Solicitation W912WJ25Q0054.pdf
PDF 774 KB Posted
- Solicitation number
- W912WJ25Q0054
About this file
This is a Request for Quotations (RFQ) issued by the U.S. Army Corps of Engineers New England District for paving work at East Brimfield Lake in Fiskdale, MA. The solicitation (W912WJ25Q0054) requires the contractor to pave an approximately 400-foot long gravel access road on the dam toe, including applying 2" of aggregate base course material, placing and compacting HMA binder course in two lifts to obtain 2" thickness, applying tack coat, and placing 1.5" thick HMA surface course. Additional requirements include installing an 8" high asphalt curb along 250' of the uphill shoulder, paving an existing drainage bowl, and applying topsoil and hydroseed to disturbed areas.
The RFQ is set aside for small businesses under NAICS code 237310 with a size standard of $45 million. The estimated cost is between $25,000 and $100,000. Quotes are due by March 18, 2025, with work to be completed within 120 days after notice to proceed. The contractor must provide payment protection (payment bond or irrevocable letter of credit) for 100% of the contract price. Site visits are strongly recommended and can be arranged with the technical point of contact. The contractor must be registered in SAM.gov at time of submission, and quotes should be submitted via email to the contract specialist Alicia LaCrosse.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment W912WJ25Q0054-0001.pdf | ||
| Attachments.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
EAST BRIMFIELD LAKE PROJ
JARED GAGNON
24 RIVERVIEW AVE
FISKDALE MA 01518-1243
TEL: 978-318-8027 FAX:
REQUEST FOR QUOTATIONS
(THIS IS NOT AN ORDER) 1
PAGE OF PAGES
1. REQUEST NO. 2. DATE ISSUED RATING
W912WJ25Q0054 05-Mar-2025 5a. ISSUED BY
8. TO: NAME AND ADDRESS, INCLUDING ZIP CODE
IMPORTANT: This is a request for information, and quotations furnished are not offers. If you are unable to quote, please so indicate on this form and return it to the address in Block 5a. This request does not commit the Government to pay any costs incurred in the preparation of the submission of this quotation or to contract for supplies or services. Supplies are of domestic origin unless otherwise indicated by quoter. Any representations and/or certifications attached to this
Request for Quotations must be completed by the quoter.
11. SCHEDULE (Include applicable Federal, State, and local taxes)
ITEM NO.
(a)
SUPPLIES/ SERVICES
(b)
QUANTITY
(c)
UNIT
(d)
UNIT PRICE
(e) (f)
SEE SCHEDULE
AMOUNT
% No. %
NOTE: Additional provisions and representations [ ] are [ ] are not attached.
13. NAME AND ADDRESS OF QUOTER (Street, City, County, State, and ZIP Code)
14. SIGNATURE OF PERSON AUTHORIZED TO
SIGN QUOTATION
15. DATE OF
QUOTATION
16. NAME AND TITLE OF SIGNER (Type or print) (Include area code)
TELEPHONE NO.
AUTHORIZED FOR LOCAL REPRODUCTION STANDARD FORM 18 (REV. 6-95)
PREVIOUS EDITION NOT USABLE Prescribed by GSA FAR (48 CFR) 53.215-1(a)
THIS RFQ X[ ] IS [ ] IS NOT A SMALL BUSINESS SET-ASIDE
6. DELIVER BY (Date)
SEE SCHEDULE
AND/OR DMS REG. 1
UNDER BDSA REG. 2
4. CERT. FOR NAT. DEF.3. REQUISITION/PURCHASE
REQUEST NO.
U S ARMY ENGR DISTRICT, NEW ENGLAND
696 VIRGINIA RD
CONCORD MA 01742-2751
9. DESTINATION (Consignee and address, including ZIP Code)
7. DELIVERY
[ ]X FOB
DESTINATION
[ ] OTHER
(See Schedule)
18-Mar-2025(Date)
PLEASE FURNISH QUOTATIONS TO THE ISSUING OFFICE IN BLOCK 5a ON OR BEFORE CLOSE OF BUSINESS:10.
978-318-8902ALICIA N LACROSSE
(Name and Telephone no.) (No collect calls)5b. FOR INFORMATION CALL:
d. CALENDAR DAYSc. 30 CALENDAR DAYSb. 20 CALENDAR DAYS12. DISCOUNT FOR PROMPT PAYMENT a. 10 CALENDAR DAYS
W912WJ25Q0054
Section B - Supplies or Services and Prices
INSTRUCTIONS TO VENDORS
VENDORS SUBMITTING A QUOTE IN RESPONSE TO A SOLICITATION ARE RESPONSIBLE FOR
ADHERING TO ALL INSTRUCTIONS AND TERMS AND CONDITIONS INCLUDED IN THE
SOLICITATION. FAILURE TO DO SO MAY RESULT IN QUOTES BEING DEEMED NON-
RESPONSIVE
INFORMATION:
1. This is a Request for Quotations (RFQ) in accordance with Federal Acquisition Regulation (FAR) Part 13.
2. Potential vendors are notified that the basis on which award will be made is price alone.
3. All responsible sources may submit a quote which, if timely received, must be considered by the Agency.
4. The Government may request that a vendor respond to a Quote Verification after the solicitation closes, but prior to award. The vendor shall respond in sufficient detail to all questions or statements no later than the response date and time listed in the correspondence. Failure to do so may result in quotes being deemed non-responsive and removed from consideration. The Government is under no obligation to provide extensions for responses.
QUESTIONS REGARDING SOLICITATIONS:
1. Questions regarding the solicitation shall be directed to the Contract Specialist:
a. Name: Alicia LaCrosse
b. Phone: 978-318-8902
c. Email: Alicia.N.LaCrosse@usace.army.mil
2. Technical Points of Contact shall not provide responses to interested vendors.
3. Please direct questions to the Contract Specialist. Any information received at the site visit which conflicts with this solicitation should be brought to the attention of the Contract Specialist. The solicitation and resulting contract shall be the governing document in all cases.
QUOTE SUBMISSION:
1. Quotes shall be submitted via email to the Contract Specialist listed above no later than the closing date and time identified in the solicitation or subsequent amendments.
2. The Government is under no obligation to consider any quote received after the solicitation closing date or time.
BID SCHEDULES:
1. If a Bid Schedule is included in the solicitation, vendors shall complete the bid schedule in its entirety
(all tasks, all years).
2. Vendors shall enter $0.00 on Bid Schedules in which items are Not Separately Priced. Blank entries will not be considered and will result in quotes being deemed non-responsive.
3. Failure to complete the Bid Schedule in its entirety and return same with a quote will result in quotes being deemed non-responsive.
SITE VISITS:
1. SITE VISITS ARE HIGHLY RECOMMENDED PRIOR TO PROVIDING A QUOTE. SEE CLAUSE
52.236-27 or 2.236-27 ALT I FOR ADDITIONAL INFORMATION.
2. If date(s)/time(s) for site visits are included in the solicitation, then interested vendors will be permitted to visit the site during those dates/times. No other dates/times will be permitted for site visits.
3. If no dates/times for site visits are included in the solicitation, then interested vendors shall contact the
Technical Point of Contact as identified in the solicitation to schedule a site visit.
4. No site visits will be permitted AFTER a solicitation closes.
BONDING:
1. In accordance with FAR 28.101-1(c), the Contractor will NOT be required to provide a Bid Guarantee.
2. In accordance with FAR 28.102-2(b), the Contractor will be required to provide the following payment protections for all construction contracts at or above $150,000.00.
(i) Payment Bond or
(ii) Irrevocable Letter of Credit and
(iii) Performance Bond
A Payment Bond or Irrevocable Letter of Credit is the SELECTED payment protection for the Government. The penal amount of bond shall be 100% of the original contract price. If the contract price increases, the Government will require an increase in the penal sum of the existing bond. This bond shall be submitted to the Contracting Officer within 10 days after receipt of award.
A Performance Bond shall be required if the total price of the quote is $150,000.00 or above. The penal amount of the Performance Bond shall be 100% of the original contract price. If the contract price increases, the Government will require an increase in the penal sum of the existing bond. This bond shall also be submitted to the Contracting Officer within 10 days after receipt of award.
3. In accordance with FAR Part 28.102-2(c), the Contractor will be required to provide one of the following payment protections for all construction contracts $35,000.00 or above, but not exceeding $150,000.00.
(i) Payment bond or
(ii) Irrevocable letter of credit
A Payment Bond or Irrevocable Letter of Credit is the SELECTED payment protection for the Government. The penal amount of bond shall be 100% of the original contract price. If the contract price increases, the Government will require an increase in the penal sum of the existing bond. This bond shall be submitted to the Contracting Officer within 10 days after receipt of award.
**No Payment Protections Required for construction contracts less than $35,000**
4. Prior to award, the Government may request that the Contractor provide a Letter of Bond Ability issued by a Surety that is listed on US Treasury Circular 570 (https://www.fiscal.treasury.gov/surety-bonds/list-certified-companies.html).
Letter of Bond Ability shall be issued to the Contractor and shall state that the Contractor is pre-qualified for bonding, include the single and aggregate bond limits that the bond company will support, and provide contact information of the bond agent or attorney-in-fact.
Failure to provide a Letter of Bond Ability as required will result in the Contractor’s quote being deemed non-responsive.
QUOTATION INSTRUCTIONS:
1. If subcontractor will be used for this work, please provide company name and contact information:
2. In accordance with FAR Part 52.204-7(b)(1) Contractors must be registered in the System for Award Management (SAM) database (www.SAM.gov) to submit a quote. Registered is considered when a SAM registration is marked “Active”.
3. In accordance with FAR Clause 52.204-8(d), Representations and Certifications are to be completed in www.sam.gov.
NOTE: SAM.gov registration takes approximately 3 weeks (Unique Entity Identified (UEI) 1-2 business days; CAGE code validation up to 10 business days; IRS validation and overall submission 7-10 business days). It is the contractor’s responsibility to track SAM.gov registration and follow-up with required tasks.
4. Provide business Unique Entity Identifier (UEI): _______________________________
5. Provide business CAGE code: __________________________________
6. Contractors are not required to submit an Accident Prevention Plan (APP) with their quote. The successful Contractor will be required to submit this document at the direction of the Technical Point of Contact. The APP must be accepted by the Government Designated Authority prior to the commencement of work.
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Job Dam Toe Access Road Paving
FFP
Contractor shall provide all labor, materials, equipment, and transportation to pave the approximately four hundred foot (400') long gravel access road on the dam toe at East Brimfield Lake, Fiskdale, MA in accordance with the Statement of Work.
FOB: Destination
PSC CD: Y1LB
NET AMT
Section C - Descriptions and Specifications
STATEMENT OF WORK
DAM TOE ACCESS ROAD PAVING
EAST BRIMFIELD LAKE
FISKDALE, MA
STATEMENT OF WORK
I. GENERAL
1. Summary:
Contractor shall furnish all materials, equipment, and labor required to pave the approximately four hundred foot (400’) long gravel access road on the dam toe at East Brimfield Lake, Fiskdale, MA. See attached map, diagram, and informational photos for more information. All work shall be completed in accordance with the following Statement of Work.
2. Location:
East Brimfield Dam is located at 24 Riverview Ave. Fiskdale, MA 01518.
3. Site Visits:
Site visits are strongly recommended to gauge the full scope of work and provide an accurate quote. No extra payment will be considered for perceived additional work caused by unfamiliarity with the site conditions and requirements. Contact the Technical Point of Contact, Park Ranger Jared Gagnon at 508-635-7545 or jared.s.gagnon@usace.army.mil to arrange a site visit.
4. Schedule:
The period of performance shall be no later than 120 days after Notice to Proceed. The project area will be open to the Contractor Monday through Friday 7:00 AM to 3:30 PM and all work must be done during those hours unless additional hours are approved by the Technical Point of Contact. No work shall be done on weekends or Government holidays.
All Pre-Construction shall be submitted, reviewed, and accepted within 30 days of Notice to Proceed. The Government reserves up to 21 days for review and acceptance on each submittal/ resubmittal from the date of receipt. If revisions are necessary to the submittals, the Contractor shall make such revisions and shall be resubmitted to the Government in an acceptable form within 14 days of the Government’s response, unless additional time is granted by the Government in writing. No field work may proceed prior to the acceptance of Pre-Construction submittals.
5. Safety Requirements
a) General: All work shall be conducted in accordance with the U.S. Army Corps of
Engineers (USACE) Safety and Occupational Health Requirements (EM 385-1-1, most recent edition), and all applicable Occupational Safety and Health Administration (OSHA), Federal, State, and local safety and health requirements.
A copy of EM 385-1-1 can be accessed electronically at the following link:
https://www.publications.usace.army.mil/Portals/76/EM%20385-1- 1%20_EFFECTIVE%2015March2024.pdf
Project staff reserve the right to cease work at any time should the safety of employees, Contractors, and/or the public become jeopardized.
b) Accident Prevention Plan: The Contractor shall prepare a site-specific Accident
Prevention Plan. The APP must be written by a Competent Person (CP) and document the specific work processes, equipment, materials to be used, hazards and applicable control measures.
The mandatory ENG Form 6293 (Accident Prevention Plan Worksheet) must be submitted and accepted prior to beginning on site work:
https://www.publications.usace.army.mil/Portals/76/Eng_Form_6293_2023Aug31.
A preparatory meeting shall be conducted by the Prime Contractor to discuss the APP contents with all effected onsite employees. The Prime Contractor is responsible for informing the subcontractors of the safety provisions under the terms of the contract, the penalties for noncompliance, and inspecting subcontractor operations to ensure that accident prevention responsibilities are being carried out.
Daily safety meetings shall be held and documented. Records shall be available to the Technical Point of Contact upon request.
c) Activity Hazard Analysis: An AHA shall be submitted and accepted for each definable feature of work (DFOW) in accordance with EM 385-1-1, Chapter 2-6.
A DFOW is defined as any task, which is separate and distinct from other tasks, has separate control requirements, or is identified as different trades or disciplines.
The AHA shall be continuously reviewed and revised to address changing site conditions as appropriate.
For a non-mandatory formatted outline of an AHA, see ENG Form 6206 (Activity Hazard Analysis) https://www.publications.usace.army.mil/Portals/76/Eng_Form_6206_2023Aug24.
d) Site Safety and Health Officer (SSHO) Requirements: Contractor shall employ a minimum of one person to function as a Level 3, SSHO. A Level 3 SSHO is a designated Qualified Person (QP) or Competent Person (CP) with Safety and Occupational Health (SOH) responsibility that meets the requirements of EM 385-
1-1, Chapter 2-3.b and 2-4.b.
Level 3 SSHOs must have training, knowledge, and/or experience identifying hazards and implementing controls for the work being performed.
The SSHO shall be present at the project site and be responsible for overseeing the implementation of the Prime Contractor’s SOH program. Contractor shall designate all SSHOs on a mandatory ENG Form 6282 (Site Safety and Health Officer Designation Letter):
https://www.publications.usace.army.mil/Portals/76/Eng_Form_6282_2023Aug28.
e) First-Aid and CPR Personnel Requirements: For shifts with multiple employees, provide at least two employees that are certified to administer First Aid and CPR.
When employees work alone, they must be certified in First Aid and be provided an effective means of communication to call for assistance in the event of an emergency. Minimum First Aid and CPR qualifications are outlined in EM 385-1- 1, Chapter 3-3.
f) Additional Personnel Requirements: Other Competent Person (CP) or Qualified Persons (QP) may be required per EM 385-1-1 and/or other sections of this Scope of Work, based on the definable features of work for this project.
g) Accident Reporting: All accidents and near misses shall be investigated by the Contractor and reported to the Technical Point of Contact in accordance with EM 385-1-1, Table 2-1.
The mandatory ENG Form 3394 shall be completed and submitted to the Technical Point of Contact within seven (7) days of an incident:
https://www.publications.usace.army.mil/Portals/76/Publications/EngineerForms/E ng_Form_3394_2021Aug.pdf
h) Employee Exposure Data: The Contractor shall electronically report total employee work hours (including subcontractors) to the Technical Point of Contact by close of business on the 10th calendar day of the following month.
6. Pre-Construction Conference:
Prior to the start of any work, the Technical Point of Contact will schedule and conduct a “Pre-Construction Conference”. The Contractor’s Project Manager and Quality Control Personnel will be physically present to attend this meeting.
The Contractor shall directly oversee all work on the project and the Project Manager and Quality Control Personnel shall have the authority to act on behalf of the Contractor. This conference will be held at the time and location agreeable to the Government and Contractor. No work may be performed under this contract prior to this conference. The purpose of the conference is to enable the Technical Point of Contact to outline the procedures that will be followed by the Government in its administration of the contract, and to discuss the performance that will be expected from the Contractor. This conference will allow the Contractor an opportunity to ask questions about the Government’s administration and inspection of contract work or obtain other pertinent information that might be required. At the Pre-Construction Conference the Contractor shall provide the name of the project superintendent with a telephone number for project coordination.
The following is a general list of items for discussion during the Pre- Construction Conference:
a) Authority of the Technical Point of Contact
b) Contractor’s Safety Program (including sub-contractors)
c) Accident Prevention Plan
d) Activity Hazard Analysis
e) Work Plan
f) Daily Safety Meetings (Documented on NED Form 251)
g) Accident Reporting (ENG Form 3394)
h) Correspondence, Communication and Administrative Procedures.
i) Invoice and payment
j) Material Specifications
7. Permits:
The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses, permits, and letters of certification. The Contractor shall comply with any applicable Federal, State, county, and municipal laws, codes, and regulations in connection with the performance of the work specified under this contract.
8. Security:
The Contractor will comply with all established security policies at the Project. Due to periods of heightened security that may affect the access to the areas covered under this contract, areas may be subject to periodic closures, which in turn may reduce or inhibit the Contractor’s ability to access certain areas. During periods of heightened security, the Government reserves the right, at any time, to close any property or portion of property and reschedule and/or cancel any subsequent service in an area. The Contractor shall be given at least 24-hour notice of any such closure.
9. Payment:
Payment shall be made on a per job basis. After final inspection and acceptance by the Government, the Contractor must submit an invoice and a completed, signed US Army Corps of Engineers ENG93 form to the Technical Point of Contact. The invoice shall include the invoice date, contract number, dates of service, description of work, quantities, process, and total amount due per line item. For jobs greater than 30 days the Contractor may request progress payments.
All invoices may be mailed to:
U.S. Army Corps of Engineers East Brimfield Lake 24 Riverview Ave.
Fiskdale, MA 01518
Or sent via email to keith.w.beecher@usace.army.mil
10. Damage to Government and Private Property:
The Contractor shall be responsible for restoring any Government facilities or structures damaged as a result of the firm’s operation. The Contractor shall also be responsible for any damage to private property or injury to any person as a result of the firm’s operations. The Contractor shall notify the Technical Point of Contact immediately of damage to Government and private property and injury to any person resulting from the firms’ operation.
II. TECHNICAL
1. Submittals:
Although the Government reviews submissions required by this Statement of Work, it is emphasized that the Contractor’s work must be completed using proper internal controls and review procedures. The Government reserves up to 21 days for review and acceptance on each submittal/resubmittal from the date of receipt. If revisions are necessary to the submittals, the Contractor shall make such revisions and shall resubmit to the Government in acceptable form within 14 days of the Government’s response, unless additional time is granted by the Government in writing
Pre-Construction Submittals: The documents identified below must be prepared in accordance with the applicable standards, submitted to the Technical Point of Contact for review within 30 days of the notice to proceed, and accepted by the Government prior to the commencement of any field work:
Accident Prevention Plan ENG Form 6293 (Accident Prevention Plan Worksheet) ENG Form 6282 (Site Safety and Health Officer Designation Letter) Appropriate licenses and certifications First Aid and CPR Certificates Activity Hazard Analysis (AHA) Material Specification Sheets
2. Clean-Up:
The Contractor shall practice good housekeeping to maintain a safe job site.
The Contractor shall keep the work area, including any storage areas, free from the accumulation of waste materials. Upon completing work in an area, the Contractor shall remove any tools, equipment, and materials that are not the property of the Government. Upon completion of work, the Contractor shall clean up the job site to the satisfaction of the Government. All construction debris shall be disposed of off-site.
3. Government Resources:
The Contractor is responsible for providing all materials to complete the project. Unless specified in the contract, the Government will not provide any equipment, electrical services, telephone services, or other resources.
4. Omissions:
This contract may not cover all specified activities, steps, and procedures required to supply the contract product. In case of omission, the normal industry, State, or Federal standards, practices, specifications, and/or guides shall prevail. In no instance shall an omission be reason to produce less than an acceptable product.
5. Quality Assurance:
The Contractor is responsible for the quality control of the contract work. The Government has the right to inspect and test all items called for by the contract, to the extent practicable at all times and at all places during the term of the contract.
6. Other Contracts:
The Government may undertake or award other contracts for additional work not related to this contract, and the Contractor shall fully cooperate with other Contractors and Government employees. The Contractor shall not commit or permit any act, which will interfere with the performance of work by another Contractor, or by Government employees.
7. Environmental Protection:
Water, air, and land resources shall not be adversely impacted. The Contractor is responsible for taking all necessary steps to ensure compliance with all Federal, State, and local environmental laws and regulations. The Contractor will not receive additional payment for environmental protection measures.
8. Sustainability:
All products provided by the Contractor must meet the recycled content requirements set forth by the Environmental Protection Agency. Under the Comprehensive Procurement Guidelines (CPG) program, the Environmental Protection Agency (EPA) designates products that are or can be made with recovered materials and recommends practices for buying these products. Any designated product that is being offered or supplied under this contract shall meet the minimum recommended content levels as identified under the CPG program. Visit https://www.epa.gov/smm/comprehensive-procurement-guideline-cpg-program for a complete list of designated products and the associated recommended contents levels.
Offerors must be able to demonstrate that each offered products meets minimum content levels upon request.
Furthermore, the Contractor should also meet the BioPreferred Program requirements. The United States Department of Agriculture (USDA) designates certain bio-based products for Federal procurement and specifies minimum bio-based content levels for those products. Any designated product that is being offered or supplied under this contract shall meet USDA BioPreferred's minimum bio-based content level. Visit the BioPreferred web site https://www.biopreferred.gov/BioPreferred/faces/pages/ProductCategories.xhtml for the complete list of designated products and the associated minimum bio based content level requirements.
9. Receiving and Storing Materials:
The Contractor is responsible for protecting any stored material until it is placed in service. The Contractor is responsible for receiving and unloading of delivered goods. Government employees will not receive material or supplies for the Contractor and will not be responsible for damage to Contractor equipment or material. The storage and staging area must be coordinated with the Technical Point of Contact.
10. Existing Conditions:
i. Approximately 400’ long gravel surface (the existing gravel road extends beyond the portion to be paved).
ii. Width varies between 10’ and 15’.
iii. Roadway is pitched toward the hillside.
iv. A 25’ long x 10’ wide x 3’ deep drainage bowl is located along the uphill side of road at the base of the hill.
11. Product Requirements:
a) Aggregate Base Course:
i. Aggregate Base Course material shall conform to M2.01.7 of the MA DOT specifications for Dense-Graded Crushed Stone.
b) Hot Mix Asphalt:
i. Hot mix asphalt (HMA) for binder course and surface course shall conform to the applicable requirements of Section 460 and Section M3.06.0 of the MA DOT specifications for Hot Mix Asphalt Pavement.
ii. Hot mix asphalt job-mix formulas (JMFs) shall be obtained from a supplier regularly producing HMA under Section 460 of the MA DOT specifications.
iii. The HMA binder course shall conform to the requirements listed in
Table A of Section M3.06.0 of the MA DOT specifications for HMA Base/Intermediate Course - Binder.
iv. The HMA surface course shall conform to the requirements listed in Table A of Section M3.06.0 of the MA DOT specifications for HMA Surface Course - Standard Top.
c) Tack Coat:
i. Bituminous material used for the tack coat shall be emulsified asphalt, grade RS-1 conforming to AASHTO M 140.
d) Topsoil:
i. Topsoil material shall conform to the requirements of M1.05.0 of the MA DOT specifications for loam.
e) Hydroseed Mix:
i. Grass see mixture shall conform to MA DOT requirements specified in Table M6.03.0-2: Grass Seed Requirements for Slopes and Shoulders.
12. Execution:
a) General:
i. All work and materials shall conform with the lines, grades, elevations, dimensions, material requirements, and testing requirements that are specified in this Statement of Work.
ii. The Contractor is responsible for all layout and field engineering required for the completion of this project. The Government will not provide any survey services.
iii. The Contractor shall verify that the actual site conditions are consistent with the existing conditions depicted in this contract.
Discrepancies, omissions, and errors shall be reported to the Technical Point of Contact prior to the start of construction.
iv. It is the Contractor’s responsibility to provide and maintain erosion prevention and sedimentation control measures as conditions require.
Erosion and sedimentation control measures shall be pre-approved by the Technical Point of Contact.
v. The Contractor shall provide protection to surrounding pavement, vegetation, structures, and utilities within the work area that are to remain in place. Damages caused by the Contractor shall be repaired or restored to original condition or better at the Contractor’s expense.
vi. At the completion of work, all disturbed areas and new pavement shall be smooth with sufficient slope to allow for proper drainage and no ponding. All disturbed areas shall receive 6” minimum of topsoil and shall be hydroseed.
vii. The gravel road beyond the approximate 400’ long area depicted in the attached map will be left as is.
b) Base Course:
i. 2” (compacted thickness) of aggregate base course material shall be applied to existing road surface.
ii. Base course shall be placed in a manner that preserves the existing road grade.
iii. Base course shall be rolled prior to paving.
c) Hot Mix Asphalt (HMA) Paving:
i. The HMA binder course shall be placed and compacted in two lifts to obtain a compacted thickness of 2”.
ii. A tack coat shall be applied to the surface of the new HMA binder course and the vertical edges of existing pavement.
iii. The HMA surface course shall be placed in one layer and compacted to obtain a compacted thickness of 1.5”.
d) Curbing:
i. A rounded 8” high asphalt curb shall be placed along the uphill shoulder of the road between the upper parking lot and the drainage bowl (approx. length of 250’).
ii. Curb shall be placed upon the binder course (see figure 1).
iii. Topsoil and hydroseed shall be placed along uphill side of curb as depicted in Figure 1 below.
e) Drainage Bowl:
i. An existing drainage ditch (i.e. bowl) will be paved according to the above specifications.
ii. The entire disturbed portion of the bowl shall be paved (see figure
2).
iii. Pavement surface shall be level with the bottom of the existing drainpipe.
f) Shoulder:
i. Shoulders shall consist of topsoil.
ii. Shoulder shall allow for gradual slope away from pavement.
iii. Surface of shoulder shall be 0.5” below the pavement surface.
iv. All new topsoil shall be hydroseeded.
ATTACHMENTS
PLEASE SEE ATTACHMENTS INCLUDED SEPARATELY FOR ADDITIONAL INFORMATION.
Section F - Deliveries or Performance
DELIVERY INFORMATION
CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
0001 120 dys. ANP 1 EAST BRIMFIELD LAKE PROJ
JARED GAGNON
24 RIVERVIEW AVE
FISKDALE MA 01518-1243
978-318-8027 FOB: Destination
961310
Section H - Special Contract Requirements
SECURITY REQUIREMENTS
General security requirements and guidance: The security requirements described below apply to all contract personnel (including employees of the prime Contractor (“Contractor”) and all subcontractor employees) supporting the performance requirements of this contract. The Contractor is responsible for compliance with these security requirements. Questions regarding security matters shall be addressed to the designated Government representative (eg., Contracting Officer Representative (COR), Requiring Activity (RA) representative, or Contracting Officer (if a COR or other RA representative is not appointed)). Contract personnel are critical to the overall security and safety of US Army Corps of Engineers (USACE) installations, facilities and activities, and security awareness training contributes to those efforts. The Department of Defense (DoD) and Army security training requirements specified below, if applicable, are performance requirements; all applicable contract personnel shall complete initial training within 30 days of contract award or the date new contract personnel begin performance on the contract. Within five business days from the completion of training, the Contractor shall provide written documentation (e.g., email or memorandum) to the Government representative. The documentation shall include the names of contract personnel trained and which training they completed; the Contractor shall maintain training records as part of their contract files and be prepared to provide copies of training certificates to the Government representative. Contractor personnel and vehicles are subject to search when entering federal installations. Additionally, all contract personnel shall comply with Force Protection Condition (FPCON) measures, Random Antiterrorism Measures (commonly referred to as “RAMs”), and Health Protection Condition (HPCON) measures. The Contractor is responsible for meeting performance requirements during elevated FPCON and/or HPCON levels in accordance with applicable RA plans and procedures –this includes identifying mission essential and non-mission essential personnel. In addition to the changes otherwise authorized by the changes clauses of this contract, should FPCON or HPCON levels at any individual facility or installation change, the Government may implement security changes that affect contract personnel. The Contractor shall ensure all contract personnel are aware of their security responsibilities, including any site-specific requirements identified in local policies or procedures.
Suspicious Activity Reporting training (e.g. iWATCH, CorpsWatch, or See Something, Say Something): All contract personnel shall receive initial and annual refresher training from the RA representative on the local suspicious activity reporting program. This locally developed training provides contract personnel with general information on suspicious behavior, and guidance on reporting suspicious activity to the project manager, security representative or law enforcement entity.
WAGE DETERMINATION
The Wage Determination for this project can be found at:
https://sam.gov/wage-determination/MA20250025/0 Wage Determination No.: MA20250025 Modification No.: 0 Date: 03 Jan 2025
Section I - Contract Clauses
CLAUSES INCORPORATED BY REFERENCE
52.204-13 System for Award Management Maintenance OCT 2018 52.204-18 Commercial and Government Entity Code Maintenance AUG 2020 52.204-19 Incorporation by Reference of Representations and
Certifications.
DEC 2014
52.209-10 Prohibition on Contracting With Inverted Domestic Corporations
NOV 2015
52.219-6 Notice Of Total Small Business Set-Aside NOV 2020 52.222-6 Construction Wage Rate Requirements AUG 2018 52.222-7 Withholding of Funds MAY 2014 52.222-8 Payrolls and Basic Records JUL 2021 52.222-9 Apprentices and Trainees JUL 2005 52.222-10 Compliance with Copeland Act Requirements FEB 1988 52.222-11 Subcontracts (Labor Standards) MAY 2014 52.222-12 Contract Termination-Debarment MAY 2014 52.222-13 Compliance With Construction Wage Rate Requirements and
Related Regulations
MAY 2014
52.222-14 Disputes Concerning Labor Standards FEB 1988 52.222-15 Certification of Eligibility MAY 2014 52.222-27 Affirmative Action Compliance Requirements for
Construction
APR 2015
52.223-4 Recovered Material Certification MAY 2008 52.226-8 Encouraging Contractor Policies To Ban Text Messaging
While Driving
MAY 2024
52.228-2 Additional Bond Security OCT 1997 52.228-11 (Dev) Individual Surety--Pledge of Assets (DEVIATION 2020-
O0016)
FEB 2021
52.228-12 Prospective Subcontractor Requests for Bonds DEC 2022 52.232-5 Payments under Fixed-Price Construction Contracts MAY 2014 52.232-23 Assignment Of Claims MAY 2014 52.232-27 Prompt Payment for Construction Contracts JAN 2017 52.236-2 Differing Site Conditions APR 1984 52.236-3 Site Investigation and Conditions Affecting the Work APR 1984 52.236-5 Material and Workmanship APR 1984 52.236-6 Superintendence by the Contractor APR 1984 52.236-7 Permits and Responsibilities NOV 1991 52.236-8 Other Contracts APR 1984 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements
APR 1984
52.236-10 Operations and Storage Areas APR 1984 52.236-11 Use and Possession Prior to Completion APR 1984 52.236-12 Cleaning Up APR 1984 52.236-13 Accident Prevention NOV 1991 52.236-21 Specifications and Drawings for Construction FEB 1997 52.236-26 Preconstruction Conference FEB 1995 52.242-14 Suspension of Work APR 1984 52.243-5 Changes and Changed Conditions APR 1984 52.246-12 Inspection of Construction AUG 1996 52.246-21 Warranty of Construction MAR 1994 52.249-1 Termination For Convenience Of The Government (Fixed
Price) (Short Form)
APR 1984
52.249-10 Default (Fixed-Price Construction) APR 1984 252.203-7000 Requirements Relating to Compensation of Former DoD
Officials
SEP 2011
252.203-7002 Requirement to Inform Employees of Whistleblower Rights DEC 2022 252.204-7000 Disclosure Of Information OCT 2016 252.204-7003 Control Of Government Personnel Work Product APR 1992 252.204-7012 Safeguarding Covered Defense Information and Cyber
Incident Reporting
MAY 2024
252.204-7015 Notice of Authorized Disclosure of Information for Litigation Support
JAN 2023
252.204-7018 Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services
JAN 2023
252.204-7020 NIST SP 800-171 DoD Assessment Requirements NOV 2023 252.223-7006 Prohibition On Storage, Treatment, and Disposal of Toxic or
Hazardous Materials
SEP 2014
252.225-7048 Export-Controlled Items JUN 2013 252.227-7033 Rights in Shop Drawings APR 1966 252.232-7004 (Dev) DoD Progress Payment Rates (DEVIATION 2020-O0010) MAR 2020 252.232-7010 Levies on Contract Payments DEC 2006 252.236-7000 Modification Proposals-Price Breakdown DEC 1991 252.243-7001 Pricing Of Contract Modifications DEC 1991 252.244-7000 Subcontracts for Commercial Products or Commercial
Services
NOV 2023
CLAUSES INCORPORATED BY FULL TEXT
52.204-27 PROHIBITION ON A BYTEDANCE COVERED APPLICATION (JUN 2023)
(a) Definitions. As used in this clause--
Covered application means the social networking service TikTok or any successor application or service developed or provided by ByteDance Limited or an entity owned by ByteDance Limited.
Information technology, as defined in 40 U.S.C. 11101(6)--
(1) Means any equipment or interconnected system or subsystem of equipment, used in the automatic acquisition, storage, analysis, evaluation, manipulation, management, movement, control, display, switching, interchange, transmission, or reception of data or information by the executive agency, if the equipment is used by the executive agency directly or is used by a contractor under a contract with the executive agency that requires the use-
(i) Of that equipment; or
(ii) Of that equipment to a significant extent in the performance of a service or the furnishing of a product;
(2) Includes computers, ancillary equipment (including imaging peripherals, input, output, and storage devices necessary for security and surveillance), peripheral equipment designed to be controlled by the central processing unit of a computer, software, firmware and similar procedures, services (including support services), and related resources; but
(3) Does not include any equipment acquired by a Federal contractor incidental to a Federal contract.
(b) Prohibition. Section 102 of Division R of the Consolidated Appropriations Act, 2023 (Pub. L. 117-328), the No TikTok on Government Devices Act, and its implementing guidance under Office of Management and Budget (OMB) Memorandum M-23-13, dated February 27, 2023, "No TikTok on Government Devices" Implementation Guidance, collectively prohibit the presence or use of a covered application on executive agency information technology, including certain equipment used by Federal contractors. The Contractor is prohibited from having or using a covered application on any information technology owned or managed by the Government, or on any information technology used or provided by the Contractor under this contract, including equipment provided by the Contractor's employees; however, this prohibition does not apply if the Contracting Officer provides written notification to the Contractor that an exception has been granted in accordance with OMB Memorandum M-23-13.
(c) Subcontracts. The Contractor shall insert the substance of this clause, including this paragraph (c), in all subcontracts, including subcontracts for the acquisition of commercial products or commercial services.
(End of clause)
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 30 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 120 calendar days after notice to proceed. The time stated for completion shall include final cleanup of the premises.
52.213-4 TERMS AND CONDITIONS--SIMPLIFIED ACQUISITIONS (OTHER THAN COMMERCIAL
PRODUCTS AND COMMERCIAL SERVICES) (JAN 2025)
(a) The Contractor shall comply with the following Federal Acquisition Regulation (FAR) clauses that are incorporated by reference:
(1) The clauses listed below implement provisions of law or Executive order:
(i) 52.203-19, Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (JAN 2017) (section 743 of Division E, Title VII, of the Consolidated and Further Continuing Appropriations Act, 2015 (Pub. L.
113-235) and its successor provisions in subsequent appropriations acts (and as extended in continuing resolutions)).
(ii) 52.204-23, Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab Covered Entities (DEC 2023) (Section 1634 of Pub. L. 115-91).
(iii) 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment. (NOV 2021) (Section 889(a)(1)(A) of Pub. L. 115-232).
(iv) 52.204-27, Prohibition on a ByteDance Covered Application (JUN 2023) (Section 102 of Division R of Pub. L.
117-328), unless the agency grants an exception--see paragraph (b) of 52.204-27.
(v) 52.204-30, Federal Acquisition Supply Chain Security Act Orders--Prohibition. (DEC 2023) (Pub. L. 115-390, title II).
(vi) 52.222-3, Convict Labor (JUN 2003) (E.O. 11755).
(vii) 52.222-21, Prohibition of Segregated Facilities (APR 2015).
(viii) 52.222-26, Equal Opportunity (SEPT 2016) (E.O. 11246).
(ix) 52.225-13, Restrictions on Certain Foreign Purchases (FEB 2021) (E.O.s, proclamations, and statutes administered by the Office of Foreign Assets Control of the Department of the Treasury).
(x) 52.232-40, Providing Accelerated Payments to Small Business Subcontractors (MAR 2023) (31 U.S.C. 3903 and 10 U.S.C. 3801).
(xi) 52.233-3, Protest After Award (AUG 1996) (31 U.S.C. 3553).
(xii) 52.233-4, Applicable Law for Breach of Contract Claim (OCT 2004) (Pub. L. 108-77 and 108-78 (19 U.S.C.
3805 note)).
(2) Listed below are additional clauses that apply:
(i) 52.232-1, Payments (APR 1984).
(ii) 52.232-8, Discounts for Prompt Payment (FEB 2002).
(iii) 52.232-11, Extras (APR 1984).
(iv) 52.232-25, Prompt Payment (JAN 2017).
(v) 52.232-39, Unenforceability of Unauthorized Obligations (JUN 2013).
(vi) 52.233-1, Disputes (MAY 2014).
(vii) 52.244-6, Subcontracts for Commercial Products and Commercial Services (JAN 2025).
(viii) 52.253-1, Computer Generated Forms (JAN 1991).
(b) The Contractor shall comply with the following FAR clauses, incorporated by reference, unless the circumstances do not apply:
(1) The clauses listed below implement provisions of law or Executive order:
(i) 52.203-17, Contractor Employee Whistleblower Rights (NOV 2023) (41 U.S.C. 4712); this clause does not apply to contracts of DoD, NASA, the Coast Guard, or applicable elements of the intelligence community--see FAR 3.900(a).
(ii) 52.204-10, Reporting Executive Compensation and First-Tier Subcontract Awards (JUN 2020) (Pub. L. 109-
282) (31 U.S.C. 6101 note) (Applies to contracts valued at or above the threshold specified in FAR 4.1403(a) on the date of award of this contract).
(iii) 52.222-19, Child Labor--Cooperation with Authorities and Remedies (JAN 2025) (E.O. 13126) (Applies to contracts for supplies exceeding the micro-purchase threshold, as defined in FAR 2.101 on the date of award of this contract).
(iv) 52.222-20, Contracts for Materials, Supplies, Articles, and Equipment (JUN 2020) (41 U.S.C. chapter 65) (Applies to supply contracts over the threshold specified in FAR 22.602 on the date of award of this contract, in the United States, Puerto Rico, or the U.S. Virgin Islands).
(v) 52.222-35, Equal Opportunity for Veterans (JUN 2020) (38 U.S.C. 4212) (Applies to contracts valued at or above the threshold specified in FAR 22.1303(a) on the date of award of this contract).
(vi) 52.222-36, Equal Employment for Workers with Disabilities (JUN 2020) (29 U.S.C. 793) (Applies to contracts over the threshold specified in FAR 22.1408(a) on the date of award of this contract, unless the work is to be performed outside the United States by employees recruited outside the United States). (For purposes of this clause, “United States” includes the 50 States, the District of Columbia, Puerto Rico, the Northern Mariana Islands, American Samoa, Guam, the U.S. Virgin Islands, and Wake Island.)
(vii) 52.222-37, Employment Reports on Veterans (JUN 2020) (38 U.S.C. 4212) (Applies to contracts valued at or above the threshold specified in FAR 22.1303(a) on the date of award of this contract).
(viii) 52.222-41, Service Contract Labor Standards (AUG 2018) (41 U.S.C. chapter 67) (Applies to service contracts over $2,500 that are subject to the Service Contract Labor Standards statute and will be performed in the United States, District of Columbia, Puerto Rico, the Northern Mariana Islands, American Samoa, Guam, the U.S.
Virgin Islands, Johnston Island, Wake Island, or the outer Continental Shelf).
(ix)(A) 52.222-50, Combating Trafficking in Persons (NOV 2021) (22 U.S.C. chapter 78 and E.O. 13627) (Applies to all solicitations and contracts).
(B) Alternate I (MAR 2015) (Applies if the Contracting Officer has filled in the following information with regard to applicable directives or notices: Document title(s), source for obtaining document(s), and contract performance location outside the United States to which the document applies).
(x) 52.222-55, Minimum Wages for Contractor Workers Under Executive Order 14026 (JAN 2022) (Applies when 52.222-6 or 52.222-41 are in the contract and performance in whole or in part is in the United States (the 50 States, the District of Columbia, Puerto Rico, the Northern Mariana Islands, American Samoa, Guam, the U.S. Virgin Islands, Johnston Island, Wake Island, and the outer Continental Shelf as defined in the Outer Continental Shelf Lands Act (43 U.S.C. 1331, et seq.))).
(xi) 52.222-62, Paid Sick Leave Under Executive Order 13706 (JAN 2022) (E.O. 13706) (Applies when 52.222-6 or 52.222-41 are in the contract and performance in whole or in part is in the United States (the 50 States and the District of Columbia.))
(xii) 52.223-5, Pollution Prevention and Right-to-Know Information (MAY 2024) (42 U.S.C. 11001-11050 and 13101-13109) (Applies to services performed on Federal facilities).
(xiii) 52.223-11, Ozone-Depleting Substances and High Global Warming Potential Hydrofluorocarbons (MAY 2024) (42 U.S.C. 7671, et seq.) (Applies to contracts for products as prescribed at FAR 23.109(d)(1)).
(xiv) 52.223-12, Maintenance, Service, Repair, or Disposal of Refrigeration Equipment and Air Conditioners (MAY 2024) (42 U.S.C. 7671, et seq.) (Applies to maintenance, service, repair, or disposal of refrigeration equipment and air conditioners).
(xv) 52.223-20, Aerosols (MAY 2024) (42 U.S.C. 7671, et seq.) (Applies to contracts for products that may contain high global warming potential hydrofluorocarbons as a propellant or as a solvent; or contracts for maintenance or repair of electronic or mechanical devices).
(xvi) 52.223-21, Foams (MAY 2024) (42 U.S.C. 7671, et seq.) (Applies to contracts for products that may contain high global warming potential hydrofluorocarbons or refrigerant blends containing hydrofluorocarbons as a foam blowing agent; or contracts for construction of buildings or facilities.
(xvii) 52.223-23, Sustainable Products and Services (MAY 2024) (E.O. 14057, 7 U.S.C. 8102, 42 U.S.C. 6962, 42 U.S.C. 8259b, and 42 U.S.C. 7671l) (Applies to contracts when the agency identifies in the statement of work, or elsewhere in the contract, the sustainable products and services that apply to the acquisition).
(xviii)(A) 52.225-1, Buy American--Supplies (OCT 2022) (41 U.S.C. chapter 67) (Applies to contracts for supplies, and to contracts for services involving the furnishing of supplies, for use in the United States or its outlying areas, if the value of the supply contract or supply portion of a service contract exceeds the micro-purchase threshold, as defined in 2.101 on the date of award of this contract, and the acquisition--
(1) Is set aside for small business concerns; or
(2) Cannot be set aside for small business concerns (see 19.502-2), and does not exceed $50,000).
(B) Alternate I (OCT 2022) (Applies if the Contracting Officer has filled in the domestic content threshold below, which will apply to the entire contract period of performance. Substitute the following sentence for the first sentence of paragraph (1)(ii)(A) of the definition of domestic end product in paragraph (a) of 52.225-1:
(A) The cost of its components mined, produced, or manufactured in the United States exceeds percent of the cost of all its components. [Contracting officer to insert the percentage per instructions at 13.302- 5(d)(4).])
(xix) 52.226-6, Promoting Excess Food Donation to Nonprofit Organizations (JUN 2020) (42 U.S.C. 1792) (Applies to contracts greater than the threshold specified in FAR 26.404 on the date of award of this contract, that provide for the provision, the service, or the sale of food in the United States).
(xx) 52.232-33, Payment by Electronic Funds Transfer--System for Award Management (OCT 2018) (Applies when the payment will be made by electronic funds transfer (EFT) and the payment office uses the System for Award Management (SAM) as its source of EFT information).
(xxi) 52.232-34, Payment by Electronic Funds Transfer--Other than System for Award Management (JUL 2013) (Applies when the payment will be made by EFT and the payment office does not use the SAM database as its source of EFT information.)
(xxii) 52.240-1, Prohibition on Unmanned Aircraft Systems Manufactured or Assembled by American Security Drone Act--Covered Foreign Entities (Nov 2024). (Sections 1821-1826, Pub. L. 118-31, 41 U.S.C. 3901 note prec.).
(xxiii) 52.247-64, Preference for Privately Owned U.S.-Flag Commercial Vessels (NOV 2021) (46 U.S.C. 55305) (Applies to supplies transported by ocean vessels (except for the types of subcontracts listed at 47.504(d).)
(xxiv) 52.247-69, Reporting Requirement for U.S.-Flag Air Carriers Regarding Training to Prevent Human Trafficking (JAN 2025) (49 U.S.C. 40118(g)). (Applies to contracts with a U.S.-flag carrier for the transportation by air of passengers; does not apply to contracts awarded by the Department of Defense or contracts for commercial products).
(2) Listed below are additional clauses that may apply:
(i) 52.204-21, Basic Safeguarding of Covered Contractor Information Systems (NOV 2021) (Applies to contracts when the contractor or a subcontractor at any tier may have Federal contract information residing in or transiting through its information system.)
(ii) 52.209-6, Protecting the Government's Interest When Subcontracting with Contractors Debarred, Suspended,…