SolicitationAttachment1StatementOfWork_1232SA26Q1009.pdf
PDF 587 KB Posted
- Solicitation number
- 1232SA26Q1009
About this file
This is a Statement of Work (SOW) for stucco repair and sealing services at the USDA Agricultural Research Service Western Regional Research Center in Albany, California.
The contractor shall repair and seal exterior stucco on the southeast corner and south wall of the main building located at 800 Buchanan Street, Albany, CA 94710. The work area encompasses approximately 665 linear feet in length and 45 feet in height, with windows covering approximately 20 percent of the surface. The southeast corner laboratories experience water intrusion during rainy seasons due to failed stucco, while the south wall contains hairline cracks requiring repair. The contractor must provide all management, supervision, labor, equipment, and tools necessary to complete the project. All work must comply with applicable federal, state, and local code requirements, current industry standards (EPA, ASTM, GSA, AASHTO), Unified Facilities Guide Specifications (UFGS), and ARS 242.1M standards. The project falls under the Davis Bacon Wage Act. The contractor is responsible for obtaining all required permits and licenses, coordinating with site personnel to minimize building downtime, providing submittals of all materials for approval, maintaining a Site Specific Safety Plan, and ensuring continuous quality control. The contract time is 90 calendar days from Notice to Proceed. Prior to final payment, the contractor must submit a one-year warranty on workmanship, operation and maintenance data, release of liens, and final invoice. The Contracting Officer is listed as TBD, with Ron Haff serving as Research Program Representative, Location Monitor, and Engineering Project Manager.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
United States Department of Agriculture Agricultural Research Service
STATEMENT OF WORK
USDA-WRRC Southeast Corner and South Wall Stucco
Repair and Sealing
USDA-ARS
Western Regional Research Center
800 Buchanan Street.
Albany, CA 94710
May 21, 2026
STATEMENT OF WORK
1.0 CONTRACT PROJECT:
a. Project Number: TBD
b. Project Title: USDA-WRRC Southeast Corner and South Wall Stucco Repair and Sealing
c. Project Location:
USDA-ARS
Western Regional Research Service 800 Buchanan Street Albany, CA 94710
2.0 PROJECT CONTACT PERSONS:
a. CONTRACTING OFFICER (CO):
TBD
b. RESEARCH PROGRAM REPRESENTATIVES (RPR):
Ron Haff
USDA-WRRC
Western Regional Research Service 800 Buchanan Street Albany, CA 94710
Phone: (510)-559-5868 Email: ron.haff@usda.gov
c. ADMINISTRATIVE OFFICER (AO acting):
Chris Carter
USDA-ARS
Western Regional Research Service 800 Buchanan Street Albany, CA 94710
Phone: (510)-559-6300 Email: Christopher.carter3@usda.gov
d. LOCATION MONITOR:
USDA-ARS
Western Regional Research Service 800 Buchanan Street Albany, CA 94710
Phone: (510) 559-5868
e. AREA SAFETY AND HEALTH MANAGER (ASHM) Ken Cushman
USDA-ARS
Email: ken.cushman@usda.gov
f. REAL PROPERTY MANAGEMENT:
N/A
g. ENGINEERING PROJECT MANAGER (EPM)
USDA-ARS
Western Regional Research Service 800 Buchanan Street Albany, CA 94710
Phone: (510) 559-5868
3.0 SCOPE OF SERVICES:
The Contractor shall provide all professional services necessary for the accomplishment of the contract project and such required services shall be in accordance with requirements as described herein.
a. The Contractor shall provide services for the following tasks marked by an “X”:
[X] Provide a cost proposal to complete the project as per project requirements.
[X] Provide and install all material to complete the project as per project requirements.
4.0 PROJECT REQUIREMENTS:
The contractor shall provide all management, supervision, labor, equipment, and tools to repair and seal the stucco on the WRRC southeast corner and south wall.
a. The Contractor will work with Location Monitor and other site personnel to ensure minimum downtime as heating the and cooling of the building will likely be affected.
b. The Contractor’s work shall adhere to the criteria stated within these project requirements.
All construction shall comply with applicable federal, state, and local code requirements as well as current industry standards, (ie: EPA, ASTM, GSA, AASHTO, etc.) and health and safety codes, in effect at the time of contract award.
c. All work must meet all pertinent Unified Facilities Guide Specifications (UFGS) and ARS
242.1M standards. UFGS available at http://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs. ARS 242.1M available at https://www.afm.ars.usda.gov/ppweb/pps-and-manuals/.
d. This project falls under the DAVIS BACON Wage Act.
e. The Contractor is responsible for visiting the site prior to submitting a bid to observe existing conditions. No compensation will be provided for conditions that would be visible during an on-site visit for people experienced in performing this type of work.
4.1 Background & Site Description:
http://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs http://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs https://www.afm.ars.usda.gov/ppweb/pps-and-manuals/ https://www.afm.ars.usda.gov/ppweb/pps-and-manuals/
The project site is the main building of the Western Regional Research Service located at 800 Buchanan Street, Albany, CA, 94710. The contractor is responsible for determining the scope of the inspections and tests to meet the code requirements in 4.0 above.
4.2 Bid Schedule:
A quotation for the following items: repair and seal the stucco on the WRRC southeast corner and south wall.
4.3 Description of Work:
The laboratories in the southeast corner of WRRC suffer from water intrusion during the rainy season due to failed stucco. The rest of the south wall does not have water intrusion that we are aware of, but has “hairline” cracks in need of repair. Damage is visually evident (see pictures attached). We require the exterior stucco to be repaired and sealed to prevent further water intrusion.
The area to be repaired and sealed is approximately 665 feet in length and 45 feet in height, with windows covering about 20% of the area. Site visits are strongly encouraged to evaluate the scope of the work. Photos are attached.
4.4 Government Furnished Equipment\Services
a. none
5.0 GENERAL REQUIREMENTS:
5.1 Permits: Where governing regulations and imposed codes and standards require notices, permits, licenses, inspections, tests, and similar items or actions in order to lawfully proceed with the required work, the Contractor shall obtain items and take those actions in accordance with the regulations of the governing authority. The costs of such permits, licenses, inspections, etc., are the obligation of the Contractor.
5.2 Existing Installations / Demolition: Contractor shall modify existing installations as needed to accommodate the new installation. Contractor shall coordinate modification of existing installations with Owner. All disturbances of existing systems shall be thoroughly coordinated with the Owner to prevent disturbances that might jeopardize on-going operations and research.
Owner reserves the right to retain any equipment / materials removed as part of the scope of work. Contractor shall coordinate any equipment / materials to be retained with Owner prior to starting demolition operations. Contractor shall legally dispose of all any materials removed that will not be retained. The contractor shall divert project waste to recycle where practical. The Contractor shall track and document the amount of waste diverted to recycle. The contractor shall submit diversion documentation as part of closeout. If no waste is diverted to recycling, the contractor shall submit a letter stating so and why diversion was not practical.
5.3 Installation: It shall be the responsibility of the Contractor to complete work in accordance with
Federal, State, and Local Code Standards. Additional procedures and materials may be required than is indicated herein. If any item specified herein conflicts with the applicable codes and recommendations, the Contractor shall bring it to the attention of the Contracting Officer Representative for immediate resolution.
5.4 Submittals: Provide manufacturer’s descriptive literature/shop drawings for all materials to the
COR for review. The descriptive literature shall be annotated/ highlighted to show its conformance with contract requirements. Submittals are required for new materials and will be stamped and/or signed by the general contractor prior to submission to the Government.
Contractor is responsible for any costs incurred for equipment ordered without prior approval.
5.5 Quality Control: The work performed under this contract shall be subject to continuous audit by the COR. Quality control is the exclusive responsibility of the Contractor.
5.6 Protection of Work and Property/Safety Requirements:
a. Contractor shall furnish a Site Specific Safety Plan (SSSP) or Accident Prevention Plan (APP) 10 days after contract award. SSSP / APP shall be approved by the Government before construction work commences.
b. The Contractor shall protect the work, the site, and all existing property and structures within the limits of the construction activities or that may be affected thereby until acceptance of the work. Any damage to property shall be repaired at the Contractor’s expense, to pre-damaged conditions to the satisfaction of the COR.
c. Safety and health matters, as they relate to the work, are the exclusive responsibility of the Contractor. The Contractor shall furnish, erect, and maintain barricades, warning lights, signs, guards, or take other precautions as may be required by law or local authorities of the protection and security.
d. Contractor is responsible for verifying location of any underground utility and is responsible for any damage caused to such utilities.
5.7 Temporary Facilities:
a. Temporary utilities (water and electricity) may be provided to the Contractor by the Government, if so requested. The Contractor shall maintain and protect all such utilities during construction and shall repair or replace any items damaged through its own negligence.
b. Should the Contractor require any power or utility shutdowns during construction, the
Contractor shall obtain approval for such shutdown from the COR 21 working days prior to the need.
5.8 Materials and Equipment:
a. The material and equipment to be furnished under these contract documents shall be the standard products of manufacturers regularly engaged in the production of such materials and equipment and shall be the manufacturer’s latest standard design.
b. All materials and equipment to be incorporated in the work shall be handled and stored by the manufacturer, fabricator, supplies and Contractor before during and after shipment in a manner to prevent any injury, theft or damage of any kind to the materials and equipment.
All materials and equipment furnished by the Contractor shall be subject to inspection and approval by the CO/COR.
c. Government will not furnish any labor or equipment to unload or move materials or supplies.
5.9 Cleanup: The construction site shall be always kept clean and free of debris. Disposal of the old equipment is required. Restore areas disturbed as nearly as possible to the original appearance and condition. Upon completion of the project, and prior to final inspection, the Contractor shall remove from the premises all unused material, trash, and debris resulting from the work to the satisfaction of the COR.
5.10 Warranty:
a. Submit data concerning the standard one-year warranty for workmanship, including the warranty periods (dates), and warranty contacts with names, addresses and telephone numbers.
b. Extended Equipment/Product Warranties: Obtain and furnish to the Contracting Officer all written warranties for equipment/products that have extended warranties (warranty periods exceeding the standard one-year warranty) furnished under the contract. The warranty period shall begin on the same date as project acceptance and shall continue for the full/product warranty period. The warranties shall be fully executed and delivered to the Contracting Officer prior to final acceptance of the facility.
5.11 Final Payment/Contract Closeout: The following documents are REQUIRED PRIOR TO
FINAL PAYMENT (other documents may also be required):
a. General contractor’s minimum one (1) year warranty on work.
b. Operation and Maintenance Data
c. Release of liens.
d. Final Invoice
6.0 PROJECT SCHEDULE: The Contract time for this project is 90 calendar days from Notice to
Proceed.
7.0 Photos, attachments, etc