KNIGHTVILLE DAM

COLIN MONKIEWICZ

RR1 BOX 285 KNIGHTVILLE DAM ROAD

HUNTINGTON MA 01050-9742

TEL: 978-318-8278 FAX:

REQUEST FOR QUOTATIONS

(THIS IS NOT AN ORDER) 1

PAGE OF PAGES

1. REQUEST NO. 2. DATE ISSUED RATING

W912WJ21Q0135 02-Aug-2021 5a. ISSUED BY

8. TO: NAME AND ADDRESS, INCLUDING ZIP CODE

IMPORTANT: This is a request for information, and quotations furnished are not offers. If you are unable to quote, please so indicate on this form and return it to the address in Block 5a. This request does not commit the Government to pay any costs incurred in the preparation of the submission of this quotation or to contract for supplies or services. Supplies are of domestic origin unless otherwise indicated by quoter. Any representations and/or certifications attached to this

Request for Quotations must be completed by the quoter.

11. SCHEDULE (Include applicable Federal, State, and local taxes)

ITEM NO.

(a)

SUPPLIES/ SERVICES

(b)

QUANTITY

(c)

UNIT

(d)

UNIT PRICE

(e) (f)

SEE SCHEDULE

AMOUNT

% No. %

NOTE: Additional provisions and representations [ ] are [ ] are not attached.

13. NAME AND ADDRESS OF QUOTER (Street, City, County, State, and ZIP Code)

14. SIGNATURE OF PERSON AUTHORIZED TO

SIGN QUOTATION

15. DATE OF

QUOTATION

16. NAME AND TITLE OF SIGNER (Type or print) (Include area code)

TELEPHONE NO.

AUTHORIZED FOR LOCAL REPRODUCTION STANDARD FORM 18 (REV. 6-95)

PREVIOUS EDITION NOT USABLE Prescribed by GSA FAR (48 CFR) 53.215-1(a)

THIS RFQ X[ ] IS [ ] IS NOT A SMALL BUSINESS SET-ASIDE

6. DELIVER BY (Date)

SEE SCHEDULE

AND/OR DMS REG. 1

UNDER BDSA REG. 2

4. CERT. FOR NAT. DEF.3. REQUISITION/PURCHASE

REQUEST NO.

U S ARMY ENGR DISTRICT, NEW ENGLAND

696 VIRGINIA RD

CONCORD MA 01742-2751

9. DESTINATION (Consignee and address, including ZIP Code)

7. DELIVERY

[ ]X FOB

DESTINATION

[ ] OTHER

(See Schedule)

12-Aug-2021(Date)

PLEASE FURNISH QUOTATIONS TO THE ISSUING OFFICE IN BLOCK 5a ON OR BEFORE CLOSE OF BUSINESS:10.

978-318-8814AMANDA N LANE

(Name and Telephone no.) (No collect calls)5b. FOR INFORMATION CALL:

d. CALENDAR DAYSc. 30 CALENDAR DAYSb. 20 CALENDAR DAYS12. DISCOUNT FOR PROMPT PAYMENT a. 10 CALENDAR DAYS

W912WJ21Q0135

Section B - Supplies or Services and Prices

INSTRUCTIONS TO OFFERORS

*SITE VISITS ARE HIGHLY RECOMMENDED PRIOR TO PROVIDING A QUOTE. SEE CLAUSE 52.236-27

FOR ADDITIONAL INFORMATION.

*PLEASE DIRECT QUESTIONS TO AMANDA LANE AT (978) 318-8814 or

AMANDA.N.LANE@USACE.ARMY.MIL. ANY INFORMATION RECEIVED AT THE SITE VISIT WHICH

CONFLICTS WITH THIS SOLICITAION SHOULD BE BROUGHT TO THE ATTENTION OF AMANDA

LANE. THE SOLICITATION AND RESULTING CONTRACT SHALL BE THE GOVERNING DOCUMENT

IN ALL CASES.

**QUOTES CAN BE E-MAILED TO AMANDA LANE AT AMANDA.N.LANE@USACE.ARMY.MIL.

NOTE 1: In accordance with FAR Part 28.102-1(b), the Contractor will be required to provide the following payment protections for all construction contracts greater than $150,000.00.

(i) Payment Bond or

(ii) Irrevocable Letter of Credit and

(iii) Performance Bond

A Payment Bond or Irrevocable Letter of Credit is the SELECTED payment protection for the Government. The penal amount of bond shall be 100% of the original contract price. If the contract price increases, the Government will require an increase in the penal sum of the existing bond. This bond shall be submitted to the Contracting Officer within 10 days after receipt of award.

A Performance Bond shall be required if the total price of the quote is greater than $150,000.00. The penal amount of the Performance Bond shall be 100% of the original contract price. If the contract price increases, the Government will require an increase in the penal sum of the existing bond. This bond shall also be submitted to the Contracting Officer within 10 days after receipt of award.

NOTE 2: In accordance with FAR Part 28.102-1(c), the Contractor will be required to provide one of the following payment protections for all construction contracts greater than $35,000.00 but not greater than $150,000.00.

(i) Payment bond or

(ii) Irrevocable letter of credit

A Payment Bond or Irrevocable Letter of Credit is the SELECTED payment protection for the Government. The penal amount of bond shall be 100% of the original contract price. If the contract price increases, the Government will require an increase in the penal sum of the existing bond. This bond shall be submitted to the Contracting Officer within 10 days after receipt of award.

**No Payment Protections Required for construction contracts less than $35,000**

NOTE 3:

QUOTATION INSTRUCTIONS:

1. If subcontractor will be used for this work, please provide company names:

2. In accordance with FAR Part 52.204-7(b)(1) Contractors must be registered in the System for Award Management (SAM) database (www.SAM.gov) to submit an offer. (Formerly the Central Contractor Registration (CCR) database and the On-Line Representations and Certifications (ORCA).) Any reference to CCR or ORCA in any clause or provision is referring to the www.sam.gov website. Please note that Google and Google Chrome are not supported browsers for SAM registration. Mozilla FireFox, Safari, and Internet Explorer are supported browsers.

NOTE: SAM.gov registration takes approximately 3 weeks (DUNS registration 1-2 business days; CAGE code validation up to 10 business days; IRS validation and overall submission 7-10 business days). It is the contractor’s responsibility to track SAM.gov registration and follow-up with required tasks.

In addition, if you are registering a new entity in SAM.gov, you must provide an original, signed notarized letter stating that you are the authorized Entity Administrator. The Entity Administrator must establish a LOGIN.GOV account using the e-mail address that will be associated with the SAM registration. See https://www.gsa.gov/about-us/organization/federal-acquisition-service/office-of-systems-management/integrated-award-environment-iae/sam-update for additional information.

3. Provide business DUNS number: _______________________________ (phone 800-333-0505 for DUNS).

4. Provide business CAGE code: __________________________________

5. Tax Identification Number: ___________________________________

6. Contractors shall provide completed FAR clause 52.204-8 (Annual Representations and Certifications) found in Section K of this solicitation with their quote, if the Contractors have not completed their annual representations and certifications electronically via the SAM website at www.sam.gov. (See Paragraph 2 above).

7. Contractors are not required to submit an Accident Prevention Plan (APP) with their quote. The successful offeror will be required to submit this document at the direction of the Technical Point of Contact. The APP must be accepted by the Government Designated Authority prior to the commencement of work.

POTENTIAL QUOTERS ARE NOTIFIED THAT THE BASIS ON WHICH AWARD WILL BE MADE IS PRICE

ALONE.

ALL RESPONSIBLE SOURCES MAY SUBMIT A RESPONSE WHICH, IF TIMELY RECEIVED, MUST BE

CONSIDERED BY THE AGENCY.

INVOICES SHALL BE SENT TO TECHNICAL POINT OF CONTACT.

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Job KVD Generator Installation

FFP

Contractor shall furnish all equipment, materials and labor to perform Generator Installlation at the Knightville Dam, Huntington, MA in accordance with the Statement of Work.

FOB: Destination

PSC CD: Y1QA

NET AMT

Section C - Descriptions and Specifications

STATEMENT OF WORK

KNIGHTVILLE OFFICE GENERATOR INSTALL

U.S. ARMY CORPS OF ENGINEERS

KNIGHTVILLE DAM

HUNTINGTON, MA

Statement of Work

June 2021

I. General

1) Scope of work

Furnish all equipment, materials and labor to install, wire, and plumb into the Knightville Dam office building one (1) 20 kilowatt 120/240 volt external pad mounted 3-phase generator, one (1) one thousand (1000) gallon underground liquid propane fuel tank, and remove one (1) 3-phase transfer switch and replace with one (1) 3-phase automatic transfer switch.

2) Location

The Knightville Dam is located at 49 Knightville Dam Road, Huntington, MA 01050.

3) Technical Point of Contact

The Technical Point of Contact (TPOC) for this contract will be Park Ranger Keith Goulet.

Park Ranger Goulet can be reached by phone at 978-318-8296 or by email at:

Keith.A.Goulet@usace.army.mil

4) Site Visit An appointment can be made by contacting the Technical Point of Contact, Park Ranger

Keith Goulet. Site visits are generally scheduled between 7:00am and 3:30 PM Monday thru Friday.

5) Schedule The period of performance shall be 120 days from Notice to Proceed. Work shall commence within fourteen (14) days from Notice to Proceed. The project area will be open to the contractor Monday through Friday 7:00 AM to 3:30 PM and all work must be done during those hours unless additional hours are approved by the Technical Point of Contact. No work shall be done on weekends or government holidays.

6) Safety

a. General:

All work shall be conducted in accordance with the U.S. Army Corps of Engineers Safety and Health Requirements Manual (EM 385-1-1, most recent edition), and all applicable Occupational Safety and Health Administration (OSHA), federal, state, and local safety and health requirements. A copy of EM 385-1-1 can be accessed at the project office or electronically at the following link:

http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385- 1-1.pdf

Project staff reserve the right to cease work at any time should the safety of employees, Contractors, and/or the public become jeopardized.

b. Accident Prevention Plan:

The Contractor shall prepare an Accident Prevention Plan (APP) specific to the activities being performed. It shall include Activity Hazard Analyses (AHAs) as described below in paragraph C. A non-mandatory, fillable APP template is available upon request. However, the contractor is permitted to submit their own plan, at a minimum it must meet the requirements of EM 385-1-1, Appendix A.

A preparatory meeting shall be conducted by the prime contractor to discuss the APP contents with all effected onsite employees. The Prime Contractor is responsible for informing the subcontractors of the safety provisions under the terms of the contract, the penalties for noncompliance, and inspecting subcontractor operations to ensure that accident prevention responsibilities are being carried out.

Weekly safety meetings shall be held and documented. Records shall be available to the Technical Point of Contact upon request.

c. Activity Hazard Analysis:

An AHA shall be submitted for each major phase of work. A major phase of work is defined as an operation involving a type of work presenting hazards not experienced in previous operations or where a new subcontractor or work crew is to perform the work. The analysis shall define all activities to be performed, identify the sequence of work, the specific hazards anticipated, and the control measures to be implemented to eliminate or reduce each hazard to an acceptable level. The AHA shall be continuously reviewed and revised to address changing site conditions as appropriate.

Note: As part of the APP and AHAs include site specific COVID-19 monitoring procedures which address, at a minimum, the following elements:

Procedures for periodic sanitation inspections Procedures for disinfecting project sites in accordance with the Center for

Disease Control and Prevention (CDC) guidelines Site Specific measures to practice social distancing while working on the project Employee training on the signs, symptoms, and protection measures in accordance with CDC guidelines A list of Personal Protective Equipment (PPE) to be used in accordance with

Center for Disease Control and state guidelines

d. Emergency Response:

Emergency procedures shall be documented in the Accident Prevention Plan and will include a map with directions to the nearest hospital, emergency contact numbers, and onsite First Aid/CPR responders.

e. Required Personnel:

The Contractor shall employ a minimum of one Competent Person (CP) at each project site to function as the Site Safety and Health Officer (SSHO). The SSHO shall be present at the project site and report to the contractor’s upper management. The SSHO is required to have related construction experience and have at a minimum completed a 10 Hour OSHA training.

In addition, when emergency medical services are not accessible within 5 minutes of the work location and there are 2 or more workers onsite, at least 2 employees shall have (in-person) training in First Aid and CPR. Minimum qualifications are listed in EM 385-1-1, Section 03.A.02.c.

*Note: Other Competent or Qualified Persons may be required per EM 385-1-1 and/or other sections of this Scope of Work, based on the characteristics of the project*

f. Accident Reporting:

All accidents and near misses shall be investigated by the Contractor. All work-related recordable injuries, illnesses, and property damage accidents (excluding on-the-road vehicle accidents), in which the property damage exceeds $5,000.00, shall be verbally reported to the Technical Point of Contact within four (4) hours of the incident. Serious accidents as described in EM 385-1-1 Section 01.D shall be immediately reported to the Technical Point of Contact. ENG Form 3394 shall be completed and submitted to the Technical Point of Contact within five (5) working days of the incident.

The Contractor shall compile employee work hours (including subcontractors) and forward the total hours to the Technical Point of Contact no later than close of business on the 10th calendar day of the following month. The method of transmission by the prime contractor to the Technical Point of Contact shall be electronically.

7) Preconstruction Conference Prior to the start of any work, the Technical Point of Contact will schedule and conduct a “Preconstruction Conference”. The Contractor’s Project Manager and Quality Control Personnel will attend this meeting. This conference will be held at the time and location agreeable to the government and contractor. No work may be performed under this contract prior to this conference. The purpose of the conference is to enable the Technical Point of Contact to outline the procedures that will be followed by the Government in its administration of the contract, and to discuss the performance that will be expected from the Contractor. This conference will allow the Contractor an opportunity to ask questions about the Government’s administration and inspection of contract work or obtain other pertinent information that might be required. At the Preconstruction conference the contractor shall provide the name of the project superintendent with a telephone number for project coordination.

The following is a general list of items for discussion during this Preconstruction Conference:

i. Authority of the Technical Point of Contact and Quality Assurance Inspectors.

ii. Contractor’s Safety Program (including sub-contractors).

iii. COVID-19

iv. Accident Prevention Plan (Submitted & accepted prior to start of work on site).

v. Activity Hazard Analysis (Submitted & accepted prior to start of work on site).

vi. Weekly Safety Meetings (Documented on NED Form 251).

vii. Accident Reporting (ENG Form 3394).

viii. Safety Data Sheet (SDS) requirements.

ix. Correspondence, Communication and Administrative Procedures

x. CPR & First Aid

xi. Invoice and payment.

8) Permits

The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses, permits, and letters of certification. The Contractor shall comply with any applicable federal, state, county, and municipal laws, codes, and regulations in connection with the performance of the work specified under this contract.

9) Security

The contractor will comply with all established security policies at Knightville Dam. Due to periods of heightened security that may affect the access to the areas covered under this contract, areas may be subject to periodic closures, which in turn may reduce or inhibit the Contractor’s ability to access certain areas. During periods of heightened security, the Government reserves the right, at any time, to close any property or portion of property and reschedule and/or cancel any subsequent service in an area. The Contractor shall be given at least 24 hour notice of any such closure.

10) Flooding

Knightville Dam is a flood control project. Occasional retention of floodwaters may inundate portions of the construction area or access roads to these areas. Therefore, it may become necessary to stop work on any or all portions of the property, and/or to close any portion of a property and delay any subsequent construction for the closed property or area. If needed payment for the decreased service will be adjusted in accordance with the contract unit prices through the section on Changes in Quantity.

11) Contractor’s Personnel

a. Minimum Personnel Requirements:

The Contractor shall provide an adequate number of fully qualified personnel to perform the specified service properly and efficiently within the time limits specified. The Contractor shall provide a list of the names and contact phone numbers for all employees prior to them working on Government Property.

b. Employee Conduct:

The Contractor shall be responsible for seeing that the firm’s employees strictly comply withal CFR 36 Rules and Regulations, federal, state, and municipal laws. Any personnel activity, which, in the opinion of the Government, is deemed detrimental to the performance of the contract may result in the removal of Contractor employee/employees.

c. Examples of unbecoming actions or conduct include but are not limited to the following:

i. Cursing, harassment, or discrimination of and/or unwarranted physical contact with visitors, U.S. Army Corps of Engineers personnel, or other contractors

ii. Recurring written and/or verbal complaints from visitors, U.S Army Corps of Engineers personnel, or other contractors.

iii. Unsafe operation of vehicles while on U.S. Army Corps of Engineers property.

d. Removal of Contractor’s Employees:

The Technical Point of Contact may require the Contractor to immediately remove from the work site any employee of the Contractor or subcontractor, who, in the opinion of the Technical Point of Contact, is incompetent, who endangers persons or property, or whose physical or mental condition is such that it would impair the employee’s ability to satisfactorily perform assigned work. Notification to the Contractor shall be promptly made in writing if time and circumstances permit. Otherwise, notification shall be verbal or by telephone, and shall be confirmed in writing as soon as possible. No such removal, however, will reduce the Contractor’s obligation to perform all work required under this contract, and immediate replacement will be made as required. This requirement shall not be made the basis of any claim for compensation or damages against the United States or any of its officers or agents.

12) Changes to Quantity The Government reserves the option, should it become necessary, to decrease or increase quantities in any or all designated contract areas. The Government may also, at any time during the duration of this contract, remove any portion of the contract responsibility and delete any subsequent work in the selected area. The Contractor shall be given adequate notification to prepare for either contingency. This decrease or increase will be deducted from or paid for in accordance a negotiated cost. Any increase in quantity must be negotiated with the Contracting Officer (KO). The Contractor shall not perform any additional work until the issuance of a formal modification signed by the Contracting Officer. In addition, the Technical Point of Contact may, on special occasions decide to reschedule work in order to avoid conflict with visitation or unnecessary expense. The Contractor shall be given at least 24 hours’ notice.

13) Payment

Payment shall be made on a per job basis. After final inspection and acceptance by the Government, the Contractor must submit an invoice to the Technical Point of Contact. The invoice shall include the invoice date, contract number, dates of service, description of work, quantities, process, and total amount due per line item. For jobs greater than 30 days the contractor may request progress payment.

All invoices may be mailed to:

U.S. Army Corps of Engineers Knightville Dam 49 Knightville Dam RD, Huntington, MA 01050

Or Emailed to keith.a.goulet@usace.army.mil

II. Technical Requirements:

Part 1 General:

1) Summary

Furnish all equipment, materials and labor to install, wire, and plumb into the Knightville Dam office building one (1) 20 kilowatt 120/240 volt external pad mounted 3-phase generator, one (1) one thousand (1000) gallon underground liquid propane fuel tank, and remove one (1) 3-phase manual transfer switch and replace with one (1) 3-phase automatic transfer switch.

2) Submittals

Although the Government technically reviews submissions required by this scope of work, it is emphasized that the Contractor’s work must be prosecuted using proper internal controls and review procedures. The documents identified below must be prepared in accordance with the applicable standards, submitted to the Technical Point of Contact for review and accepted by the government prior to the commencement of any field activities.

a. Generator System Specification Sheet

b. Fuel Tank Specification Sheet

c. Automatic Transfer Switch Specification Sheet

d. Manufacturer Warranties

e. Activity Hazard Analysis (AHA)- Prior to start of work

f. Accident Prevention Plan (APP)- Prior to start of work

g. First-Aid, CPR Certifications

h. Safety Data Sheets (SDS)

i. Security Verification (E-Verify) unless exempt from E-Verify. https://www.e-verify.gov/employers/federal-contractors/exemptions-and-exceptions

3) Existing Conditions

Currently 120/240v 3-phase power is brought into the office building through a buried metal conduit from a breaker panel mounted behind the office building next to the service pole.

(See informational photo numbers 2&3) The power currently passes through a manual transfer switch and into the buildings electrical system. (See informational photo numbers 7&8) There currently is no generator wired into the transfer switch.

4) Clean Up The Contractor shall practice good housekeeping to maintain a safe job site. The contractor shall keep the work area, including any storage areas, free from the accumulation of waste materials. Upon completing work in an area, the contractor shall remove any tools, equipment, and materials that are not the property of the government. Upon completion of work, the Contractor shall clean up the job site to the satisfaction of the Government.

5) Environmental Protection

The contractor shall prevent pollution or damage to the environment resulting from construction during this contract. The contractor will receive no additional payment for environmental protection work. Prevention of pollution and environmental damage is a contractor obligation under current State and federal Laws and regulations. Assurance of compliance with this section by subcontractors shall be the responsibility of the contractor.

6) Sustainability

Under the Comprehensive Procurement Guidelines (CPG) program, the Environmental Protection Agency (EPA) designates products that are or can be made with recovered materials and recommends practices for buying these products. Any designated product that is being offered or supplied under this contract shall meet the minimum recommended content levels as identified under the CPG program. Visit https://www.epa.gov/smm/comprehensive-procurement-guideline-cpg-program for a complete list of designated products and the associated recommended contents levels.

Offerors must be able to demonstrate that each offered products meets minimum content levels upon request. Products that fall under these requirements are things such as cement, concrete, non-pressure pipes, etc.

Furthermore, the contractor should also meet the BioPreferred Program requirements set in place by the United States Department of Agriculture (USDA) . The USDA designates certain bio-based products for federal procurement and specifies minimum bio based content levels for those products. Any designated product that is being offered or supplied under this contract shall meet USDA BioPreferred's minimum bio based content level. Visit the BioPreferred web site https://www.biopreferred.gov/BioPreferred/faces/pages/ProductCategories.xhtml for the complete list of designated products and the associated minimum bio based content level requirements.These will include products such as wood and concrete sealers, erosion-controlled materials, sorbents, etc.

7) Personal Protective Equipment

It is the contractor’s responsibility to furnish and supply personnel with the proper personal protective equipment necessary for performing the work.

8) Government Resources

The contractor is responsible for providing all materials to complete the project. Unless specified in the contract, the Government will not provide any equipment, telephone services or other resources. The contractor may use the restroom at the Littleville Lake Project Office but must proceed directly to and from the restroom.

9) Damage to Government and Private Property

The Contractor shall be responsible for restoring any Government facilities or structures damaged as a result of the Contractor’s actions. The Contractor shall also be responsible for any damage to private property or injury to any person as a result of the firm’s operations.

The Contractor shall notify the Technical Point of Contact immediately of damage to Government and private property and injury to any person resulting from the Contractors’ operation. Also, the Contractor shall notify the Technical Point of Contact of damage to Government facilities due to vandalism or other causes on the day such damage is first noticed. Trucks and/or trailers will be driven on existing roads only and not across or through park areas to facilities.

10) Omissions

This contract may not cover all specified activities, steps, and procedures required to supply the contract product. In case of omission, the normal industry, state, or federal standards, practices, specifications, and/or guides shall prevail. In no instance shall an omission be reason to produce less than an acceptable product.

11) Quality Control

The contractor is responsible for the quality control of the contract work. The government has the right to inspect and test all items called for by the contract, to the extent practicable at all times and at all places during the term of the contract.

12) Other Contracts

The Government may undertake or award other contracts for additional work not related to this contract, and the Contractor shall fully cooperate with other Contractors and Government employees. The contractor shall not commit or permit any act, which will interfere with the performance of work by another contractor, or by Government employees.

13) Receiving and Storing Materials

The contractor is responsible for protecting any stored material until it is placed in service.

The contractor is responsible for receiving and unloading of delivered goods. Government employees will not receive material or supplies for the contractor and will not be responsible for damage to contractor equipment or material.

Part 2 Products:

Backup Power System – Shall meet the following minimum requirements:

a) Generator

i) Uses Liquid Propane Fuel

ii) Provides 120/240 Volt 3-Phase Electrical Power

iii) Rated for 20kW of Power Draw

iv) Automatic Self-Test with programable schedule.

v) Digital Controller that Manages Generator as well as Transfer Switch Functions, Including Monitoring Functions for the Generator

vi) Absorbed Glass Mat Type Starting Battery

vii) Built-in Battery Charger

viii) Battery Heater

b) Generator Housing

i) Lockable with changeable lock core

ii) Wiring to exit the box into conduits underground to the building

iii) Housing will have sound reducing insulation installed

c) Generator Pad

i) May be Prefab Concrete Generator Pad designed to fit Generator and Housing being used.

ii) May be poured in place as long as pad meets Manufacturer Specifications for

Generator and Housing being used.

iii) May include a spot for the Fuel Tank to be set.

d) Fuel Tank

i) Designed to hold Liquid Propane

ii) 1000 Gallon Capacity

iii) American Society of Mechanical Engineers Certified

iv) Float Style Fuel Level Gauge

v) Designed for Underground Installation

vi) Properly Grounded

e) Transfer Switch

i) Designed for 120/240 Volt 3-Phase Electrical Power

ii) Rated for a Minimum of 200 Amps

iii) Automatic Operation

Part 3 Execution:

Demolition:

1) The Contractor shall remove existing manual transfer switch and dispose of it in accordance with Massachusetts laws.

Installation:

The Contractor shall install the new standby generator system in accordance with the Manufacturer’s Recommendations.

1) Installation shall conform with NFPA 70. (National Electric Code)

2) Installation shall conform with NFPA 110. (Standards for Emergency and Stand-by Power

Systems)

3) Generator wiring shall be performed by a Massachusetts Licensed Electrician.

4) Install the generator onto a prefab or poured in place concrete pad in accordance with manufacturers recommendations and Massachusetts building codes.

5) Install propane tank with required setbacks and distances and in accordance with manufactures recommendations and Massachusetts building codes.

6) Install new automatic transfer switch in the same place as the old manual transfer switch.

7) Make all required electrical connections according to building code.

8) Install regulator and plumb new propane tank into the fuel supply of the generator.

9) Contractor will test and verify the correct operation of the new generator and transfer switch.

10) Building will be transferred to generator power to verify correct operation of generator.

11) Digital Controller shall be placed inside building in the same room as the transfer switch.

ATTACHMENTS

PLEASE REFER TO THE ATTACHMENTS INCLUDED AT THE END OF THIS SOLICITATION FOR

ADDITIONAL INFORMATION.

Section F - Deliveries or Performance

DELIVERY INFORMATION

CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /

CAGE

0001 120 dys. ANP 1 KNIGHTVILLE DAM

COLIN MONKIEWICZ

RR1 BOX 285 KNIGHTVILLE DAM ROAD

HUNTINGTON MA 01050-9742

978-318-8278 FOB: Destination

961312

Section H - Special Contract Requirements

SECURITY REQUIREMENTS

The contractor and all associated sub-contractors shall receive a brief/training (provided by the RA) on the local suspicious activity reporting program. This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the project manager, security representative or law enforcement entity. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the Technical Point of Contact NLT 5 calendar days after the completion of the training.

WAGE DETERMINATION

"General Decision Number: MA20210003 04/30/2021

Superseded General Decision Number: MA20200003

State: Massachusetts

Construction Type: Building

Counties: Berkshire, Franklin, Hampden and Hampshire Counties in Massachusetts.

BUILDING CONSTRUCTION PROJECTS Does not include residential construction consisting of single family homes and apartments up to and including 4 stories)

Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.95 for calendar year 2021 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.95 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2021. If this contract is covered by the EO and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must pay workers in that classification at least the wage rate determined through the conformance process set forth in 29 CFR 5.5(a)(1)(ii) (or the EO minimum wage rate,if it is higher than the conformed wage rate). The EO minimum wage rate will be adjusted annually. Please note that this EO applies to the above-mentioned types of contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but it does not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60). Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Modification Number Publication Date

0 01/01/2021 1 02/12/2021 2 04/02/2021 3 04/30/2021

ASBE0006-011 09/01/2020

Rates Fringes

Insulator/asbestos worker (Includes the application of all insulating materials, protective coverings, coatings and finishes to all types of mechanical systems).....$ 49.00 31.75

BOIL0029-001 01/01/2017

Rates Fringes

BOILERMAKER......................$ 42.42 24.92

BRMA0001-001 08/01/2020

SPRINGFIELD/PITTSFIELD CHAPTER FRANKLIN, HAMPDEN, and

HAMPSHIRE COUNTIES

Rates Fringes

BRICKLAYER

BRICKLAYERS; CEMENT

MASONS; PLASTERERS; STONE

MASONS; MARBLE, TILE &

TERRAZZO WORKERS............$ 44.16 33.63

BRMA0001-003 08/01/2020

SPRINGFIELD/PITTSFIELD

BERKSHIRE

Rates Fringes

BRICKLAYER

BRICKLAYERS; CEMENT

MASONS; PLASTERERS; STONE

MASONS; MARBLE, TILE &

TERRAZZO WORKERS............$ 44.16 33.63

CARP0056-014 08/01/2020

Rates Fringes

PILEDRIVERMAN....................$ 49.07 35.57

CARP0336-006 03/01/2020

Franklin County (Erving, Orange, North Orange and Warwick)

Rates Fringes

CARPENTER........................$ 42.40 29.10

CARP0336-009 03/01/2020

HAMPDEN; HAMPSHIRE AND FRANKLIN (Remainder)

Rates Fringes

Carpenter/Lather/Drywall Applicator.......................$ 42.40 29.10

CARP0336-013 03/01/2020

BERKSHIRE COUNTY

Rates Fringes

CARPENTER........................$ 42.40 29.10

CARP1121-004 01/06/2020

Rates Fringes

MILLWRIGHT.......................$ 36.71 31.15

CARP2168-003 09/01/2020

Rates Fringes

FLOOR LAYER: Carpet.............$ 47.79 29.40

ELEC0007-002 06/28/2020

HAMPDEN (Except Chester & Holyoke); HAMPSHIRE (Belchertown, Ware)

ELECTRICIAN......................$ 44.01 24.67

ELEC0007-003 06/28/2020

BERKSHIRE; FRANKLIN; HAMPDEN (Chester, Holyoke); HAMPSHIRE (Except Belchertown, Ware)

ELECTRICIAN......................$ 44.01 24.67

ELEC0007-006 06/28/2020

Rates Fringes

Teledata System Installer........$ 44.01 24.67

ELEC0042-003 09/03/2017

Rates Fringes

Line Construction:

Heavy Equipment Operator....$ 42.26 6.5%+19.81 Lineman, Cable Splicer and Dynamite Man................$ 46.96 6.5%+22.00 Material Man, Tractor Trailer Driver, Equipment Operator....................$ 39.92 6.5%+19.21

ELEV0041-001 01/01/2020

Rates Fringes

ELEVATOR MECHANIC................$ 54.85 34.765+a+b

FOOTNOTE:

a.Vacation: 6%/under 5 years based on regular hourly rate for all hours worked. 8%/over 5 years based on regular hourly rate for all hours worked.

b. PAID HOLIDAYS: New Year's Day; Memorial Day; Independence Day; Labor Day; Veterans' Day; Thanksgiving Day; the Friday after Thanksgiving Day; and Christmas Day.

ENGI0098-001 12/01/2016

Rates Fringes

Power equipment operators:

(BUILDING & RESIDENTIAL)

Group 1...................$ 33.68 23.96+A Group 2...................$ 33.37 23.96+A Group 3...................$ 33.15 23.96+A Group 4...................$ 32.54 23.96+A Group 5...................$ 29.92 23.96+A Group 6...................$ 28.80 23.96+A Group 7...................$ 26.86 23.96+A Group 8...................$ 305.95 23.962+A Group 9...................$ 230.69 23.96+A Group 10...................$ 35.17 23.96+A Group 11...................$ 38.18 23.96+A Group 12...................$ 39.68 23.96+A Group 13...................$ 40.68 23.96+A Group 14...................$ 41.68 23.96+A

Group 15...................$ 43.18 23.96+A

HAZARDOUS WASTE PREMIUM $2.00

FOOTNOTE FOR POWER EQUIPMENT OPERATORS:

Group 8 and Group 9 are per day wages.

A. Paid Holidays: New year's Day, Washington's Birthday, Memorial Day, Independence Day, Labor Day, Columbus Day, Veterans Day, Thanksgiving Day and Christmas Day

POWER EQUIPMENT OPERATORS CLASSIFICATIONS

Group 1: Shovels; crawlers and truck cranes including all tower; self-propelled hydraulic cranes 10 tons and over;

draglines; clam shells; cableways; shaft hoists; mucking machines derricks; backhoes; bulldozers; gradalls;

elevating graders; pile drivers; concrete pavers; trenching machines; front end loaders- 5 1/2 cu yds and over; dual drum paver; automatic grader-excavator(C.M.I. or equal);

scrapers towing pan or wagon; tandem dozers or push cats(2 units in tandem); shotcrete machine; tunnel boring machine;

combination backhoe/loader 3/4 cu yd hoe or over; jet engine dryer; tree shredder; post hole digger; post hole hammer; post extractor; truck mounted concrete pump with boom; roto-mill; Grader; Horizontal Drilling Machine; John Henry Rock Drill and similar equipment.

Group 2: Rotary drill with mounted compressor; compressor house (3 to 6 compressors); rock and earth boring machines (excluding McCarthy and similar drills); front end loaders 4 cu yds to 5 1/2 cu yds); forklifts-7 ft lift and over 3 ton capacity; scraper 21 yds and over (struck load); sonic hammer console; reclaimers road planer/milling machine; cal tracks; ballast regulators; rail anchor machines; switch tampers, asphalt pavers; mechanic; welder and transfer machine.

Group 3: Combination backhoe/loader up to 3/4 cu yd;

scrapers up to 21 cu yd (struck load, self propelled or tractor drawn); tireman; front end loaders up to 4 yds;

well drillers; engineer or fireman on high pressure boiler;

self-loading batch plant; well point operators electric pumps used in well point system; pumps, 16 inches and over (total discharge); compressor, one or two 900 cu ft and over; powered grease truck; tunnel locomotives and dingys;

grout pumps; hydraulic jacks; boom truck; hydraulic cranes-up to 10 ton.

Group 4: Asphalt rollers; self-powered rollers and compactors; tractor without blade drawing sheepsfoot roller; rubber tire roller; vibratory roller or other type of compactors including machines for pulverizing and aerating soil; york rake.

Group 5: Hoists; conveyors; power pavement breakers;

self-powered concrete pavement finishing machines; two bag mixers with skip; McCarthy and similar drills; batch plants (not self loading); bulk cement plants; self-propelled material spreaders; three or more 10 KW light plants; 30 KW or more generators; power broom.

Group 6: Compressor (one or two) 315 cu ft to 900 cu ft;

pumps 4 inches to 16 inches (total discharge).

Group 7: Compressors up to 315 cu ft; small mixers with skip; pumps up to 4 inches; power heaters; oiler; A-frame trucks; forklifts-up to 7 ft. lift and up to 3 ton capacity; hydro broom; stud welder.

Group 8: Truck crane crews Group 9: Oiler Group 10: Master Mechanic Group 11: Boom lengths over 150 feet including jib Group 12: Boom lengths over 200 feet including jib Group 13: Boom lengths over 250 feet including jib Group 14: Boom lengths over 300 feet including jib Group 15: Boom lengths over 350 feet including jib

IRON0007-014 03/16/2020

BERKSHIRE (Becket, East Otis, Hinsdale, Monterey, New Marlboro, North Otis, Otis, Peru, Sandisfield, Savoy, Sheffield, Washington, Windsor); FRANKLIN; HAMPDEN; HAMPSHIRE

IRONWORKER.......................$ 35.33 30.01

IRON0012-003 07/01/2020

BERKSHIRE (Lee)

Rates Fringes

IRONWORKER.......................$ 32.10 25.48

IRON0012-004 07/01/2020

BERKSHIRE (Remainder of County)

Rates Fringes

Ironworkers:

Sheeter.....................$ 32.35 25.48 Structural, Ornamental, Reinforcing, Fence Erector, Machinery Mover, Rigger, Rodman, Stone Derrickman..................$ 32.10 25.48

LABO0014-004 12/01/2017

BERKSHIRE COUNTY

FRANKLIN COUNTY (the towns of Ashfield, Buckland, Charlemont, Hawley, Heath, and Rowe only) HAMPSHIRE COUNTY (the towns of Chesterfield, Cummington, Goshen, Middlefield, Plainfield, and

Worthington only)

Plasterer tender.................$ 26.10 20.90

LABO0014-005 12/01/2017

HAMPDEN COUNTY

HAMPSHIRE COUNTY (with the exception of Chesterfield, Cummington, Goshen, Middlefield, Plainfield, and Worthington) FRANKLIN COUNTY (with the exception of Ashfield, Buckland, Charlemont, Hauley, Heath, Orange, Rowe, and Warwick)

Plasterer tender.................$ 30.60 21.91

LABO0022-002 06/01/2020

FRANKLIN (Orange, Warwick)

Rates Fringes

Laborers:

GROUP 1.....................$ 34.06 25.72

GROUP 2.....................$ 34.31 25.72

GROUP 3.....................$ 34.81 25.72

GROUP 4.....................$ 35.06 25.72

GROUP 5.....................$ 34.31 25.72

GROUP 6.....................$ 34.25 22.92

LABORERS CLASSIFICATIONS

GROUP 1: Laborers; carpenter tenders; cement finisher tenders, plasterer tenders

GROUP 2: Asphalt raker; fence and guard rail erector; laser beam operator; mason tenmder; pipelayer; pneumatic drill operator; pneumatic tool operator; wagon drill operatorm jackhammer operator, pavement breaker, carbide core drilling machine, chain saw operator, barco type jumping tampers, concrete pump, motorized mortar miner, ride-on motorized buggy

GROUP 3: Air track operator; block paver; rammer; curb setter, hydraulic and similar self-powered drills

GROUP 4: Blaster; powderman

GROUP 5: Precast floor and roof, plank erector

GROUP 6: Asbestos Abatement, Toxic and Hazardous waste laborers

LABO0473-001 06/01/2018

BERKSHIRE COUNTY, FRANKLIN COUNTY, (THE TOWNS OF ASHFIELD,

BUCKLAND, CHARLEMONT, HAWLEY, HEATH, AND ROWE ONLY) HAMPSHIRE

COUNTY (THE TOWNS OF CHESTERFIELD, CUMMINGTON, GOSHEN,

MIDDLEFIELD, PLAINFIELD, AND WORTHINGTON ONLY)

Laborers:........................$ 26.40 20.75

LABO0596-001 06/04/2018

HAMPDEN COUNTY, HAMPSHIRE COUNTY (WITH THE EXCEPTION OF

CHESTERFIELD, CUMMINNGTON, GOSHEN, MIDDLEFIELD, PLAINFIELD, AND

WORTHINGTON) FRANKLIN COUNTY (WITH THE EXCEPTION OF ASHFIELD,

BUCKLAND, CHARLEMONT, HAULY, HEATH, ORANGE,ROWE AND WARWICK)

Laborers:

GROUP 1.....................$ 31.00 22.19

GROUP 2.....................$ 31.25 22.19

GROUP 3.....................$ 31.75 22.19

GROUP 4.....................$ 31.75 22.19

GROUP 5.....................$ 32.00 22.19

LABORERS CLASSIFICATIONS

GROUP 1: Laborers, carpenter tenders, wrecking laborers

GROUP 2: Asphalt rakers, carbide core driller operators, chain saw operators, pipelayers, jackhammer and paving breaker operators, Barco type jumping tampers, laser beam operators, concrete pump operators, mason tenders, motorized mortar mixers, ride-on motorized buggy operators, wagon drill operators

GROUP 3: precast floor and roof plank erectors, sign erectors, asbestos removal laborers, haz-mat laborers

GROUP 4: Air track operators, block pavers, rammers and curb setters, hydraulic and similar self-powered drills

GROUP 5: Powderman and blaster

MARB0097-001 03/01/2012

MARBLE FINISHER..................$ 28.43 25.85

PAIN0011-008 06/01/2020

Rates Fringes

GLAZIER..........................$ 39.18 22.55+A

FOOTNOTE:

A. PAID HOLIDAY: LABOR DAY (provided employee has worked any part of the week prior to Labor Day and any part of the week after Labor Day

PAIN0035-007 07/01/2019

Rates Fringes

PAINTER

NEW CONSTRUCTION:

Brush, Taper...............$ 32.33 26.35 Spray, Sandblast...........$ 34.03 27.00

REPAINT:

Brush, Taper...............$ 29.65 26.35 Spray, Sandblast...........$ 31.35 27.00

* PLUM0004-003 03/01/2021

FRANKLIN (Orange)

Rates Fringes

Plumber and Steamfitter..........$ 47.85 26.92

* PLUM0104-004 03/17/2021

BERKSHIRE (Becket, Otis, Sandisfield); FRANKLIN (Except Monroe, Rowe, and the Western part of Charlemont); HAMPDEN; HAMPSHIRE

Plumbers and Pipefitters.........$ 43.21 26.90

FOOTNOTE:

A. Two paid holidays, Independence Day and Labor Day, provided the employee has been employed seven days prior to the holiday by the same employer

* PLUM0104-009 03/17/2021

BERKSHIRE (Except Otis, Becket, Sandisfield); FRANKLIN (Monroe, Rowe and the Western part of Charlemont)

Plumber and Steamfitter..........$ 43.21 26.90

FOOTNOTE FOR PLUMBERS & STEAMFITTERS:

A. Paid holidays: Independence Day and Labor Day, provided the employee has been employed seven days prior to the holiday by the same employer.

ROOF0248-001 07/16/2020

All tear-off and/or removal (of any types of roofing), and all spudding, sweeping, vacuuming and/or cleanup of any and all areas of any type where a roof is to be relaid.

Roofers:

Composition Roofers & Damp Waterproofers...............$ 33.16 28.30 Pitch,Slate, Tile and Precast Concrete............$ 33.66 28.80

* SFMA0550-003 03/01/2021

Rates Fringes

SPRINKLER FITTER.................$ 56.21 31.35

a. PAID HOLIDAYS: Memorial Day, July 4th, Labor Day, Thanksgiving Day and Christmas Day, provided the employee has been in the employment of a contractor 20 working days prior to any such paid holidays.

SHEE0063-001 01/01/2020

Rates Fringes

Sheet metal worker...............$ 35.49 31.04

TEAM0379-001 08/01/2020

Rates Fringes

Truck drivers:

Group 1.....................$ 34.98 26.6325+A+B Group 2.....................$ 35.15 26.6325+A+B Group 3.....................$ 35.22 26.6325+A+B Group 4.....................$ 34.44 26.6325+A+B Group 5.....................$ 35.44 26.6325+A+B

Group 6.....................$ 35.73 26.6325+A+B Group 7.....................$ 36.02 26.6325+A+B

POWER TRUCKS $.25 DIFFERENTIAL BY AXLE

TUNNEL WORK (UNDERGROUND ONLY) $.40 DIFFERENTIAL BY AXLE

HAZARDOUS MATERIALS (IN HOT ZONE ONLY) $2.00 PREMIUM

TRUCK DRIVERS CLASSIFICATIONS

Group 1: Station wagons; panel trucks; and pickup trucks

Group 2: Two axle equipment; & forklift operator

Group 3: Three axle equipment and tireman

Group 4: Four and Five Axle equipment

Group 5: Specialized earth moving equipment under 35 tons other than conventional type trucks; low bed; vachual;

mechanics, paving restoration equipment

Group 6: Specialized earth moving equipment over 35 tons

Group 7: Trailers for earth moving equipment (double hookup)

FOOTNOTES:

A. PAID HOLIDAYS: New Year's Day, Washington's Birthday, Memorial Day, Independence Day, Labor Day, Patriot's Day, Columbus Day, Veteran's Day, Thanksgiving Day and Christmas Day

B. PAID VACATION: Employees with 4 months to 1 year of service receive 1/2 day's pay per month; 1 week vacation for 1 - 5 years of service; 2 weeks vacation for 5 - 10 years of service; and 3 weeks vacation for more than 10 years of service

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.

Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of ""identifiers"" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).

Union Rate Identifiers

A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than ""SU"" or ""UAVG"" denotes that the union classification and rate were prevailing for that classification in the survey. Example:

PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.

Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.

Survey Rate Identifiers

Classifications listed under the ""SU"" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.

Survey wage rates are not updated and remain in effect until a new survey is conducted.