This document is a solicitation for Park Water System Services at Elm Brook Park in Hopkinton, New Hampshire. It requires the contractor to furnish all equipment, supplies, materials, transportation, and labor to perform plumbing services, including de-winterizing the park water system in the spring, winterizing it in the fall, and replacing a section of plumbing for a spigot and the pressure tank union assembly. The service period is from contract award through October 31, 2024. This is a small business set-aside procurement under NAICS code 561990 with a $16.5 million size standard. The solicitation provides detailed requirements and specifications for each task, as well as the service schedule, locations, safety and security requirements, and other terms. Offers are due by 2:00 PM on April 12, 2024, and award will be made on the basis of price alone to the responsible offeror.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachments.pdf | ||
| Amendment W912WJ24Q0105-0001.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SEE ADDENDUM
(No Collect Calls)
W912WJ24Q0105 01-Apr-2024
b. TELEPHONE NUMBER
978-318-8324
8. OFFER DUE DATE/LOCAL TIME
02:00 PM 12 Apr 2024
5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
STANDARD FORM 1449 (REV. 2/2012)
Prescribed by GSA – FAR (48 CFR) 53.212
(TYPE OR PRINT)
(SIGNATURE OF CONTRACTING OFFICER)
ADDENDA X ARE
26. TOTAL AWARD AMOUNT (For Gov t. Use Only )
23.
CODE 10. THIS ACQUISITION IS
SUCH ADDRESS IN OFFER
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT
BELOW IS CHECKED
TELEPHONE NO.
W912WJ9. ISSUED BY
18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a. UNLESS BLOCK
7. FOR SOLICITATION
INFORMATION CALL:
a. NAME
JENNIFER M SAMELA
2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NUMBER
(TYPE OR PRINT)
30b. NAME AND TITLE OF SIGNER 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER
30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a.UNITED STATES OF AMERICA
1 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1. 52.212-4. FAR 52.212-3. 52.212-5 ARE ATTACHED.X
25. ACCOUNTING AND APPROPRIATION DATA
1. REQUISITION NUMBER
20.
ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.
OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
ARE NOT ATTACHED
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED
(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE
SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:
. YOUR OFFER ON SOLICITATION
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN
% FOR:SET ASIDE:UNRESTRICTED OR X
SMALL BUSINESSX
17a.CONTRACTOR/ CODE FACILITY
OFFEROR CODE
U S ARMY ENGR DISTRICT, NEW ENGLAND
696 VIRGINIA RD
CONCORD MA 01742-2751
18a. PAYMENT WILL BE MADE BY CODE
RATED ORDER UNDER
DPAS (15 CFR 700)
13a. THIS CONTRACT IS A
13b. RATING
CODE15. DELIVER TO CODE 16. ADMINISTERED BY
SEE SCHEDULE
12. DISCOUNT TERMS11. DELIVERY FOR FOB DESTINA-
TION UNLESS BLOCK IS
MARKED
SEE SCHEDULE
14. METHOD OF SOLICITATION
RFQ IFB RFPX
FAX:
TEL: 978-318-8159 SERVICE-DISABLED
VETERAN-OWNED
SMALL BUSINESS
8(A)
HUBZONE SMALL
BUSINESS
SIZE STANDARD:
$16,500,000
NAICS:
561990
X
OFFER DATED
29. AWARD OF CONTRACT: REF.
DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND
EMAIL:
TEL:
31c. DATE SIGNED
SEE SCHEDULE
SCHEDULE OF SUPPLIES/ SERVICESITEM NO. QUANTITY UNIT UNIT PRICE AMOUNT
24.22.21.19.
WOMEN-OWNED SMALL BUSINESS (WOSB)
ELIGIBLE UNDER THE WOMEN-OWNED
SMALL BUSINESS PROGRAM
EDWOSB
32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
(CONTINUED)
PAGE 2 OF64
ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED: ______________________________________________________
32a. QUANTITY IN COLUMN 21 HAS BEEN
RECEIVED INSPECTED
32b. SIGNATURE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32c. DATE 32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f . TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE
37. CHECK NUMBER
FINALPARTIALCOMPLETE
36. PAYMENT35. AMOUNT VERIFIED
CORRECT FOR
34. VOUCHER NUMBER
FINAL
33. SHIP NUMBER
PARTIAL
38. S/R ACCOUNT NUMBER 39. S/R VOUCHER NUMBER 40. PAID BY
41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT
41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE
42a. RECEIVED BY (Print)
42b. RECEIVED AT (Location)
42c. DATE REC'D (YY/MM/DD) 42d. TOTAL CONTAINERS
STANDARD FORM 1449 (REV. 2/2012) BACK
Prescribed by GSA – FAR (48 CFR) 53.212
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
SEE SCHEDULE
20.
SCHEDULE OF SUPPLIES/ SERVICES
21.
QUANTITY UNIT
22. 23.
UNIT PRICE
24.
AMOUNT
19.
ITEM NO.
W912WJ24Q0105
Section SF 1449 - CONTINUATION SHEET
INSTRUCTIONS TO VENDORS
QUESTIONS REGARDING SOLICITATIONS:
1. Questions regarding the solicitation shall be directed to the Contract Specialist:
a. Name: Jennifer M. Samela
b. Phone: 978-318-8324
c. Email: Jennifer.M.Samela@usace.army.mil
2. Technical Points of Contact shall not provide responses to interested vendors.
QUOTE SUBMISSION:
1. Quotes shall be submitted via email to the Contract Specialist listed above no later than the closing date and time identified in the solicitation or subsequent amendments.
2. The Government is under no obligation to consider any quote received after the solicitation closing date or time.
BID SCHEDULES:
1. If a Bid Schedule is included in the solicitation, vendors shall complete the bid schedule in its entirety
(all tasks, all years).
2. Vendors shall enter $0.00 on Bid Schedules in which items are Not Separately Priced. Blank entries will not be considered and will result in quotes being deemed non-responsive.
3. Failure to complete the Bid Schedule in its entirety and return same with a quote will result in quotes being deemed non-responsive.
SITE VISITS:
1. If dates/times for site visits are included in the solicitation, then interested vendors will be permitted to visit the site during those dates/times. No other dates/times will be permitted for site visits.
2. If no dates/times for site visits are included in the solicitation, then interested vendors shall contact the
Technical Point of Contact as identified in the solicitation to schedule a site visit.
SYSTEM FOR AWARD MANAGEMENT (SAM) REGISTRATIONS:
1. In accordance with FAR Clause 52.204-7:
a. Vendors are REQUIRED to be registered in SAM when submitting a quotation and shall continue to be registered until time of award, during performance, and through final payment.
b. “Registered” in SAM means that the Government has marked the record “Active”.
2. The Government will deem quotes non-responsive from vendors that do not have an active SAM at the time of quote submission.
Provide Unique Entity Identifier (UEI): ___________________________
Provide CAGE code: ____________________________
SUBMITTALS:
1. Submittals (Accident Prevention Plan, Activity Hazard Analyses, Products, etc.) and
Certifications/Licenses (10-hour OSHA, 30-hour OSHA, Competent Person in Fall Protection, Electrician’s License, etc.) that are specified in the scope as required by this solicitation are not to be submitted with a quote. The awarded Contractor will be required to provide all submittals and certifications within the time stated in the solicitation and resultant contract. Failure to do so may result in termination.
BASIS OF AWARD:
1. Potential vendors are notified that the basis on which award will be made is price alone.
2. All responsible sources may submit a quote which, if timely received, must be considered by the Agency.
SECURITY REQUIREMENTS
General security requirements and guidance: The security requirements described below apply to all contract personnel (including employees of the prime Contractor (“Contractor”) and all subcontractor employees) supporting the performance requirements of this contract. The Contractor is responsible for compliance with these security requirements. Questions regarding security matters shall be addressed to the designated Government representative (eg., Contracting Officer Representative (COR), Requiring Activity (RA) representative, or Contracting Officer (if a COR or other RA representative is not appointed)). Contract personnel are critical to the overall security and safety of US Army Corps of Engineers (USACE) installations, facilities and activities, and security awareness training contributes to those efforts. The Department of Defense (DoD) and Army security training requirements specified below, if applicable, are performance requirements; all applicable contract personnel shall complete initial training within 30 days of contract award or the date new contract personnel begin performance on the contract. Within five business days from the completion of training, the Contractor shall provide written documentation (e.g., email or memorandum) to the Government representative. The documentation shall include the names of contract personnel trained and which training they completed; the Contractor shall maintain training records as part of their contract files and be prepared to provide copies of training certificates to the Government representative. Contractor personnel and vehicles are subject to search when entering federal installations. Additionally, all contract personnel shall comply with Force Protection Condition (FPCON) measures, Random Antiterrorism Measures (commonly referred to as “RAMs”), and Health Protection Condition (HPCON) measures. The Contractor is responsible for meeting performance requirements during elevated FPCON and/or HPCON levels in accordance with applicable RA plans and procedures –this includes identifying mission essential and non-mission essential personnel. In addition to the changes otherwise authorized by the changes clauses of this contract, should FPCON or HPCON levels at any individual facility or installation change, the Government may implement security changes that affect contract personnel. The Contractor shall ensure all contract personnel are aware of their security responsibilities, including any site-specific requirements identified in local policies or procedures.
Suspicious Activity Reporting training (e.g. iWATCH, CorpsWatch, or See Something, Say Something): All contract personnel shall receive initial and annual refresher training from the RA representative on the local suspicious activity reporting program. This locally developed training provides contract personnel with general information on suspicious behavior, and guidance on reporting suspicious activity to the project manager, security representative or law enforcement entity.
BID SCHEDULE
PARK WATER SYSTEM SERVICES
U.S. ARMY CORPS OF ENGINEERS
HOPKINTON EVERETT LAKES
HOPKINTON, NH
PERFORMANCE WORK STATEMENT
Bid Schedule
TASK / ITEM NUMBER UNIT QTY
UNIT
PRICE
TOTAL
1. De-Winterize Park Water System
Job
2. Option: Second Disinfectant Treatment
Job 1
3. Winterize Park Water System
Job
4. Replace Plumbing for Spigot Job 1
5. Replace Pressure Tank Union
Assembly
Job 1
TOTAL
PARK WATER SYSTEM SERVICES
U.S. ARMY CORPS OF ENGINEERS
HOPKINTON EVERETT LAKES
HOPKINTON, NEW HAMPSHIRE
I. General:
1. Scope – Furnish all equipment, supplies, materials, transportation, and labor to perform plumbing services at the Elm Brook Park recreation area, including de-winterizing the park water system in the spring, winterizing the park water system in the fall, and replacing a section of plumbing for a spigot, as well as replacing the union, pipe, and elbow on the pressure tank for the lower restroom. The services are to be provided in accordance with the following performance work statement and schedule.
NOTE: This work requires the following submittals prior to commencement of work (Refer to Section II. Technical Requirements for a full list of submittals):
Accident Prevention Plan Activity Hazard Analysis Site Safety and Health Officer Designation Letter Safety Data Sheets All Certifications and Licenses as determined by the scope of work.
2. Location(s) – Elm Brook Park is located at 102 Elm Brook Park Road in Hopkinton, New
Hampshire.
3. Site Visit – Contact the Technical Point of Contact (TPOC) to arrange a site visit. The TPOC for the project is Project Ranger, Samantha Schupp (978-318-8735, 603-746-3601 ext.
735 or Samantha.N.Schupp@usace.army.mil).
4. Schedule – The period of performance shall be from Contract Award through 31 October 2024. Work shall be performed Monday through Friday 8:00 AM to 4:00 PM unless otherwise approved by the TPOC. The Pre-Work Conference shall be completed within 14 days of Contract Award.
All pre-work submittals shall be submitted within 21 days of contract award. The Government reserves up to 21 days for review and acceptance on each submittal/resubmittal from the date of receipt. If revisions are necessary to the submittals, the Contractor shall make such revisions and shall be resubmitted to the Government in an acceptable form within 14 days of the Government’s response, unless additional time is granted by the Government in writing. No field work may proceed prior to the acceptance of pre-work submittals.
Work shall be performed in a timely manner and to the satisfaction of the TPOC or their representative.
The following tables identify the line-item number, description, and frequency.
Service Schedule: 01 May 2024 through 31 October 2024.
Item # Description Frequency Qty.
1 De-winterize Elm Brook Park Water System Once (May)
2 Option: Second Disinfectant Treatment Once If Needed (May)
3 Winterize Elm Brook Park Water System Once (October) 1 4 Replace Plumbing for Spigot Once (May) 1 5 Replace Pressure Tank Union Assembly Once (May) 1
5. Safety Requirements:
a. General:
All work shall be conducted in accordance with the U.S. Army Corps of Engineers (USACE) Safety and Occupational Health Requirements (EM 385-1-1, most recent edition), and all applicable Occupational Safety and Health Administration (OSHA), federal, state, and local safety and health requirements. A copy of EM 385-1-1 can be accessed electronically at the following link:
https://www.publications.usace.army.mil/Portals/76/EM%20385-1- 1%20_EFFECTIVE%2015March2024.pdf
Project staff reserve the right to cease work at any time should the safety of employees, Contractors, and/or the public become jeopardized.
b. Accident Prevention Plan (APP):
The Contractor shall prepare a site-specific Accident Prevention Plan. The APP must be written by a Competent Person (CP) and document the specific work processes, equipment, materials to be used, hazards and applicable control measures.
The mandatory ENG Form 6293 (Accident Prevention Plan Worksheet) must be submitted and accepted prior to beginning on site work:
https://www.publications.usace.army.mil/Portals/76/Eng_Form_6293_2023Aug31.pdf
A preparatory meeting shall be conducted by the Prime Contractor to discuss the APP contents with all effected onsite employees. The Prime Contractor is responsible for informing the subcontractors of the safety provisions under the terms of the contract, the penalties for noncompliance, and inspecting subcontractor operations to ensure that accident prevention responsibilities are being carried out.
Daily safety meetings shall be held and documented. Records shall be available to the TPOC upon request.
c. Activity Hazard Analysis (AHA):
An AHA shall be submitted and accepted for each definable feature of work (DFOW) in accordance with EM 385-1-1, Chapter 2-6. A DFOW is defined as any task, which is separate and distinct from other tasks, has separate control requirements, or is identified as different trades or disciplines. The AHA shall be continuously reviewed and revised to address changing site conditions as appropriate.
For a non-mandatory formatted outline of an AHA, see ENG Form 6206 (Activity Hazard Analysis):
https://www.publications.usace.army.mil/Portals/76/Eng_Form_6206_2023Aug24.pdf
d. Site Safety and Health Officer (SSHO) Requirements:
The Contractor shall employ a minimum of one person to function as a Level 3, SSHO. A Level 3 SSHO is a designated Qualified Person (QP) or Competent Person (CP) with Safety and Occupational Health (SOH) responsibility that meets the requirements of EM 385-1-1, Chapter 2-3.b and 2-4.b.
Level 3 SSHOs must have training, knowledge, and/or experience identifying hazards and implementing controls for the work being performed.
The SSHO shall be present at the project site and be responsible for overseeing the implementation of the prime contractor’s SOH program. Contractor shall designate all SSHOs on a mandatory ENG Form 6282 (Site Safety and Health Officer Designation Letter):
https://www.publications.usace.army.mil/Portals/76/Eng_Form_6282_2023Aug28.pdf
e. First-Aid and CPR Personnel Requirements:
For shifts with multiple employees, provide at least two employees that are certified to administer First Aid and CPR. When employes work alone, they must be certified in First Aid and be provided an effective means of communication to call for assistance in the event of an emergency. Minimum First Aid and CPR qualifications are outlined in EM 385-1-1, Chapter 3-3.
f. Additional Personnel Requirements:
Other Competent Person (CP) or Qualified Persons (QP) may be required per EM 385-1- 1 and/or other sections of this Scope of Work, based on the definable features of work for this project.
g. Accident Reporting:
All accidents and near misses shall be investigated by the Contractor and reported to the TPOC in accordance with EM 385-1-1, Table 2-1.
The mandatory ENG Form 3394 shall be completed and submitted to the TPOC within seven (7) days of an incident:
https://www.publications.usace.army.mil/Portals/76/Publications/EngineerForms/Eng_Fo rm_3394_2021Aug.pdf
h. Employee Exposure Data:
The Contractor shall electronically report total employee work hours (including subcontractors) to the TPOC by close of business on the 10th calendar day of the following month.
6. Flooding – Hopkinton Everett Lakes is primarily a Flood Risk Management Project.
Occasional retention of floodwaters may inundate portions of the dam property or access roads in the areas covered by this contract. The TPOC will notify the Contractor as areas are closed as a result of floodwaters. When flooding ends and waters recede, the TPOC will notify the Contractor as areas reopen and services may resume.
7. Changes to Frequency and/or Quantities - The Government reserves the option, should it become necessary, to decrease or increase service frequencies and/or facility quantities in any or all designated project areas. The Government may also, at any time during the duration of this contract, close any property or portion of the property and delete any subsequent service in the closed property or area. The Contractor shall be given adequate notification to prepare for either contingency. This decrease or increase will be deducted from or paid for in accordance with the bidding schedule or a negotiated cost. Any increase in quantity or frequency of services must be negotiated with the Contracting Officer. The Contractor shall not perform any additional services until the issuance of a formal modification signed by the Contracting Officer. In addition, the TPOC may, on special occasions decide to reschedule a service frequency in order to avoid conflict with visitation or unnecessary expense. The Contractor shall be given at least 24 hours’ notice.
8. Pre-Work Conference – Prior to the start of any work, the TPOC will schedule and conduct a “Pre-Work Conference”. The Contractor’s Project Manager and Quality Control Personnel shall be physically present at this meeting. The Contractor shall directly oversee all work on the project and the Project Manager and Quality Control Personnel shall have the authority to act on behalf of the Contractor. This conference will be held at the time and location agreeable to the Government and Contractor. No work may be performed under this contract prior to this conference. The purpose of the conference is to enable the TPOC to outline the procedures that will be followed by the Government in its administration of the contract, and to discuss the performance that will be expected from the Contractor. This conference will allow the Contractor an opportunity to ask questions about the Government’s administration and inspection of contract work or obtain other pertinent information that might be required.
At the Pre-Work Conference the Contractor shall provide the name of the project superintendent with a telephone number for project coordination.
The following is a general list of items for discussion during this Pre-Work Conference:
i. Authority of the Technical Point of Contact and Quality Assurance Inspectors.
ii. Contractor’s Safety Program (including sub-contractors).
iii. Accident Prevention Plan and Activity Hazard Analysis (Submitted & accepted prior to start of work on site)
iv. Safety Meetings (Documented on NED Form 251)
v. Accident Reporting (ENG Form 3394)
vi. Safety Data Sheet (SDS) requirements
vii. Contractor’s Quality Control Plan
viii. Contractor’s Equipment
ix. Correspondence, Communication, Security and Administrative Procedures.
x. Invoice and payment.
9. Permits – The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses, permits, and letters of certification. The Contractor shall comply with any applicable federal, state, county, and municipal laws, codes, and regulations in connection with the performance of the work specified under this contract.
10. Security – The Contractor will comply with all established security policies at the Hopkinton Dam and Everett Dam. Due to periods of heightened security that may affect the access to the areas covered under this contract, the Government reserves the right to close any property or portion of property and reschedule and/or cancel any subsequent service. The Contractor shall be given at least 24-hour notice of any such closure.
11. Payment – The Contractor shall furnish the TPOC with one invoice per month. The invoice shall include the invoice date, contract number, dates of service, description of work, quantities, labor hours, and total amount due per line item. The invoice must also include the company letterhead, and this must match the data that is registered in the System for Award Management (SAM) registry. Payment shall be made monthly for the actual services performed at the applicable contract unit price.
All invoices may be mailed to:
U.S. Army Corps of Engineers Hopkinton Everett Lakes
2097 Maple Street Hopkinton, New Hampshire 03229
Or emailed to: Samantha.N.Schupp@usace.army.mil
II. Technical Requirements:
Part 1 General:
1. Summary – Furnish all equipment, supplies, materials, transportation, and labor to perform plumbing services at the Elm Brook Park recreation area, including de-winterizing the park water system in the spring, winterizing the park water system in the fall, and replacing a section of plumbing for a spigot, as well as replacing the union, pipe, and elbow on the pressure tank for the lower restroom. Services are to be provided in accordance with the following performance work statement and schedule.
2. Submittals – Although the Government reviews submissions required by this Performance
Work Statement, it is emphasized that the Contractor’s work must be completed using proper internal controls and review procedures. The Government reserves up to 21 days for review and acceptance on each submittal/resubmittal from the date of receipt. If revisions are necessary to the submittals, the Contractor shall make such revisions and shall resubmit to the Government in an acceptable form within 14 days of the Government’s response, unless additional time is granted by the Government in writing.
The documents identified below must be prepared in accordance with the applicable standards, submitted to the TPOC for review and must be accepted by the Government.
Pre-Work Submittals: Submitted within 21 days of contract award. Submittals must be accepted prior to the commencement of any field work activities.
Accident Prevention Plan Activity Hazard Analysis Site Safety and Health Officer Designation Letter Safety Data Sheets All Certifications and Licenses as determined by the scope of work.
3. References – All work shall be in conformance with:
a. U.S. Army Corps of Engineers
i. EM-385-1-1 2024 Safety and Occupational Health Requirements, U.S. Army
Engineering Manual
b. Code of Federal Regulations
i. Title 36 – Parks, Forests, and Public Property; Chapter III, Part 327 – Corps of Engineers, Department of the Army.
c. Other appropriate federal, state, and local codes for such an installation
d. Env-Dw 506 Seasonal Public Water Systems
4. Other Contracts – The Government may undertake or award other contracts for additional work not related to this contract, and the Contractor shall fully cooperate with other contractors and Government employees. The Contractor shall not commit or permit any act which will interfere with the performance of work by another contractor or by Government employees.
5. Preferred Sequence for Work Schedules – The Contractor must provide sufficient personnel and equipment to accomplish services stated in the contract. The Contractor will coordinate a work schedule for each service, and approximate times for beginning and ending of each required service listed with the TPOC. Any changes or alterations to the schedule must be coordinated and approved by the TPOC in advance of actual schedule changes.
6. Clean Up and Waste Disposal – The Contractor shall practice good housekeeping to maintain a safe job site. The Contractor shall keep the work area, including any designated storage areas free from accumulation of waste materials. Upon completing work in an area, the Contractor shall remove any tools, equipment, and materials that are not the property of the Government. Any and all disturbed areas resulting from Contractor activities shall be restored by the Contractor to the satisfaction of the TPOC. All waste material will be disposed of offsite in accordance with all federal, state, and local regulations.
7. Environmental Protection –Water, air and land resources shall not be adversely impacted during the course of the work. The Contractor will take necessary steps to ensure all federal, state, and local environmental regulatory requirements are met at no additional cost to the Government. Assurance of compliance with this section by subcontractors shall be the responsibility of the Contractor.
8. Sustainability & Environmentally Preferred Products - The United States Department of
Agriculture (USDA) designates certain bio-based products for federal procurement and specifies minimum bio-based content levels for those products. Any designated product that is being offered or supplied under this contract shall meet USDA BioPreferred's minimum bio-based content level. Visit the BioPreferred web site https://www.biopreferred.gov/BioPreferred/faces/pages/ProductCategories.xhtml for the complete list of designated products and associated minimum bio based content level requirements.
9. Personal Protective Equipment - It is the Contractor’s responsibility to furnish and supply personnel with the proper personal protective equipment necessary for performing the work.
10. Government Resources – The Contractor shall supply his own means of communication (telephone). The restrooms in Elm Brook Park will be available for use after the de-winterization service is completed. The Contractor would have to provide these resources or have an acceptable alternative plan for these resources.
11. Damage to Government and Private Property – The Contractor shall be responsible for restoring all Government facilities or structures damaged as a result of the Contractor’s operation. The Contractor shall also be responsible for any damage to private property or injury to any person as a result of the Contractor’s operation. The Contractor shall notify the TPOC immediately of damage to Government and private property and injury to any person resulting from the Contractor’s operation. Also, the Contractor shall notify the TPOC of damage to Government facilities due to vandalism or other causes on the day such damage is first noticed. Trucks and/or trailers will be driven on existing roads only and not across or through park areas to facilities. The Contractor shall also restore landscape features (shrubs, flowers, grasses, etc.), which are damaged or destroyed by the Contractor’s operation.
Damaged or destroyed grass areas shall be re-planted as directed by the TPOC, and shrubs and flowers which are damaged or destroyed shall be replaced from nursery stock of like size and kind.
12. Contractor’s Personnel –
a. Minimum Personnel Requirements - The Contractor shall provide an adequate number of fully qualified personnel to perform the specified service properly and efficiently within the time limits specified. The Contractor shall provide a list of the names and contact phone numbers for all employees prior to them working on Government Property.
Note: At least one (1) of the Contractor employees on site shall be able to communicate effectively and efficiently with project staff.
b. Employee Conduct - The Contractor shall be responsible for seeing that the Contractor’s employees strictly comply with Code of Federal Regulations (CFR) Title 36, Chapter III, Part 327, and all federal, state, and municipal laws. Any personnel activity, which, in the opinion of the Government, is deemed detrimental to the performance of the contract may result in the removal of Contractor employee(s).
Examples of unbecoming actions or conduct include but are not limited to the following:
i. Cursing, harassment, or discrimination of and/or unwarranted physical contact with visitors, USACE personnel, or other contractors.
ii. Recurring written and/or verbal complaints from visitors, USACE personnel, or other contractors.
iii. Unsafe operation of vehicles while on USACE property.
c. Removal of Contractor’s Employees - The TPOC may require the Contractor to immediately remove from the work site any employee of the Contractor or subcontractor, who, in the opinion of the TPOC, who endangers persons or property, or whose physical or mental condition is such that it would impair the employee’s ability to satisfactorily perform assigned work. Notification to the Contractor shall be promptly made in writing if time and circumstances permit. Otherwise, notification shall be verbal or by telephone, and shall be confirmed in writing as soon as possible. No such removal, however, will reduce the Contractor’s obligation to perform all work required under this contract, and immediate replacement will be made as required. This requirement shall not be made the basis of any claim for compensation or damages against the United States or any of its officers or agents.
13. Quality Assurance – The Contractor is responsible for the quality control of the contract work. The Contractor shall establish and maintain a quality control system to assure compliance with the contract requirements. The Government has the right to inspect and test all items called for by the contract, to the extent practicable at all times and at all places during the term of the contract.
14. Inspections-
a. Contractor Quality Control - The Contractor is responsible for establishing and maintaining an adequate quality control system to satisfactorily inspect and ensure that all work performed by the Contractor’s organization in each separate service is in full compliance with this contract and the instructions, provisions, specifications, drawings, and maps herein.
b. General Inspection - Upon the completion of each service requirement, the Contractor will perform an inspection of all areas under this contract to ensure compliance with the Performance Work Statement. The Contractor or their representative must be able to commit personnel, equipment, and resources to correct deficiencies. A Government representative may accompany the Contractor on an inspection of completed work and will identify any contract deficiencies. Any deficiencies noted will be corrected within original contract time frames or appropriate deductions in payment will be made.
c. Equipment/Supplies Inspections - The TPOC may inspect required equipment and, supplies at any time when in use on Government property. Any equipment found deficient shall be removed from service immediately until faulty conditions have been corrected and passed by the TPOC. No such removal will reduce the Contractor’s obligation to perform all work required within the time scheduled under this contract.
This requirement shall not be made the basis of any claim for compensation or damages against the United States or any of its officers or agents.
d. Government Inspections - The Government will monitor the Contractor’s service performance and make deductions accordingly.
15. Receiving and Storing Materials – The Contractor is responsible for receiving and unloading of delivered goods. Government employees will not receive materials or supplies for the Contractor and will not be responsible for damage to the Contractor’s equipment or materials.
16. Omissions – This contract may not cover all specified activities, steps, and procedures required to supply the contract product. In case of omission, the normal industry, state, or federal standards, practices, specifications, and/or guides shall prevail. In no instance shall an omission be reason to produce less than an acceptable product.
Part 2 Equipment:
1. Condition of Equipment– All equipment used to perform work under this contract must be in good operating and mechanical condition and comply with EM 385-1-1, Army Corps of Engineers Safety and Health Requirements. A regular schedule of preventive maintenance must be followed on all equipment. All vehicles utilized under this contract will be presentable, serviceable, and shall comply with safety standards.
2. Type of Equipment-
b. The Contractor shall provide the appropriate equipment and tools of the trade to execute the requirements of the Performance Work Statement.
c. Types of equipment for this work may include but not be limited to:
i. Air compressor
a. Air compressor shall have the capacity to purge all water from the park water system without rupturing any pipes.
ii. Propane torch
3. Equipment Storage – No Government space or facilities shall be provided under this contract.
Part 3 Materials and Supplies:
1. Provided by Government:
a. Sloan flush valve assemblies
b. Kohler (Model K-84325-SS-0) wall-mounted toilets and mounting hardware
c. Madera FloWise (Model 3248.001.020) floor-mounted toilet and mounting hardware
d. Toto UT447E wall-mount urinals and mounting hardware
e. Pressure tanks
NOTE: Government furnished supplies valued under $300.00 each.
2. Provided by Contractor:
a. Chlorine pellets or standard liquid bleach
b. Non-toxic RV anti-freeze
c. Lead free plumbing components needed to replace 1” copper plumbing for an existing spigot.
d. Lead free plumbing components needed to replace the pressure tank union assembly on a
Well-X-Trol WX-350 Pressure tank with a 1 ¼” NPT discharge connection size.
e. Plumbing tools (pliers, wrenches, etc.)
f. Lead-free solder and flux compliant for use in plumbing potable water systems.
g. Flexible PVC Caps for drain/waste/vent (DWV) to cap pressure tanks and pressure tank connections
h. Garden hoses
NOTE: The Contractor is responsible for collecting all appropriate field measurements prior to purchasing plumbing materials.
NOTE: All materials shall be new, un-used and to the satisfaction of the TPOC.
Part 4 Service Requirements:
1. General: Furnish all equipment, supplies, materials, transportation, and labor to perform plumbing services at the Elm Brook Park recreation area, including de-winterizing the park water system in the spring, winterizing the park water system in the fall, and replacing a section of plumbing for a spigot, as well as replacing the union, pipe, and elbow on the pressure tank for the lower restroom. Services are to be provided in accordance with the following performance work statement and schedule.
2. Service Definition:
a. One service is defined as a single completion of all requirements for each task as described in Section 3, Service Tasks below.
b. The Contractor shall only be paid for work fully completed. If a partial service is rendered, payment will be adjusted according to percent of area completed. Partial service is defined as completing anything other than all tasks for designated locations as identified in Part 5, Service Locations and Schedule(s).
3. Service Tasks:
a. De-Winterizing Park Water System Requirements:
i. Connect three (3) water pressure tanks; one at the well pump house and one located in each of the restroom pipe chases.
ii. Connect twelve (12) toilet and four (4) urinal flush valve assemblies.
iii. Connect nine (9) sink traps.
iv. Connect four (4) spigots to water fountains.
v. Check all flush valves, faucets, and water fountains for leaks.
vi. Disconnect 3 cracked wall-mounted toilets, 1 floor-mounted toilet, and 2 wall-mounted urinals from the wall. Properly dispose of cracked toilets and urinals in accordance with federal, state, and local regulations. Mount new Government-provided toilets and urinals utilizing the existing holes. Secure toilets and urinals to the wall with hardware. Connect flushometers and check to ensure there are no leaks.
vii. Remove up to 16 broken flush valves from flushometers. The exact number of flush valves needing to be replaced will be determined at the time of service.
Replace broken flush valves with Government-provided flush valves. Properly dispose of broken flush valves in accordance with federal, state, and local regulations. Reassemble flushometers. Check for proper operation of flushometers and ensure there are no leaks.
viii. Disinfect the park water system and the Park Ranger cabin water system using the proper dosage of either standard liquid bleach (8.25%) or 70% chlorine pellets to obtain a disinfection dose of approximately 50 ppm in all parts of the well and water system. The recommended dosage consists of approximately ¾ gallon of standard liquid bleach (8.25%) and 25 chlorine pellets per drilled well.
ix. Follow manufacturer procedures for system startup and perform a full flush cycle on the two water sediment filtration systems located in the well pump house.
Ensure that the chlorine treatment has fully entered the filtration systems. See Exhibit 8 and 9 for existing conditions.
The water sediment filtration systems each have a Clack Corporation size 1665 mineral / media vessel with a Water-Right Water Conditioner valve system and control panel model number: IMBF-1665A-00-05-00-00-00.
Each vessel contains standard water sediment filtration media (AG) as prescribed in 2010 when the system was installed.
x. Systematically run the water system from the well pump house to the next valve opening until the bleach solution is in all of the water lines. The Contractor shall be able to detect the smell of bleach from all fixtures to know the bleach solution has been distributed to all water lines and end points. The disinfection dose shall remain in the system for 12-24 hours.
xi. After the disinfectant has been in the system for 12-24 hours, flush the chlorine from the system. Connect garden hoses to the spigots at the water fountains and restrooms and flush the water to either a wood line or field as specified by the TPOC. After flushing the water from the spigots at half the flow capacity for approximately 2 hours, continue flushing the system by turning on all sink faucets and flushing toilets until the free chlorine level is less than 1.0 mg/L free chlorine and the scent of chlorine can no longer be detected at the end points. This procedure is specified in the NHDES Drinking Water & Groundwater Bureau’s Start-up Guidance for Seasonal Public Water Systems.
xii. Check to ensure the wellhead caps or covers are secure with seals intact and a screened vent.
NOTE: The standard liquid bleach used shall be free of detergents or fragrances.
NOTE: Pool bleach additives are not permitted for disinfecting the park water system. Pool bleach additives contain algaecides and are not certified for drinking water use.
NOTE: Wells deeper than 200 ft. require chlorine pellets in addition to bleach to improve dispersion deep into the well. Both drilled wells in Elm Brook Park are 340 feet deep.
NOTE: When flushing the disinfectant from the water lines, caution shall be taken not to draw the static water level below the pump level. The lines shall be flushed at half the flow capacity at the end points.
NOTE: The park water system may require a second round of disinfection if the water quality samples test positive for bacteria. The water quality testing will be completed as part of a separate contract. The initial water quality testing will occur within one (1) week of the de-winterization service being completed. If a second round of disinfection is needed, the Contractor shall be notified within 1 business day, and a second round of disinfection would be required to be completed no later than May 22.
b. Option: Second Disinfectant Treatment
i. If water quality samples from either the park water system and/or the Park Ranger cabin water system test positive for bacteria after the first disinfection treatment, a second round of disinfection treatment will be required for one or both water systems. The second round of disinfection treatment shall involve repeating steps viii to x from Service Task a. De-Winterizing Park Water System Requirements.
ii. The Government is only obligated to pay for work completed.
c. Winterizing Park Water System Requirements:
i. Perform a full flush cycle on the two water sediment filtration systems located in the well pump house and follow manufacturer procedures to prepare for winter closing. See Exhibit 8.
ii. Disconnect three (3) water pressure tanks; one at the well pump house and one located in each of the restroom pipe chases.
iii. Transport the water pressure tank from the lower restroom to the well pump house for storage.
iv. Cap the pipe connections for the pressure tanks at each restroom and well pump house connection.
v. Cap each of the pressure tank connections on each pressure tank after they have been disconnected and emptied.
vi. Open drain valves at each water fountain to drain.
vii. Drain the water system and blow out the piping with air pressure starting at the well house tank.
viii. Remove all fixture stop stems and toilet/urinal flush valves to drain them.
ix. Disconnect sink traps.
x. Pour enough non-toxic RV anti-freeze into each of the toilets and urinals to fill the traps.
xi. Final product shall include all water being purged from the park water system.
d. Replace Plumbing for Spigot
i. Remove existing section of 1” diameter copper pipe including one (1) street 90 elbow, two (2) standard 90 elbows, connecting pipe(s), and a female adapter fitting.
See Exhibit 5.
ii. Replace the section of plumbing with new 1” diameter copper pipe and fittings to fully reconnect the system with the spigot.
iii. Properly connect/solder all pipe connections for a proper fit and finish.
iv. Check the pipe for leaks.
e. Replace Pressure Tank Union Assembly
i. Remove the existing 90 elbow, straight pipe, and pressure tank union assembly on a Government furnished Well-X-Trol WX-350 pressure tank. See Exhibit 6 and 7 for existing conditions.
ii. Replace with a new 90 elbow, straight pipe, and male NPT union assembly.
iii. All new replacement materials shall consist entirely of lead-free components.
NOTE: The Contractor is responsible for collecting all appropriate field measurements prior to purchasing plumbing materials.
Part 5 Service Locations and Schedule(s): The services for this contract are located at the following locations:
A. Elm Brook Park is located at 102 Elm Brook Park Rd, Hopkinton, NH.
1. See Exhibit 1.
1. ITEM NO. 1 – De-Winterize Park Water System
a. Service Area:
i. Two (2) waterborne restrooms
ii. Four (4) urinals
a. Includes 2 broken wall-mounted urinals
iii. Twelve (12) toilets
a. Includes 3 broken wall-mounted toilets and 1 broken floor-mounted toilet
iv. Nine (9) sink traps
v. Three (3) water pressure tanks
vi. Two (2) Water Sediment Filtration Systems
vii. Four (4) water fountains with spigots
viii. Two (2) drilled wells
a. Elm Brook Park Cabin well: 6” casing @ 340ft
b. Elm Brook Park well: 6” casing @ 340 ft
b. Service Schedule:
i. One time (May)
ii. Between May 1st and May 15th.
iii. Specific date to be coordinated with the TPOC.
2. ITEM NO. 2 – Option: Second Disinfectant Treatment
i. Two (2) drilled wells
a. Elm Brook Park Cabin well: 6” casing @ 340 ft
b. Elm Brook Park well: 6” casing @ 340 ft
ii. Two (2) waterborne restrooms
iii. Nine (9) sinks
iv. Two (2) Water Sediment Filtration Systems
v. Four (4) water fountains with spigots
b. Service Schedule:
i. One time (May) if needed
ii. A second disinfection treatment may be needed prior to May 22nd if water quality samples test positive for bacteria. Specific date to be coordinated with the TPOC.
3. ITEM NO. 3 – Winterize Park Water System
i. Two (2) waterborne restrooms
ii. Four (4) urinals
iii. Twelve (12) toilets
iv. Three (3) water pressure tanks
v. Two (2) Water Sediment Filtration Systems
vi. Four (4) water fountains with spigots
vii. Nine (9) sink traps
b. Service Schedule:
i. One time (October)
ii. Between October 1st and October 31st.
iii. Specific date to be coordinated with the TPOC.
4. ITEM NO. 4 – Replace Plumbing for Spigot
a. Service Area:
i. Lower restroom pipe chase
ii. Section of pipe plumbing connected to the spigot in the men’s restroom.
b. Service Schedule:
i. One time (May)
ii. Specific date to be coordinated with the TPOC.
5. ITEM NO. 5 – Replace Lower Restroom Pressure Tank Union Assembly
i. Lower restroom pipe chase
ii. One (1) pressure tank union assembly for a Well-X-Trol WX-350 pressure tank with 1¼” NPT discharge connection size to connect pressure tank to park water system.
b. Service Schedule:
i. One time (May)
ii. Specific date to be coordinated with the TPOC. In conjunction with the de-winterization service.
ATTACHMENTS
PLEASE REFER TO THE ATTACHMENTS INCLUDED WITH THIS SOLICITATION FOR ADDITIONAL
INFORMATION.
CLAUSES INCORPORATED BY REFERENCE
52.204-7 System for Award Management OCT 2018 52.204-9 Personal Identity Verification of Contractor Personnel JAN 2011 52.204-13 System for Award Management Maintenance OCT 2018 52.204-16 Commercial and Government Entity Code Reporting AUG 2020 52.204-18 Commercial and Government Entity Code Maintenance AUG 2020 52.204-19 Incorporation by Reference of Representations and
Certifications.
DEC 2014
52.204-22 Alternative Line Item Proposal JAN 2017 52.204-24 Representation Regarding Certain Telecommunications and
Video Surveillance Services or Equipment
NOV 2021
52.212-1 Instructions to Offerors--Commercial Products and Commercial Services
SEP 2023
52.212-4 Contract Terms and Conditions--Commercial Products and Commercial Services
NOV 2023
52.217-5 Evaluation Of Options JUL 1990 52.219-6 Notice Of Total Small Business Set-Aside NOV 2020 52.223-1 Biobased Product Certification MAY 2012 52.223-5 Pollution Prevention and Right-to-Know Information MAY 2011 52.225-25 Prohibition on Contracting with Entities Engaging in Certain
Activities or Transactions Relating to Iran-- Representation and Certifications.
JUN 2020
52.232-39 Unenforceability of Unauthorized Obligations JUN 2013 52.237-1 Site Visit APR 1984 52.242-15 Stop-Work Order AUG 1989 52.245-1 Government Property SEP 2021 52.245-9 Use And Charges APR 2012 252.203-7000 Requirements Relating to Compensation of Former DoD
Officials
SEP 2011
252.203-7002 Requirement to Inform Employees of Whistleblower Rights DEC 2022 252.203-7005 Representation Relating to Compensation of Former DoD
Officials
SEP 2022
252.204-7003 Control Of Government Personnel Work Product APR 1992 252.204-7008 Compliance With Safeguarding Covered Defense Information
Controls
OCT 2016
252.204-7012 Safeguarding Covered Defense Information and Cyber Incident Reporting
JAN 2023
252.204-7015 Notice of Authorized Disclosure of Information for Litigation Support
JAN 2023
252.204-7016 Covered Defense Telecommunications Equipment or Services -- Representation
DEC 2019
252.204-7017 Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services -- Representation
MAY 2021
252.204-7018 Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services
JAN 2023
252.204-7019 Notice of NIST SP 800-171 DoD Assessment Requirements NOV 2023 252.204-7020 NIST SP 800-171 DoD Assessment Requirements NOV 2023 252.223-7006 Prohibition On Storage, Treatment, and Disposal of Toxic or
Hazardous Materials
SEP 2014
252.225-7048 Export-Controlled Items JUN 2013 252.232-7010 Levies on Contract Payments DEC 2006 252.243-7001 Pricing Of Contract Modifications DEC 1991 252.244-7000 Subcontracts for Commercial Products or Commercial
Services
NOV 2023
252.245-7003 Contractor Property Management System Administration APR 2012 252.245-7004 (Dev) Reporting, Reutilization, and Disposal (DEVIATION 2022-
O0006)
NOV 2021
252.245-7005 Management and Reporting of Government Property JAN 2024
CLAUSES INCORPORATED BY FULL TEXT
52.204-26 COVERED TELECOMMUNICATIONS EQUIPMENT OR SERVICES--REPRESENTATION (OCT
2020)
(a) Definitions. As used in this provision, “covered telecommunications equipment or services” and "reasonable inquiry" have the meaning provided in the clause 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment.
(b) Procedures. The Offeror shall review the list of excluded parties in the System for Award Management (SAM) (https://www.sam.gov) for entities excluded from receiving federal awards for “covered telecommunications equipment or services”.
(c) Representations.
(1) The Offeror represents that it [ ___ ] does, [ ___ ] does not provide covered telecommunications equipment or services as a part of its offered products or services to the Government in the performance of any contract, subcontract, or other contractual instrument.
(2) After conducting a reasonable inquiry for purposes of this representation, the offeror represents that it [ ___ ] does, [ ___ ] does not use covered telecommunications equipment or services, or any equipment, system, or service that uses covered telecommunications equipment or services.
(End of provision)
52.204-27 PROHIBITION ON A BYTEDANCE COVERED APPLICATION (JUN 2023)
(a) Definitions. As used in this clause--
Covered application means the social networking service TikTok or any successor application or service developed or provided by ByteDance Limited or an entity owned by ByteDance Limited.
Information technology, as defined in 40 U.S.C. 11101(6)--
(1) Means any equipment or interconnected system or subsystem of equipment, used in the automatic acquisition, storage, analysis, evaluation, manipulation, management, movement, control, display, switching, interchange, transmission, or reception…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .