SolicitationAttachment1SOW_ 1232SA26Q1004.pdf
PDF 294 KB Posted
- Attached to
- Greenhouse Repairs, CRL, Ft. Collins, Colorado
- Solicitation number
- 1232SA26Q1004
About this file
Statement of Work Summary
This is a Statement of Work (SOW) from the US Department of Agriculture (USDA) Agricultural Research Service (ARS) for greenhouse repairs at the Crops Research Laboratory (CRL) facility located at 1701 Centre Ave, Fort Collins, CO 80526. The contractor must provide all labor, materials, tools, equipment, and supervision necessary to complete repairs across 16 greenhouse units (A1, A2, A3, B1, B2, B3, B4, C1, C2, D1, D2, D3, D4, D5, D6) and two corridors (AB and CD). Work includes correction of mechanical, structural, ventilation, and shading deficiencies, with specific repairs encompassing damaged sash hardware, bent gear bars, worn gaskets, roof vent gears, bow bars, shade guide wires, shade drive cables, and damaged roof panels. The contractor must attend a mandatory on-site pre-bid visit to verify scope and document additional deficiencies.
The period of performance is 180 days from Notice to Proceed, with schedule adjustments requiring Contracting Officer (CO) approval. No government-furnished items are provided. The contractor must perform all repairs according to manufacturer specifications and USDA-ARS facility standards, with post-installation testing required to verify proper function. A comprehensive Quality Assurance/Quality Control program is mandatory, including material inspections, operational testing, and documentation of deficiencies and corrective actions. The contractor must submit a QA/QC completion report and final punch list for COR review and approval. Full compliance with OSHA, federal, state, and USDA-ARS safety regulations is required, including appropriate Personal Protective Equipment, Lockout/Tagout procedures, ladder and lift safety compliance, daily safety briefings, and immediate incident reporting to the COR.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SolicitationAttachment2WageDetermination_1232SA26Q1004.pdf | ||
| Solicitation_ 1232SA26Q1004.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Department of Agriculture (USDA)
Statement of Work
1167371-966-USDA/ARS/CARR/CRL
Greenhouse Repairs
1701 Centre Ave
Fort Collins, CO 80526
Contents
1. 1.0 Scope of Work
2. 2.0 Background
3. 3.0 Contractor Requirements
4. 4.0 Technical Requirements / Tasks
5. 5.0 Government-Furnished Items
6. 6.0 Period of Performance
7. 7.0 Quality Assurance / Quality Control (QA/QC)
8. 8.0 Safety Requirements
1. 1.0 Scope of Work
The Contractor shall provide all labor, materials, tools, equipment, and supervision necessary to complete greenhouse repairs across CRL Greenhouses A1, A2, A3, B1, B2, B3, B4, C1, C2, D1, D2, D3, D4, D5, D6, Corridor AB, and CD.
Work includes correction of mechanical, structural, ventilation, and shading deficiencies identified during the site visit.
Repairs include but are not limited to:
• Repair of damaged sash hardware
• Replacement of bent gear bars
• Realignment and lubrication of sashes
• Replacement of worn sash gaskets
• Cleaning and replacement of screens
• Lubrication and replacement of roof vent gears
• Replacement of bow bars
• Repair of shade guide wires and shade drive cables
• Repair or replacement of damaged roof panels
2. 2.0 Background
The CRL Greenhouses support ongoing USDA-ARS research requiring precise environmental and structural integrity. Due to age, weather exposure, and continuous operational demand, several greenhouse systems have degraded. Repairs are required to maintain safe, functional, and research-ready greenhouse environments.
3. 3.0 Contractor Requirements
All Contractors must attend the mandatory on-site pre-bid visit to verify scope, document additional deficiencies, and confirm material and equipment requirements.
Contractors must:
• Produce a comprehensive punch list of completed repairs for Contracting Officer Representative (COR) approval.
• Coordinate work schedules with the COR to prevent disruption of active research.
• Follow all USDA facility access and safety requirements.
4. 4.0 Technical Requirements / Tasks
Contractor shall perform all repairs according to manufacturer specifications and USDA-ARS facility standards.
All repaired systems must undergo post-installation testing to verify proper function.
5. 5.0 Government-Furnished Items None.
6. 6.0 Period of Performance The total period of performance is 180 days from Notice to Proceed. Schedule adjustments require CO approval.
7. 7.0 Quality Assurance / Quality Control (QA/QC)
The Contractor shall implement a Quality Assurance / Quality Control (QA/QC) program to ensure all work meets USDA-ARS standards and manufacturer specifications.
QA/QC requirements include:
• Inspecting all materials prior to installation to verify they meet required specifications.
• Verifying all greenhouse components are installed, aligned, and functioning properly.
• Ensuring all fasteners, seals, and moving parts are properly tightened, lubricated, and secured.
• Performing operational testing on repaired components including vents, shades, sashes, and mechanical linkages.
• Documenting deficiencies and corrective actions taken.
• Submitting a QA/QC completion report along with the final punch list for COR review and approval.
8. 8.0 Safety Requirements
The Contractor is responsible for maintaining a safe work environment and complying with all OSHA, federal, state, and USDA-ARS safety regulations.
Required safety practices:
• Use of appropriate Personal Protective Equipment (PPE) including gloves, eye protection, fall protection, and respiratory protection when applicable.
• Lockout/Tagout procedures when working on powered systems.
• Ladder and lift safety compliance.
• Daily safety briefings for all on-site employees.
• Immediate reporting of all incidents, near-misses, or hazardous conditions to the COR.
• Maintaining controlled access to work zones to avoid interference with USDA personnel or research operations.