This is a Request for Quote (RFQ) solicitation issued by the U.S. Army Corps of Engineers Seattle District for hazardous tree removal services at Albeni Falls Dam recreation areas near Oldtown and Sandpoint, Idaho. The project encompasses tree removal at four recreation areas: Albeni Cove (13 trees), Priest River (12 trees), Riley Creek (3 trees), and Vista Day Use Area (28 trees), totaling 56 trees marked for removal. The contractor must provide all personnel, equipment, supplies, materials, transportation, tools, and supervision necessary to perform safe tree removal while preserving infrastructure and surrounding vegetation. The period of performance runs from September 17, 2026 through February 26, 2027, with no extensions permitted. Questions regarding the solicitation must be submitted two days prior to the closing date, and quotes are due to Charles.d.idle@usace.army.mil with the RFQ title in the subject line. The work will be subject to 100% inspection by the Contracting Officer's Representative, and award will be made to the lowest priced responsible quoter whose quote conforms to solicitation requirements.
This is a 100% small business set-aside, specifically designated for Women-Owned Small Business (WOSB) concerns, with pricing arranged on a firm fixed-price basis for each of the six line items (one for each recreation area or location grouping). All prospective offerors must be registered in the System for Award Management (SAM) prior to contract award and must provide Federal Taxpayer ID, Unique Entity ID, and CAGE Code. Contractors are required to maintain workers' compensation and employers' liability insurance ($100,000 minimum), general liability insurance ($500,000 per occurrence for bodily injury and property damage), and automobile liability insurance ($200,000 per person, $50,000 per occurrence for bodily injury, and $20,000 per occurrence for property damage). Payment will be made by Electronic Funds Transfer unless the contractor qualifies for an exception. The contractor must obtain all necessary permits and licenses for tree disposal and comply with Occupational Safety and Health Act standards and Corps of Engineers Safety and Health Requirements Manual EM 385-1-1. The contractor is responsible for all site access, restroom facilities, equipment mobilization, and material disposal costs, which must be incorporated into the quoted prices. Performance standards are detailed in the Quality Assurance Surveillance Plan, and the contractor must submit a Quality Control Plan, work schedule, security requirements documentation, insurance certificates, equipment and vehicle lists, and invoices according to the Deliverables Schedule.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Army Corps of Engineers
Seattle District
This is a 100% Small Business Set-Aside
July 2026
RFP No. W912DW26QA083 Request For Quote (RFQ)
Albani Falls Dam Hazardous Tree Removal
Oldtown, ID
Solicitation
Request for Quote (RFQ)
WOMEN-OWNED SMALL
BUSINESS (WOSB)
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES
1. REQUISITION NUMBER PAGE 1 OF
2. CONTRACT NUMBER 3. AWARD/EFFECTIVE
DATE
4. ORDER NUMBER 5. SOLICITATION NUMBER 6. SOLICITATION ISSUE
DATE
7. FOR SOLICITATION
INFORMATION CALL:
a. NAME b. TELEPHONE NUMBER (No collect 8. OFFER DUE DATE/
LOCAL TIME
9. ISSUED BY
13b. RATING
14. METHOD OF SOLICITATION
CODE
15. DELIVER TO 16. ADMINISTERED BY CODE
18a. PAYMENT WILL BE MADE BY CODE17a. CONTRACTOR/
OFFEROR
CODE
FACILITY
CODE
CODE
TELEPHONE NUMBER
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN
OFFER
18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK
BELOW IS CHECKED
REQUEST
FOR QUOTE
(RFQ)
INVITATION
FOR BID
(IFB)
REQUEST
FOR
PROPOSAL
(RFP)
SEE ADDENDUM
19.
ITEM NUMBER
20.
SCHEDULE OF SUPPLIES/SERVICES
21.
QUANTITY
22.
UNIT
23.
UNIT PRICE
24.
AMOUNT
(Use Reverse and/or Attach Additional Sheets as Necessary)
25. ACCOUNTING AND APPROPRIATION DATA 26. TOTAL AWARD AMOUNT (For Government Use Only)
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH
AND DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND
ON ANY ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS
SPECIFIED
29. AWARD OF CONTRACT: REFERENCE OFFER
DATED . . YOUR OFFER ON SOLICITATION
(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE
SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:
30a. SIGNATURE OF OFFEROR/CONTRACTOR
30b. NAME AND TITLE OF SIGNER (Type or print) 30c. DATE SIGNED
31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER)
31b. NAME OF CONTRACTING OFFICER (Type or print) 31c. DATE SIGNED
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
STANDARD FORM 1449 (REV. 11/2021)
Prescribed by GSA - FAR (48 CFR) 53.212
10. THIS ACQUISITION IS UNRESTRICTED OR
NORTH AMERICAN
INDUSTRY CLASSIFICATION
STANDARD (NAICS):
SIZE STANDARD:
13a. THIS CONTRACT IS A
RATED ORDER UNDER
THE DEFENSE PRIORITIES
AND ALLOCATIONS
SYSTEM - DPAS (15 CFR 700)
SET ASIDE: % FOR:
11. DELIVERY FOR FREE ON
BOARD (FOB) DESTINATION
UNLESS BLOCK IS MARKED
SEE SCHEDULE
12. DISCOUNT TERMS
ARE ARE NOT ATTACHED
ARE ARE NOT ATTACHED
27a. SOLICITATION INCORPORATES BY REFERENCE (FEDERAL ACQUISITION REGULATION) FAR 52.212-1, 52.212-4. FAR 52.212-3
AND 52.212-5 ARE ATTACHED. ADDENDA
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA
8(A)
ECONOMICALLY
DISADVANTAGED
WOMEN-OWNED SMALL
BUSINESS (EDWOSB)
SERVICE-DISABLED
VETERAN-OWNED
SMALL BUSINESS
(SDVOSB)
HUBZONE SMALL
BUSINESS
SMALL BUSINESS
NOTE: OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30.
calls)
Section A - Solicitation/Contract Form
AFD Hazard Tree RemovalInstrument Name:
Product Service Code : S208
Quoter Instructions
1. The solicitation is "100% small business set-aside". All work shall be in accordance with the Product Description, attachments, and all other terms and conditions herein.
2. Quotes shall be submitted per the following: All emailed offers shall contain the RFQ title in the subject line and emailed to the following email address Charles.d.idle@usace.army.mil.
- Faxed quotations will be NOT accepted.
- Quotes must set forth full, accurate and complete information, as required by this RFQ.
3. State and Local Taxes
The U.S. Army Corps of Engineers is exempt from paying state and local taxes per Title 4 United States Code 104-107. The U.S. Army Corps of Engineers Tax ID Number is 62-1642142.
Contractors performing services for the U.S. Army Corps of Engineers are not exempt from state and local taxes in transactions with vendors, suppliers or subcontractors. It is the contractor's responsibility to investigate applicable federal, state, and local taxes, along with any specific exemptions that may exist. This includes any applicable Value-Added Taxes (VAT), sales, use, and excise taxes.
The U.S. Army Corps of Engineers will not accept any invoice with a separate tax line. If there are any appropriate taxes, the contractor should considerer that tax as the cost of doing business and incorporate that cost within the cost of the item or job.
4. Delivery: This is F.O. B. Destination. All shipping/freight costs must be incorporated into the unit price. See the purchase description for delivery address.
5. PROSPECTIVE OFFERORS: Contractors shall be registered in the System for Awards Management (SAM) prior to award of a contract or agreement resulting from solicitations.
"Registered in the System for Award Management (SAM) database" means that -
(1) The Offeror has entered all mandatory information, including the unique entity identifier and the EFT indicator, if applicable, the Commercial and Government Entity (CAGE) code, as well as data required by the Federal Funding Accountability and Transparency Act of 2006 (see subpart 4.14), into the SAM database; www.sam.gov.
W912DW26QA083
mailto:Charles.d.idle@usace.army.mil
6. ELECTRONIC FUNDS TRANSFER (EFT): Effective 99 Jun 01, the Government will make all payments by EFT (unless the Government VISA credit card is accepted). The only exceptions are: 1) Foreign Vendors, 2) Government Agencies, and 3) One-time payments.
VENDOR PAYMENT ALERT: The USACE Finance Center (UFC) has altered their process for obtaining electronic funds transfer (EFT) banking information utilized for vendor contract payment and will no longer accept UFC Form 23 to update EFT banking information for vendors. Banking information for all vendors will be retrieved from SAM.gov and entered into CEFMS II. There are no exceptions to this policy change. All contractors must notify the UFC via e-mail at: cefc-fc-eft@usace.army.mil when banking information has been updated in SAM.gov. Compliance with this requirement will help ensure timely payment to the correct bank account.
7. All questions resulting from this RFQ shall be submitted two (2) days prior to the closing date. Questions will be answered via an amendment.
8. Award will be made to the lowest priced responsible quoter whose quote conforms to the requirements of the solicitation.
9. Required Submittals:
- Signed and dated STANDARD FORM 1449 (Solicitation/Contract/Order for Commercial Items).
- Signed and dated STANDARD FORM 30 (Amendment of Solicitation/Modification of Contract), if applicable, for any Amendments to the solicitation. Contractors are responsible for checking the System for Award Management for any Amendments.
- Completed FAR/DFARS Representations & Certifications
- Warranty Information
10. The contractor is to provide the following information with your required quote:
Federal Taxpayer's ID Number:
Unique Entity ID (UEI) Number:
Cage Code Number (This requires registration in SAM, web site for registration is www.sam.gov)
W912DW26QA083
mailto:cefc-fc-eft@usace.army.mil mailto:cefc-fc-eft@usace.army.mil
Remit to Address:
Company Name:
Address:
City/State/Zip:
Phone & Fax Numbers:
Point of Contact:
E-Mail Address:
All quoted items must meet the requirements of the Request for Quote (RFQ) including Performance Work Statement.
*** END OF NARRATIVE ***
W912DW26QA083
Section B - Supplies or Services & Prices or Costs
Additional Information/Notes
Item Supplies/Service Quanti ty
Unit Unit Price Amount
0001 Tree Removal - Albeni Cove
Product Service Code: S208
Pricing Arrangement: Firm Fixed Price
1 Job
0002 Tree Removal - Priest River
Product Service Code: S208
North American Industry Classification System (NAICS):
238290
Pricing Arrangement: Firm Fixed Price
1 Job
0003 Tree Removal - Riley Creek
Product Service Code: S208
North American Industry Classification System (NAICS):
238290
Pricing Arrangement: Firm Fixed Price
1 Job
0004 Tree Removal - Springy Point
Product Service Code: S208
1 Job
North American Industry Classification System (NAICS):
238290
Pricing Arrangement: Firm Fixed Price
0005 Tree Removal - Vista
Product Service Code: S208
North American Industry Classification System (NAICS):
238290
Pricing Arrangement: Firm Fixed Price
1 Job
0006 Tree Removal - Trestle Creek
Product Service Code: S208
North American Industry Classification System (NAICS):
238290
Pricing Arrangement: Firm Fixed Price
1 Job
Section C - Description/Specifications/Statement of Work
Requirements Provide Tree service by accordance with the PWS with multiple locations.
PERFORMANCE WORK STATEMENT (PWS)
Tree Removal at Albeni Falls Dam Project
1. GENERAL: This is a non-personal services contract to provide Tree Removal Services at various recreational areas managed by Albeni Falls Dam around Oldtown and Sandpoint, Idaho.
The Government shall not exercise any supervision or control over the contract service providers performing the services herein. Such contract service providers shall be accountable solely to the Contractor who, in turn is responsible to the Government.
1.1 Description of Services: The Contractor shall provide all personnel, equipment, supplies, materials, transportation, tools, supervision, and other items and non-personal services necessary to perform hazard tree removal in a safe manner that will maintain a clean and orderly appearance and in such a manner that preserves both the infrastructure and on site vegetation as defined in this performance work statement (PWS), except for those items specified in Section 3 as government-furnished property and services. The Contractor shall perform to the standards in this PWS (See Technical Exhibit 1).
1.1.1 All tree removal shall be performed in a manner that will maintain a clean, orderly, and professional appearance of recreation areas as defined in this performance work statement (PWS).
1.1.2 Tree Removal services shall preserve the facilities, infrastructure, and vegetation in a manner that maximizes facility use.
1.1.3 Tree Removal shall allow the Government to perform its duty to provide a safe work environment for its personnel and the public, which includes their safety, wellbeing, health, and welfare.
1.2 Background: The US Army Corps of Engineers (USACE) manages developed recreation areas consisting of campgrounds, day use areas and associated features (see Technical Exhibit 2). It is our responsibility to ensure that these areas are safe for public use. A part of the management of these lands requires the evaluation of trees for defects or other issues, with removal of those found to be hazardous to health, safety and/or infrastructure, to ensure a safe environment for personnel and public visitation.
1.3 Scope: Tree Removal service for 2026 shall be conducted at the Albeni Cove Recreation Area, Priest River Recreation Area, Riley Creek Recreation Area, and Vista Day Use Area which are all mapped in (Technical Exhibit 2). The Contractor shall provide tree removal services at the designated locations specified between 17 September 2026 and 26 February 2027. Services shall include, but not be limited to: felling and removing trees (marked with numbered red flagging) deemed as hazardous or undesirable by the Albeni Falls Dam Natural Resource Management Staff, removing existing logs and debris, limbing fallen trees, and disposing logs, limbs, debris and other materials created as a result of falling operations of those trees scheduled for removal. The Contractor is to obtain all permits and licenses legally necessary to dispose of ALL tree logs and associated debris. Due to the nature of the recreation areas, the Contractor must be prepared to remove trees from locations that are near buildings, campsites and campsite features and roadways in a manner that preserves both the infrastructure and surrounding vegetation to the maximum extent possible.
1.4 Period of Performance: The period of performance shall begin no sooner than 17 September 2026 and 26 February 2027. Extensions will not be allowed. If weight limits or road closures due to “spring break up” prohibit hauling of materials or equipment, storage of equipment, logs, materials, and debris in a safe manner within the boundaries of the recreation areas may occur with the understanding that hauling, removal, and disposal shall commence within 3 days of restrictions being lifted.
1.5 General Information
1.5.1 Quality Control (QC): The Contractor shall develop and maintain an effective quality control program to ensure services are performed in accordance with this PWS. The Contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. The Contractor’s quality control program (QCP) will be used to ensure that his/her work complies with the requirement of the contract. The QCP shall be delivered to the Contracting Officer’s Representative (COR) at the post award conference (see Technical Exhibit 3).
1.5.2 Quality Assurance (QA): The Government shall evaluate the contractor’s performance under this contract in accordance with the Quality Assurance Surveillance Plan (QASP) (see Technical Exhibit 1). This plan is primarily focused on what the Government must do to ensure that the contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied and the frequency of the surveillance.
1.5.3 Recognized Holidays: Tree Removal Services are not required during the following holidays:
New Year’s Day 1 January Martin Luther King Jr. Birthday Third Monday in January Presidents Day Third Monday in February Memorial Day Last Monday in May Juneteenth 19 June Independence Day 4 July Labor Day First Monday in September Columbus Day Second Monday in October Veterans Day 11 November Thanksgiving Day Fourth Thursday in November Christmas Day 25 December
1.5.4 Hours of Operation: The Contractor is responsible for conducting business between the hours of 0630 and 1700, Monday through Friday, except Federal holidays, or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings. The Contractor shall be responsible to provide an adequate staff to assure fully adequate performance and timely completion of these services. The Contractor must always maintain an adequate workforce for the uninterrupted performance of all tasks defined within this PWS when the Government facility is not closed for the above reasons. When hiring personnel, the Contractor shall keep in mind that the stability and continuity of the workforce are essential.
a. Work Control. The Contractor shall implement all necessary work control procedures to ensure timely accomplishment of work requirements, as well as to permit tracking of work in progress. The Contractor shall plan and schedule work to ensure material, labor, supplies, and equipment are available to complete work requirements within the specified time limits and in conformance with the quality standards established herein.
b. Work Schedule. The Contractor's initial work schedule shall indicate the hours of the day and the days of the week that work will be performed. The schedule shall list the type of work to be performed, the areas to be worked, and the estimated time to complete the work in each area. When scheduled services fall on a holiday, the next scheduled work date shall be specified. The initial work schedule shall be submitted to the Contract Officer’s Representative (COR) at the post award conference (see Technical Exhibit 3). Once approved, all work shall be performed in strict compliance with the work schedule to facilitate the Government's inspection of the work. Changes to the work schedule shall be submitted to the COR for approval 24 hours prior to performance. In preparing the work schedule, the Contractor shall comply with all general requirements.
c. Interference with government business. The Contractor shall schedule and arrange work to cause the least interference with the normal occurrence of Government business and mission. In those cases where some interference may be essentially unavoidable, the Contractor shall be responsible for making every effort to minimize the impact of the interference, inconvenience, customer discomfort, etc.
1.5.5 Place of Performance: The work to be performed under this contract will be performed at the Recreation Areas listed below and mapped (see Technical Exhibit 2).
Name of Recreation Area Location
Albeni Cove 2141 Albeni Cove Road
Oldtown, Idaho 83822
Priest River 7120 Highway 2
Priest River, Idaho 83856
Riley Creek 1099 Riley Creek Park Drive
Laclede, Idaho 83841
The Vista 2376 E. Highway 2
Oldtown, Idaho 83822
1.5.6 Safety Standards: Contractor shall comply with all applicable Occupational Safety and Health
Act (OSHA) Standards, as well as the Corps of Engineers Safety and Health Requirements Manual, EM 385-1-1, revised November 2014, as amended. Copies of EM 385-1-1 shall be provided to any Contractor by request, or copies may be picked up in person at the Albeni Falls Project Office.
1.5.6.1 Public Safety: The areas in which the work is to be performed are highly utilized by the visiting public. During the closed season, the public is allowed into the recreation areas (walk-in only, no vehicle access) and may be onsite during Contractor operations.
The Contractor shall post a sign with the following wording: “CAUTION: Logging Operation in Progress.” The sign shall have dimensions no less than 18 inches by 20 inches and shall be posted at the entrance to the area prior to work beginning in the designated areas. The Contractor shall ensure that reasonable precautions are taken to always protect the public where work is being performed. The Contractor shall immediately report to the COR any potential hazards found by his employees on the project. Equipment shall be operated and work always performed with the safety of the public in mind.
1.5.7 Security Requirements: Contractor personnel performing work under this contract must have a valid driver’s license and a background security investigation. All contract personnel shall submit the following information: a. Employee name, b. SSN, c. Date of Birth, d. Place of Birth, e.
Driver’s license number & issuing state. All security requirements of contract personnel shall be submitted to the COR no later than 7 business days after the initial contract award (see Technical Exhibit 3).
All contractor and all associated sub-contractors’ employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The contractor shall also provide all information required for background checks or background investigation and to meet installation/facility access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any installation or facility change, the Government may require changes in contractor security matters or processes.
All contract employees, including subcontractor employees who are not in possession of the appropriate security clearance or access privileges, will be escorted in areas where they may be exposed to classified and/or sensitive materials and/or sensitive or restricted areas.
The Contractor must pre-screen Candidates using the E-verify Program (http://www.uscis.gov/e-verify) website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to enrollment to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates must be provided to the COR no later than 3 business days after the initial contract award (see Technical Exhibit 3).
1.5.7.1 Physical Security: The Contractor shall be responsible for safeguarding all government equipment, information and property provided for contractor use. At the close of each work period, government facilities, equipment, and materials shall be secured, and entrance gates locked.
1.5.7.2 Key Control: The Contractor is responsible for securing keys issued by the Government. Keys shall not be duplicated. Each occurrence of lost or stolen keys shall be reported to the COR within 24 hours of occurrence. For each occurrence of a key being lost, the Contractor shall be required to reimburse the Government for actual costs of re-keying all locks affected by the lost key.
1.5.7.3 Contractor shall prohibit the use of Government issued keys by any persons other than the Contractor’s employees. The Contractor shall prohibit the opening of locked areas by Contractor employees to permit entrance of persons other than Contractor employees engaged in the performance of assigned work in those areas, or personnel authorized entrance by the Contracting Officer.
1.5.8 Special Qualifications: The Contractor shall obtain all necessary licenses and/or permits required to perform this work. He/she shall take all precautions necessary to protect persons and property from injury or damage during the performance of this contract. He/she shall be responsible for any injury to themselves, their employee, or others, as well as for any damage to personal or public property that occurs during the performance of this contract that is caused by him/her employees’ fault or negligence.
1.5.9 Required Insurances: The Contractor shall procure and maintain during the entire period of performance under this contract the following insurances:
• Workers Compensation and Employers Liability. Contractors are required to comply with applicable Federal and State Workers Compensation and occupational disease statutes. If occupational diseases are not compensable under those statutes, they shall be covered under the employer’s liability section of the insurance policy, except when contract operations are so commingled with the contractor’s commercial operations that it would not be practical to require this coverage. Employer’s liability coverage of at least $100,000 shall be required, except in States with exclusive or monopolistic funds that do not permit workers compensation to be written on private carriers.
• General Liability. Bodily injury liability insurance coverage of at least $500,000 per occurrence shall be written on the comprehensive form of the policy. Property damage liability insurance of at least $500,000 per occurrence shall be written on the comprehensive form of the policy.
• Automobile Liability. Automobile liability insurance shall be written on the comprehensive form of the policy. The policy shall provide for bodily injury and property damage liability covering the operation of all automobiles used in connection with performing the contract.
Policies covering automobiles operated in the United States shall provide coverage of at least $200,000 per person and $50,000 per occurrence for bodily injury and $20,000 per occurrence for property damage. The amount of liability coverage on other policies shall be commensurate with any legal requirements of the locality in sufficient coverage to meet normal and customary claims.
A copy of the required insurance coverages can be provided to the COR at the post award conference (see Technical Exhibit 3).
1.5.10 Accidents: The Contractor shall notify the COR immediately of any damage to Government and private property as well as injury to any person resulting from his/her operations. If an accident or injury should occur, the Contractor shall immediately notify the appropriate local emergency service organization, if needed, and the COR. The Contractor shall make a written report of each separate case of an injury or accident. These reports shall include, but not be limited to, location, nature of the injury or accident, authorities notified, individuals involved, the action taken, and all other pertinent information. These reports should be accompanied by sketches and/or photographs, if possible, and forwarded to the COR within 1 working day.
1.5.11 Protection of the Resources: The areas in which work is to be performed are developed recreation areas and associated features. The Contractor must be prepared to remove trees from locations that are near buildings, campsites and campsite features and roadways in a manner that preserves both the infrastructure and surrounding vegetation to the maximum extent possible. All damage to infrastructure and/or vegetation must be reported immediately to the COR.
1.5.11.1 Historical, Archeological or Cultural Resources: If during contract activities the Contractor observes unusual items that might have historical or archeological value, such observances shall be reported as soon as practical to the COR.
1.5.11.2 Protection of Water Resources: The Contractor shall not pollute drainage ditches, ponds, rivers, or lakes with fuels, oils, bitumen, calcium chloride, acids, cleaning solvents or chemicals or other harmful materials. Disposal of any materials, wastes, effluents, trash, garbage, oil, grease, chemicals, etc., in areas adjacent to drainage ditches, ponds, rivers, or lakes will not be permitted. If contamination occurs the Contractor must contact the COR.
1.5.11.3 Removal of Materials and Rubbish: The Contractor shall remove from the work sites, all their equipment and unused materials provided by them, logs, limbs, debris and any waste materials and rubbish resulting from operations performed. The methods and locations of disposal of materials, wastes, effluents, trash, garbage, oil, grease, and chemicals shall be such that harmful debris must not enter project lands, lakes, rivers, ditches, canals, waterways, or reservoirs. Material shall be disposed of off-site in accordance with all local, State and Federal rules and regulations at the Contractor’s expense prior to final payment of this contract. The Contractor is responsible for all permits and other permissions for disposal of materials.
1.5.12 Damages: The Contractor shall be responsible for restoring any Government facilities, structures or equipment damaged because of his/her operation. Reasonable care shall be used to avoid damage to structures and equipment in the recreation areas. Any such damage shall be repaired, items replaced, or the damages repaired to the original condition at no cost to the Government. If the Contractor does not make such repair or replacement, the cost will be deducted from payments to be made to them.
1.5.12.1 Restoration of Landscape Damages: Any trees, shrubs, turf, or other landscape features unreasonably scarred or damaged by the Contractor’s equipment or operations shall be restored to a condition satisfactory to the COR. Skidding damage or ruts greater than two inches deep shall be restored to the original condition. All at no cost to the Government. No vegetation or trees, other than those identified for removal, will be removed without prior authorization of the COR.
1.5.12.2 Deductions: Trees removed or damaged to the extent that they must be removed, without the prior authorization of the COR shall be felled, limbed, hauled away.
Additionally, each tree removed without prior authorization of the COR shall be subject to the following costs being assessed by the contractor and deducted from the government payment:
Tree Size Assessed Deduction < 4 inches diameter breast height $100.00 5 to 8 inches diameter breast height $200.00 9 to 12 inches diameter breast height $300.00 13 to 16 inches diameter breast height $400.00 17 to 20 inches diameter breast height $500.00
21 to 24 inches diameter breast height $600.00 25 to 28 inches diameter breast height $700.00 > 28 inches diameter breast height $800.00
1.5.13 Contractor Travel: All expenses getting to the job site and all travel during the performance of the job is the Contractor’s responsibility and shall be at no additional cost to the Government.
1.5.14 Contractor Personnel: The personnel specified below are essential to the work being performed under this contract.
1.5.14.1 Contract Manager: The contractor shall provide a contract manager who shall be responsible for the performance of the work. The name of this person and an alternate or alternates, who shall act for the contractor when the manager is absent, shall be designated in writing to the COR. The contract manager or alternate must have full authority to act for the contractor on all contract matters relating to daily operation of this contract. The contract manager shall maintain an adequate workforce to complete work in accordance with the time and quality standards contained here under.
1.5.15 Payment Terms: An original invoice shall be submitted to the COR for approval prior to submission for processing. Invoices shall include the contract number, item numbers, and description of work, quantities, unit prices, and total prices (see Technical Exhibit 3).
1. SPECIFIC TASKS:
2.1 Basic Services: Trees slated for removal will be marked in each recreation area. Red flagged trees shall be felled and removed. Removal of existing logs and debris as identified. A map of the location of existing logs and debris to be removed, and trees to be removed or felled from each recreation area and size tables shall be provided. (NOTE: tree ID numbers included in the size tables may not be in sequential order). The Contractor shall:
2.1.1 Fall all marked trees in a manner that preserves and prevents any damage to the surrounding infrastructure (i.e., buildings, tables, grills, bumper logs, water faucets, etc.). If necessary, movable structures such as picnic tables shall be removed from the direction of tree fall. All attempts shall be made to avoid immovable objects by appropriate cutting techniques and judgment.
2.1.2 To the maximum extent possible, adjacent vegetation shall be preserved during logging operations. Marked trees within the recreation area shall be felled in such a manner as to avoid damage to unmarked trees or other vegetation. All trees and vegetation damaged during operations and determined to be unsafe by the COR shall be removed by the Contractor as stated above with no additional cost to the Government and assessed a fee as per the schedule outlined in 1.5.12.2 which will be deducted from contract payment.
2.1.3 Trees marked for removal (red flagging) smaller than six inches DBH (diameter breast height) shall be limbed and bucked on-site to a suitable firewood length approximately 14 – 16-inch lengths and left in-place or, at the Contractor’s discretion, disposed of offsite.
2.1.4 Stumps shall be cut flush at the ground to avoid tripping hazards. Any remaining butts may be left on-site. Sharp wood or points left on the butt, as a result, of the felling shall be trimmed to remove dangerous points or sharp tips.
2.1.5 Limb material: For limb material greater than one inch in diameter or longer than three feet shall be removed from the area and hauled off-site for disposal. No material shall be left on roads, campsites, trails, or other facilities. Material may be removed whole, chipped, or otherwise transported. If chipping is utilized as a disposal method, the resultant chips shall be transported and disposed of off-site; chipped material shall not be left on the ground. Material shall not be raked into, dumped in, burned on or otherwise transported to other locations within the recreation areas.
The cost of disposal shall be included in the contract price. Material shall be disposed of off-site in accordance with all local, State and Federal rules and regulations at the Contractor’s expense. The Contractor is responsible for all permits and other permissions for disposal of logs and slash material.
2.1.6 Special instructions, such as “Tree #5 is on the ground needing only to be cut from the root system and removed” will be listed in the instructions of each Recreation Area if applicable.
2.1.7 At Albeni Cove (see Technical Exhibit 4), there are 13 trees marked for removal and disposal (see Technical Exhibit 5).
2.1.8 At Priest River (see Technical Exhibit 6), there are 12 trees marked for removal and disposal (see Technical Exhibit 7).
2.1.9 At Riley Creek (see Technical Exhibit 8), there are 3 trees marked for removal and disposal (see Technical Exhibit 9).
2.1.10 At Vista (see Technical Exhibit 10) there are 28 trees marked for removal and disposal (see Technical Exhibit 11).
Note: Due to snow and wind loads, there may be trees that were standing or not broken at the time of the assessment. If any marked trees break or uproot, the bole, downed top, and associated limbs/debris will need to be removed from the recreation area. Snow removal to aid in access is the responsibility of the Contractor.
2. GOVERNMENT FURNISHED ITEMS AND SERVICES:
3.1 Government Services: None.
3.2 Government Furnished Facilities: None.
3.3 Utilities: None.
3.4 Equipment: None.
3.5 Materials: The Government will not provide any materials.
3. POST AWARD CONFERENCE:
4.1 Post Award Conference/Periodic Progress Meetings: The Contractor agrees to attend the post award conference convened by the contracting activity or contract administration office in accordance with Federal Acquisition Regulation Subpart 42.5 within seven (7) days of contract award if requested. The Contractor shall provide the Contracting Officer’s Representative (COR) the following deliverables as described in Technical Exhibit 3: a. His/her Quality Control Plan (QCP) (outlined above in section 1.5.1), b. A list of all equipment to be used by the Contractor at the work sites, c. A list of vehicles, vessels, and license plate numbers to be used during the course of the contract, d. Required certificates of insurance (outlined above in section 1.5.5), e. All required Employee Personnel Information (outlined above in 1.5.7), and Approximate work schedule, including dates and locations, of work to be performed (outlined above in 1.5.4.b). The contracting officer, Government Designated Representative (GDR), Contracting Officer’s Representative (COR), and other Government personnel, as appropriate, may meet periodically with the contractor to review the contractor's performance. At these meetings the contracting officer will apprise the contractor of how the government views the contractor's performance and the contractor will apprise the Government of problems, if any, being experienced. Appropriate action shall be taken to resolve outstanding issues. These meetings shall be at no additional cost to the government.
4. CONTRACTING OFFICER’S REPRESENTATIVE (COR)
5.1 The COR, and other Government personnel, as appropriate, may meet periodically with the contractor to review the contractor's performance. At these meetings the COR will apprise the contractor of how the government views the contractor's performance and the contractor will apprise the Government of problems, if any, being experienced. Appropriate action shall be taken to resolve outstanding issues. These meetings shall be at no additional cost to the government. The COR is not legally able to change or update the contract.
5.2 The COR monitors all technical aspects of the contract and assists in contract administration.
The COR is authorized to perform the following functions:
Assure that the Contractor performs the technical requirements of the contract.
• Perform inspections necessary in connection with contract performance.
• Maintains written and oral communications with the Contractor concerning technical aspects of the contract.
• Issue written interpretations of technical requirements, including Government drawings, designs, and specifications.
• Monitor Contractor's performance and notifies both the Contracting Officer and
Contractor of any deficiencies.
• Coordinates availability of government Furnished property and may provide site entry of Contractor personnel.
The contractor shall be notified who will assume the role of the COR at the post award conference. The COR will inform the Contractor of the responsibilities and limitations of the COR, especially about changes in cost or price, estimates or changes in delivery dates. The COR is not authorized to change any of the terms and conditions of the resulting order.
5. CONTRACTOR FURNISHED ITEMS AND RESPONSIBILITIES:
6.1 General: The Contractor shall furnish all supplies, equipment, facilities, and services required to perform work under this contract.
6.2 Materials: All materials will be provided by the Contractor.
6.3 Equipment: The Contractor shall furnish all equipment needed to fulfill contract obligations.
All equipment shall be of commercial quality and shall be in operable condition and meet local requirements. Completion of the specifications of this contract requires the use of heavy-duty, commercial-grade logging equipment operated by skilled and competent operators. Due to the nature of the sites, only RUBBER-TIRED or approved track equipment machinery will be allowed.
6.4 Restroom Facilities: Prior to the opening dates for the Albeni Cove, Priest River, Riley Creek, Springy Point, and the Trestle Creek Recreation Areas, Government restroom facilities may not be available for use by Contractor personnel due to winterization procedures. The Contractor shall be responsible for ensuring their employees have access to adequate restroom facilities.
6.5 Office Space: The Contractor shall secure and maintain the necessary office space and other facilities required for the performance of this contract at his/her own expense.
6. APPLICABLE PUBLICATIONS:
7.1 The Contractor must abide by all applicable regulations, publications, manuals, and local policies and procedures.
7. TECHNICAL EXHIBIT LIST:
Technical Exhibit 1 – Quality Assurance Surveillance Plan
Technical Exhibit 2 – Map of Albeni Falls Dam Hazard Tree Removal Vicinity Map
Technical Exhibit 3 – Deliverables Schedule
Technical Exhibit 4 – Albeni Cove Recreation Area Tree Size Table
Technical Exhibit 5 – Map of Tree Work to be performed at Albeni Cove Recreation Area
Technical Exhibit 6 – Priest River Recreation Area Tree Size Table
Technical Exhibit 7 – Map of Tree Work to be performed at Priest River Recreation Area
Technical Exhibit 8 – Riley Creek Recreation Area Tree Size Table
Technical Exhibit 9 – Map of Tree Work to be performed at Riley Creek Recreation Area
Technical Exhibit 10 – Vista Area Tree Size Table
Technical Exhibit 11 – Map of Tree Work to be performed at VistaArea
HAZARD TREE REMOVAL
ALBENI FALLS PROJECT
IDAHO
1. Objective. The purpose of this plan is to provide a quality assurance surveillance plan for Hazard Tree Removal Services at the Albeni Falls Dam recreation areas. This plan provides a basis for the COR and/or the quality assurance evaluator (QAE) to evaluate the quality of the contractor’s performance. The oversight provided for in the contract and in this plan will help ensure that service levels reach and maintain the required levels throughout the contract term.
2. Performance Standards.
A. Quality Level. By monitoring the contractor, the COR will determine whether the performance levels set forth in the contract and have been attained. Performance standards for all tasks are specified in the Performance Work Statement, Performance Requirements Summary, and contract clauses.
B. Frequency. During performance of this contract, the COR and/or the QAE will perform inspections of the work and will analyze whether the work is being performed in accordance with the PWS and PRS. The COR and/or QAE will confirm whether the contractor has satisfactorily met all contract requirements.
3. Evaluation Methods. The COR and/or QAE will conduct performance evaluations to ensure performance levels identified in the contract are met. The following techniques will be used to perform surveillance:
A. 100% Inspection. The COR will perform 100% inspections during the contract. Sites will be inspected to ensure that all performance standards identified in the PWS have been completed to the satisfaction of the COR. Any discrepancies noted during the inspections will be discussed with the contractor as soon as practicable. The COR will document any findings, discrepancies, and discussions as necessary.
B. To minimize unnecessary mobilizations and demobilizations, the contractor will keep the COR informed of schedules and locations throughout the course of the contract. This will allow specific areas to be inspected after the work is performed, ensuring that inspections are not performed prior to the contractor’s entry to the work area.
C. Any findings, discrepancies and discussions will be identified and documented on a form like the attached inspection report as is necessary. The report will be filed with all other pertinent contract documents and will be used to determine compliance with all contract requirements.
QUALITY ASSURANCE SURVEILLANCE PLAN (QASP)
Technical Exhibit 1, continued
ALBENI FALLS PROJECT
INSPECTION REPORT AREA:
HAZARD TREE REMOVAL
CONTRACT #:
Date:
Time:
CONTRACTOR:
WORK DESCRIPTION SAT UNSAT COMMENTS
Fell All Marked Trees Trim/Flush Cut Tree Boles and Wood Left on Site
Buck Saw Logs to Appropriate Length Limb Trees Trim/Flush Cut Stumps at Ground Level Remove All Tree Debris and Logs Remove All Equipment, Rubbish and Garbage Place Barrier Logs at Recreation Areas Post a Caution Sign at Recreation Area Entrances
Identify damages and discrepancies
ADDITIONAL COMMENTS:
COR Signature
Technical Exhibit 2
Technical Exhibit 3
DELIVERABLES SCHEDULE
Deliverable Frequency # of Copies Medium/Format Submit to
DS#1
Quality Control Plan Paragraph 1.5.1
Prior to start of work
1 copy Hard Copy COR at Post Award Conference
DS#2
Work Schedule Paragraph 1.5.4. b
Prior to start of work
1 copy Hard Copy COR at Post Award Conference
DS#3
Security Requirements Paragraph 1.5.7
Prior to start of work
1 copy Hard Copy COR at Post Award Conference
DS#4
E-verify Requirements Paragraph 1.5.7
No more than 3 days from award
1 copy Digital Copy COR
DS#5
Insurance Certificates Paragraph 1.5.9
Prior to start of work
1 copy Hard Copy COR at Post Award Conference
DS#6
List of all equipment Paragraph 4.1
Prior to start of work
1 copy Hard Copy COR at Post Award Conference
DS#7
Vehicle list Paragraph 4.1
Prior to start of work
1 copy Hard Copy COR at Post Award Conference
DS#8
Deduction Logs Paragraph 1.5.12.2
Completion of work
Material Logs COR at Specified Decking Location
DS#8
Invoice Paragraph 1.5.15
Completion of work
1 copy Digital Copy COR within 7 days of work completion
Technical Exhibit 4
Albeni Falls Project Hazard Tree Removal
Tree Size Table
Recreation Area: Albeni Cove
ID Number
Species
DBH
(Inches)
Height (Feet)
Disposition
1 Douglas Fir 16 74 Remove 2 Douglas Fir 18 93 Remove 3 Western Red Cedar 15 57 Remove 4 Douglas Fir 19 100 Remove 5 Douglas Fir 25 110 Remove 6 Douglas Fir 10 45 Remove 7 Douglas Fir 18 78 Remove 8 Douglas Fir 6 52 Remove 9 Douglas Fir 10 62 Remove
10 Douglas Fir 13 91 Remove 11 Douglas Fir 11 72 Remove 12 Douglas Fir 17 88 Remove 13 Western White Pine 11 58 Remove
Technical Exhibit 5
Technical Exhibit 6
Recreation Area: Priest River
(Inches)
1 Ponderosa Pine 28 123 Remove 2 Western Red Cedar 17 73 Remove 3 Western Red Cedar 13 75 Remove 4 Grand Fir 14 80 Remove 5 Ponderosa Pine 22 48 Remove 6 Western Larch 18 120 Remove 7 Western Red Cedar 20 63 Remove 8 Douglas Fir 30 45 Remove 9 Grand Fir 21 43 Remove
10 Grand Fir 18 77 Remove 11 Western White Pine 33 112 Remove 12 Ponderosa Pine 18 42 Remove
Technical Exhibit 7
Technical Exhibit 8
Recreation Area: Riley Creek
(Inches)
1 Western White Pine 29 128 Remove 2 Lodgepole Pine 21 90 Remove 3 Lodgepole Pine 22 100 Remove
Technical Exhibit 9
Technical Exhibit 10
Recreation Area: Vista
(Inches)
1 Western White Pine 22 83 Remove 2 Western White Pine 19 80 Remove 3 Western White Pine 10 57 Remove 4 Western White Pine 18 76 Remove 5 Western White Pine 14 75 Remove 6 Western White Pine 19 79 Remove 7 Western White Pine 11 49 Remove 8 Western White Pine 15 64 Remove 9 Western White Pine 8 64 Remove 10 Western White Pine 9 58 Remove 11 Western White Pine 14 59 Remove 12 Western White Pine 22 78 Remove 13 Western White Pine 9 31 Remove 14 Western White Pine 14 60 Remove 15 Western White Pine 12 62 Remove 16 Western White Pine 9 58 Remove 17 Western White Pine 11 64 Remove 18 Western White Pine 11 59 Remove 19 Western White Pine 8 60 Remove 20 Western White Pine 10 59 Remove 21 Western White Pine 10 74 Remove 22 Western White Pine 22 63 Remove 23 Western White Pine 10 58 Remove 24 Western White Pine 17 79 Remove 25 Western White Pine 9 50 Remove 26 Western White Pine 10 50 Remove 27 Western White Pine 11 63 Remove 28 Western White Pine 23 73 Remove
Technical Exhibit 11
8. DEFINITIONS AND ACRONYMS:
• CONTRACTOR: A supplier or vendor awarded a contract to provide specific supplies or service to the government. The term used in this contract refers to the prime.
• CONTRACTING OFFICER: A person with authority to enter, administer, and or terminate contracts, and make related determinations and findings on behalf of the government. Note: The only individual who can legally bind the government.
• CONTRACTING OFFICER’S REPRESENTATIVE: An employee of the U.S.
Government appointed by the contracting officer to administer the contract. Such appointment shall be announced at the post award conference and shall state the scope of authority and limitations. This individual has authority to provide technical direction to the Contractor if that direction is within the scope of the contract, does not constitute a change, and has no funding implications. This individual does NOT have authority to change the terms and conditions of the contract.
• DEFECTIVE SERVICE: A service output that does not meet the standard of performance associated with the Performance Work Statement.
• DELIVERABLE: Anything that can be physically delivered but may include non-manufactured things such as meeting minutes or reports.
• DIAMETER BREAST HEIGHT: A measurement of the diameter of a tree bole approximately four feet above ground level.
• KEY PERSONNEL: Contractor personnel that are evaluated in a source selection process and that may be required to be used in the performance of a contract by the Key Personnel listed in the PWS. When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the persons that are listed in the proposal.
• PHYSICAL SECURITY: Actions that prevent the loss or damage of Government property.
• QUALITY ASSURANCE: The government procedures to verify that services being performed by the Contractor are performed according to acceptable standards.
• QUALITY ASSURANCE Surveillance Plan: An organized written document specifying the surveillance methodology to be used for surveillance of contractor performance.
• CONTRACTING OFFICER’S REPRESENTATIVE: The Government employee designated to evaluate the quality of services produced.
• QUALITY CONTROL: All necessary measures taken by the Contractor to assure that the quality of the end-product or service shall meet contract requirements.
• SUBCONTRACTOR: One that enters a contract with a prime contractor. The Government does not have privity of contract with the subcontractor.
• WORKDAY: The number of hours per day the Contractor provides services in accordance with the contract.
• WORK WEEK: Monday through Friday, unless specified otherwise.
• FACILITY: Any Government building, structure, campsite, campsite feature, roadway, trail, equipment, or day use feature.
9.1 ACRONYMS:
DA Department of the Army DBH Diameter Breast Height KO Contracting Officer POC Point of Contact PWS Performance Work Statement QA Quality Assurance QAP Quality Assurance Program COR Contracting Officer’s Representative QASP Quality Assurance Surveillance Plan QC Quality Control QCP Quality Control Program TE Technical Exhibit
Section E - Inspection and Acceptance
Overall Contract Inspection/Acceptance Locations
0001 Inspection and Acceptance Location
Both Destination Instructions: Follow the PWS
DoDAAC: 960513 CountryCode: USA
ARMY CORPS OF ENGINEERS CIVIL WORKS
SEATTLE DIST 2376 E HIGHWAY 2, PROJECT ENGINEER ALBENI FALLS DAM
OLDTOWN, ID 83822-9243
UNITED STATES
0002 Inspection and Acceptance Location
Both Destination Instructions: Follow the PWS
DoDAAC: 960513 CountryCode: USA
ARMY CORPS OF ENGINEERS CIVIL WORKS
SEATTLE DIST 2376 E HIGHWAY 2, PROJECT ENGINEER ALBENI FALLS DAM
OLDTOWN, ID 83822-9243
UNITED STATES
0003 Inspection and Acceptance Location
Both Destination Instructions: Follow the PWS
DoDAAC: 960513 CountryCode: USA
ARMY CORPS OF ENGINEERS CIVIL WORKS
SEATTLE DIST 2376 E HIGHWAY 2, PROJECT ENGINEER ALBENI FALLS DAM
OLDTOWN, ID 83822-9243
UNITED STATES
0004 Inspection and Acceptance Location
Both Destination Instructions: Follow the PWS
DoDAAC: 960513 CountryCode: USA
ARMY CORPS OF ENGINEERS CIVIL WORKS
SEATTLE DIST 2376 E HIGHWAY 2, PROJECT ENGINEER ALBENI FALLS DAM
OLDTOWN, ID 83822-9243
UNITED STATES
0005 Inspection and Acceptance Location
Both Destination Instructions: Follow the PWS
DoDAAC: 960513 CountryCode: USA
ARMY CORPS OF ENGINEERS CIVIL WORKS
SEATTLE DIST 2376 E HIGHWAY 2, PROJECT ENGINEER ALBENI FALLS DAM
OLDTOWN, ID 83822-9243
UNITED STATES
0006 Inspection and Acceptance Location
Both Destination Instructions: Follow the PWS
DoDAAC: 960513 CountryCode: USA
ARMY CORPS OF ENGINEERS CIVIL WORKS
SEATTLE DIST 2376 E HIGHWAY 2, PROJECT ENGINEER ALBENI FALLS DAM
OLDTOWN, ID 83822-9243
UNITED STATES
Section F - Deliveries or Performance
0001 Delivery Schedule Delivery Period From 17 Sep 2026 to 26 Feb 2027
1 JobQuantity
Address and POC Service Performance Site DoDAAC: 960513 CountryCode: USA
ARMY CORPS OF ENGINEERS CIVIL WORKS
SEATTLE DIST 2376 E HIGHWAY 2, PROJECT ENGINEER ALBENI FALLS DAM
OLDTOWN, ID 83822-9243 UNITED STATES
Period of Performance From 17 Sep 2026 To 26 Feb 2027
0002 Delivery Schedule Delivery Period From 17 Sep 2026 to 26 Feb 2027
1 JobQuantity
Address and POC Service Performance Site DoDAAC: 960513…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .