW RUS Bulletin 345-65 (PE-33). Cable shields shall be bonded and continuous throughout the cable distribution system.

2.1.13.8 Cable Tags

All tags shall be permanently labeled, easily visible and corrosion resistant. Install cable tags in all maintenance holes/hand-holes, cable vaults, pull boxes and building entrance terminal locations. When cables pass through a maintenance hole, put a tag on the cable, approximately 2 feet from each duct entrance. Information on the cable tag shall identify cable by size, type, cable number and count. Tagging and labeling of new cables shall be IAW the following:

12L8.3F

FO 1901-1922, 1-12

Line One: A = Armored Sheath (otherwise leave blank) 12 = Fiber Count. L = Loose Tube Buffer or (T) Tight Tube Buffer. 8.3 = Single Mode. F = Filled core (otherwise leave blank).

Lines Two - Five: 1901-1922 = From-To Building numbers. 1-12 = Cable/strand Count.

2.1.13.9 Cable Terminations

Newly installed fiber optic cables shall be terminated on new fiber optic distribution panels using fusion spliced pigtails with LC connectors or LC fusion splice direct connectors. Distribution panels shall be designed for rack mounting in 19-in (48 cm) racks or wall mounted as required. Panels shall be sized accordingly to cable and method of termination.

2.1.13.9.1 Cable Shields N/A

2.1.13.9.2 Backboards

Newly installed backboards shall be AF-standard 0.75”-thick plywood, with two coats of white, fire-resistant paint.

2.1.13.10 FOC Maintenance Loop

The Contractor shall install a minimum of a 50 foot fiber optic cable maintenance loop at the first MH from the building, at each splice point MH location and at every third manhole. The maintenance loop shall be properly labeled and securely supported by two cable hooks. Cable hooks are to be positioned so the highest one supports the underside of the top of the coil and the bottom hook supports the underside of the bottom of the coil.

2.1.13.11 New Maintenance Holes/Hand-holes

Maintenance holes installed under this Task Order shall have an American Association of State Highway and Transportation Officials (AASHTO) rating of H-20 or equivalent. Unless otherwise stated, HHs shall have a minimum interior dimension of 3’W x 5’L x 4’H. New hand-holes shall have a self-latching torsion assisted full-opening diamond plate stainless steel 2-piece lid. Hand holes shall be furnished with cable rack hardware, pulling irons, a sump, water resistance gaskets, bonding ribbon and a grounding system. HHs shall meet the requirements of TIA-758-B, paragraph 5.2.2. Prefabricated HHs are preferred.

It is understood that some Maintenance Holes are precast with bonding ribbons or some similar connection, to the manhole rebar and therefore do not require a ground rod. This method of grounding in lieu of a ground rod is satisfactory just as long as the achieved impedance to ground is twenty five (25) ohms or less.

HH shall be installed so that they are reasonably level on a gravel bed of 6 inches to allow drainage of water from the walls. The gravel bed should extend 8 inches to 12 inches beyond the outer edges of the MH/HH. MH/HH covers shall be labeled with 1/8” raised letters stating “COMMUNICATIONS”.

All HHs shall be of concrete construction. Polymer concrete (i.e., Quazite) construction is NOT authorized.

2.1.13.11.1 Cable Racks and Cable Rack Supports

Cable racks shall be installed in maintenance holes and hand holes as required - this includes new and existing MHs/HHs. Splices shall not be supported by the cables that enter each end of the splice case. The splices shall be supported by cable hooks under the splice case. Telecommunications industry standard cable hooks of the appropriate length shall be provided to support cables and splice cases. The cable hooks shall be secured using cable rack locking clips. All cables shall be supported using racking clips, cable racks, and cable hooks.

2.1.13.11.2 Grounding

Grounding hardware such as corrosion resistant wire, bonding ribbon, clamps, ground rod, etc. necessary to properly bond/ground the cable in MHs/HHs shall be provided by the contractor. Reference TIA 607.

2.1.13.12 Underground Conduit System

The Contractor shall be responsible for any required trenching and/or boring necessary to lay the duct system. Contractor is also responsible for backfilling ditch lines and compaction of fill materials with appropriate compaction tools. Provide a minimum of 12" cover of clean fill above the conduit. Backfill material shall be clean and free from all organic material, clay, marl or unstable materials, debris, lumps, or broken paving. No rocks or stones larger than 3 inches in diameter shall be allowed in backfill. Material for backfill may be material resulting from excavation, if it meets the above requirements. Directional drilling will be used for major road crossings. Otherwise, crossing of paved surfaces may be performed by pavement cuts and resurfacing with appropriate matching road material. This does not prevent the Contractor from using directional drilling if it is more cost effective. Ducts will be appropriately protected when placed under paved surfaces.

2.1.13.12.1 Composition

The ducts shall be corrosion resistant and 4-inch inside diameter (I.D.) round or metric equivalent. The ducts shall be made of EPC-40 Polyvinyl Chloride (PVC) (Schedule 40) IAW NEMA TC-2. For unique situations the ducts shall be EPC-80-PVC (Schedule 80) IAW NEMA TC-2, high density polyethylene (HDPE) SIDR 13.5, Galvanized Iron Pipe (GIP) or “thickwall” stainless steel. Schedule 80 PVC shall be limited to risers, all above ground conduit and under the roadway/parking pavement. High density polyethylene (HDPE) SIDR 13.5 shall be used when directional boring is used. GIP or stainless steel shall be used under major roadways, taxiways, and runways. The ducts shall be appropriately labeled indicating the composition material. Ducts shall have a sleeve or bell end type coupling and shall be watertight when assembled. In addition, the Contractor shall adhere to any additional Host Base/site specific requirements.

2.1.13.12.2 Installation

Installation of underground conduits/ducts shall be IAW RUS Bulletin 1751F-643 and RUS Bulletin 1753F-151. Ducts installed beneath roads, sidewalks, parking areas, other paved surfaces or areas to be paved, etc. shall be installed a minimum of 36" below grade. All ducts installed beneath any paved surfaces shall be installed by means of horizontal directional boring beneath the paved surface so as not to damage the existing pavement, unless not physically possible due to geographical or man-made obstructions. In MH with knockouts, ducts shall start at the bottom knockout, allowing for upward expansion in the MH. All ducts not installed across roads, sidewalks, parking areas, or areas to be paved, etc. shall have a minimum of 36 inches ground cover, where possible. The Contractor shall provide other protective measures, concrete cap, etc., in those areas where the minimum ground cover cannot be achieved. Grading of ducts shall be accomplished IAW RUS Bulletin 1751F-643.

2.1.13.12.3 Bends and Sealing

All bends between MHs shall be a minimum of ten times (10X) the diameter of the duct size (i.e, 4 inch duct = 40 inches) with the sum of bends in all directions not exceeding a total of 90 degrees where practical. Coordinate with 87 CS if runs have bends that total more than 90 degrees is required. Ducts shall have bell ends and enter a MH perpendicular to the surface of the wall through which it is entering. All ducts/inner-ducts entering MH shall be sealed. Universal duct plugs or removable putty sealants may be used. Upon completion of conduit sections, a rigid test mandrel ¼” (6.4mm) smaller than the inside diameter of the conduit shall be pulled through two diagonally opposite ducts to ensure proper alignment. In addition, all ducts shall be cleared of loose materials such as concrete, mud, dirt, stones, etc.

2.1.13.12.4 Utility Separation

When communications ducts cross either power duct or buried power cable, maintain a minimum separation of 3 inches of concrete or 12 inches of well-tamped earth between the two or 12 inches of well tamped earth when parallel; for pipes (e.g., gas, water, oil) maintain 6 inches when crossing or 12 inches when parallel.

2.1.13.12.5 Spacers and Tracer Wire

Along the length of the duct run, if the ducts are installed by trenching, spacers shall be placed at an interval of four (4) spacers per 20 feet. At least one duct or roll pipe shall have tracer wire or be otherwise locatable from the surface. All new tracer wire installed for this project needs to have a wire nut and label installed at all wire ends, and those wire ends secured but not connected to grounds. The tracer wire shall be exposed; free from the conduit and capped (insulated). The tracer shall be secured and routed to the maintenance hole or hand-hole neck to a point where maintenance personnel may access the wire without having to enter the maintenance hole/hand-hole, and tagged with a label so indicating it as a “Duct Tracer Wire to xxx – Do Not Remove (where xxx is the other end of the wire).” Tracer wires shall not be connected to any grounding system. Tracer wire shall be pulled back from building entrances until it is underground to prevent lightning damage.

2.1.13.12.6 Warning Tape

Cable warning tape shall be buried one (1) foot below the surface and shall follow the duct route. The tape shall be a minimum of three inches wide and orange in color with the appropriate warning message.

2.1.13.12.7 Entrance Conduits into Existing Maintenance Holes When new entrance conduits/ducts or sleeves are required, the Contractor shall bore and install the necessary holes and install the ducts or sleeves, if knockout doesn’t exist. Penetration shall not be in such a location through the wall as to block use of existing ducts in the maintenance hole. New ducts will be a minimum of 18 inches from either the maintenance hole floor or ceiling, if practical. Ducts shall have bell ends and enter the MH perpendicular to the surface of the wall through which it is entering and shall be installed flush with the interior wall of the MH. Ducts and openings around ducts shall be sealed to prevent moisture from entering the maintenance holes.

2.1.13.12.8 Excavation/Building Penetrations

All wall penetrations, including inside buildings, shall be restored to meet the required base fire ratings.

2.1.13.12.9 Conduit Bends or Sweeps

Where a bend or sweep is placed in PVC nonmetallic duct bank between maintenance holes, the duct bank must be encased in concrete with a minimum compressive strength of 3000 pounds per square inch (psi).

2.1.13.12.10 Pulling Tape

All new vacant ducts shall be provided with a waterproof, corrosion resistant pre-lubricated flat woven polyester pull tape with sequential footage markings (1250 lb. pulling strength) for future cable installation. The mule tape shall extend into the MH and be secured to the cable rack or pulling iron, etc.

2.1.14 Outside Plant Installation

This section describes the underground maintenance hole/conduit system, flexible geotextile multiple cell fabric inner-duct and fiber optic cable installation requirements. The Contractor shall design and install Customer-Owned Outside Plant Telecommunications Infrastructure in according with TIA-758-B. Each cable installation shall be coordinated with the 87CS/SCXP so that the impact on the building users is properly coordinated. The sequence of installation is at the Contractor’s discretion.

See Attachment 1, Project Sketches for reference and estimated distances of existing and proposed infrastructure and cables routes. This is only a proposed solution. The Contractor is free to make any recommendations pertaining to the accomplishment of this requirement in their proposal.

The Contractor shall install underground outside plant infrastructure as described below.

2.1.14.1 McGuire

2.1.14.1.1 EBs 2704 and 2706 Visitor Quarters, EB 3700 United Communities

2.1.14.1.1.1 Infrastructure Installation

Install the following new infrastructure. All new locations and distances are approximate. (See Sketches 2 and 3B)

2.1.14.1.1.1.1 Manholes/Hand-holes

a) Install two (2) new 3’ x 5’ x 4’ hand-holes at the approximate locations shown on the attached sketch 1A. Coordinate with 87CS for final hand-hole placement and numbering scheme.

b) Install two (2) new 3’ x 5’ x 4’ hand-hole at the approximate locations shown on the attached sketch 1B. Coordinate with 87CS for final hand-hole placement and numbering scheme.

2.1.14.1.1.1.2 Duct bank Infrastructure

Install the following 4“ PVC Duct banks

From Manhole
To

Manhole

Quantity
Size
Approx. Distance (Feet)
Sketch
Comment
MMH 0027
MHH-027A

(new)

2
4”
380’
1A
All paved surfaces shall be bored.

MHH-027A

(new)

MHH-027B

(new)

2
4”
550’
1A
All paved surfaces shall be bored.

MHH-027B

MMH-032

2
4”
560’
1A,1B
All paved surfaces shall be bored.
MMH-032
MHH-0451
2
4”
425’
1B
All paved surfaces shall be bored.
MMH 0040
MHH-0040A

(new)

2
4”
270’
1B
All paved surfaces shall be bored.

MHH-0040A

MHH-0040B

(new)

2
4”
370’
1B
All paved surfaces shall be bored.

2.1.14.1.1.1.3 Entry Conduit Infrastructure

Install the following 4“ PVC Building Entry Conduits

From Manhole
To

Manhole

Quantity
Size
Approx. Distance (Feet)
Sketch
Comment

MHH-027A

(new)

EB 2706

1
4”
140’
1A, 1C
All paved surfaces shall be bored.

Building Entry. Stub up into a NEMA type 4 wall mounted pull box and penetrate the building

MHH-027B

(new)

EB 2704

1
4”
200’
1A, 1C
All paved surfaces shall be bored.

Building Entry. Penetrate below ground into the basement mechanical room.

MHH-0040B

(new)

EB 3700

1
4”
40’
1B, 1D
All paved surfaces shall be bored.

Building Entry. Stub up into a NEMA type 4 wall mounted pull box and penetrate the building

2.1.14.1.1.1.4 Geotextile Inner-duct (Max Cell)

Each new 3-cell shall have a separate thread color.

Except as noted here there should be available inner-duct to complete this installation.

Install the following 3” 3-cell Geotextile Inner-ducts

From
To
Quantity
Approx. Distance (Feet)
Sketch
Comment
MMH 0027
MHH-027A

(new)

3
380’
1A
New empty 4” duct.

MHH-027A

MHH-027B

(new)

3
550’
1A
New empty 4” duct.

MHH-027B

MMH-032

3
560’
1A,1B
New empty 4” duct.
MMH-032
MHH-0451
3
425’
1B
New empty 4” duct.

MHH-027A

EB 2706

2
140’
1A, 1C
Building Entry. New empty 4” Duct.

MHH-027B

(new)

EB 2704

2
200’
1A, 1C
Building Entry. New empty 4” Duct.
MHH-0451
MMH-0038
3
360’
1B
Existing empty 4” duct
MMH-0038
MPB-0039
N/A
1B
Empty geotextile inner-ducts are available
MPB-0039
MMH-0040
N/A
1B
Empty geotextile inner-ducts are available
MMH-0040
MHH-0040A

(new)

3
270’
1B
New empty 4” Duct.

MHH-0040A

(new)

MHH-0040B

(new)

3
370’
1B
New empty 4” Duct.

MHH-0040B

(new)

EB 3700

2
40’
1B,1D
Building Entry. New empty 4” Duct.

2.1.14.1.1.2 Fiber Optic Cable Installation

All fiber optic cables shall be installed in new or existing geotextile inner duct/ inner-duct.

Install the Following Single Mode Fiber Optic Cables.

From
To
Via Maintenance Holes/Hand-holes
Strand Count
Approx. Distance (Feet)
Sketch
Comment
ITB 1901
MMH-0027
144
N/A
1A
There is an existing 144 strand FOC from ITB 1901 to MMH-0027. Only strands 1-72 are terminated. Terminate strands 73-144 in ITB 1901.
MMH 0027
EB 2706
MHH-0027A
12
650’
1A, 1C
Install a 12 strand single mode (SM) fiber optic cable (12L8.3F, FO1901-2706, 25-36).

In MMH 0027 fusion splice the new 12 strand FOC to 12 of the terminated strands of the existing 144 strand FOC from ITB 1901.

Co-ordinate with the 87CS for which strands to use.

In EB 2706 first floor comm room install a 4’ x 4’ plywood backboard adjacent to the existing backboard and mount a new 12U lockable equipment cabinet. Provide a dedicated power circuit from the breaker panel on the opposite wall.

Terminate the new 12 strand FOC on a new 12 port FODP using fiber pigtails with LC Connectors. Mount the new FODP in the new lockable equipment cabinet installed above. Co-ordinate with the 87CS for exact details.

Install the Following Single Mode Fiber Optic Cables.

From
To
Via Maintenance Holes/Hand-holes
Strand Count
Approx. Distance (Feet)
Sketch
Comment
MMH 0027
EB 2704
MHH-0027A,

MHH-0027B

12
1300’
1A, 1C
Install a 12 strand single mode (SM) fiber optic cable (12L8.3F, FO1901-2704, 37-48). Indoor/outdoor fiber is acceptable to avoid a transition splice in EB 2704.

In MMH 0027 fusion splice the new 12 strand FOC to 12 of the terminated strands of the existing 144 strand FOC from ITB 1901. Co-ordinate with the 87CS for which strands to use.

In EB 2704 route the fiber from the basement up through the first floor mech room to the second floor mech room and over into the proposed second floor comm room. (Follow the path of the existing lodging FOC) In EB 2704 install a 4’ x 4’ plywood backboard adjacent to the air conditioning unit. Mount a new 12U lockable equipment cabinet. Provide a dedicated power circuit from the nearest breaker panel.

Terminate the new 12 strand FOC on a new 12 port FODP using fusion spliced fiber pigtails with LC Connectors. Mount the new FODP in the new lockable equipment cabinet installed above. Co-ordinate with the 87CS for exact details.

The existing AFNET drops will need to be rerouted to the new comm location. There should be enough slack to reroute the second floor drops. It may be necessary to add a patch panel and patch the first floor drops up to the second floor location.

Install the Following Single Mode Fiber Optic Cables.

From
To
Via Maintenance Holes/Hand-holes
Strand Count
Approx. Distance (Feet)
Sketch
Comment
MMH 0027
EB 3700 (United Communities)
MMH-0027A,

MMH-0027B,

MMH-0032,

MHH-0451,

MMH-0038,

MPB-0039,

MMH-0040,

MHH-0040A,

MHH-0040B

12
4300’
1A, 1B, 1D
Install a 12 strand single mode (SM) fiber optic cable (12L8.3F, FO1901-3700, 49-60).

In MMH 0027 fusion splice the new 12 strand FOC to 12 of the terminated strands of the existing 144 strand FOC from ITB 1901.

Co-ordinate with the 87CS for which strands to use.

In EB 3700 route the FOC through the entry utility room, use the existing conduit up to the attic and then over and down into the second floor comm closet.

Terminate the new 12 strand FOC on a new 12 port FODP using fiber pigtails with LC Connectors. Mount the new FODP in the existing equipment rack. Co-ordinate with the 87CS for exact details.

2.1.14.1.2 EB 1922 Fuels Pump House

2.1.14.1.2.1 Infrastructure Installation

Install the following new infrastructure. All new locations and distances are approximate. (See Sketches 2A, 2B)

2.1.14.1.2.1.1 Manholes/Hand-holes

Install one (1) new 3’ x 5’ x 4’ hand-hole at the approximate location shown on the attached sketch 2A. Coordinate with 87CS for final hand-hole placement and numbering scheme.

2.1.14.1.2.1.2 Duct bank Infrastructure

Install the following 4“ PVC Duct banks

From Manhole
To

Manhole

Quantity
Size
Approx. Distance (Feet)
Sketch
Comment
MMH 0012
MHH-0012A

(new)

2
4”
480’
2A
All paved surfaces shall be bored.

2.1.14.1.2.1.3 Entry Conduit Infrastructure

Install the following 4“ PVC Building Entry Conduits

From Manhole
To

Manhole

Quantity
Size
Approx. Distance (Feet)
Sketch
Comment

MHH-0012A

(new)

EB 1922

1
4”
85’
2A, 2B
All paved surfaces shall be bored.

Building Entry. Stub up into a NEMA type 4 wall mounted pull box and penetrate the building.

2.1.14.1.2.1.4 Geotextile Inner-duct (Max Cell)

Each new 3-cell shall have a separate thread color Except as noted here there should be available geotextile inner-duct to complete this installation.

Install the following 3” 3-cell Geotextile Inner-ducts

From
To
Quantity
Approx. Distance (Feet)
Sketch
Comment
MMH 0012
MHH-0012A

(new)

3
480’
2A
New empty 4” Duct

MHH-0012A

(new)

EB 1922
2
85’
2A, 2B
New empty 4” Duct

2.1.14.1.2.2 Fiber Optic Cable Installation

All fiber optic cables shall be installed in new or existing geotextile inner duct/ inner-duct.

Install the Following Single Mode Fiber Optic Cables.

From
To
Via Maintenance Holes/Hand-holes
Strand Count
Approx. Distance (Feet)
Sketch
Comment
ITB 1907A
EB 1922 (Fuels Pump House)
MHH-0015,

MMH-0006,

MMH-0007,

MMH-0008,

MMH-0009,

MMH-0011,

MMH-0012,

MHH-0012A

12
3200’
2A, 2B
Install a 12 strand single mode (SM) indoor/outdoor fiber optic cable (12L8.3F, FO1907A-1922, 1-12).

In ITB 1907A terminate the new 12 strand FOC on a new 12 port FODP using fusion spliced pigtails with LC connectors or LC fusion splice direct connectors. Mount the new FODP in the existing equipment rack. Co-ordinate with the 87CS for exact details.

In EB 1922 install a plywood backboard and mount a new 8U lockable equipment cabinet. Provide a dedicated power circuit from the nearest breaker panel.

Terminate the new 12 strand FOC on a new 12 port FODP using fusion spliced pigtails with LC connectors or LC fusion splice direct connectors. Mount the new FODP in the new lockable equipment cabinet installed above. Co-ordinate with the 87CS for exact details

2.1.15 Project Residue

All residues from this project shall be disposed of off base and in accordance with Federal, State, local and base environmental laws and regulations. All residue produced by horizontal directional boring operations (i.e., slurry) shall be disposed of off base on the same day the residue is produced, at an appropriate disposal facility at the contractor’s expense, IAW federal and state environmental laws and regulations. Under no circumstances will the contractor stage or store boring residue in slurry ponds or other containment areas on JBMDL.

2.1.16 Site Restoration

The Contractor shall restore all disturbed grounds to the “as found” condition or better after installation. The Contractor shall comply with all base grounds restoration requirements. Common use areas shall be restored with sod.

2.1.17 Service Outages

The Contractor shall be responsible for preventing any unscheduled (i.e. cutting or disabling any in-service cables or equipment.), Contractor-caused, interruptions of communications capabilities that are properly identified. The Contractor shall coordinate planned outages with the site POC at least 10 calendar days in advance of the outage if the implementation necessitates disruption of service, (e.g., communications, electrical, or other utilities).

2.1.18 Configuration Management Reserved

2.1.19 Identification/Marking

The Contractor shall clearly mark all Contractor-Furnished Property and Equipment (CFP/CFE) with their company's name. The Contractor shall place an easily read, very visible, sign (minimum 8.5" x 11") on large containers, construction equipment, or un-manned rental vehicles while on the Government installation indicating the company name and both the Contractor and Site POC's names and local telephone numbers.

2.1.20 Installation Schedules

The Contractor shall provide a complete milestone schedule that denotes project activities to include time-phased start and completion dates for the project and sub-projects associated with the installation of the components and system. All submissions shall be delivered electronically in MS Office-compatible format NLT 10 business days after contract award and as significant schedule changes occur to be determined by the IPT.

2.1.21 Weekly Status Reports

The Contractor shall prepare a Weekly Status Report and distribute to the Government Contracting Officer (CO), the System Engineer(s), the Government Project Manager, and other base personnel as required. The purpose of the report is to inform IPT members of project progress, problems being encountered, and other topics necessary/beneficial to ensure success and timely completion of the contract requirements.

2.1.22 Drawings

2.1.22.1 As-Built Drawings

The Contractor shall submit red line drawings showing the “as-built” configuration in format specified by base SCX project manager. The base communications squadron will provide baseline drawings. The Contractor shall provide As-Built Rack Elevation, Inside Cable Plant and Outside Cable Plant drawings.

2.1.22.2 Butterfly Drawings

The Contractor shall record and submit butterfly, cable path and building penetration drawing information for all new installations including butterfly drawings for all Maintenance Holes, hand-hole and pull boxes that contain new or reused FOC. Drawings shall record the path and arrangement of new and reused fiber optic cables, splices, and the arrangement duct banks, ducts, inner-duct and shall show MH orientation with respect to geodetic north. Drawings shall be submitted in an easily read electronic format such as pdf. Scanned data sheets or legible sketches are acceptable.

2.1.22.3 Geospatial Deliverables

The Contractor shall collect and record geospatial data and provide as-built documentation (shape files) of all new installed MHDS components and new cable components (including metadata) compatible with the Cyberspace Infrastructure Planning System (CIPS) Visualization Component (CVC) drawing system. Data points shall be recorded at the center of each manhole/hand-hole lid and at intervals not to exceed 25 feet along cable routes. Sufficient data points shall be recorded to capture any change in direction along the route. All GPS coordinates shall have +/- 3 feet accuracy for all readings. The government will review the shape files and transcribe the information to the CVC system. Shape files shall be delivered within 30 days of project completion. Provide geospatial data via CD as Environmental Systems Research Institute (ESRI) Shape files.

2.1.23 Test and Acceptance/Installation Test Plan

The Contractor shall provide a test plan as to how the system shall be pre-tested, in-progress-tested and post-tested. Draft Cut-over Test Plan shall be submitted NLT 10 calendar days after contract award. Government comments will be provided after review of the draft. A final plan will be submitted 30 calendar days before the actual cut-over date. The Contractor shall test the system to demonstrate to the Government quality assurance representative that the system is fully operational and meets or exceeds the specified requirements and that the system is fully ready to be placed into service. These tests shall be accomplished prior to the system being placed into service.

2.1.23.1 Testing

The Contractor shall conduct on-site testing IAW OEM’s installation manuals, practices and the appropriate vendor’s test procedures. The Contractor shall furnish all test equipment and personnel required to conduct all required testing. During any testing phase, the Government reserves the right to perform any of the contractor performed inspections and tests to assure solutions conform to prescribed requirements. The Contractor shall provide on-site support during the acceptance testing. The Contractor shall participate with the Government in testing the complete communications system. When any system, subsystem, component or requirement test fails to meet the requirements of the test, Government acceptance and payment will be withheld until such time as the cause of the failure is corrected to the Government’s satisfaction. After appropriate corrective action has been taken, all tests including those previously completed, related to the failed test and the corrective action shall be repeated and successfully completed prior to Government acceptance.

2.1.23.2 In-progress Testing

2.1.23.2.1 Excavations

All excavations shall be inspected for compliance with applicable installation and safety directives, and installation plan procedures. After material is placed, the contractor shall inspect and document the installation prior to backfilling. In addition, the designated government representative shall be allowed to inspect the installation prior to backfilling.

2.1.23.2.2 Splices

All splices shall be tested for cable faults and splicing errors as they are completed. All cable faults and/or splicing errors detected shall be corrected after the completion of each splice point test and prior to sealing the closure. The contractor's QCM and the designated government representative shall inspect all splices prior to sealing the closure. If, for any reason, moisture contaminates a splice, all modules and/or connectors shall be replaced and the entire splice retested.

2.1.23.2.3 Fiber Optic Tests

All strands of all fiber optic cables shall be tested in accordance with TIA 526-7-(2002) Measurement of Optical Power Loss of Installed Single-mode Fiber Cable Plant, or equivalent. As a minimum, the following tests shall be performed. Both Optical Time Domain Reflectometer (OTDR) and Optical Power Meter tests will be used for all end-to-end circuits. For incomplete circuits that end in Maintenance Holes, only OTDR testing is required.

2.1.23.2.4 Optical Attenuation

End to end attenuation tests shall be conducted on all fiber optic cable strands. Tests shall be accomplished to ensure the installed cable is within the specified parameters.

2.1.23.2.5 Distance

Test to determine the installed cable length between optical patch panels. All strands of all fiber optic cables shall be tested.

2.1.24 Acceptance/Installation Test Report

The Contractor shall provide an installation test report of the results of the testing accomplished under the installation test plan NLT 10 business days after Government Witness Testing is complete.

2.1.25 Final Acceptance

The Contractor shall schedule a final project walk-through with the Base POC. This should be scheduled 5 calendar days prior to acceptance.

2.1.25.1 Training Plan Reserved

3.0 GENERAL INFORMATION

Period of Performance The period of performance for the project shall be determined based on the proposed schedule and actual contract award date. Project is expected to be completed within 6 months of the award date.

Place of Performance The place of performance is Joint Base McGuire-Dix-Lakehurst, NJ.

Hours of Operation The Contractor shall routinely work during normal duty hours (07:30 to 16:30) of the…