OTTER BROOK LAKE PROJ OF

MICHAEL SERVANT

480 BRANCH ROAD

KEENE NH 03431-9801

TEL: 978-318-8300 FAX:

SEE SCHEDULE

REQUEST FOR QUOTATIONS

(THIS IS NOT AN ORDER) 1

PAGE OF PAGES

1. REQUEST NO. 2. DATE ISSUED RATING

W912WJ23Q0039 13-Mar-2023 5a. ISSUED BY

8. TO: NAME AND ADDRESS, INCLUDING ZIP CODE

IMPORTANT: This is a request for information, and quotations furnished are not offers. If you are unable to quote, please so indicate on this form and return it to the address in Block 5a. This request does not commit the Government to pay any costs incurred in the preparation of the submission of this quotation or to contract for supplies or services. Supplies are of domestic origin unless otherwise indicated by quoter. Any representations and/or certifications attached to this

Request for Quotations must be completed by the quoter.

11. SCHEDULE (Include applicable Federal, State, and local taxes)

ITEM NO.

(a)

SUPPLIES/ SERVICES

(b)

QUANTITY

(c)

UNIT

(d)

UNIT PRICE

(e) (f)

SEE SCHEDULE

AMOUNT

% No. %

NOTE: Additional provisions and representations [ ] are [ ] are not attached.

13. NAME AND ADDRESS OF QUOTER (Street, City, County, State, and ZIP Code)

14. SIGNATURE OF PERSON AUTHORIZED TO

SIGN QUOTATION

15. DATE OF

QUOTATION

16. NAME AND TITLE OF SIGNER (Type or print) (Include area code)

TELEPHONE NO.

AUTHORIZED FOR LOCAL REPRODUCTION STANDARD FORM 18 (REV. 6-95)

PREVIOUS EDITION NOT USABLE Prescribed by GSA FAR (48 CFR) 53.215-1(a)

THIS RFQ X[ ] IS [ ] IS NOT A SMALL BUSINESS SET-ASIDE

6. DELIVER BY (Date)

SEE SCHEDULE

AND/OR DMS REG. 1

UNDER BDSA REG. 2

4. CERT. FOR NAT. DEF.3. REQUISITION/PURCHASE

REQUEST NO.

U S ARMY ENGR DISTRICT, NEW ENGLAND

696 VIRGINIA RD

CONCORD MA 01742-2751

9. DESTINATION (Consignee and address, including ZIP Code)

7. DELIVERY

[ ]X FOB

DESTINATION

[ ] OTHER

(See Schedule)

24-Mar-2023(Date)

PLEASE FURNISH QUOTATIONS TO THE ISSUING OFFICE IN BLOCK 5a ON OR BEFORE CLOSE OF BUSINESS:10.

978-318-8324JENNIFER M SAMELA

(Name and Telephone no.) (No collect calls)5b. FOR INFORMATION CALL:

d. CALENDAR DAYSc. 30 CALENDAR DAYSb. 20 CALENDAR DAYS12. DISCOUNT FOR PROMPT PAYMENT a. 10 CALENDAR DAYS

W912WJ23Q0039

Section B - Supplies or Services and Prices

INSTRUCTIONS TO VENDORS

*SITE VISITS ARE HIGHLY RECOMMENDED PRIOR TO PROVIDING A QUOTE. SEE CLAUSE 52.236-27

FOR ADDITIONAL INFORMATION.

*PLEASE DIRECT QUESTIONS TO JENNIFER M. SAMELA AT (978) 318-8324 or

JENNIFER.M.SAMELA@USACE.ARMY.MIL. ANY INFORMATION RECEIVED AT THE SITE VISIT

WHICH CONFLICTS WITH THIS SOLICITATION SHOULD BE BROUGHT TO THE ATTENTION OF

JENNIFER M. SAMELA. THE SOLICITATION AND RESULTING CONTRACT SHALL BE THE

GOVERNING DOCUMENT IN ALL CASES.

**QUOTES CAN BE E-MAILED TO JENNIFER M. SAMELA AT

JENNIFER.M.SAMELA@USACE.ARMY.MIL.

NOTE 1: In accordance with FAR Part 28.102-1(b), the Contractor will be required to provide the following payment protections for all construction contracts greater than $150,000.00.

(i) Payment Bond or

(ii) Irrevocable Letter of Credit and

(iii) Performance Bond

A Payment Bond or Irrevocable Letter of Credit is the SELECTED payment protection for the Government. The penal amount of bond shall be 100% of the original contract price. If the contract price increases, the Government will require an increase in the penal sum of the existing bond. This bond shall be submitted to the Contracting Officer within 10 days after receipt of award.

A Performance Bond shall be required if the total price of the quote is greater than $150,000.00. The penal amount of the Performance Bond shall be 100% of the original contract price. If the contract price increases, the Government will require an increase in the penal sum of the existing bond. This bond shall also be submitted to the Contracting Officer within 10 days after receipt of award.

NOTE 2: In accordance with FAR Part 28.102-1(c), the Contractor will be required to provide one of the following payment protections for all construction contracts greater than $35,000.00 but not greater than $150,000.00.

(i) Payment bond or

(ii) Irrevocable letter of credit

A Payment Bond or Irrevocable Letter of Credit is the SELECTED payment protection for the Government. The penal amount of bond shall be 100% of the original contract price. If the contract price increases, the Government will require an increase in the penal sum of the existing bond. This bond shall be submitted to the Contracting Officer within 10 days after receipt of award.

**No Payment Protections Required for construction contracts less than $35,000**

NOTE 3:

QUOTATION INSTRUCTIONS:

1. If subcontractor will be used for this work, please provide company names:

2. In accordance with FAR Part 52.204-7(b)(1) Contractors must be registered in the System for Award Management (SAM) database (www.SAM.gov) to submit a quote (formerly the Central Contractor Registration

(CCR) database and the On-Line Representations and Certifications (ORCA)). Any reference to CCR or ORCA in any clause or provision is referring to the www.sam.gov website.

NOTE: SAM.gov registration takes approximately 3 weeks (DUNS registration 1-2 business days; CAGE code validation up to 10 business days; IRS validation and overall submission 7-10 business days). It is the contractor’s responsibility to track SAM.gov registration and follow-up with required tasks.

In addition, if you are registering a new entity in SAM.gov, you must provide an original, signed notarized letter stating that you are the authorized Entity Administrator. The Entity Administrator must establish a LOGIN.GOV account using the e-mail address that will be associated with the SAM registration. See https://www.gsa.gov/about-us/organization/federal-acquisition-service/office-of-systems-management/integrated-award-environment-iae/sam-update for additional information.

3. Provide business Unique Entity Identifier (UEI): _______________________________

4. Provide business CAGE code: __________________________________

5. Tax Identification Number: ___________________________________

6. Contractors shall provide completed FAR clause 52.204-8 (Annual Representations and Certifications) found in Section K of this solicitation with their quote if the Contractors have not completed their annual representations and certifications electronically via the SAM website at www.sam.gov. (See Paragraph 2 above).

7. Contractors are not required to submit an Accident Prevention Plan (APP) with their quote. The successful Contractor will be required to submit this document at the direction of the Technical Point of Contact. The APP must be accepted by the Government Designated Authority prior to the commencement of work.

POTENTIAL QUOTERS ARE NOTIFIED THAT THE BASIS ON WHICH AWARD WILL BE MADE IS PRICE

ALONE.

ALL RESPONSIBLE SOURCES MAY SUBMIT A RESPONSE WHICH, IF TIMELY RECEIVED, MUST BE

CONSIDERED BY THE AGENCY.

INVOICES SHALL BE SENT TO TECHNICAL POINT OF CONTACT.

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Job Otter Brook Lake Micro-surfacing

FFP

Contractor shall furnish all labor, materials, and equipment necessary to fill cracks and micro-surface approximately 8,750 square yards of pavement at Otter Brook Lake, Keene, NH in accordance with the Statement of Work.

FOB: Destination

MILSTRIP: W13G8630349168

PURCHASE REQUEST NUMBER: W13G86303491680001

PSC CD: Y1LB

NET AMT

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0002 1 Job OPTION OPTION Otter Brook Lake Micro-surfacing

FFP

Contractor shall furnish all labor, materials, and equipment necessary to fill cracks and micro-surface approximately 600 square yards of pavement at Otter Brook Lake, Keene, NH in accordance with the Statement of Work.

FOB: Destination

MILSTRIP: W13G8630349168

PURCHASE REQUEST NUMBER: W13G86303491680002

PSC CD: Y1LB

NET AMT

Section C - Descriptions and Specifications

STATEMENT OF WORK

OTTER BROOK LAKE MICRO-SURFACING

U.S. ARMY CORPS OF ENGINEERS

OTTER BROOK LAKE

KEENE, NH

I. General:

1. Scope – Furnish all labor, materials, and equipment necessary to micro-surface approximately 4,100ft by 19ft (8,750 Square Yards) of existing pavement at Otter Brook Lake. The Government may also exercise an option to micro-surface an additional parking area of dimensions approximately 65ft x 80ft (600 square yards).

2. Location – Otter Brook Lake is located at 480 Branch Road Keene, NH 03431

3. Site Visit – Contact the Technical Point of Contact to arrange a site visit. The Technical Point of Contact (TPOC) for the project is Michael Servant 978-318-8300 or Michael.E.Servant@usace.army.mil

4. Schedule – The work shall be completed no later than July 1st, 2023. The Contractor will coordinate with the Government for the estimated start date. Work shall be performed Monday through Friday 7:00 AM to 3:30 PM unless otherwise approved by the Technical Point of Contact. No work shall be done on weekends or Government holidays. All submittals to include safety and product submittals shall be submitted, reviewed, and accepted within 30 days of Notice to Proceed.

5. Safety Requirements – All work shall be conducted in accordance with the U.S. Army Corps of Engineers (USACE) Safety and Health Requirements Manual (EM 385-1-1, most recent edition), and all applicable Occupational Safety Health Administration (OSHA), federal, state, and local safety and health requirements. A copy of EM 385-1-1 can be accessed at the project office or electronically at Headquarters USACE website under publications using the following link:

http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385- 1-1.pdf

Project staff reserve the right to cease work at any time should the safety of employees, Contractors, and/or the public become jeopardized.

a. Accident Prevention Plan:

The Contractor shall prepare an Accident Prevention Plan (APP) specific to the activities being performed. It shall include Activity Hazard Analyses (AHAs) as described below.

A non-mandatory, fillable APP template is available upon request. However, the

Contractor is permitted to submit their own plan, at a minimum it must meet the requirements of EM 385-1-1, Appendix A, Section K.

A preparatory meeting shall be conducted by the prime Contractor to discuss the APP contents with all effected onsite employees. The Prime Contractor is responsible for informing their subContractors of the safety provisions under the terms of the contract, the penalties for noncompliance, and inspecting subContractor operations to ensure that accident prevention responsibilities are being carried out.

Weekly safety meetings shall be held and documented. Records shall be available to the TPOC upon request.

b. Activity Hazard Analysis:

An AHA shall be submitted for each major phase of work. A major phase of work is defined as an operation involving a type of work presenting hazards not experienced in previous operations or where a new subContractor or work crew is to perform the work.

The analysis shall define all activities to be performed, identify the sequence of work, the specific hazards anticipated, and the control measures to be implemented to eliminate or reduce each hazard to an acceptable level. The AHA shall be continuously reviewed and revised to address changing site conditions as appropriate.

Note: As part of the APP and AHAs, the Contractor shall include site specific COVID-19 monitoring procedures which address, at a minimum, the following elements:

Procedures for periodic sanitation inspections.

Procedures for disinfecting project sites in accordance with Centers of Disease

Control and Prevention (CDC) guidelines.

Site specific measures to practice social distancing while working on the project.

Employee training on the signs, symptoms, and protection measures in accordance with CDC guidelines.

A list of Personal Protective Equipment to be used in accordance with CDC and state guidelines.

c. Emergency Response:

Emergency procedures shall be documented in the Accident Prevention Plan and will include a map with directions to the nearest hospital, emergency contact numbers, and onsite First Aid/CPR responders.

d. Required Personnel:

The Contractor shall employ a minimum of one Competent Person (CP) at each project site to function as the Site Safety and Health Officer (SSHO). The SSHO shall be present at the project site and report to the Contractor’s upper management. The SSHO is required to have related construction experience and have at a minimum completed a 10 Hour OSHA training.

In addition, when emergency medical services are not accessible within five (5) minutes of the work location and there are two (2) or more workers onsite, at least two (2) employees shall have (in-person) training in First Aid and CPR. Minimum qualifications are listed in EM 385-1-1, Section 03.A.02.c.

*Note: Other Competent or Qualified Persons may be required per EM 385-1-1 and/or other sections of this Statement of Work, based on the characteristics of the project*

e. Accident Reporting:

All accidents and near misses shall be investigated by the Contractor. All work-related recordable injuries, illnesses, and property damage accidents (excluding on-the-road vehicle accidents), in which the property damage exceeds $5,000.00, shall be verbally reported to the TPOC within four (4) hours of the incident. Serious accidents as described in EM 385-1-1 Section 01.D shall be immediately reported to the TPOC. ENG Form 3394 shall be completed and submitted to the TPOC within five (5) working days of the incident.

The Contractor shall compile employee work hours (including subContractors) and forward the total hours to the TPOC no later than close of business on the 10th calendar day of the following month. The method of transmission by the prime Contractor to the TPOC shall be electronically.

6. Pre-Construction Conference – Prior to the start of any work, the Technical Point of Contact will schedule and conduct a “Pre-Construction Conference”. The Contractor’s Project Manager and Quality Control Personnel will attend this meeting. This conference will be held at the time and location agreeable to the Government and Contractor. No work may be performed under this contract prior to this conference. The purpose of the conference is to enable the Technical Point of Contact to outline the procedures that will be followed by the Government in its administration of the contract, and to discuss the performance that will be expected from the Contractor. This conference will allow the Contractor an opportunity to ask questions about the Government’s administration and inspection of contract work or obtain other pertinent information that might be required. At the Pre-Construction conference the Contractor shall provide the name of the project superintendent with a telephone number for project coordination.

The following is a general list of items for discussion during this Pre-Construction Conference:

i. Authority of the Technical Point of Contact and Quality Assurance Inspectors.

ii. Contractor’s Safety Program (including sub-Contractors).

iii. Accident Prevention Plan and Activity Hazard Analysis

iv. Accident Reporting (ENG Form 3394)

v. Safety Data Sheet (SDS) requirements

vi. Contractor’s Equipment

vii. Correspondence, Communication, Security and Administrative Procedures.

viii. Invoice and payment.

7. Permits – The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses, permits, and letters of certification. The Contractor shall comply with any applicable Federal, State, County, and Municipal laws, codes, and regulations in connection with the performance of the work specified under this contract.

8. Security - The Contractor will comply with all established security policies at Otter Brook Lake. Due to periods of heightened security that may affect the access to the areas covered under this contract, the Government reserves the right to close any property or portion of property and reschedule and/or cancel any subsequent service. The Contractor shall be given at least 24-hours’ notice of any such closure.

9. Payment – After final inspection and acceptance by the Government, the Contractor must submit an invoice to the Technical Point of Contact. The invoice shall include the invoice date, contract number, dates of service, description of work, quantities, process, and total amount due per line item. The invoice must also include the company letterhead, and this must match the data that is registered in the System for Award Management (SAM) registry.

For jobs greater than 30 days the Contractor may request progress payment.

All invoices may be mailed to U.S. Army Corps of Engineers Otter Brook Lake

480 Branch Road Keene, NH 03431

Or emailed to: michael.e.servant@usace.army.mil

II. Technical Requirements:

Part 1 General:

1. Summary – Furnish all labor, materials, and equipment necessary to micro-surface approximately 4,100ft by 19ft (8,750 square yards) of existing pavement at Otter Brook Lake. The Government may also exercise an option to micro-surface an additional parking area of dimensions approximately 65ft x 80ft (600 square yards).

2. Submittals – Although the Government technically reviews submissions required by this Statement of Work, it is emphasized that the Contractor’s work must be completed using proper internal controls and review procedures. The documents identified below must be prepared in accordance with the applicable standards, submitted to the Technical Point of Contact for review and accepted by the Government within 30 days of Notice to Proceed. Submittals must be accepted by the Government prior to the commencement of any field activities

Accident Prevention Plan including Fall Protection Plan Activity Hazard Analysis Copy of Contractor’s licenses and qualifications

Product submittals

3. Existing Conditions: The existing pavement at Otter Brook Lake is worn but structurally sound throughout the work area. The pavement is approximately 4,100ft long by 19ft wide. The area to be micro-surfaced shall be cleaned of debris (sand, soil, leaves and anything that may impede bonding). All manholes shall be protected from the surfacing material to maintain full operability. There are various slopes and angles in the work areas as well that Contractors should be aware of. There are cracks in the surface and before micro-surfacing occurs, these shall be treated in with a crack sealant.

The parking area existing pavement at Otter Brook Lake is worn but structurally sound throughout the work area. The parking area pavement is approximately 65ft by 80ft. The area to be micro-surfaced shall be cleaned of debris (sand, soil, leaves and anything that may impede bonding). There are cracks in the surface and before micro-surfacing occurs, these shall be treated in with a crack sealant.

4. Other Contracts - The Government may undertake or award other contracts for additional work not related to this contract, and the Contractor shall fully cooperate with other Contractors and Government employees. The Contractor shall not commit or permit any act which will interfere with the performance of work by another Contractor or by Government employees.

5. Clean Up and Waste Disposal – The Contractor shall practice good housekeeping to maintain a safe job site. The Contractor shall keep the work area, including any designated storage areas free from accumulation of waste materials. Upon completing work in an area, the Contractor shall remove any tools, equipment, and materials that are not the property of the Government. Any and all disturbed areas resulting from Contractor activities shall be restored by the Contractor to the satisfaction of the Technical Point of Contact. All waste material will be disposed of offsite in accordance with all federal, state, and local regulations.

6. Environmental Protection – Containers for excess and/ or waste materials, rubbish, etc. shall be provided by the Contractor at the site, and the site will be inspected/ cleaned on a daily basis. No burning is permissible. Water, air, and land resources shall not be adversely impacted during the course of the work. Storage, fueling and lubrication of equipment and motor vehicles shall be conducted in a manner that affords the maximum protection against spills and evaporation. Storage and usage of lubricants and daily fueling of machinery and equipment shall occur at least 50 feet from any drainage inlets, water bodies (rivers, streams, and lakes), environmentally sensitive areas (wetlands, vernal pools). Contractor will take necessary steps to ensure all federal, state, and local environmental regulatory requirements are met.

7. Sustainability & Environmentally Preferred Products – Under the Comprehensive Procurement Guidelines (CPG) program, the Environmental Protection Agency (EPA) designates products that are or can be made with recovered materials and recommends practices for buying these products. Any designated product that is being offered or supplied under this contract shall meet the minimum recommended content levels as identified under the CPG program. Visit https://www.epa.gov/smm/comprehensive-procurement-guideline-cpg-program for a complete list of designated products and the associated recommended contents levels. Offerors must be able to demonstrate that each offered products meets minimum content levels upon request.

The United States Department of Agriculture (USDA) designates certain bio-based products for federal procurement and specifies minimum bio-based content levels for those products. Any designated product that is being offered or supplied under this contract shall meet USDA BioPreferred's minimum bio-based content level. Visit the BioPreferred web site https://www.biopreferred.gov/BioPreferred/faces/pages/ProductCategories.xhtml for the complete list of designated products and the associated minimum bio-based content level requirements.

8. Personal Protective Equipment - It is the Contractor’s responsibility to furnish and supply personnel with the proper personal protective equipment necessary for performing the work.

9. Government Resources – The Contractor is responsible for providing all materials to complete the project. Unless specified in the contract, the Government will not provide any equipment, telephone services or other resources. The Contractor may use the restroom at the office but must proceed directly to and from the restroom.

10. Damage to Government and Private Property – The Contractor shall be responsible for restoring all Government facilities or structures damaged as a result of the Contractor’s operation. The Contractor shall also be responsible for any damage to private property or injury to any person as a result of the Contractor’s operation. The Contractor shall notify the Project Manager immediately of damage to Government and private property and injury to any person resulting from the Contractor’s operation. Also, the Contractor shall notify the Technical Point of Contact of damage to Government facilities due to vandalism or other causes on the day such damage is first noticed. Trucks and/or trailers will be driven on existing roads only and not across or through park areas to facilities. The Contractor shall also restore landscape features (shrubs, flowers, grasses, etc.), which are damaged or destroyed by the Contractor’s operation. Damaged or destroyed grass areas shall be re-planted as directed by the Technical Point of Contact, and shrubs and flowers which are damaged or destroyed shall be replaced from nursery stock of like size and kind.

11. Contractor’s Personnel –

a. Minimum Personnel Requirements - The Contractor shall provide an adequate number of fully qualified personnel to perform the specified service properly and efficiently within the time limits specified. The Contractor shall provide a list of the names and contact phone numbers for all employees prior to them working on Government Property.

b. Employee Conduct - The Contractor shall be responsible for seeing that the firm’s employees strictly comply with the Code of Federal Regulations Title 36, Chapter III, Part 327, and all, federal, state, and municipal laws. Any personnel activity, which, in the opinion of the Government, is deemed detrimental to the performance of the contract may result in the removal of Contractor employee/employees.

Examples of unbecoming actions or conduct include but are not limited to the following:

i. Cursing, harassment, or discrimination of and/or unwarranted physical contact with visitors, USACE personnel, or other Contractors

ii. Recurring written and/or verbal complaints from visitors, USACE personnel, or other Contractors.

iii. Unsafe operation of vehicles while on USACE property

c. Removal of Contractor’s Employees - The Technical Point of Contact may require the Contractor to immediately remove from the work site any employee of the Contractor or subcontractor, who, in the opinion of the Technical Point of Contact, who endangers persons or property, or whose physical or mental condition is such that it would impair the employee’s ability to satisfactorily perform assigned work. Notification to the Contractor shall be promptly made in writing if time and circumstances permit. Otherwise, notification shall be verbal or by telephone, and shall be confirmed in writing as soon as possible. No such removal, however, will reduce the Contractor’s obligation to perform all work required under this contract, and immediate replacement will be made as required.

This requirement shall not be made the basis of any claim for compensation or damages against the United States or any of its officers or agents.

12. Omissions – This contract may not cover all specified activities, steps, and procedures required to supply the contract product. In case of omission, the normal industry, state, or federal standards, practices, specifications, and/or guides shall prevail. In no instance shall an omission be reason to produce less than an acceptable product.

13. Quality Assurance – The Contractor is responsible for the quality control of the contract work. The Contractor shall establish and maintain a quality control system to assure compliance with the contract requirements. The Government has the right to inspect and test all items called for by the contract, to the extent practicable at all times and at all places during the term of the contract.

14. Receiving and Storing Materials – The Contractor is responsible for protecting any stored material until it is placed in service. The Contractor is responsible for receiving and unloading of delivered goods. Government employees will not receive materials or supplies for the Contractor and will not be responsible for damage to the Contractor’s equipment or materials.

Part 2 Products:

All products shall be new, unused and to the satisfaction of the Technical Point of Contact. Products shall be approved by the Technical Point of Contact prior to installation.

1. Materials & Equipment – General

a. Crack Sealant

i. Fiberized Crack Sealant

ii. Polymer and crumb rubber modified asphalt cement (PCRM) asphalt

iii. Crack sealer shall be a polymer and crumb rubber modified asphalt cement including not less than 3% polymers, 7% recycled tire crumb rubber (80 mesh), and 8% polyester fibers (PCRM + fibers).

iv. The modified asphalt cement incorporated in the PCRM + fibers material must meet PG 64-28E MSCR testing requirements.

b. Micro-Surface Material

i. Emulsified Asphalt

ii. Quick set

iii. Polymer modified cationic type CSS-1H emulsion

iv. Before work commences, the Contractor shall submit a signed and certified mix design covering the specific materials to be used on the project.

v. This design shall be performed by an AASHTO resource accredited facility specifically accredited for Pavement Preservation and micro-surfacing mix designs.

vi. Proof of such AASHTO accreditation shall be submitted with the mix design.

vii. Once the materials are approved, no substitution will be permitted unless first tested and approved by the laboratory preparing the mix design.

c. Aggregate

i. The mineral aggregate used shall be of the type and grade specified for

Micro-Surfacing.

ii. The aggregate shall be manufactured crushed stone such as granite, slag, limestone, chat, or other high-quality aggregate or combination thereof.

iii. Grading- The aggregate including natural fines when tested by AASHTO methods T11 or T27 or ASTM C117 or C136, should meet the referenced gradation requirements.

iv. Deleterious Substances- To limit the permissible amount of clay-like fines in an aggregate, a sand equivalency value of 65 or higher is required when tested by ASTM 2419.

v. Soundness- The aggregate shall have a weighted loss of not more than 15% when the sodium sulfate test is used, or 20% when the magnesium sulfate test is used.

vi. Hardness- The aggregate wear, from resistance to abrasion, shall be a maximum of 35% when using AASHTO T96 or ASTM C131 test methods.

d. Water

i. Potable and free of harmful soluble salts.

e. Modifier

i. Special quick-setting emulsifier agents shall be milled into the asphalt emulsion.

ii. The emulsified asphalt shall be so formulated that when the paving mixture is applied at a thickness of one inch with the relative humidity at not more than 50% and an ambient air temperature of at least 75 degrees Fahrenheit, the material will cure sufficiently so that rolling traffic can be allowed in one hour with no damage to the surface.

f. Additives

i. A mineral additive shall be introduced to the aggregate and may be any recognized brand of non-air entrained Portland cement or hydrated lime that is free of lumps, or other approved mineral additive. It may be accepted upon visual inspection.

ii. The amount of mineral additive needed shall be determined by the laboratory mix design and will be considered as part of the material gradation requirement.

iii. A liquid field control additive may be introduced and blended with water to provide effective control of the required quick-set properties. This additive shall be made available by the chemical supplier or emulsion manufacturer and certified to be compatible with the mixture.

a. Mixing Equipment

i. The material shall be mixed by a self-propelled Micro-Surfacing mixing machine which shall be a continuous flow, continuous run mixing unit able to accurately deliver and proportion the aggregate, emulsified asphalt, mineral and field control additives, and water to a revolving multi-blade twin shafted mixer and discharge the mixed product on a continuous flow basis.

ii. The Contractor shall have available two (2) continuous flow, continuous run mixing machines to ensure highest quality, and to mitigate the effect of equipment breakdowns.

iii. The machines shall have sufficient storage capacity for aggregate, emulsified asphalt, mineral and field control additives, and water to maintain an adequate supply to the proportioning controls.

iv. The machines shall be equipped with self-loading devices which provide for the loading of materials while continuing to lay micro-surfacing, thereby minimizing construction joints.

b. Proportioning Devices

i. Individual volume or weight controls for proportioning each material to be added to the mix, i.e., aggregate, emulsified asphalt, mineral and field control additives, and water shall be provided and properly marked.

ii. These proportioning devices are usually revolution counters or similar devices and are used in material calibration and determining the materials output at any time.

c. Emulsion Pump

i. The emulsion pump shall be a heated, positive displacement type pump.

d. Spreading Equipment

i. The surfacing mixture shall be spread uniformly by means of a mechanical type spreader box attached to the mixer, equipped with paddles to agitate and spread the materials throughout the box.

ii. The spreader box width shall be capable of adjustment while paving in order to accommodate the changing width of some roadways without excessive overlaps.

iii. A front seal shall be provided to ensure no loss of the mixture at the road contact point.

iv. The rear seal and secondary strike-off shall act as the final strike-off, and both shall be adjustable.

v. The mixture shall be spread to fill cracks and minor surface irregularities and leave a uniform skid resistant application of material on the surface.

vi. The spreader box and rear strike-off shall be so designed and operated that a uniform consistency is achieved to produce a free flow of material to the rear strike-off.

vii. The longitudinal joint where two passes join shall be neat in appearance, uniform and lapped.

viii. All excess material shall be removed from the jobsite prior to opening the road.

ix. The spreader box shall have suitable means provided to side-shift the box to compensate for variations in pavement width and longitudinal alignment.

x. A rut box shall be available to pre-fill wheel ruts when necessary, prior to overlay to eliminate puddles or runoff interruption.

xi. The rut box shall be no less than 4’ wide and no more than 6’ wide

Part 3 Execution:

1. General

a. Surface Preparation

i. The area to be resurfaced shall be thoroughly cleaned of vegetation, loose aggregate, and soil, particularly soil that is bound to the surface.

ii. Manholes, valve boxes and other service entrances will be protected from the surfacing material with polyethylene sheeting.

iii. All services will be uncovered upon completion of work.

b. Crack Sealing

i. Treat the cracks in the surface with a fiberized crack sealer prior to the application of the micro-surfacing.

c. Stockpile Area/ Staging Area

i. Contractor shall have access to the Davis Road Parking lot for stockpiling and staging area.

ii. Precautions shall be taken to ensure that aggregate stockpiles do not become contaminated.

iii. The mineral aggregate shall be re-screened prior to being directly loaded onto micro-surfacing equipment.

d. Weather Limitations

i. The material shall be spread only when the road surface and atmospheric temperatures are at least 45 degrees Fahrenheit and rising, the weather is not rainy, and there is no forecast of temperatures below 32 degrees Fahrenheit within 48 hours from the time of placement of the mixture.

e. Application

i. The surface should be pre-wetted by fogging ahead of the spreader box when required by surface and ambient conditions.

ii. The rate of application of the fog spray shall be adjusted during the day to suit temperatures, surface texture, humidity, and dryness of the pavement surface.

iii. The micro-surfacing mixture shall be of the desired consistency upon leaving the mixer and no additional materials should be added.

iv. Enough material shall be carried in all parts of the spreader at all times so that a complete coverage is obtained.

v. Overloading of the spreader shall be avoided. No lumping, balling, or unmixed aggregate shall be permitted.

vi. No streaks, such as those caused by oversized aggregate, will be left in the finished surface.

vii. If excessive amounts of oversized aggregates appear in the mix, the Contractor will be required to take corrective action to remedy any unsatisfactory applications and document corrective action to prevent further recurrence.

f. Joints

i. No excessive buildup, uncovered areas or unsightly appearances shall be permitted on longitudinal or transverse joints.

ii. The Contractor shall provide suitable width spreading equipment to produce a minimum number of longitudinal joints throughout the project.

iii. When possible, longitudinal joints shall be placed on lane lines.

iv. Half passes and odd width passes will be used only in minimum amounts.

If half passes are used, they shall not be the last pass of any paved areas.

g. Mix Stability

i. The micro-surfacing mixture shall possess sufficient stability so that premature breaking of the material in the spreader box does not occur.

ii. The mixture shall be homogeneous during and following mixing and spreading.

iii. It shall be free of excess water or emulsion, and free of segregation of the emulsion and aggregate fines from the coarser aggregate.

h. Hand Work

i. Areas which cannot be reached with the mixing machine shall be surfaced using hand squeegees to provide complete and uniform coverage.

ii. The area to be hand-worked shall be lightly dampened prior to mix placement.

iii. Care shall be exercised to leave no unsightly appearance from handwork.

The same type of finish as applied by the spreader box shall be required.

iv. Handwork shall be completed immediately after the Micro-Surfacing mixture is discharged from the spreader box.

i. Lines

i. Care shall be taken to ensure straight lines along curbs and shoulders. No runoff on these areas will be permitted.

ii. Lines at intersections will be kept straight to provide a neat workmanship appearance.

ATTACHMENTS

PLEASE REFER TO THE ATTACHMENTS INCLUDED WITH THIS SOLICITATION FOR ADDITIONAL

INFORMATION.

OTTER BROOK LAKE MICRO-SURFACING

U.S. ARMY CORPS OF ENGINEERS

OTTER BROOK LAKE

Informational Maps

Map 1 : Overall map with both the main roadway and parking area option

OTTER BROOK LAKE MICRO-SURFACING

U.S. ARMY CORPS OF ENGINEERS

OTTER BROOK LAKE

Informational Maps

Map 2: Map showing the option parking area location and shape

Section F - Deliveries or Performance

DELIVERY INFORMATION

CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /

CAGE

0001 01-JUL-2023 1 OTTER BROOK LAKE PROJ OF

MICHAEL SERVANT

480 BRANCH ROAD

KEENE NH 03431-9801

978-318-8300 FOB: Destination

961405

0002 01-JUL-2023 1 (SAME AS PREVIOUS LOCATION)

FOB: Destination 961405

Section H - Special Contract Requirements

SECURITY REQUIREMENTS

General security requirements and guidance: The security requirements described below apply to all contract personnel (including employees of the prime Contractor (“Contractor”) and all subcontractor employees) supporting the performance requirements of this contract. The Contractor is responsible for compliance with these security requirements. Questions regarding security matters shall be addressed to the designated Government representative (eg., Contracting Officer Representative (COR), Requiring Activity (RA) representative, or Contracting Officer (if a COR or other RA representative is not appointed)). Contract personnel are critical to the overall security and safety of US Army Corps of Engineers (USACE) installations, facilities and activities, and security awareness training contributes to those efforts. The Department of Defense (DoD) and Army security training requirements specified below, if applicable, are performance requirements; all applicable contract personnel shall complete initial training within 30 days of contract award or the date new contract personnel begin performance on the contract. Within five business days from the completion of training, the Contractor shall provide written documentation (e.g., email or memorandum) to the Government representative. The documentation shall include the names of contract personnel trained and which training they completed; the Contractor shall maintain training records as part of their contract files and be prepared to provide copies of training certificates to the Government representative. Contractor personnel and vehicles are subject to search when entering federal installations. Additionally, all contract personnel shall comply with Force Protection Condition (FPCON) measures, Random Antiterrorism Measures (commonly referred to as “RAMs”), and Health Protection Condition (HPCON) measures. The Contractor is responsible for meeting performance requirements during elevated FPCON and/or HPCON levels in accordance with applicable RA plans and procedures –this includes identifying mission essential and non-mission essential personnel. In addition to the changes otherwise authorized by the changes clauses of this contract, should FPCON or HPCON levels at any individual facility or installation change, the Government may implement security changes that affect contract personnel. The Contractor shall ensure all contract personnel are aware of their security responsibilities, including any site-specific requirements identified in local policies or procedures.

Suspicious Activity Reporting training (e.g. iWATCH, CorpsWatch, or See Something, Say Something): All contract personnel shall receive initial and annual refresher training from the RA representative on the local suspicious activity reporting program. This locally developed training provides contract personnel with general information on suspicious behavior, and guidance on reporting suspicious activity to the project manager, security representative or law enforcement entity.

WAGE DETERMINATION

General Decision Number: NH20230034 01/06/2023

Superseded General Decision Number: NH20220034

State: New Hampshire

Construction Type: Highway

County: Cheshire County in New Hampshire.

Note: Contracts subject to the Davis-Bacon Act are generally required to pay at least the applicable minimum wage rate required under Executive Order 14026 or Executive Order 13658.

Please note that these Executive Orders apply to covered contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but do not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60).

|If the contract is entered | Executive Order 14026 | |into on or after January 30, | generally applies to the | |2022, or the contract is | contract. | |renewed or extended (e.g., an | The contractor must pay | |option is exercised) on or | all covered workers at | |after January 30, 2022: | least $16.20 per hour (or | | | the applicable wage rate | | | listed on this wage | | | determination, if it is | | | higher) for all hours | | | spent performing on the | | | contract in 2023. | |If the contract was awarded on| Executive Order 13658 | |or between January 1, 2015 and| generally applies to the | |January 29, 2022, and the | contract. | |contract is not renewed or | The contractor must pay all| |extended on or after January | covered workers at least | |30, 2022: | $12.15 per hour (or the | | | applicable wage rate listed| | | on this wage determination,| | | if it is higher) for all | | | hours performing on that | | | contract in 2023. |

The applicable Executive Order minimum wage rate will be adjusted annually. If this contract is covered by one of the Executive Orders and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must still submit a conformance request.

Additional information on contractor requirements and worker protections under the Executive Orders is available at http://www.dol.gov/whd/govcontracts.

Modification Number Publication Date 0 01/06/2023

SUNH2019-003 11/22/2022

Rates Fringes

CARPENTER........................$ 25.75 2.28

CEMENT MASON/CONCRETE FINISHER...$ 18.50 0.00

INSTALLER - GUARDRAIL............$ 20.50 2.69

IRONWORKER, REINFORCING..........$ 22.35 2.03

LABORER: Asphalt, Includes Raker, Shoveler, Spreader and Distributor......................$ 18.57 2.68

LABORER: Common or General......$ 18.04 3.42

LABORER: Pipelayer..............$ 20.36 0.00

OPERATOR:

Backhoe/Excavator/Trackhoe.......$ 24.22 6.08

OPERATOR: Bobcat/Skid Steer/Skid Loader................$ 20.84 0.66

OPERATOR: Broom/Sweeper.........$ 20.29 2.52

OPERATOR: Bulldozer.............$ 29.10 4.94

OPERATOR: Crane.................$ 27.81 7.02

OPERATOR: Grader/Blade..........$ 28.55 0.53

OPERATOR: Loader................$ 23.38 4.62

OPERATOR: Mechanic..............$ 24.73 6.96

OPERATOR: Milling Machine.......$ 28.42 4.14

OPERATOR: Paver (Asphalt, Aggregate, and Concrete).........$ 25.50 6.70

OPERATOR: Roller................$ 22.67 4.50

PAINTER: Spray..................$ 28.88 12.06

TRAFFIC CONTROL: Flagger.......$ 14.65 ** 1.37

TRUCK DRIVER: Dump Truck........$ 19.99 2.87

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

** Workers in this classification may be entitled to a higher minimum wage under Executive Order 14026 ($16.20) or 13658 ($12.15). Please see the Note at the top of the wage determination for more information.

Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.

Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at https://www.dol.gov/agencies/whd/government-contracts.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of ""identifiers"" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).

Union Rate Identifiers

A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than ""SU"" or ""UAVG"" denotes that the union classification and rate were prevailing for that classification in the survey. Example:

PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.

Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.

Survey Rate Identifiers

Classifications listed under the ""SU"" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.

Survey wage rates are not updated and remain in effect until a new survey is conducted.

Union Average Rate Identifiers

Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.

A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour National Office because National Office has responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.) and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:

Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .