SEE ADDENDUM
(No Collect Calls)
W912EQ21T0026 06-Aug-2021
b. TELEPHONE NUMBER
901-544-3710
8. OFFER DUE DATE/LOCAL TIME
10:00 AM 26 Aug 2021
5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
STANDARD FORM 1449 (REV. 2/2012)
Prescribed by GSA – FAR (48 CFR) 53.212
(TYPE OR PRINT)
(SIGNATURE OF CONTRACTING OFFICER)
ADDENDA X ARE
26. TOTAL AWARD AMOUNT (For Gov t. Use Only )
23.
CODE 10. THIS ACQUISITION IS
SUCH ADDRESS IN OFFER
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT
BELOW IS CHECKED
TELEPHONE NO.
W912EQ9. ISSUED BY
18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a. UNLESS BLOCK
7. FOR SOLICITATION
INFORMATION CALL:
a. NAME
KIRK A MIDDLETON II
2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NUMBER
(TYPE OR PRINT)
30b. NAME AND TITLE OF SIGNER 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER
30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a.UNITED STATES OF AMERICA
1 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1. 52.212-4. FAR 52.212-3. 52.212-5 ARE ATTACHED.X
25. ACCOUNTING AND APPROPRIATION DATA
1. REQUISITION NUMBER
20.
ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.
OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
W38XGR11053576
ARE NOT ATTACHED
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED
(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE
SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:
. YOUR OFFER ON SOLICITATION
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN
% FOR:SET ASIDE:UNRESTRICTED ORX
SMALL BUSINESS
17a.CONTRACTOR/ CODE FACILITY
OFFEROR CODE
US ARMY ENGINEER DISTRICT, MEMPHIS
KIRK A. MIDDLETON 167 N MAIN ST
MEMPHIS TN 38103-1894
18a. PAYMENT WILL BE MADE BY CODE
RATED ORDER UNDER
DPAS (15 CFR 700)
13a. THIS CONTRACT IS A
13b. RATING
CODE15. DELIVER TO CODE W912EQ 16. ADMINISTERED BY
12. DISCOUNT TERMS11. DELIVERY FOR FOB DESTINA-
TION UNLESS BLOCK IS
MARKED
SEE SCHEDULE
14. METHOD OF SOLICITATION
RFQ IFB RFPX
DA, MEMPHIS DISTRICT, CE
W. G. HUXTABLE PUMPING PLANT
MARIANNA, AR 72360-0269
TEL: FAX:
901-544-3710FAX:
TEL: 901-544-0786 SERVICE-DISABLED
VETERAN-OWNED
SMALL BUSINESS
8(A)
HUBZONE SMALL
BUSINESS
SIZE STANDARD:
$16,500,000
NAICS:
238220
X
OFFER DATED
29. AWARD OF CONTRACT: REF.
DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND
EMAIL:
TEL:
31c. DATE SIGNED
SEE SCHEDULE
SCHEDULE OF SUPPLIES/ SERVICESITEM NO. QUANTITY UNIT UNIT PRICE AMOUNT
24.22.21.19.
WOMEN-OWNED SMALL BUSINESS (WOSB)
ELIGIBLE UNDER THE WOMEN-OWNED
SMALL BUSINESS PROGRAM
EDWOSB
32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
(CONTINUED)
PAGE 2 OF60
ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED: ______________________________________________________
32a. QUANTITY IN COLUMN 21 HAS BEEN
RECEIVED INSPECTED
32b. SIGNATURE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32c. DATE 32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f . TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE
37. CHECK NUMBER
FINALPARTIALCOMPLETE
36. PAYMENT35. AMOUNT VERIFIED
CORRECT FOR
34. VOUCHER NUMBER
FINAL
33. SHIP NUMBER
PARTIAL
38. S/R ACCOUNT NUMBER 39. S/R VOUCHER NUMBER 40. PAID BY
41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT
41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE
42a. RECEIVED BY (Print)
42b. RECEIVED AT (Location)
42c. DATE REC'D (YY/MM/DD) 42d. TOTAL CONTAINERS
STANDARD FORM 1449 (REV. 2/2012) BACK
Prescribed by GSA – FAR (48 CFR) 53.212
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
SEE SCHEDULE
20.
SCHEDULE OF SUPPLIES/ SERVICES
21.
QUANTITY UNIT
22. 23.
UNIT PRICE
24.
AMOUNT
19.
ITEM NO.
W912EQ21T0026
Section B - Supplies or Services and Prices
ARMY CORPS OF ENGINEERS
HUXTABLE PUMPING STATION NEW BOILER INSTALLATION
LEE COUNTY, AR
SECTION B – SUPPLIES OR SERVICES AND PRICE/COSTS
BASE BID: Project to include the installation of one (1) hot water boiler with accessories, inspection and testing, and transportation of the equipment to and from the premises, and site cleanup, all as described in the specifications.
ITEM DESCRIPTION QTY U/I AMOUNT
01 Mobilization and Demobilization 1 LS $______________
02 Install new hot water boiler 1 LS $______________
TOTAL $______________
NOTES
NOTE 1: Any bid price for items indicated above which are unbalanced as to price may be rejected as non-responsive. An unbalanced bid is one which is based on price significantly less than cost for some work and price which is significantly overstated for other work.
Award will be made as a whole to one bidder.
NOTE 2: If a bid or modification to a bid based on unit prices is submitted and provides for a lump sum adjustment to the total estimated cost, the application of the lump sum adjustment to each unit price, including lump sum units, in bid schedule must be stated, or, if it is not stated, the bidder agrees that the lump sum adjustment shall be applied on a pro rata basis to every unit price in the bid schedule.
CLAUSES INCORPORATED BY FULL TEXT
52.237-1 SITE VISIT (APR 1984)
Offerors or quoters are urged and expected to inspect the site where services are to be performed and to satisfy themselves regarding all general and local conditions that may affect the cost of contract performance, to the extent that the information is reasonably obtainable. In no event shall failure to inspect the site constitute grounds for a claim after contract award.
(End of provision)
CONDITIONS AND NOTICES TO OFFERORS
A. REQUEST FOR QUOTE – Copies of the Solicitation are available by INTERNET ACCESS ONLY to the Contract Opportunties website at:
https://beta.sam.gov/
Prospective Offerors should submit technical questions concerning this Request for Quote via email to the Contract Specialist, Kirk A. Middleton II.
PLEASE RETURN QUOTE TO:
kirk.a.middleton@usace.army.mil
B. PLEASE RETURN THE FOLLOWING INFORMATION WITH YOUR QUOTE:
1. SF 1449, Solicitation, Offer and Award (bock 17a) and your signature; name, title;
and date (30a-c)
2. Section B - Schedule of bids/prices
3. Review and submit the required information from clause 52.212-2 in the solicitation.
4. All amendments must be acknowledged.
5. Faxed proposals will not be accepted.
C. OFFEROR’S ADDRESS - Prospective offerors should indicate in the offer, the address to which payment and/or correspondence should be mailed, if such address is different from that shown for the offeror on Standard Form 1449.
D. AMENDMENTS PRIOR TO SOLICITATION CLOSING - The right is reserved as the interest of the Government may require, to revise or amend the specifications prior to the date set for proposals. Such revisions and amendments, if any, will be announced by an amendment or amendments to this Request for Quote. If the revisions and amendments are of a nature which requires material changes in quantities or prices bid or both, the date set for opening quotes may be postponed by such number of days as in the opinion of the issuing officer will enable offerors to revise their proposal. In such cases, the amendment will include an announcement of the new date for proposal response time.
E. REQUIRED SYSTEM FOR AWARD MANAGEMENT REGISTRATION - By submission of a offer, the offeror acknowledges the requirement that a prospective awardee must be registered in the SAM database prior to award, during performance, and through final payment of any contract resulting from this solicitation. Lack of registration in the SAM database will make a bidder ineligible for award. Bidders and contractors may obtain information on registration and annual confirmation requirements by calling 1-866-606-8220, or at: http://www.sam.gov See clause 252.204-7004 Alt A, “System for Award Management”.
F. BASIS OF AWARD – The Government will award a contract resulting from this solicitation to the responsible Offeror whose offer conforming to the solicitation will be most advantageous to the Government.
G. QUESTIONS AND ANSWERS- All questions shall be submitted via email (kirk.a.middleton@usace.army.mil) no later than Wednesday 18 August 2021 by 2:00pm CST.
Section C - Descriptions and Specifications
ARMY CORPS OF ENGINEERS
HUXTABLE PUMPING STATION NEW BOILER INSTALLATION
LEE COUNTY, AR
TABLE OF CONTENTS
SECTION C – WORK STATEMENT/DESCRIPTION/SPECIFICATIONS
C-1 DESCRIPTION OF WORK
C-1.1 GENERAL
C-1.2 DESCRIPTION OF WORK
C-1.3 OBJECTIVES
C.1.4 PLACE OF PERFORMANCE
C.1.5 SECURITY MEASURES
C.1.6 PERIOD OF PERFORMANCE
C.1.7 DELIVERY DESTINATION
C-1.8 NEW BOILER
C-1.9 BOILER CONSTRUCTION
C-1.10 BOILER TRIM
C-1.11 CONTROL PANEL
C-1.12 START-UP SERVICES
C-1.13 QUALITY ASSURANCE
C-2 GOVERNMENT FURNISHED ITEMS AND SERVICES
C-2.1 SERVICES
C-2.2 UTILITIES
C-2.3 EQUIPMENT
C-3 CONTRACTOR FURNISHED ITEMS AND RESPONSIBILITIES
C-3.1 GENERAL
C-3.2 SUBMITTALS
C-3.3 TRAINING
C-3.4 ACCEPTANCE TESTING
C-3.5 COMMERCIAL WARRANTY
C-4.0 OTHER CONTRACTOR REQUIREMENTS
C-4.1 SAFETY RELATED SPECIAL REQUIRMENTS
TECHNICAL EXHIBITS
PERFORMANCE REQUIREMENTS SUMMARY
DELIVERABLES SCHEDULE
ARMY CORPS OF ENGINEERS
HUXTABLE PUMPING STATION NEW BOILER INSTALLATION
LEE COUNTY, AR
SECTION C – SCOPE OF WORK
C-1 DESCRIPTION OF WORK
C-1.1 GENERAL
Work will include the ONSITE disassembly, inspection, and testing. The Contractor shall be responsible for inspection of all components, removal of the existing equipment being modified. The Contractor shall provide transportation to and from Huxtable Pumping Station for the removal and return of all parts. The contractor shall be totally responsible to the Government for any subcontractor on this contract. The Contractor shall also install all new parts to provide fully functional hot water boiler.
C-1.2 DESCRIPTION OF WORK
The work consists of furnishing all plant, labor, materials and equipment to successfully do all the work described herein, and to transport and install one new hot water boiler FM/UL rated with modulating burner with a 2:5:1 turndown with all new pressure rated flue piping, and all in accordance with NFPA 211 and NFPA 31. Contract includes new base mounted centrifugal pumps, expansion tanks of same size and pressure rating as existing boiler system in use. The Contractor shall also clean the inside surfaces of the vertical stack and remove all debris resulting from that operation. The Contractor shall remove the clean-out door assembly in the bottom of stack and weld on a new one so there is no soot allowed to enter into the building. The contractor shall provide, furnish, and install all necessary and appropriate components, items, fasteners, anchors, pads, cables, conduit, mounts, grout or similar incidental items necessary and required to install the new boiler and all other ancillary equipment. Boiler and associated piping shall have the required seismic protection measures to resist lateral forces induced by earthquakes without consideration of friction resulting from gravity loads. Upon completion, the boiler shall perform to the standards and rates specified by the manufacturer. The boiler shall be tuned and tested to insure it is firing at the proper fuel/air ratio. New equipment shall come with at minimum a standard 1 year warranty. Contractor shall provide all labor, parts and tools for this project. All work shall conform to local, state, and federal codes. The Contractor shall inspect existing conditions before submitting a proposal.
The following is a list of requirements for the installation and testing of the new boiler. The work required under this contract may include, but is not limited to, the following items/activities.
New water tube boiler with power flame modulating burner Provide and install two (2) base mounted centrifugal pumps with triple duty valves, stainless steel flex connections, gauges, 2hp starters with base mounting pad included.
New boiler will be installed on the main operating floor.
C-1.3 OBJECTIVES
This statement of work requires a contractor to complete the work described in the description of work and Scope in accordance with the contract requirement. The boiler shall be 100% mission capable once all work has been completed.
C-1.4 PLACE OF PERFORMANCE
The work will be performed at the Huxtable Pumping Plant, located on the St. Francis River near Marianna, Arkansas.
C-1.5 SECURITY MEASURES
All contractor's and all associated sub‐contractor's employees shall comply with applicable District and facility access and local security policies and procedures (provided by government representative). Contractor workforce must comply with all personal identity verification requirements as directed by DOD, HQDA and/or local policy.
Should the Force Protection Condition (FPCON) at the facility change, the Government may require changes in contractor security matters or processes. The Contractor must pre‐screen Candidates using the E‐verify Program (http://www.dhs.gov/E‐Verify ) website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to ensure the correct information is entered into the E‐verify system. An initial list of verified/eligible Candidates must be provided to the COR no later than 3 business days after the initial contract award. All contract employees, including subcontractor employees who are not in possession of the appropriate security clearance or access privileges, will be escorted in areas where they may be exposed to classified and/or sensitive materials and/or sensitive or restricted areas.
C-1.6 PERIOD OF PERFORMANCE
Within 10 days of contract award, the Contractor shall submit a proposed production schedule for Contracting Officer approval. Approval by the Contracting Officer of the schedule is necessary to begin work. The Contractor shall begin work NLT 10 calendar days after approval of the schedule. Contractor shall make delivery of equipment within the schedule submitted by the Contractor. The Contractor shall install all equipment in accordance with the submitted shop drawings. The Contractor shall provide sufficient manpower to effectively install and test all supplied equipment and shall be finished and demobilized by the time specified. All work shall be complete and ready for use no later than 90 calendar days after the date of receipt of Notice to Proceed (NTP). The stated time for completion shall include final cleanup of the premises. The Contractor Normal business hours at Huxtable are 0700 -1800 Monday through Thursday. Contractor hours may be adjusted. If alternate hours are requested, this must be agreed upon by Government’s Technical Representative or the Contracting Officer’s Representative (COR), if appointed, and contractor. A pre-work conference is mandatory. The Contracting Officer’s notification will include specific details regarding the date, time, and location of the conference and the information regarding the items to be discussed.
C-1.7 DELIVERY DESTINATION
All materials and equipment to be delivered Freight-On-Board (F.O.B.) destination to the Memphis District, W.G.
Huxtable Pumping Plant. The Contractor shall notify the Contracting Officer at least five days in advance of any shipment to be made under this contract, and on the date of shipment, a copy of the bill of lading and packing list will be forwarded addressed as follows:
U.S. Army Engineer District, Memphis W.G. Huxtable Pumping Plant P.O. Box 269 Marianna, AR 72360-0269
C-1.8 NEW BOILER
C-1.8.1 Furnish a low pressure, hot water, wet-base, cast-iron, sectional boiler with power burner that pressurizes the firebox and operates under forced and balanced draft.
C-1.8.2 Burner shall be capable of burning No. 2 fuel oil. Burner shall have provisions for connecting to the existing outside air intake duct and the existing vertical stack.
C-1.8.3 Boiler-burner unit shall be fully packaged and fire tested.
C-1.8.4 Boiler shall have minimum I=B=R Hydronics Institute net output, at 100% firing rate, of 1,712 MBH.
Efficiency shall be a minimum of 81.5%.
C-1.8.6 Boiler shall be furnished complete with all trim, all necessary controls and sensors, and full control panel.
C-1.8.7 New Flue Pipe to dual wall with 1” air gap, pressure rated. Flue pipe shall have 304 or 316 stainless steel inner pipe with outer casing being an aluminized 304 or 316 stainless steel. The flue pipe shall utilize a high temperature silicone sealant for quick installation and good sealing performance. The flue from boiler shall be 12” minimum and the horizontal flue from boiler to stack shall be 14” minimum.
C-1.8.8 The new bladder type expansion tank and associated piping shall be installed.
C-1.8.9 Boiler and piping shall be installed with the required seismic protection measures consistent with Risk Category II, Site Class D – Stiff Soil, and in accordance with the applicable ACI, AISC, ASCE, ICC, UFC, and MFMA standards
C-1.9 BOILER CONSTRUCTION
C-1.9.1 Boiler shall be of heavy duty steel frame, built and stamped in accordance with the appropriate ASME boiler code.
C-1.9.2 Sections to be cast with sealing grooves for high temperature sealing rope to assure permanent gas-tight seal.
C-1.9.3 Sections shall be sealed watertight by elastomer sealing rings, not cast iron nipples. Each port opening shall be machined to completely capture sealing ring between sections.
C-1.9.4 Boiler must be hydro-wall construction to provide completely water-cooled combustion chamber.
C-1.9.5 Boiler shall be provided with sufficient tappings to install required controls.
C-1.9.6 Boiler shall be provided with cast-in air elimination to separate air from circulating water.
C-1.9.7 Boiler shall be provided with expansion tank tapping to divert separated air to expansion tank.
C-1.9.8 Boiler shall be constructed to provide balanced water flow through the entire section assembly using single supply and return connections for water. No external headers will be required for water.
C-1.9.9 Boiler shall be furnished with insulated burner mounting plate and burner. High temperature sealing rope shall be used to provide permanent gas tight seal between front section and plate.
C-1.9.10 Boiler shall be furnished with two observation ports (one in front and one in back) to allow visual inspection of the flame.
C-1.9.11 Boiler shall be furnished with cast iron flue collar with a built-in adjustable damper capable of being locked into place after adjustment.
C-1.9.12 Boiler shall have high temperature sealing rope used to provide permanent gas-tight seal between hood and section assembly.
C-1.9.13 Boiler shall be furnished with heavy gauge steel cleanout plates to cover cleanout openings on the side of the boiler.
C-1.9.14 Port openings shall be of captured seal design – a machined groove assures uniform compression of the sealing ring and protects the seal from contaminants. Elastomer sealing rings shall be used to provide permanent watertight seal between sections.
C-1.10 BOILER TRIM
C-1.10.1 All electrical components shall be of high quality and bear the U.L. label.
C-1.10.2 Water boiler shall be furnished with following controls:
o ASME Relief Valve, set to relieve at 30 psig o High Limit Control o U.L. labeled probe LWCO with ASME working pressure rating equal to the ASME rating of the relief valve. Locate so burner shuts down if boiler water level falls below allowable safe waterline.
o Water Temp Control o Oil Pressure Gauge & Oil Y strainer o Flow Switch Mounted & Wired o Stack Thermometer o Low Fired Hold Switch o Sealed Combination Air Intake o Automatic Air Vent o Double wall flue vent with support plate elbows, insulated thimble, full angle ring, wall support, rain cap
Low temperature limit set according to system design. High temperature limit set at least 20 degrees F higher than the low limit.
C-1.11 CONTROL PANEL
C-1.11.1 Boiler shall be furnished with electronic control panel suitable for maintaining proper start-up and operating procedure.
C-1.11.2 Panel shall be furnished with following features:
C-1.11.2.1 Power on/fuel on light.
C-1.11.2.2 Call for heat.
C-1.11.2.3 Ignition On.
C-1.11.2.4 Pilot Failure.
C-1.11.2.5 Low Water.
C-1.11.2.6 Flame Failure.
C-1.11.2.7 Silencing Switch.
C-1.11.2.8 Control Fuse and Holder.
C-1.11.2.9 Post Purge Timer.
C-1.11.2.10 Alarm Bell.
C-1.12 START-UP SERVICES
C-1.12.1 The Contractor shall obtain the services of a factory-authorized agent to provide burner light-off and adjustment. The start-up agent shall provide a burner light-off report as written proof that the burner was adjusted to optimum performance.
C-1.12.2 The Contractor shall provide a one-year service warranty beginning at start-up.
C-1.12.3 The Contractor shall be responsible for connecting up all control wiring prior to start-up. The Contractor shall make sure all controls and safety devices are working properly.
C-1.13 QUALITY ASSURANCE
Before commencement of work, the Contractor shall submit to the Contracting Officer, for approval, the quality control system he proposes to use, before commencement of work under this contract. The government shall evaluate the contractor’s performance under this contract in accordance with the Quality Assurance Plan. This plan is primarily focused on what the Government must do to ensure that the contractor has performed the work in an acceptable manner.
C-2 GOVERNMENT FURNISHED ITEMS AND SERVICES
C-2.1 SERVICES
C-2.1.1 The Government will provide the electrical connections from the boiler to the main power panel in the station. At project completion, the Contractor and the Plant Superintendent will make a joint visual inspection of the project and needed repairs noted shall be identified. The contractor shall be responsible for the repair of any noted damages related to the contract performance and will make needed repairs immediately and at no additional cost to the Government.
C-2.1.2 The Government will remove the existing chimney between ELEV 180.0 and ELEV 212.2 to allow for routing of new water lines.
C-2.2 UTILITIES
The Government will provide reasonable utilities at its discretion.
C-2.3 EQUIPMENT
The Government will provide the use of the station’s 50 ton bridge crane for installation of equipment.
C-3 CONTRACTOR FURNISHED ITEMS AND RESPONSIBILITIES
C-3.1 GENERAL
Contractor is to provide all labor and material for the entire scope of work. The contractor is to provide an on-site supervisor at the job site for the duration of the contract. The contractor shall be responsible for damages and repairs to any Corps of Engineers equipment caused by the contractor’s action.
C-3.2 SUBMITTALS
Installation details and equipment cut-sheets, including boiler and burner ratings, shall be submitted for prior approval by the Government Technical Representative. All operation and maintenance manuals shall be furnished prior to closure of contract. Burner and Energy Management Control System must be tested and approved for installation with specified boiler, by the manufacturer.
C-3.3 TRAINING
The Contractor must conduct a formal training course for operating staff, as designated by the Contracting Officer.
The training period, of at least 8 hours of normal working time, shall start after the system is functionally completed, but prior to final acceptance tests. The field instructions shall cover all of the items contained in the operating and maintenance instructions, as well as a demonstration of routine maintenance operations. The Contractor shall be notified at least 14 days prior to the date of proposed conduction of training course.
C-3.4 ACCEPTANCE TESTING
Upon completion, and prior to acceptance of the project, the entire boiler, blower, and control equipment shall be tested in accordance with manufacturer’s codes and standards, by the Contractor, to demonstrate indicated performance. The fuel/air mixture shall be adjusted to give optimum combustion. The Contracting Officer shall be notified 10 days in advance of the test date. If any deficiencies are revealed during testing, such deficiencies shall be corrected and the tests re-conducted at no additional cost to the Government.
C-3.5 COMMERCIAL WARRANTY
The Contractor agrees that the equipment furnished under this contract shall be covered by the most favorable commercial warranty the Contractor gives to any customer for such products and that the rights and remedies provided herein are in addition to and do not limit any rights afforded to the Government by any other clause of this contract. The warranty will take effect immediately upon the day of acceptance, by the Government, of the completed work.
C-4.0 OTHER CONTRACTOR REQUIREMENTS
C-4.1 SAFETY RELATED SPECIAL REQUIRMENTS
ALL WORK UNDER THIS CONTRACT SHALL COMPLY WITH THE LATEST VERSION OF U.S.
ARMY CORPS OF ENGINEERS SAFETY AND HEALTH REQUIREMENTS MANUAL, EM 385-1-1, AND
OCCUPATIONAL SAFETY AND HEALTH ACT (OSHA) STANDARDS IN EFFECT ON THE DATE OF THE
SOLICITATION. THE MANUAL CAN BE ACCESSED AT THE FOLLOWING LINK.
HTTP://WWW.USACE.ARMY.MIL/SAFETYANDOCCUPATIONALHEALTH.ASPX. NO SEPARATE
PAYMENT WILL BE MADE FOR COMPLIANCE WITH THE EM 385-1-1, NOR FOR COMPLIANCE WITH
ANY OF THE OTHER SAFETY-RELATED SPECIAL REQUIREMENTS.
TECHNICAL EXHIBITS
PERFORMANCE REQUIREMENTS SUMMARY
The contractor service requirements are summarized into performance objectives that relate directly to mission essential items. The performance threshold briefly describes the minimum acceptable levels of service required for each requirement. These thresholds are critical to mission success.
Performance Objective Standard Performance Threshold / Acceptable Quality Level
(AQL)
Method of Surveillance
PRS # 1
Contractor shall install one new boiler with water, electrica,l and diesel fuel hook-ups, breeching and intake duct connections.
Installation of new boiler and accessories shall be 100 percent mission capable and perform to or nearly to the original specifications.
Full Government Acceptance
100 % Inspection
PRS # 2
Contractor shall complete performance within 90 days of Notice To Proceed.
Contractor shall inform customer of possible problems that would delay performance as soon as possible.
Not more than 1 failure during contract period
Periodic Surveillance
PRS # 3
Contractor shall receive Contracting Officer’s approval for any changes in scope and price in advance of performance
Contractor shall not proceed with changes or modifications of the contract without the Contracting Officer’s approval
No deviations allowed
Random Inspections
DELIVERABLES SCHEDULE
This technical exhibit lists any reports or documentation that is required as a deliverable to include the frequency, # of copies, medium/format and who/where it is to be submitted. A deliverable is anything that can be physically delivered but may include non-physical things such as meeting minutes.
Deliverable Frequency # of Copies Medium/Format Submit To Fully installed and functioning boiler with accessories and incidentals as outlined in PWS.
Upon completion N/A N/A N/A
New boiler performance test
Upon Completion Two (2) Not specified COR/Government Technical Representative
Design Data and Operation and Maintenance Instructions
Upon completion Two (2) Not specified COR/Government Technical Representative
Section E - Inspection and Acceptance
CLAUSES INCORPORATED BY FULL TEXT
52.246-4 INSPECTION OF SERVICES--FIXED-PRICE (AUG 1996)
(a) Definitions. "Services," as used in this clause, includes services performed, workmanship, and material furnished or utilized in the performance of services.
(b) The Contractor shall provide and maintain an inspection system acceptable to the Government covering the services under this contract. Complete records of all inspection work performed by the Contractor shall be maintained and made available to the Government during contract performance and for as long afterwards as the contract requires.
(c) The Government has the right to inspect and test all services called for by the contract, to the extent practicable at all times and places during the term of the contract. The Government shall perform inspections and tests in a manner that will not unduly delay the work.
(d) If the Government performs inspections or tests on the premises of the Contractor or a subcontractor, the Contractor shall furnish, and shall require subcontractors to furnish, at no increase in contract price, all reasonable facilities and assistance for the safe and convenient performance of these duties.
(e) If any of the services do not conform with contract requirements, the Government may require the Contractor to perform the services again in conformity with contract requirements, at no increase in contract amount. When the defects in services cannot be corrected by reperformance, the Government may (1) require the Contractor to take necessary action to ensure that future performance conforms to contract requirements and (2) reduce the contract price to reflect the reduced value of the services performed.
(f) If the Contractor fails to promptly perform the services again or to take the necessary action to ensure future performance in conformity with contract requirements, the Government may (1) by contract or otherwise, perform the services and charge to the Contractor any cost incurred by the Government that is directly related to the performance of such service or (2) terminate the contract for default.
(End of clause)
Section G - Contract Administration Data
0010 CONTRACTING OFFICER AUTHORITY
Only a warranted Contracting Officer (either a Procuring Contracting Officer (PCO), or an Administrative Contracting Officer (ACO)), acting within their delegated limits, has the authority to issue modifications or otherwise change the terms and conditions of this contract. If an individual other than the Contracting Officer attempts to make changes to the terms and conditions of this contract you shall not proceed with the change and shall immediately notify the Contracting Officer.
0020 CUSTOMER INSTRUCTIONS
The customer is responsible for forwarding proof of delivery (SF 1449/DD FORM 1155 or DD 250 or electronic equivalent) signed by a government official to the address located in block 18a.
Failure to do so may cause a delay in payment to the contractor. If any items delivered are not in accordance with the contract or purchase order, notify the contracting officer in writing.
0030 CONTRACTING OFFICE E-MAIL ADDRESS/PHONE/FAX NUMBER(S)
kirk.a.middleton@usace.army.mil – 901-544-0786 (PH) - Contract Specialist Monica.A.Moody@usace.army.mil 901-544-0838 (PH) – Contracting Officer
0040 CONTRACT ADMINISTRATION
All contract inquiries, after award of this contract, shall be directed to the Contracting Officer:
NAME: Kirk Middleton II LOCATION: 167 North Main, Rm A-665
TELEPHONE NO.: 901-544-0786
E-MAIL ADDRESS: kirk.a.middleton@usace.army.mil
b. The authorized representatives of the Government during the performance period are as follows:
(1) The Contracting Officer’s Representative (COR) will be designated, by letter of appointment, by the Contracting Officer and will represent the Contracting Officer in the technical phases of the work, but will not be authorized to change any of the terms and conditions of the contract.
The COR is responsible for monitoring performance and the technical management of the effort required hereunder, and should be contacted regarding questions or problems of a technical nature.
(2) The designated Contract Specialist will be the Administrative Contracting Officer's representative on all other contract administrative matters. The Contract Specialist should be contacted regarding all matters pertaining to the contract or task orders.
0060 BLOCK 18a OF SF 1449, PAYMENT WILL BE MADE BY:
USACE FINANCE CENTER
5722 INTEGRITY DRIVE
BLDG S-787
MILLINGTON TN 38054-5005
0070 BLOCK 18b OF SF 1449, SUBMIT INVOICES:
DESIGNATED BILLING OFFICE:
USACE FINANCE CENTER
5722 INTEGRITY DRIVE
BLDG S-787
MILLINGTON TN 38054-5005
CEFC.B1invoices@usace.army.mil
AND
USING ACTIVITY
US ARMY ENGINEER DISTRICT, MEMPHIS
Huxtable Pumping Plant
P.O. Box 269 Marianna, AR 72360 POC: Marsalis Roddy
PHONE: (901) 544-4229
Marsalis.A.Roddy@usace.army.mil
TO EXPEDITE PAYMENT (Preferred): Please email your invoice to:
CEFC.B1invoices@usace.army.mil (Designated Billing Office)
Invoice(s) must include:
(1) Name and address of the Contractor;
(2) Invoice date;
(3) Contract number, contract line item number and, if applicable, the order number;
(4) Description, quantity, unit of measure, unit price and extended price of the items delivered;
(5) Shipping number and date of shipment including the bill of lading number and weight of shipment if shipped on Government bill of lading;
(6) Terms of any prompt payment discount offered;
(7) Name and address of official to whom payment is to be sent; and
(8) Name, title, and phone number of person to be notified in event of defective invoice.
Failure to mail/email your invoice(s) to the above addresses or to provide all responsive information may delay payment.
Section H - Special Contract Requirements
WAGE DETERMINATION
"REGISTER OF WAGE DETERMINATIONS UNDER | U.S. DEPARTMENT OF LABOR
THE SERVICE CONTRACT ACT | EMPLOYMENT STANDARDS ADMINISTRATION
By direction of the Secretary of Labor | WAGE AND HOUR DIVISION
| WASHINGTON D.C. 20210
| Wage Determination No.: 2015-5127
Daniel W. Simms Division of | Revision No.: 16 Director Wage Determinations| Date Of Last Revision: 07/21/2021 Note: Under Executive Order (EO) 13658 an hourly minimum wage of $10.95 for calendar year 2021 applies to all contracts subject to the Service Contract Act for which the contract is awarded (and any solicitation was issued) on or after January 1 2015. If this contract is covered by the EO the contractor must pay all workers in any classification listed on this wage determination at least $10.95 per hour (or the applicable wage rate listed on this wage determination if it is higher) for all hours spent performing on the contract in calendar year 2021. The EO minimum wage rate will be adjusted annually.
Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.
State: Arkansas
Area: Arkansas County of Phillips
**Fringe Benefits Required Follow the Occupational Listing**
OCCUPATION CODE - TITLE FOOTNOTE RATE
01000 - Administrative Support And Clerical Occupations 01011 - Accounting Clerk I 13.60 01012 - Accounting Clerk II 15.27 01013 - Accounting Clerk III 17.08 01020 - Administrative Assistant 23.12 01035 - Court Reporter 14.97 01041 - Customer Service Representative I 12.67 01042 - Customer Service Representative II 14.25 01043 - Customer Service Representative III 15.54 01051 - Data Entry Operator I 12.63 01052 - Data Entry Operator II 13.78 01060 - Dispatcher Motor Vehicle 17.38 01070 - Document Preparation Clerk 11.92 01090 - Duplicating Machine Operator 11.92 01111 - General Clerk I 13.34 01112 - General Clerk II 14.56 01113 - General Clerk III 16.35 01120 - Housing Referral Assistant 16.69 01141 - Messenger Courier 9.72 01191 - Order Clerk I 10.92 01192 - Order Clerk II 11.92
01261 - Personnel Assistant (Employment) I 13.39 01262 - Personnel Assistant (Employment) II 14.97 01263 - Personnel Assistant (Employment) III 16.69 01270 - Production Control Clerk 23.56 01290 - Rental Clerk 11.50 01300 - Scheduler Maintenance 13.39 01311 - Secretary I 13.39 01312 - Secretary II 14.97 01313 - Secretary III 16.69 01320 - Service Order Dispatcher 16.45 01410 - Supply Technician 23.12 01420 - Survey Worker 12.77 01460 - Switchboard Operator/Receptionist 12.49 01531 - Travel Clerk I 14.02 01532 - Travel Clerk II 15.00 01533 - Travel Clerk III 16.08 01611 - Word Processor I 11.92 01612 - Word Processor II 13.39 01613 - Word Processor III 14.97
05000 - Automotive Service Occupations 05005 - Automobile Body Repairer Fiberglass 18.85 05010 - Automotive Electrician 18.09 05040 - Automotive Glass Installer 16.14 05070 - Automotive Worker 16.14 05110 - Mobile Equipment Servicer 14.55 05130 - Motor Equipment Metal Mechanic 18.09 05160 - Motor Equipment Metal Worker 16.14 05190 - Motor Vehicle Mechanic 18.09 05220 - Motor Vehicle Mechanic Helper 13.31 05250 - Motor Vehicle Upholstery Worker 16.14 05280 - Motor Vehicle Wrecker 16.14 05310 - Painter Automotive 17.15 05340 - Radiator Repair Specialist 16.14 05370 - Tire Repairer 12.37 05400 - Transmission Repair Specialist 18.09
07000 - Food Preparation And Service Occupations 07010 - Baker 17.36 07041 - Cook I 12.17 07042 - Cook II 13.96 07070 - Dishwasher 10.01 07130 - Food Service Worker 10.28 07210 - Meat Cutter 16.73 07260 - Waiter/Waitress 10.12
09000 - Furniture Maintenance And Repair Occupations 09010 - Electrostatic Spray Painter 18.56 09040 - Furniture Handler 12.01 09080 - Furniture Refinisher 18.56 09090 - Furniture Refinisher Helper 14.00 09110 - Furniture Repairer Minor 16.21 09130 - Upholsterer 18.56
11000 - General Services And Support Occupations 11030 - Cleaner Vehicles 12.96 11060 - Elevator Operator 12.68 11090 - Gardener 15.28 11122 - Housekeeping Aide 10.88 11150 - Janitor 10.88 11210 - Laborer Grounds Maintenance 11.61 11240 - Maid or Houseman 10.70 11260 - Pruner 10.46 11270 - Tractor Operator 14.10 11330 - Trail Maintenance Worker 11.61 11360 - Window Cleaner 12.08
12000 - Health Occupations 12010 - Ambulance Driver 17.23 12011 - Breath Alcohol Technician 18.29 12012 - Certified Occupational Therapist Assistant 28.19 12015 - Certified Physical Therapist Assistant 26.97 12020 - Dental Assistant 17.25 12025 - Dental Hygienist 35.20 12030 - EKG Technician 27.72 12035 - Electroneurodiagnostic Technologist 27.72 12040 - Emergency Medical Technician 17.23 12071 - Licensed Practical Nurse I 16.36 12072 - Licensed Practical Nurse II 18.29 12073 - Licensed Practical Nurse III 20.39 12100 - Medical Assistant 13.59 12130 - Medical Laboratory Technician 22.47 12160 - Medical Record Clerk 13.95 12190 - Medical Record Technician 17.28 12195 - Medical Transcriptionist 16.36 12210 - Nuclear Medicine Technologist 40.20 12221 - Nursing Assistant I 12.02 12222 - Nursing Assistant II 13.51 12223 - Nursing Assistant III 14.74 12224 - Nursing Assistant IV 16.56 12235 - Optical Dispenser 18.29 12236 - Optical Technician 16.36 12250 - Pharmacy Technician 15.04 12280 - Phlebotomist 16.36 12305 - Radiologic Technologist 23.21 12311 - Registered Nurse I 22.42 12312 - Registered Nurse II 27.42 12313 - Registered Nurse II Specialist 27.42 12314 - Registered Nurse III 33.18 12315 - Registered Nurse III Anesthetist 33.18 12316 - Registered Nurse IV 39.76 12317 - Scheduler (Drug and Alcohol Testing) 22.66 12320 - Substance Abuse Treatment Counselor 28.83
13000 - Information And Arts Occupations 13011 - Exhibits Specialist I 17.79 13012 - Exhibits Specialist II 20.96 13013 - Exhibits Specialist III 26.91 13041 - Illustrator I 17.79 13042 - Illustrator II 20.96 13043 - Illustrator III 26.91 13047 - Librarian 24.38 13050 - Library Aide/Clerk 14.16 13054 - Library Information Technology Systems 22.02 Administrator 13058 - Library Technician 15.73 13061 - Media Specialist I 15.88 13062 - Media Specialist II 17.76 13063 - Media Specialist III 19.81 13071 - Photographer I 14.95 13072 - Photographer II 17.79 13073 - Photographer III 21.05 13074 - Photographer IV 26.94 13075 - Photographer V 30.67 13090 - Technical Order Library Clerk 15.49 13110 - Video Teleconference Technician 15.88
14000 - Information Technology Occupations 14041 - Computer Operator I 11.80 14042 - Computer Operator II 13.20 14043 - Computer Operator III 14.72
14044 - Computer Operator IV 19.77 14045 - Computer Operator V 21.45 14071 - Computer Programmer I (see 1) 17.96 14072 - Computer Programmer II (see 1) 22.24 14073 - Computer Programmer III (see 1) 26.41 14074 - Computer Programmer IV (see 1) 14101 - Computer Systems Analyst I (see 1) 26.83 14102 - Computer Systems Analyst II (see 1) 14103 - Computer Systems Analyst III (see 1) 14150 - Peripheral Equipment Operator 11.80 14160 - Personal Computer Support Technician 21.75 14170 - System Support Specialist 21.45
15000 - Instructional Occupations 15010 - Aircrew Training Devices Instructor (Non-Rated) 24.09 15020 - Aircrew Training Devices Instructor (Rated) 29.15 15030 - Air Crew Training Devices Instructor (Pilot) 34.94 15050 - Computer Based Training Specialist / Instructor 24.39 15060 - Educational Technologist 27.71 15070 - Flight Instructor (Pilot) 34.94 15080 - Graphic Artist 24.95 15085 - Maintenance Test Pilot Fixed Jet/Prop 37.43 15086 - Maintenance Test Pilot Rotary Wing 37.43 15088 - Non-Maintenance Test/Co-Pilot 37.43 15090 - Technical Instructor 20.40 15095 - Technical Instructor/Course Developer 24.95 15110 - Test Proctor 16.47 15120 - Tutor 16.47
16000 - Laundry Dry-Cleaning Pressing And Related Occupations 16010 - Assembler 11.39 16030 - Counter Attendant 11.39 16040 - Dry Cleaner 13.67 16070 - Finisher Flatwork Machine 11.39 16090 - Presser Hand 11.39 16110 - Presser Machine Drycleaning 11.39 16130 - Presser Machine Shirts 11.39 16160 - Presser Machine Wearing Apparel Laundry 11.39 16190 - Sewing Machine Operator 14.63 16220 - Tailor 15.59 16250 - Washer Machine 11.93
19000 - Machine Tool Operation And Repair Occupations 19010 - Machine-Tool Operator (Tool Room) 20.23
19040 - Tool And Die Maker 24.73 21000 - Materials Handling And Packing Occupations 21020 - Forklift Operator 17.57 21030 - Material Coordinator 23.56 21040 - Material Expediter 23.56 21050 - Material Handling Laborer 13.55 21071 - Order Filler 13.56 21080 - Production Line Worker (Food Processing) 17.57 21110 - Shipping Packer 16.37 21130 - Shipping/Receiving Clerk 16.37 21140 - Store Worker I 11.82 21150 - Stock Clerk 16.33 21210 - Tools And Parts Attendant 17.57 21410 - Warehouse Specialist 17.57
23000 - Mechanics And Maintenance And Repair Occupations 23010 - Aerospace Structural Welder 25.71 23019 - Aircraft Logs and Records Technician 19.96 23021 - Aircraft Mechanic I 24.30 23022 - Aircraft Mechanic II 25.71 23023 - Aircraft Mechanic III 27.19 23040 - Aircraft Mechanic Helper 17.07
23050 - Aircraft Painter 22.84 23060 - Aircraft Servicer 19.96 23070 - Aircraft Survival Flight Equipment Technician 22.84 23080 - Aircraft Worker 21.38 23091 - Aircrew Life Support Equipment (ALSE) Mechanic 21.38 I 23092 - Aircrew Life Support Equipment (ALSE) Mechanic 24.30
II
23110 - Appliance Mechanic 21.80 23120 - Bicycle Repairer 17.35 23125 - Cable Splicer 32.46 23130 - Carpenter Maintenance 19.92 23140 - Carpet Layer 20.40 23160 - Electrician Maintenance 23.96 23181 - Electronics Technician Maintenance I 20.40 23182 - Electronics Technician Maintenance II 21.80 23183 - Electronics Technician Maintenance III 23.18 23260 - Fabric Worker 19.04 23290 - Fire Alarm System Mechanic 23.18 23310 - Fire Extinguisher Repairer 17.64 23311 - Fuel Distribution System Mechanic 23.18 23312 - Fuel Distribution System Operator 17.64 23370 - General Maintenance Worker 18.48 23380 - Ground Support Equipment Mechanic 24.30 23381 - Ground Support Equipment Servicer 19.96 23382 - Ground Support Equipment Worker 21.38 23391 - Gunsmith I 17.64 23392 - Gunsmith II 20.40 23393 - Gunsmith III 23.18 23410 - Heating Ventilation And Air-Conditioning 21.07 Mechanic 23411 - Heating Ventilation And Air Contidioning 22.31 Mechanic (Research Facility) 23430 - Heavy Equipment Mechanic 23.18 23440 - Heavy Equipment Operator 18.83 23460 - Instrument Mechanic 23.18 23465 - Laboratory/Shelter Mechanic 21.80 23470 - Laborer 13.55 23510 - Locksmith 21.80 23530 - Machinery Maintenance Mechanic 22.92 23550 - Machinist Maintenance 18.97 23580 - Maintenance Trades Helper 11.45 23591 - Metrology Technician I 23.18 23592 - Metrology Technician II 24.54 23593 - Metrology Technician III 25.95 23640 - Millwright 24.78 23710 - Office Appliance Repairer 21.80 23760 - Painter Maintenance 21.80 23790 - Pipefitter Maintenance 23.17 23810 - Plumber Maintenance 21.79 23820 - Pneudraulic Systems Mechanic 23.18 23850 - Rigger 23.18 23870 - Scale Mechanic 20.40 23890 - Sheet-Metal Worker Maintenance 19.00 23910 - Small Engine Mechanic 19.00 23931 - Telecommunications Mechanic I 26.70 23932 - Telecommunications Mechanic II 28.27 23950 - Telephone Lineman 26.13 23960 - Welder Combination Maintenance 19.92 23965 - Well Driller 23.18 23970 - Woodcraft Worker 23.18 23980 - Woodworker 17.64
24000 - Personal Needs Occupations 24550 - Case Manager 14.36 24570 - Child Care Attendant 10.14 24580 - Child Care Center Clerk 12.83 24610 - Chore Aide 10.86 24620 - Family Readiness And Support Services 14.36 Coordinator 24630 - Homemaker 14.36
25000 - Plant And System Operations Occupations 25010 - Boiler Tender 23.18 25040 - Sewage Plant Operator 18.04 25070 - Stationary Engineer 23.18 25190 - Ventilation Equipment Tender 16.29 25210 - Water Treatment Plant Operator 18.04
27000 - Protective Service Occupations 27004 - Alarm Monitor 14.91 27007 - Baggage Inspector 14.76 27008 - Corrections Officer 18.21 27010 - Court Security Officer 16.46 27030 - Detection Dog Handler 16.41 27040 - Detention Officer 18.21 27070 - Firefighter 15.80 27101 - Guard I 14.76 27102 - Guard II 16.41 27131 - Police Officer I 17.85 27132 - Police Officer II 19.84
28000 - Recreation Occupations 28041 - Carnival Equipment Operator 11.86 28042 - Carnival Equipment Repairer 12.82 28043 - Carnival Worker 8.92 28210 - Gate Attendant/Gate Tender 15.71 28310 - Lifeguard 13.99 28350 - Park Attendant (Aide) 17.58 28510 - Recreation Aide/Health Facility Attendant 12.83 28515 - Recreation Specialist 21.77 28630 - Sports Official 13.99 28690 - Swimming Pool Operator 22.19
29000 - Stevedoring/Longshoremen Occupational Services 29010 - Blocker And Bracer 23.74 29020 - Hatch Tender 23.74 29030 - Line Handler 23.74 29041 - Stevedore I 22.18 29042 - Stevedore II 25.38
30000 - Technical Occupations 30010 - Air Traffic Control Specialist Center (HFO) (see 2) 40.29 30011 - Air Traffic Control Specialist Station (HFO) (see 2) 27.78 30012 - Air Traffic Control Specialist Terminal (HFO) (see 2) 30.59 30021 - Archeological Technician I 14.03 30022 - Archeological Technician II 17.45 30023 - Archeological Technician III 20.55 30030 - Cartographic Technician 20.55 30040 - Civil Engineering Technician 19.44 30051 - Cryogenic Technician I 21.24 30052 - Cryogenic Technician II 23.46 30061 - Drafter/CAD Operator I 14.03 30062 - Drafter/CAD Operator II 17.45 30063 - Drafter/CAD Operator III 18.71 30064 - Drafter/CAD Operator IV 21.53 30081 - Engineering Technician I 12.50 30082 - Engineering Technician II 14.03 30083 - Engineering Technician III 17.45 30084 - Engineering Technician IV 20.55
30085 - Engineering Technician V 26.38 30086 - Engineering Technician VI 28.77 30090 - Environmental Technician 18.68 30095 - Evidence Control Specialist 19.18 30210 - Laboratory Technician 21.41 30221 - Latent Fingerprint Technician I 21.24 30222 - Latent Fingerprint Technician II 23.46 30240 - Mathematical Technician 20.55 30361 - Paralegal/Legal Assistant I 16.19 30362 - Paralegal/Legal Assistant II 20.06 30363 - Paralegal/Legal Assistant III 24.54 30364 - Paralegal/Legal Assistant IV 29.69 30375 - Petroleum Supply Specialist 23.46 30390 - Photo-Optics Technician 20.55 30395 - Radiation Control Technician 23.46 30461 - Technical Writer I 18.88 30462 - Technical Writer II 23.08 30463 - Technical Writer III 27.93 30491 - Unexploded Ordnance (UXO) Technician I 25.60 30492 - Unexploded Ordnance (UXO) Technician II 30.98 30493 - Unexploded Ordnance (UXO) Technician III 37.13 30494 - Unexploded (UXO) Safety Escort 25.60 30495 - Unexploded (UXO) Sweep Personnel 25.60 30501 - Weather Forecaster I 21.59 30502 - Weather Forecaster II 26.26 30620 - Weather Observer Combined Upper Air Or (see 2) 18.71 Surface Programs 30621 - Weather Observer Senior (see 2) 20.55
31000 - Transportation/Mobile Equipment Operation Occupations 31010 - Airplane Pilot 30.98 31020 - Bus Aide 10.49 31030 - Bus Driver 14.90 31043 - Driver Courier 11.50 31260 - Parking and Lot Attendant 9.44 31290 - Shuttle Bus Driver 12.35 31310 - Taxi Driver 12.74 31361 - Truckdriver Light 12.35 31362 - Truckdriver Medium 15.23 31363 - Truckdriver Heavy 17.56 31364 - Truckdriver Tractor-Trailer 17.56
99000 - Miscellaneous Occupations 99020 - Cabin Safety Specialist 15.10 99030 - Cashier 10.28 99050 - Desk Clerk 10.01 99095 - Embalmer 23.85 99130 - Flight Follower 25.60 99251 - Laboratory Animal Caretaker I 16.50 99252 - Laboratory Animal Caretaker II 17.84 99260 - Marketing Analyst 22.07 99310 - Mortician 23.85 99410 - Pest Controller 20.91 99510 - Photofinishing Worker 13.45 99710 - Recycling Laborer 17.46 99711 - Recycling Specialist 21.03 99730 - Refuse Collector 15.73 99810 - Sales Clerk 12.11 99820 - School Crossing Guard 13.27 99830 - Survey Party Chief 18.86 99831 - Surveying Aide 12.35 99832 - Surveying Technician 16.90 99840 - Vending Machine Attendant 17.89 99841 - Vending Machine Repairer 22.41
99842 - Vending Machine Repairer Helper 17.89
Note: Executive Order (EO) 13706 Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Service Contract Act for which the contract is awarded (and any solicitation was issued) on or after January 1 2017. If this contract is covered by the EO the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work up to 56 hours of paid sick leave each year. Employees must be permitted to use paid sick leave for their own illness injury or other health-related needs including preventive care; to assist a family member (or person who is like family to the employee) who is ill injured or has other health-related needs including preventive care; or for reasons resulting from or to assist a family member (or person who is like family to the employee) who is the victim of domestic violence sexual assault or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.
ALL OCCUPATIONS LISTED ABOVE RECEIVE THE FOLLOWING BENEFITS:
HEALTH & WELFARE: $4.60 per hour up to 40 hours per week or $184.00 per week or $797.33 per month
HEALTH & WELFARE EO 13706: $4.23 per hour up to 40 hours per…