This is a Solicitation for roof waterproofing services for the United States Embassy in New Delhi, India. The project involves comprehensive waterproofing work at 142 Malcha Marg, covering approximately 3,500 square feet (3,000 sq. ft. main roof and 500 sq. ft. DSQ roof). The solicitation requires a qualified roofing contractor to perform a complete restoration, including removing existing layers, repairing the concrete slab, installing multiple waterproofing membranes, applying insulation, and finishing with vitrified anti-skid floor tiles. Key requirements include a 30-working-day completion timeline, submission of a detailed project plan, adherence to strict safety standards, and provision of a five-year warranty. Contractors must submit their quotation by email to newdelhibids@state.gov by 1700 hours on August 25, 2025, and are required to attend a mandatory construction safety seminar. The contract will be awarded to the lowest-priced, acceptable, responsible quoter, with the embassy reserving the right to reject any offers.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Solicitition 191N6525Q0143 clauses.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation No. 191N6525Q0143 P a g e 1 | 12
Solicitation No. 191N6525Q0143 Dated: August 11, 2025
Name & address of Offeror Issued by: GSO/Contracting
You are invited to submit your lowest prices for the services listed in the attached cost sheets.
Please email your quotation, along with the project bar chart, to newdelhibids@state.gov no later than 1700 hours on August 25, 2025.
Ensure that your name, address, and contact phone number are included on each page of your submission.
The Contracting Officer is available to provide additional information or clarifications regarding this solicitation upon request.
Services - Description
1. Perform waterproofing work at 142 Malcha Marg in accordance with the attached Scope of
Work (SOW).
2. Offerors registered with GST or service tax authorities must submit a copy of their GST/service tax registration certificate with their offer. For GST registration, specify the category of registration (e.g., work vendor or composite vendor).
Submission of this certificate is mandatory for evaluation purposes. The Government will assess acceptability by reviewing the offeror's compliance with the solicitation terms. Contractor responsibility will be determined in accordance with FAR 9.1, based on whether the apparent successful offeror meets the required standards.
To enable the U.S. Government to claim GST refunds, offerors must indicate GST separately in their quotation. If GST is indicated separately, the contractor must provide tax invoices that comply with New Delhi GST regulations.
Vendors registered with the Government of India (GOI) must include the Embassy’s UIN:
0717USA00138UNS on their invoices. Failure to include the UIN will result in the rejection of the invoice by the Embassy.
3. Completion time: 30 working days from the receipt of letter to proceed.
4. Notwithstanding anything contained hereinafter, the following clause, Liquidated Damages— Construction (FAR Subpart 52.211-12), applies:
a) If the contractor fails to complete the work within the time specified in the contract, the contractor shall pay liquidated damages to the U.S. Government at a rate of 1% of the total contract value per calendar day of delay, up to a maximum of 10% of the total contract value, until the work is completed or accepted.
Embassy of The United States of America New Delhi mailto:newdelhibids@state.gov
Solicitation No. 191N6525Q0143 P a g e 2 | 12
b) If the Government terminates the contractor's right to proceed, liquidated damages will continue to be accrued until the work is completed. These damages are in addition to the excess costs incurred under the Termination clause.
5. “DOSAR 652.236-70 Accident Prevention (APR 2004)” clauses shall apply.
6. For appliances and materials provided by the Embassy as outlined in the Statement of Work (SOW), the contractor must submit detailed installation and consumption statements signed by the Facility Management Officer along with their invoice. Failure to provide these statements will result in the invoice not being processed.
7. In case there are contradictory statements in the SOW and the Purchase Order Clauses, the
Purchase Order shall prevail.
8. After the award of the contract, the contractor must attend a Construction Safety Seminar at the Embassy before starting the project, unless they have previously attended. The seminar, which lasts one hour, will be arranged by the Embassy and is mandatory for security and safety reasons.
Site Inspection: 1400 Hours on August 19, 2025
The award will be made to the lowest-priced, acceptable, responsible quoter. The Government reserves the right to reject quotations that are unreasonably low or high in price. The Embassy also reserves the right to reject any or all offers and to remove portions or items from solicitation.
Offers must remain valid for at least 90 days from the submission date. Once the Purchase Order is awarded, the prices shall remain fixed until the work is completed.
Solicitation No. 191N6525Q0143 P a g e 3 | 12
STATEMENT OF WORKS
FOR
ROOF WATERPROOFING AT 142 MALCHA MARG
1.0 BRIEF DESCRIPTION OF WORK:
1.1 The United States Embassy, New Delhi has a requirement to re-store roof waterproofing for 142
Malcha Marg.
1.2 Contractors are advised to visit the site, verify measurements as mentioned in the SOW.
1.3 Any ambiguity found later will be at the discretion of the contracting officer for any modification.
1.4 Complete waterproofing job shall be done by skilled/professional workers.
1.5 Project requires a qualified Roof Contractor to perform a restoration as per scope of work.
1.6 The contractor shall be given total 30 working days to complete this project.
2.0 GENERAL GUIDELINES
2.1 The Contractor shall provide all required labor, material (except the GFI), equipment, and supervision to complete the project.
2.2 Contractors are advised to conduct the site visit to understand the requirement and verify measurements.
2.3 Contractors are recommended to seek clarifications regarding this statement of work and site conditions at the time of walk thru from the COR of this project.
2.4 The contractors can write the uncleared queries to the contracting office after the walk thru.
2.5 Embassy contracting office will consult with COR and respond to all the queries in writing before the due date of the submission of quotes.
2.6 Embassy expects professional craftsmanship and supervision from the bidders.
2.7 The timeline for this project is 30 calendar days.
2.8 The contractor must adhere to the safety mandates explained in this document,
2.9 The contractor and his/ her staff must wear Personnel Protective Equipment (PPE) while at embassy construction site. Contractor can add cost of PPE to the bid and must comply the PPE guidelines 100% at USG facilities. Contractor will be countable for the delay caused by non-compliance.
Solicitation No. 191N6525Q0143 P a g e 4 | 12
2.10 No work will be allowed to perform at USG construction sites without the PPEs and the contractor will be accountable for the delays caused due to the safety issues.
2.11 PPE includes steel toe shoes, protective goggles, hard hats, coveralls and COVID -19 protective masks.
2.12 The contractor shall include the cost of the PPEs and other logistical expenses to manage the safety and PPE guidelines while bidding.
2.13 The contractor will be held responsible and accountable for any deviations from the safety and PPE guidelines specified in this document.
2.14 All work shall be performed by skilled and competent crew.
2.15 The Contractor shall follow security and safety directions as mentioned in the statement of works and explained by the COR.
2.16 The Contractor shall submit the construction bar chart to the COR within 2 working days upon obtaining the letter to proceed from the contracting office.
2.17 The Contractor shall submit all the cut sheets / broachers and material samples for COR approval before delivery of material at site.
2.18 All materials shall be delivered, hoisted on the exterior and stored as per space allotted.
2.19 Contractor shall dispose of all the debris from the site and keep the site clean and in workable condition throughout the project duration.
3.0 SCOPE OF WORK FOR ROOF WATERPROOFING OF 142 MALCHA MARG (3000 sq.ft. + 500 sq.ft.
DSQ)
3.1Remove existing tile, mortar, membrane layers complete with insulation, vermiculite etc. and reach up to RCC slab. (app. 3000 sq. ft.)
3.2 Contractor shall do necessary repair to the slab with recommended polymer mortar of SIKKA or Fosrock or equivalent makes.
3.3 After repair of RCC slab, provide a layer of form concrete or mortar layer mixed with waterproof compound (SIKKA LATEX) as per manufacturer instructions, to make slop towards drains on entire slab. The slope shall be 2% towards rainwater drains.
3.5 After curing the mortar layer, install a layer of bitumen primer, followed by layer of hot bitumen once dried. The bitumen shall be laid or spread @ 1.7 kg/sq. mt. Then install embassy provided bituminous felt (two layers) over the 85/25-grade hot bitumen. The felt shall laid by touching the membrane and by heating the felt in accordance with manufacturer's recommendation to achieve continuous edge flow and complete bond. A coat of bitumen shall be done between two layers of membrane. The terminated end of bitumen membrane shall be done as per site condition requirement. The membrane termination point shall be 6” above the curb
Solicitation No. 191N6525Q0143 P a g e 5 | 12 of roof. 1” wide 14 gauge thick aluminum flat shall be install to seal the terminated edge of membrane.
Note: The longitudinal side of felt shall be overlap minimum 4 inches and end laps minimum 8 inches. All the gaps and overlaps/ joints shall be sealed with hot bitumen.
3.6 On top of second layer of felt a final coat of hot bitumen shall be done as per details and standards.
3.7 Once hot layer of bitumen done, contractor shall do the flood test (minimum 48 hrs.) of complete roof after waterproofing. 4” to 5” water shall be standing over the roof after placing the sand bags around to hold the water.
3.8 Above the final layer of bitumen, provide a layer of mortar with chicken wire mesh in between slop toward drain. The slope shall be 2% towards rainwater drains and thickness of mortar shall be minimum 1” and any points.
3.9 On top of mortar a protection layer of primer and hot bitumen shall be done as per above specifications.
3.9 The contractor shall provide and lay 300-micron polythene sheet of transparent color over the mortar layer.
3.10 Install embassy provided PVC drain board, DRENTEX protect 50 of TEXSA/DELTA makes over and above the polythene sheet.
3.11 Install embassy provided 2” (50 mm) thick inter lockable Extruded Polystyrene Insulation over drain board. The insulation will be applied in parallel rows and all sides/end joints will be installed closely but not forced.
3.12 Over the insulation the contractor shall spread 300-micron polythene sheet of transparent color.
3.13 Install layer of mortar with chicken mesh for installation of tiles.
3.14 Provide and install 2’ X 2’ vitrified anti-skit floor tiles with tile adhesive. Fill all the joints of tiles with waterproofing grouting materials.
3.15 The contractor shall build curb around the roof edge to cover and protect membrane termination. The floor tiles shall continue above the curb,
3.16 Provide and install drain cover, made of stain-less steel bar (1”x 1”) and S/S screen/wire-mesh (10-gauge, stainless steel-316 grade) for all the drains (including DSQ) so that no leaves can pass through. The metal frame shall be painted before installing wire-mesh over it.
3.17 DSQ Rood : remove all existing layer and reach upto RCC slab. Follow 3.2 to 3.9 line items. Over the mortar draintex board shall be laid followed by insulation. On top of insulation layer of filter fabric and shall be spread. Then on top concrete pavers shall be placed with marble chips.
Solicitation No. 191N6525Q0143 P a g e 6 | 12
3.16 Warranties and Flood Test
a) Contractor’s warranty: Furnish a written warranty agreeing to repair / replace defective installation and workmanship causing leakage of water, deterioration of materials and other failures of the installed system, sealants, painting, coatings, and related work on this project, to perform as required within the warranty period. Warranty period is five years after date of the written final acceptance.
b) Flood Test : The contractor shall complete the flood test for recently waterproof roof. For testing at least 4” water to be filled and retained for 48 hours. Any leakage found shall be repaired appropriately.
3.17 Materials/Makes
Government Supplied Materials : The Embassy will provide following material for completion of this job, rest all materials shall be provided by the contractor :
1. APP modified bitumen, non-woven polyester felt both 3mm and 4mm thick
2. Bituminous primer
3. bitumen of 85/25-grade
4. Drentex Board
5. Extruded Polystyrene Insulation
6. Chicken wire-mesh
7. Pavers
8. Filter fabric
9. Marble Chips
Contractor Supplied Materials: The contractor shall provide following materials to complete the job as per given scope of work.
1. Stone Dust
2. Cement
3. Polythene Sheet 300 micron.
4. Tile adhesive
5. Verified Tiles
6. Tile grouting materials.
7. Foam Blocks
8. Waterproofing coating compound
9. Aluminum Flat
10. Flashing as required.
11. S/S drain covers
Note ; The contractor shall provide sample of the material for the approval from COR before using it at project site or before delivery of material at site.
Contractor shall use material of brands or make as given or equivalent quality material.
4 SITE CLEANING
Solicitation No. 191N6525Q0143 P a g e 7 | 12
4.1 Contractor shall broom clean the entire site and the storage area after the completion of the project and on each day at close of business.
4.2 Contractor will paint the area of the exterior walls or other areas which will be affected during the project matching to existing paint.
5 CONTRACTOR’S RESPONSBILITY
5.1 The Contractor shall be responsible for the professional quality, technical accuracy, and the coordination of all construction and other services furnished under this contract. The Contractor shall correct or revise any errors or deficiencies in its construction and other services without additional compensation,
5.2 The Contractor shall identify a Project Manager/Supervisor who shall be responsible for the overall management of this Contract. Project Manager shall be qualified and have the experience in same type of job.
5.3 The Contractor is responsible for safety and shall comply with all local labor laws, regulations, customs, and practices pertaining to labor, safety, and similar matters. The Contractor shall promptly report all accidents resulting in lost time, disabling, or fatal injuries to the COR.
5.4 . Embassy will provide water and power at site, but the Contractor shall be responsible for connection from the main source to project location.
5.5 All expenses towards mobilization at site and demobilization including bringing in equipment, workforce and materials, profit and overheads, dismantling the equipment, removal of debris, clearing the site etc. should be included in the rates quoted by the contractor. No separate payment on such expenses shall be entertained.
5.6 Contractor should keep the site clean and accessible to Embassy employee all time.
5.7 The contractor shall provide and install safe and workable scaffolding at site for daily transportation of materials and commuting of labor.
5.8 Embassy provided materials shall be delivered at nearest gate at ground. Transporting materials from ground to roof shall be contractor’s resposbility.
6 SAFETY
In addition to the attached Accidental prevention clause contractor will be responsible for
6.1 Any miss-happening at the site due to negligence in the safety measures.
6.2 Contractor will provide all Personal Protective Equipment for the workers as per the requirement of the site. Work will be stopped in case proper protection equipment are not find with the workers and lapse of the time will at the part of the contractor.
Solicitation No. 191N6525Q0143 P a g e 8 | 12
6.3 Contractor will make sure that all the arrangements for the work are working conditions are safe in all respect. Under no circumstance Embassy will be held responsible for any incident happen on the site due to negligence of the contractor / worker.
7 General Notes
7.1 Once the project starts, it is contractor’s responsibility to secure the roof against any kind of seepage / leakage to the floors underneath. Any damage / seepage / leakage occurred to the slab or to the other parts of the building while project is in progress will be contractor’s responsibility and will repair the damages matching to existing.
7.2 Contractor will be responsible for the safety of all the existing wires running on the roof during demolition phase.
7.3 Contractor will provide all the material required to complete the job in satisfactory manner except Embassy supply items.
7.4 Contractor shall provide and use LPG gas kettle for heating of bitumen. Contractor shall arrange for fire extinguishers while the gas cylinder is in use at the site. Under no circumstance wood will be allowed for heating the bitumen. In case of any miss-happening Embassy will not be responsible.
7.5 Contractor should arrange the visit of the professional in this field from manufacturer side time to time (once or twice throughout the duration of the project) to supervise the project during work in progress.
7.6 One qualified technical supervisor from contractor side should always be present on the site. He should be able to speak and understand English language.
7.7 All demolished material shall be removed from the site, unless otherwise specified, on daily basis. The contractor will be entirely responsible for the disposal of all the trash and debris and will be the only one to attend to any fine or penalty imposed by city authorities for improper disposal. The contractor shall take all necessary precaution/protection and approval from local authorities for disposal of debris.
7a) Working Hours
• Working hours shall be 8.30 A.M. to 5.00P.M. Monday to Saturday. No work shall be done on Sundays/holidays unless otherwise approved. Total 45 working days shall be given.
• List of criteria for technical evaluation
• (1) Name of a Project Manager (or other liaison to the Embassy/Consulate) who understands written and spoken English;
• (2) Evidence that the offeror/quoter operates an established business with a permanent address and telephone listing;
• (3) List of clients, demonstrating prior experience with relevant past performance information and references. Please provide pictures of completed work.
Solicitation No. 191N6525Q0143 P a g e 9 | 12
• (4) Evidence that the offeror/quoter can provide the necessary personnel, equipment, and financial resources need to performance the work. Can the offeror/quoter provide the necessary personnel?
• (5) Evidence that the offeror/quoter has all licenses and permits required by local law? Were licenses and permits required by local law provided?
• (6) The offeror’s strategic plan for the services
• (7) Technical data sheet and company catalogue/brochure of the products/services.
• (8) Evidence that the Contractor has the capability to install and maintain the Required services?
SAFETY STANDARDS TO BE FOLLOWED AT CONSTRUCTION AND RENOVATION SITES
Contractor:
Work Site Address:
Contractor Safety Officer Name:
Signature for Acceptance by the contractor:
Safety standards to be followed at construction and renovation sites AHA – Activity
Hazard Analysis
1. The contractor must document in the bid for the work how the control of each hazard will be implemented and maintained during the project by submission of a safety plan and activity hazard analysis (AHA) for high hazard activities. The POSHO or qualified Post representative must review the contractor's proposal and provide feedback to the responsible project manager and Contracting Officer prior to acceptance of the bid.
2. Any situation where in the work in progress can pose a threat to the user of work area in emergency, contractor shall ensure proper barricading (sturdy enough for the purpose) to avoid any risk.
Covid 19 Precautions
1. Every worker on site shall wear a mask and gloves all the time.
2. Workers shall maintain social distancing – six feet - all the time.
3. Sanitize or wash your hands frequently.
4. No worker shall be in proximity with other worker for more than 10 minutes and that too with the mask and gloves on.
5. Contractor shall ensure temperature testing of all workers coming on site in the morning and randomly during entire day to make sure that no one is suffering from fever.
6. Any worker showing any symptoms of fever, cough and cold, body ache etc. shall not be allowed to work till he is been ruled out of being positive.
General
Solicitation No. 191N6525Q0143 P a g e 10 | 12
1. All workers on the work site must wear safety shoes on construction site. No worker with flip flops will be allowed to work at site.
2. All the workers should wear full clothes. No half pants and other non- appropriate clothing (Dhoti) will be accepted.
3. Malba / trash accumulated on the site should be removed at a regular interval (if possible on daily basis) so that it should not pose any trip hazard.
4. Employee exposed to hazards created by different works environment shall be protected by personal protective equipment. Appropriate protective clothing for any operation varies with the size, nature and location of work to be performed.
5. In extreme hot conditions drinking water must be made available to the worker and working duration in exposed conditions should be scheduled accordingly.
6. It is the responsibility of the contractor to made available all the PPE (Personal Protective Equipment) as per the requirement of the work site and as directed by the COR. Any mishap due to negligence on the part of the contractor will be entirely contractor’s responsibility.
Machinist / Welding Jobs
1. Hot work permit is required to be filled for each hot work to be performed on USG site.
2. Contractor shall follow attached standards regarding different type of welding to be done on the site.
3. All workers who are arc welding must use a full face shield with #10 or darker lenses. No worker will be allowed to arc weld with sun glasses, no matter how dark the lenses.
4. All the workers working on grinding and sanding job should have approved face masks and goggles for face and eye protection.
5. Workers handling the heavy metallic material should have appropriate gloves and safety shoes as per the job requirement.
6. Lifting and shifting of the heavy material to be done with the help of appropriate machines.
7. Compressed gas cylinder shall be properly marked and should always be kept in standing positing with guard against fall.
8. Hoses connected to the cylinder should be in good condition.
9. In case Arc welding is done inside the premises proper ventilation should be arranged in the vicinity.
10. Contractor should use welding shield during the work to protect the people around against any potential vision hazard.
11. Always keep an approved fire extinguisher near the site of welding.
12. Workers working with metal sheets must wear appropriate gloves to avoid any cuts on the hands or mishap on the site.
13. Electrical connections for the welding set and the grounding for the same shall be done properly to the satisfaction of the embassy electrician. Please refer electrical section in the document.
Ladders Safety
1. Contractor will use aluminum or fiber glass ladders for all purposes. Wooden ladders are not allowed on the site.
2. Proper ladder for a specific job should be used (for example fiber glass ladders for electrical work etc.).
3. Damaged ladders or ladders with missing supports, shoes etc should not be used on the
Solicitation No. 191N6525Q0143 P a g e 11 | 12 site.
4. Height of the ladder should be at least two feet above the required height for the work.
Electrical
1. All the equipment / machines to be used for the execution of the job should be properly grounded.
2. All the extension boards to be used at the site should have proper earthing.
3. All connections to any of the outlets should be through three pin plug. Direct connection of wires in not allowed on the site.
4. Damaged wiring/ cabling for the machines / tools to be used at site are not acceptable. The extension cord or wire with the machines should be one core.
5. Electricians working on the site should wear shoes with rubber soles and should use rubber gloves during execution of the work.
6. Any heavy equipment to be plugged in for the work should be done under supervision of the embassy electrician. Contractor on his own should not plug in heavy equipment.
7. No taped joint or undersize wiring is allowed at the site for the work.
Carpentry
1. Carpenters should have dust mask to protect them from the potential hazard from saw dust.
In case sanding machine is used at the site the machine should have proper guards and operator should have suitable PPE (personal protective equipment) with them. For e.g. safety goggles, safety shoes, gloves etc.
2. All the wood to be used at the site should be properly stacked at one side. It should not be scattered around and pose a threat for a trip hazard.
3. Entire site should be kept clean from the saw dust at the end of the day.
4. Carpenter shall use machine guards if at all machines are used at the site.
5. All the care should be taken to protect the flooring against any kind of potential damage.
6. All the drill machines or other electrical tools to be used at the site should be properly grounded and wired.
7. Contractor should use proper tools and tackles for the execution of the work at site.
8. Nails and other sharp material which can pose a threat of accident should not be scattered on the site.
Fire
1. Contractor shall provide and place fire extinguishers as per the requirement of the site (as recommended by the COR).
2. No flammable material should be kept inside the premises at any given point of time.
Lock Out / Tag Out
1. Lock out devices should be used during the testing of the electrical points and wiring.
Confined spaces
Solicitation No. 191N6525Q0143 P a g e 12 | 12
1. If at all contractor has to work in a confined space he should contact the COR before proceeding with the work. Contractor should arrange all the equipment as instructed by the COR to accomplish the job in a safe manner.
Hearing Protection
1. Contractor should assure that all the workers working in noisy surroundings should wear ear muffs or other approved devices.
Height Protection
1. Any work to be carried out over and above 8’-0” needs a sturdy metal pipe scaffolding to carry out that work. Ladder or any other arrangement needs to a preapproval from COR to be implemented on the site.
For any further clarification please contact POSHO (Post Occupational Safety and Health Officer) at # 011-24198280 OR APOSHO Mr. Rohit Soni at 011-24198682.
| Covid 19 Precautions |
| 1. Every worker on site shall wear a mask and gloves all the time. |
| 2. Workers shall maintain social distancing – six feet - all the time. |
| 3. Sanitize or wash your hands frequently. |
| 4. No worker shall be in proximity with other worker for more than 10 minutes and that too with the mask and gloves on. |
| 5. Contractor shall ensure temperature testing of all workers coming on site in the morning and randomly during entire day to make sure that no one is suffering from fever. |
| 6. Any worker showing any symptoms of fever, cough and cold, body ache etc. shall not be allowed to work till he is been ruled out of being positive. |
| General |
| Machinist / Welding Jobs |
| Ladders Safety |
| Electrical |
| Carpentry |
| Fire |
| Lock Out / Tag Out |
| Confined spaces |
| Hearing Protection |
| Height Protection |
File details come from the government source that posted it. Updated .