This solicitation is for a construction contract to repair a federal levee in Missouri known as MRLS 246-L. The work includes repairing the levee crown, landside toe erosion, and breaches, as well as constructing an underseepage berm. Sod kill will be repaired with over-seeding, and the new embankment section will be seeded and mulched. The U.S. Army Corps of Engineers, Kansas City District, will evaluate bids received in response to this invitation for bid according to FAR 14.1. Technical questions must be submitted through ProjNet by the specified date. The complete solicitation and attachments are provided in the document.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Solicitation W912DQ20B1041 - Attachment 01 - Supplemental Bid Schedule.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Army Corps of Engineers Kansas City District Building Strong
Federal Levee Rehab
MRLS 246-L
Chariton County, Missouri
As Advertised
Construction Specifications and Solicitation
May 2020
W912DQ20B1041
This page was intentionally left blank for duplex printing.
TC-1
DEPARTMENT OF THE ARMY
Kansas City District, Corps of Engineers
647 Federal Building Kansas City, Missouri 64106
SPECIFICATIONS FOR CONSTRUCTION OF
MULTIPLE AWARD TASK ORDER CONTRACT (MATOC)
FCCE 2019 FEDERAL MRLS L246 LEVEE UNIT
COVER
TABLE OF CONTENTS
DIVISION 00 PROCUREMENT AND CONTRACTING REQUIREMENTS
SECTION TITLE
00 01 05 CERTIFICATION PAGE
00 10 00 SOLICITATION
00 21 13 INSTRUCTIONS TO BIDDERS
00 22 13 SUPPLEMENTARY INSTRUCTIONS TO BIDDERS
00 45 00 REPRESENTATIONS AND CERTIFICATIONS
00 70 00 CONDITIONS OF THE CONTRACT
00 73 00 SUPPLEMENTARY CONDITIONS
01 00 00 GENERAL REQUIREMENTS
DIVISION 1 – GENERAL REQUIREMENTS
THE FOLLOWING SPECIFICATIONS ARE PROVIDED IN THE BASE CONTRACT AND ARE
APPLICABLE FOR THIS TASK ORDER
01 11 00 SUMMARY OF WORK
01 22 00.00 10 PRICE AND PAYMENT PROCEDURES
01 30 00 ADMINISTRATIVE REQUIREMENTS
01 32 16.01 23 PROGRESS CHART (KCD)
01 33 00 SUBMITTAL PROCEDURES
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.00 10 QUALITY CONTROL
01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
01 78 00 CLOSEOUT SUBMITTALS
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 15 00 AGGREGATE SURFACING
32 92 19 SEEDING
DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION
35 31 19 STONE, CHANNEL, PROTECTION FOR STRUCTURES
35 41 00 LEVEE CONSTRUCTION
-- End of Project Table of Contents --
This page was intentionally left blank for duplex printing.
The U.S. Army Corps of Engineers, Kansas City District, has a need for Construction Activities for Levee repair to MRLS 246-L Levee due to damages sustained during the 2019 flood events. The w ork covered by this contract consist of furnishing all equipment, labor, operators, supervision/site superintendent, quality control, supplies, materials, and incidentals necessary to satisfactorily perform and provide construction to potentially include, but not limited to repair the crow n and landside toe erosion, breaches are also recommended to be repaired and construction of an underseepage berms. Sod kill to be repaired w ith over-seeding. New embankment section w ill be seeded and mulched w ith a maintenance period.
X
CHRISTOPHER W ANDERSON 816-389-3850
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
11-May-2020
(RFP)
(IFB)
CALL:
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA
FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________ calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________52.211-10
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
X YES NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________11 Jun 2020 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time of fers are due.
B. An offer guarantee X is, is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______90 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
USACE, KANSAS CITY +
FEDERAL BLDG CT-H 601 E 12TH ST RM 647
KANSAS CITY MO 64106-2896
W912DQ
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
02:00 PM (hour)
Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
8. ADDRESS OFFER TO (If Other Than Item 7)
816-389-2030FAX:TEL: 816-389-3812 TEL: FAX:
W912DQ20B1041 71
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
Section 00 01 05 - Certification Page
CAUTION PAGE:
CAUTION!
BEFORE SIGNING AND MAILING YOUR BID, please take note of the following, as failure to perform any one of these actions may cause your bid to be rejected.
1. AMENDMENTS: Have you acknowledged receipt of ALL Amendments? If in doubt as to number of amendments issued, please contact our office.
2. SEALED BIDS: Sealed envelopes containing bids shall be marked to show the bidder’s name and address, the solicitation number, title of project, amendments received, and the date and time bids are due.
3. AMENDED BID PAGES: If any of the Amendments furnished amended bid pages, the amended bid page(s) must be used in submitting your bid.
4. LATE BIDS: In order for a late mailed bid to be considered, generally it must have been sent by either registered or certified mail not later than 5 calendar days before the receipt of bids due date.
5. BID GUARANTEE: Sufficient bid guarantee in proper form must be furnished with your bid, if your bid exceeds $150,000.
6. MISTAKE IN BID: Have you reviewed your bid prices for possible errors in calculations or work left out?
7. FACSIMILE BIDS AND MODIFICATIONS: Will not be considered. Facsimile withdrawals will be considered.
8. HAND-DELIVERED BID: If bids are hand-delivered, you must be aware of enhanced security requirements in effect in the Federal Building and allow for extra time to clear security. You must have a valid picture ID in order to enter the building. No additional time will be allowed due to security requirements. Please ensure that the solicitation number and title of project appear or can be identified on the outside of bid package.
9. BUY AMERICAN ACT: All bidders are cautioned that, prior Government conduct notwithstanding, the
Contractor's selection of a domestic construction material which would require the subsequent selection of a foreign construction material for compatibility is not a justification for waiver of the Buy American Act.
It is the Contractor's responsibility to verify, prior to submitting the materials for approval that each system can be built to meet the contract specifications without the use of foreign construction materials.
10. BOLLING FEDERAL BUILDING ENHANCED SECURITY: Due to enhanced security in the
Bolling Federal Building the Bid Opening Room S101, will open 30 minutes prior to bid opening and will remain open until all bids are opened and read. If bids are hand-delivered, you must be aware of enhanced security requirements in effect in the Federal Building and allow for extra time to clear security. You must have a valid picture ID in order to enter the building. No additional time will be allowed due to security requirements. Security Personnel may require you to be escorted to room S101. S101 is located at the end of the hall between the elevators on the first floor. Person(s) attending the bid opening, will no longer be allowed to remain on Corps of Engineers floors (4, 5 & 6) other than in the Bid Opening Room. The Bid Opening Room is available to all persons delivering bids or attending the bid opening. Bidders may wait in the Federal Building cafeteria on the Ground level or outside the building. Under The Federal Acquisition Regulations bids cannot be accepted after the time set for bid opening. Therefore, to ensure your bid is not late, all bidders are encouraged to complete their bids prior to arrival at the Bid Opening Room.
(END)
SYSTEM FOR AWARD MANAGMENT (SAM):
In accordance with FAR 52.204-7: By submission of an offer, the offeror acknowledges the requirement that a prospective awardee shall be registered in the SAM database prior to award, during performance and through final payment of any contract resulting from this solicitation. If the Offeror does not become registered in the SAM database in the time prescribed by the Contracting Officer, the Contracting Officer will proceed to award to the next otherwise successful registered Offeror. Offerors may obtain information on registration and annual confirmation requirements via the SAM database accessed through https://sam.gov/portal/SAM/#1 . It is highly encouraged that all prospective Offeror’s start the SAM’s registration process as soon as possible.
OFFEROR MUST BE REGISTERED IN THE SYSTEM FOR AWARD MANAGEMENT PRIOR TO THE
BID OPENING OR THE CONTRACT OFFICER MAY PROCEED WITH AWARD TO THE NEXT
SUCCESSFUL CONTRACTOR.
If you were not previously registered, please go to https://www.sam.gov. Instructions for new registration are also located at the following link https://www.sam.gov/sam/transcript/Quick_Guide_for_Contract_Registrations_v1.7.pdf to register.
If you have questions about Government procurements in general or need assistance in the preparation of your proposal, a local Procurement Technical Assistance Center (PTAC) may be able to help. The Procurement Technical Assistance Program was authorized by Congress in 1985 in an effort to expand the number of businesses capable of participating in the Government marketplace. To locate a PTAC near you, go to http://www.aptac-us.org/sam-registration/ THIS A FREE SERVICE BY A NON PROFIT PAID FOR BY THE US GOVERNMENT
(END)
SUPPLEMENTAL BID SCHEDULE
The contractor shall complete the attached Supplemental Bid Schedule in addition to the Bid Schedule. This Supplemental Bid Schedule is not contractually binding. The Government will use this Supplemental Bid Schedule to assist in the evaluation of prices. The individual supplemental bid items should add up to the prices for the bid schedule. In the event that the CLIN subtotal in the supplemental bid schedule does not match the CLIN total in the bid schedule, the CLIN bid schedule shall control and will be the price evaluated by the Government.
(END)
Section 00 10 00 - Solicitation
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Job Mobilization and Demobilization
FFP
The Government's payment for the items listed in this CLIN shall constitute full compensation to the Contractor for furnishing all plant, labor, equipment, appliances, and materials; and performing all operations required to complete the work in conformity with the drawings and specifications.
FOB: Destination
NET AMT
0002 1 Job Levee Repairs
FFP
The Government's payment for the items listed in this CLIN shall constitute full compensation to the Contractor for furnishing all plant, labor, equipment, appliances, and materials; and performing all operations required to complete the
0003 1 Job Seeding
FFP
The Government's payment for the items listed in this CLIN shall constitute full compensation to the Contractor for furnishing all plant, labor, equipment, appliances, and materials; and performing all operations required to complete the
0004 1 Job Palmer Creek Drainage Structure Station
FFP
The Government's payment for the items listed in this CLIN shall constitute full compensation to the Contractor for furnishing all plant, labor, equipment, appliances, and materials; and performing all operations required to complete the
0005 1 Job Setback Levee Cut
FFP
The Government's payment for the items listed in this CLIN shall constitute full compensation to the Contractor for furnishing all plant, labor, equipment, appliances, and materials; and performing all operations required to complete the
0006 130,000 Cubic
Yard
Setback Levee Embankment Fill
FFP
The Government's payment for the items listed in this CLIN shall constitute full compensation to the Contractor for furnishing all plant, labor, equipment, appliances, and materials; and performing all operations required to complete the
0007 50,000 Cubic
Setback Levee Underseepage Berm Fill
The Government's payment for the items listed in this CLIN shall constitute full compensation to the Contractor for furnishing all plant, labor, equipment, appliances, and materials; and performing all operations required to complete the
0008 1,500 Cubic
Palmer Creek Right Bank Breach Pervious
The Government's payment for the items listed in this CLIN shall constitute full compensation to the Contractor for furnishing all plant, labor, equipment, appliances, and materials; and performing all operations required to complete the
0009 7,500 Cubic
Palmer Creek Right Bank Breach Levee Fil
The Government's payment for the items listed in this CLIN shall constitute full compensation to the Contractor for furnishing all plant, labor, equipment, appliances, and materials; and performing all operations required to complete the
0010 7,000 Cubic
Palmer Creek Left Bank Breach Pervious F
The Government's payment for the items listed in this CLIN shall constitute full compensation to the Contractor for furnishing all plant, labor, equipment, appliances, and materials; and performing all operations required to complete the
0011 15,500 Cubic
Palmer Creek Left Bank Breach Levee Fill
The Government's payment for the items listed in this CLIN shall constitute full compensation to the Contractor for furnishing all plant, labor, equipment, appliances, and materials; and performing all operations required to complete the
0012 24,000 Cubic
Breach 637+00 to 641+35 Levee Fill
The Government's payment for the items listed in this CLIN shall constitute full compensation to the Contractor for furnishing all plant, labor, equipment, appliances, and materials; and performing all operations required to complete the
0013 10,800 Cubic
641+00 to 653+00 Berm Fill
The Government's payment for the items listed in this CLIN shall constitute full compensation to the Contractor for furnishing all plant, labor, equipment, appliances, and materials; and performing all operations required to complete the
0014 35,000 Cubic
Breach 706+40 to 720+00 Levee Fill
The Government's payment for the items listed in this CLIN shall constitute full compensation to the Contractor for furnishing all plant, labor, equipment, appliances, and materials; and performing all operations required to complete the
0015 Job Repair of Overtopping Erosion
FFP
The Government's payment for the items listed in this CLIN shall constitute full compensation to the Contractor for furnishing all plant, labor, equipment, appliances, and materials; and performing all operations required to complete the
DELIVERY INFORMATION
CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
0001 180 dys. ANP 1 N/A
0002 180 dys. ANP 1 N/A
0003 790 dys. ANP 1 N/A
0004 180 dys. ANP 1 N/A
0005 100 dys. ANP 1 N/A
0006 100 dys. ANP 130,000 N/A
0007 210 dys. ANP 50,000 N/A
0008 180 dys. ANP 1,500 N/A
0009 180 dys. ANP 7,500 N/A
0010 180 dys. ANP 7,000 N/A
0011 180 dys. ANP 15,500 N/A
0012 120 dys. ANP 24,000 N/A
0013 210 dys. ANP 10,800 N/A
0014 150 dys. ANP 35,000 N/A
0015 180 dys. ANP N/A
Section 00 21 13 - Instructions to Bidders
SUBMISSION REQUIREMENTS:
All bids are due by the time specified in box 13 A.
The public bid opening will begin at the time specified in Box 13 A, at the following address:
Bolling Federal Building US Army Corps of Engineers Civil Contracting Branch 601 E. 12th Street Kansas City, MO 64106 Room S101
Submit one (1) original and one (1) copy of the following:
a. Bid schedule - complete by fully entering all amounts in the supplemental bid schedule.
b. Ensure Bid is signed by a Principal of your company with authority to do so.
c. Ensure all Amendments are acknowledged.
d. Bid Bonds – (Original with raised seal) required with your submission. (See solicitation for details).
INQUIRIES/QUESTIONS:
Prospective Bidders shall submit contracting and technical inquiries and questions concerning this solicitation document via Bidder Inquiry in ProjNet at www.projnet.org/projnet.
a. To submit and review bid inquiry items, bidders will need to be a current registered user or self-register into the system. To self-register, go to the aforementioned web page and click on the BID tab. Select Bidder Inquiry, select agency USACE, enter the Bidder Inquiry Key for this solicitation listed below, your email address, and then click login. Fill in all required information and click create user. Verify that information on the next screen is correct and click continue.
b. From this page, you may view all bidder inquiries or add a new inquiry.
c. Bidders will receive an acknowledgement of their questions via email, followed by an answer to their questions after it has been processed by our technical team. ***Please Note: Bidders shall only submit one (1) Question per inquiry. All inquiries containing multiple questions shall be rejected***
d. The Solicitation Number is: W912DQ20B1041
e. The Plan Room Key is: JCZJRY-7MFJ58
f. The Bidder Inquiry Key is: H6V8M4-9KU994
The Bidder Inquiry System will be unavailable for new inquiries after 29 May 2020, at 5:00 PM local, Kansas City, time in order to ensure adequate time is allotted to form an appropriate response to inquiries and amend the Solicitation if necessary.
Bidders are requested to review the specification in its entirety, and review the Bidder Inquiry System for answers to questions prior to submission of a new inquiry.
The ProjNet call center operates weekdays from 8AM to 5PM U.S. Central Time Zone (Chicago) or by appointment for OCONUS. The telephone number for the Call Center is 1-800-428-HELP. Email to staff@rcesupport.com.
(End of Submission Requirements)
SUPPLEMENTAL BID SCHEDULE:
CLAUSES INCORPORATED BY REFERENCE
52.204-6 Unique Entity Identifier OCT 2016 52.204-16 Commercial and Government Entity Code Reporting JUL 2016 52.207-1 Notice Of Standard Competition MAY 2006 52.214-34 Submission Of Offers In The English Language APR 1991 52.214-35 Submission Of Offers In U.S. Currency APR 1991 52.222-23 Notice of Requirement for Affirmative Action to Ensure
Equal Employment Opportunity for Construction
FEB 1999
52.225-10 Notice of Buy American Requirement--Construction Materials
MAY 2014
252.204-7008 Compliance With Safeguarding Covered Defense Information Controls
OCT 2016
252.215-7007 Notice of Intent to Resolicit JUN 2012 252.225-7050 Disclosure of Ownership or Control by the Government of a
Country that is a State Sponsor of Terrorism
DEC 2018
252.227-7028 Technical Data or Computer Software Previously Delivered to the Government
JUN 1995
252.236-7008 Contract Prices-Bidding Schedules DEC 1991
CLAUSES INCORPORATED BY FULL TEXT
52.204-7 SYSTEM FOR AWARD MANAGEMENT (OCT 2018)
(a) Definitions. As used in this provision--
Electronic Funds Transfer (EFT) indicator means a four-character suffix to the unique entity identifier. The suffix is assigned at the discretion of the commercial, nonprofit, or Government entity to establish additional System for Award Management records for identifying alternative EFT accounts (see subpart 32.11) for the same entity.
Registered in the System for Award Management (SAM) means that--
(1) The Offeror has entered all mandatory information, including the unique entity identifier and the EFT indicator, if applicable, the Commercial and Government Entity (CAGE) code, as well as data required by the Federal Funding Accountability and Transparency Act of 2006 (see subpart 4.14) into SAM;
(2) The offeror has completed the Core, Assertions, and Representations and Certifications, and Points of Contact sections of the registration in SAM;
(3) The Government has validated all mandatory data fields, to include validation of the Taxpayer Identification Number (TIN) with the Internal Revenue Service (IRS). The offeror will be required to provide consent for TIN validation to the Government as a part of the SAM registration process; and
(4) The Government has marked the record ``Active''.
Unique entity identifier means a number or other identifier used to identify a specific commercial, nonprofit, or Government entity. See www.sam.gov for the designated entity for establishing unique entity identifiers.
(b)(1) An Offeror is required to be registered in SAM when submitting an offer or quotation, and shall continue to be registered until time of award, during performance, and through final payment of any contract, basic agreement, basic ordering agreement, or blanket purchasing agreement resulting from this solicitation.
(2) The Offeror shall enter, in the block with its name and address on the cover page of its offer, the annotation ``Unique Entity Identifier'' followed by the unique entity identifier that identifies the Offeror's name and address exactly as stated in the offer. The Offeror also shall enter its EFT indicator, if applicable. The unique entity identifier will be used by the Contracting Officer to verify that the Offeror is registered in SAM.
(c) If the Offeror does not have a unique entity identifier, it should contact the entity designated at www.sam.gov for establishment of the unique entity identifier directly to obtain one. The Offeror should be prepared to provide the following information:
(1) Company legal business name.
(2) Tradestyle, doing business, or other name by which your entity is commonly recognized.
(3) Company physical street address, city, state, and Zip Code.
(4) Company mailing address, city, state and Zip Code (if separate from physical).
(5) Company telephone number.
(6) Date the company was started.
(7) Number of employees at your location.
(8) Chief executive officer/key manager.
(9) Line of business (industry).
(10) Company headquarters name and address (reporting relationship within your entity).
(d) Processing time should be taken into consideration when registering. Offerors who are not registered in SAM should consider applying for registration immediately upon receipt of this solicitation. See https://www.sam.gov for information on registration.
(End of Provision)
52.214-3 AMENDMENTS TO INVITATIONS FOR BIDS (DEC 2016)
(a) If this solicitation is amended, then all terms and conditions which are not modified remain unchanged.
(b) (1) Bidders shall acknowledge receipt of any amendment to this solicitation--
(i) By signing and returning the amendment;
(ii) By identifying the amendment number and date in space provided for this purpose on the form for submitting a bid;
(iii) By letter;
(iv) By facsimile, if facsimile bids are authorized in the solicitation; or
(v) By email, if email bids are authorized in the solicitation.
(2) The Government must receive the acknowledgement by the time and at the place specified for receipt of bids.
(End of provision)
52.214-4 FALSE STATEMENTS IN BIDS (APR 1984)
Bidders must provide full, accurate, and complete information as required by this solicitation and its attachments.
The penalty for making false statements in bids is prescribed in 18 U.S.C. 1001.
52.214-5 SUBMISSION OF BIDS (DEC 2016)
(a) Bids and bid modifications shall be submitted in sealed envelopes or packages (unless submitted by electronic means) (1) addressed to the office specified in the solicitation, and (2) showing the time and date specified for receipt, the solicitation number, and the name and address of the bidder.
(b) Bidders using commercial carrier services shall ensure that the bid is addressed and marked on the outermost envelope or wrapper as prescribed in subparagraphs (a)(1) and (2) of this provision when delivered to the office specified in the solicitation.
(c) Facsimile bids, modifications, or withdrawals, will not be considered unless authorized by the solicitation.
(d) Bids submitted by electronic commerce shall be considered only if the electronic commerce method was specifically stipulated or permitted by the solicitation.
52.214-6 EXPLANATION TO PROSPECTIVE BIDDERS (APR 1984)
Any prospective bidder desiring an explanation or interpretation of the solicitation, drawings, specifications, etc., must request it in writing soon enough to allow a reply to reach all prospective bidders before the submission of their bids. Oral explanations or instructions given before the award of a contract will not be binding. Any information given a prospective bidder concerning a solicitation will be furnished promptly to all other prospective bidders as an amendment to the solicitation, if that information is necessary in submitting bids or if the lack of it would be prejudicial to other prospective bidders.
52.214-6 EXPLANATION TO PROSPECTIVE BIDDERS (APR 1984)
Any prospective bidder desiring an explanation or interpretation of the solicitation, drawings, specifications, etc., must request it in writing soon enough to allow a reply to reach all prospective bidders before the submission of their bids. Oral explanations or instructions given before the award of a contract will not be binding. Any information given a prospective bidder concerning a solicitation will be furnished promptly to all other prospective bidders as an amendment to the solicitation, if that information is necessary in submitting bids or if the lack of it would be prejudicial to other prospective bidders.
52.214-7 LATE SUBMISSIONS, MODIFICATIONS, AND WITHDRAWALS OF BIDS (NOV 1999)
(a) Bidders are responsible for submitting bids, and any modifications or withdrawals, so as to reach the Government office designated in the invitation for bids (IFB) by the time specified in the IFB. If no time is specified in the IFB, the time for receipt is 4:30 p.m., local time, for the designated Government office on the date that bids are due.
(b)(1) Any bid, modification, or withdrawal received at the Government office designated in the IFB after the exact time specified for receipt of bids is “late” and will not be considered unless it is received before award is made, the Contracting Officer determines that accepting the late bid would not unduly delay the acquisition; and--
(i) If it was transmitted through an electronic commerce method authorized by the IFB, it was received at the initial point of entry to the Government infrastructure not later than 5:00 p.m. one working day prior to the date specified for receipt of bids; or
(ii) There is acceptable evidence to establish that it was received at the Government installation designated for receipt of bids and was under the Government's control prior to the time set for receipt of bids.
(2) However, a late modification of an otherwise successful bid that makes its terms more favorable to the Government, will be considered at any time it is received and may be accepted.
(c) Acceptable evidence to establish the time of receipt at the Government installation includes the time/date stamp of that installation on the bid wrapper, other documentary evidence of receipt maintained by the installation, or oral testimony or statements of Government personnel.
(d) If an emergency or unanticipated event interrupts normal Government processes so that bids cannot be received at the Government office designated for receipt of bids by the exact time specified in the IFB and urgent Government requirements preclude amendment of the IFB, the time specified for receipt of bids will be deemed to be extended to the same time of day specified in the solicitation on the first work day on which normal Government processes resume.
(e) Bids may be withdrawn by written notice received at any time before the exact time set for receipt of bids. If the IFB authorizes facsimile bids, bids may be withdrawn via facsimile received at any time before the exact time set for receipt of bids, subject to the conditions specified in the provision at 52.214-31, Facsimile Bids. A bid may be withdrawn in person by a bidder or its authorized representative if, before the exact time set for receipt of bids, the identity of the person requesting withdrawal is established and the person signs a receipt for the bid.
52.214-7 LATE SUBMISSIONS, MODIFICATIONS, AND WITHDRAWALS OF BIDS (NOV 1999)
(a) Bidders are responsible for submitting bids, and any modifications or withdrawals, so as to reach the Government office designated in the invitation for bids (IFB) by the time specified in the IFB. If no time is specified in the IFB, the time for receipt is 4:30 p.m., local time, for the designated Government office on the date that bids are due.
(b)(1) Any bid, modification, or withdrawal received at the Government office designated in the IFB after the exact time specified for receipt of bids is “late” and will not be considered unless it is received before award is made, the Contracting Officer determines that accepting the late bid would not unduly delay the acquisition; and--
(i) If it was transmitted through an electronic commerce method authorized by the IFB, it was received at the initial point of entry to the Government infrastructure not later than 5:00 p.m. one working day prior to the date specified for receipt of bids; or
(ii) There is acceptable evidence to establish that it was received at the Government installation designated for receipt of bids and was under the Government's control prior to the time set for receipt of bids.
(2) However, a late modification of an otherwise successful bid that makes its terms more favorable to the Government, will be considered at any time it is received and may be accepted.
(c) Acceptable evidence to establish the time of receipt at the Government installation includes the time/date stamp of that installation on the bid wrapper, other documentary evidence of receipt maintained by the installation, or oral testimony or statements of Government personnel.
(d) If an emergency or unanticipated event interrupts normal Government processes so that bids cannot be received at the Government office designated for receipt of bids by the exact time specified in the IFB and urgent Government requirements preclude amendment of the IFB, the time specified for receipt of bids will be deemed to be extended to the same time of day specified in the solicitation on the first work day on which normal Government processes resume.
(e) Bids may be withdrawn by written notice received at any time before the exact time set for receipt of bids. If the IFB authorizes facsimile bids, bids may be withdrawn via facsimile received at any time before the exact time set for receipt of bids, subject to the conditions specified in the provision at 52.214-31, Facsimile Bids. A bid may be withdrawn in person by a bidder or its authorized representative if, before the exact time set for receipt of bids, the identity of the person requesting withdrawal is established and the person signs a receipt for the bid.
52.214-18 PREPARATION OF BIDS--CONSTRUCTION (APR 1984)
(a) Bids must be (1) submitted on the forms furnished by the Government or on copies of those forms, and (2) manually signed. The person signing a bid must initial each erasure or change appearing on any bid form.
(b) The bid form may require bidders to submit bid prices for one or more items on various bases, including--
(1) Lump sum bidding;
(2) Alternate prices;
(3) Units of construction; or
(4) Any combination of subparagraphs (1) through (3) above.
(c) If the solicitation requires bidding on all items, failure to do so will disqualify the bid. If bidding on all items is not required, bidders should insert the words "no bid" in the space provided for any item on which no price is submitted.
(d) Alternate bids will not be considered unless this solicitation authorizes their submission.
52.214-19 CONTRACT AWARD--SEALED BIDDING--CONSTRUCTION (AUG 1996)
(a) The Government will evaluate bids in response to this solicitation without discussions and will award a contract to the responsible bidder whose bid, conforming to the solicitation, will be most advantageous to the Government, considering only price and the price-related factors specified elsewhere in the solicitation.
(b) The Government may reject any or all bids, and waive informalities or minor irregularities in bids received.
(c) The Government may accept any item or combination of items, unless doing so is precluded by a restrictive limitation in the solicitation or the bid.
(d) The Government may reject a bid as nonresponsive if the prices bid are materially unbalanced between line items or subline items. A bid is materially unbalanced when it is based on prices significantly less than cost for some work and prices which are significantly overstated in relation to cost for other work, and if there is a reasonable doubt that the bid will result in the lowest overall cost to the Government even though it may be the low evaluated bid, or if it is so unbalanced as to be tantamount to allowing an advance payment.
(End of provison)
52.216-1 TYPE OF CONTRACT (APR 1984)
The Government contemplates award of a Firm- Fixed Price (FFP) contract resulting from this solicitation.
52.228-1 BID GUARANTEE (SEP 1996)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States.
The Contracting Officer will return bid guarantees, other than bid bonds, (1) to unsuccessful bidders as soon as practicable after the opening of bids, and (2) to the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.-
(c) The amount of the bid guarantee shall be 20 percent of the bid price or $3,000,000.00, whichever is less.-
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.-
(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
52.233-2 SERVICE OF PROTEST (SEP 2006)
(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from
U.S. Army Corps of Engineers – Kansas City District
CECT-NWK-C
601 East 12th ST. Room 647 Kansas City, MO 64106-2896 ATTN: David Best
(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.
52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) – ALTERNATE I (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) An organized site visit has been scheduled for—
Date: 20 May 2020
Time: 09:00 AM CST local time, Kansas City, MO POC: Kent Myers Phone: 816-389-3399 Email: Kent.N.Myers@usace.army.mil
(c) Participants will meet at—
805 E Broadway St
Brunswick, MO 65236 Approximate GPS Lat. 39°25’20.5”, Long. -93°07’7.5”
***ATVs or UTVs will be necessary to see the project site from the ground.***
In order to view the locations for this site, an ATV\UTV will be required. The government will not supply transportation for non-governmental personnel. Contractors should provide their own ATV\UTV to participate fully in the site visit."
The site visit is not mandatory. It will be held despite the “STAY HOME MISSOURI” order, as levee rehabilitation efforts are considered critical infrastructure projects and essential work\service.
Please follow all CDC recommendation if at all possible. Everyone is reminded of the social distancing rules – No handshakes, stay 6 feet away from each other and if you have been sick recently or feel you may be sick, or exposed to someone that has been sick, STAY HOME."
52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):
Federal Acquisition Regulations System (FAR) https://www.acquisition.gov/browse/index/far
Department of Defense Federal Acquisition Regulation Supplement https://www.acq.osd.mil/dpap/dars/dfarspgi/current/index.html
Department of Army Federal Acquisition Regulation Supplement https://spcs3.kc.army.mil/asaalt/procurement/AFARS/Home.aspx
252.211-7002 AVAILABILITY FOR EXAMINATION OF SPECIFICATIONS, STANDARDS, PLANS,
DRAWINGS, DATA ITEM DESCRIPTIONS, AND OTHER PERTINENT DOCUMENTS (DEC. 1991)
The specifications, standards, plans, drawings, data item descriptions, and other pertinent documents cited in this solicitation are not available for distribution but may be examined at the following location:
ProjNet at www.projnet.org/projnet The Plan Room Key is: JCZJRY-7MFJ58
252.215-7008 ONLY ONE OFFER (JUL 2019)
(a) Cost or pricing data requirements. After initial submission of offers, if the Contracting Officer notifies the Offeror that only one offer was received, the Offeror agrees to--
(1) Submit any additional cost or pricing data that is required in order to determine whether the price is fair and reasonable or to comply with the statutory requirement for certified cost or pricing data (10 U.S.C. 2306a and FAR 15.403-3); and
(2) Except as provided in paragraph (b) of this provision, if the acquisition exceeds the certified cost or pricing data threshold and an exception to the requirement for certified cost or pricing data at FAR 15.403-1(b)(2) through (5) does not apply, certify all cost or pricing data in accordance with paragraph (c) of DFARS provision 252.215-7010, Requirements for Certified Cost or Pricing Data and Data Other Than Certified Cost or Pricing Data, of this solicitation.
(b) Canadian Commercial Corporation. If the Offeror is the Canadian Commercial Corporation, certified cost or pricing data are not required. If the Contracting Officer notifies the Canadian Commercial Corporation that additional data other than certified cost or pricing data are required in accordance with DFARS 225.870-4(c), the Canadian Commercial Corporation shall obtain and provide the following:
(1) Profit rate or fee (as applicable).
(2) Analysis provided by Public Works and Government Services Canada to the Canadian Commercial Corporation to determine a fair and reasonable price (comparable to the analysis required at FAR 15.404-1).
(3) Data other than certified cost or pricing data necessary to permit a determination by the U.S. Contracting Officer that the proposed price is fair and reasonable [U.S. Contracting Officer to provide description of the data required in accordance with FAR 15.403-3(a)(1) with the notification].
(4) As specified in FAR 15.403-3(a)(4), an offeror who does not comply with a requirement to submit data that the U.S. Contracting Officer has deemed necessary to determine price reasonableness or cost realism is ineligible for award unless the head of the contracting activity determines that it is in the best interest of the Government to make the award to that offeror.
(c) Subcontracts. Unless the Offeror is the Canadian Commercial Corporation, the Offeror shall insert the substance of this provision, including this paragraph (c), in all subcontracts exceeding the simplified acquisition threshold defined in FAR part 2.
Section 00 22 13 - Supplementary Instructions to Bidders
SPECIAL CONTRACT REQUIREMENTS:
FIELD OFFICE OVERHEAD (JUL 2002)
NOTICE TO BIDDERS: For your bid to be responsive, you must declare below the single accounting practice that you apply to contracts to calculate field office overhead for all change orders, modifications and requests for equitable adjustment. Pursuant to Federal Acquisition Regulations (FAR) Parts 31.105(d)(3) and 31.203(d)(1), an accounting practice that varies from modification to modification is not allowable. Select one of the following:
1. TIME DISTRIBUTION BASE FOR A PER DIEM RATE
If you use this practice, see Special Clause “Field Office Overhead Per Diem Rate” _____
2. DIRECT COST DISTRIBUTION BASE FOR A PERCENTAGE MARKUP
If you use this practice, see Special Clause “Field Office Overhead Percentage Markup” _____
3. OTHER ACCOUNTING PRACTICE THAT IS ALLOWABLE _____
UNDER THE FAR AND THAT USES A SINGLE DISTRIBUTION BASE.
If you choose 3, you must describe the accounting practice in sufficient detail below to allow the contracting officer to determine what accounting practice is being utilized by your company and that it complies with the FAR.
FAILURE TO FULLY COMPLY WITH THE ABOVE REQUIREMENT OR, IF ALTERNATIVE 3 IS
DECLARED AND YOUR DESCRIPTION DOES NOT CLEARLY STATE OR DESCRIBE A CONSISTENT
ACCOUNTING PRACTICE USING A SINGLE DISTRIBUTION BASE, WILL BE CAUSE FOR YOUR BID
TO BE REJECTED AS NON-RESPONSIVE.
(End)
Points of Contact
Contract Specialist: Chris Anderson Phone: 816-389-3850 Email: Christopher.W.Anderson@usace.army.mil
Project Manager: Kent Myers Phone: 816-389-3399 Email: Kent.N.Myers@usace.army.mil
MAGNITUDE OF PROJECT—CONSTRUCTION (Jul 2002)
The magnitude of this project is represented by the following estimated price range (contracting officer mark as appropriate):
_____Less than $25,000
_____Between $25,000 and $100,000
_____Between $100,000 and $250,000
_____Between $250,000 and $500,000
_____Between $500,000 and $1,000,000
_____Between $1,000,000 and $5,000,000
_XX_Between $5,000,000 and $10,000,000
_____Between $10,000,000 and $25,000,000
_____Between $25,000,000 and $100,000,000
_____Between $100,000,000 and $250,000,000
_____Between $250,000,000 and $500,000,000
_____Over $500,000,000
(End)
PROPOSALS TO BECOME PART OF THE CONTRACT
1. When an offeror submits its proposal in response to a Request For Proposals, and a staffing plan including the names and qualifications of key personnel who are proposed to work on the project is required to be submitted, those personnel who are offered will be the same personnel who will actually perform on the project. If, during performance of the contract, it becomes necessary for the contractor to substitute personnel for one of those whose qualifications were the basis for evaluation of the offer and award of the contract, the contractor shall submit to the Contracting Officer the same information that was required in the initial proposal regarding the proposed substitute employee. The Contracting Officer shall have the right to review the qualifications of the proposed substitute employee and to approve or disapprove his or her qualifications. If the proposed substitute employee's qualifications are disapproved by the Contracting Officer, the contractor will propose another employee who does possess equivalent qualifications.
2. When an offeror submits its proposal in response to a Request For Proposals, and the name of a specific subcontractor is a required submittal, then that subcontractor who is offered will be the same subcontractor who will actually perform the specified work on the project. If, during performance of the contract, it becomes necessary for the contractor to substitute a subcontractor for one of those whose qualifications were the basis for evaluation of the offer and award of the contract, the contractor shall submit to the Contracting Officer the same information that was required in the initial proposal regarding the proposed substitute subcontractor. The Contracting Officer shall have the right to review the qualifications of the proposed substitute subcontractor and to approve or disapprove its qualifications. If the proposed substitute subcontractor's qualifications are disapproved by the Contracting Officer, the contractor will propose another subcontractor who does possess equivalent qualifications.
3. When an offeror submits its proposal in response to a Request For Proposals, and a schedule for the performance of the work on the project is a required submittal, the terms of the proposed schedule will become the schedule that will be utilized for completion of the project, adjusted as necessary to reflect the actual issue date of the Notice to Proceed
4. When an offeror submits its proposal in response to a Request For Proposals and that proposal contains any work, materials, methods or other type of betterment that provides an advantage to the Government that is above the minimum requirements contained in the RFP, the terms of the proposal will be the basis for evaluation and, if successful, will become the terms of the contract upon award. If a change in one of those terms is made to one that is less favorable to the Government than the one on which the award of the contract was based, a credit to the Government will be negotiated by the contractor. Only the Contracting Officer has the authority to negotiate a waiver of the terms of the contract.
(End)
Section 00 45 00 - Representations and Certifications
52.209-7 Information Regarding Responsibility Matters OCT 2018 52.209-13 Violation of Arms Control Treaties or Agreements --
Certification.
JUN 2018
252.203-7002 Requirement to Inform Employees of Whistleblower Rights SEP 2013 252.203-7005 Representation Relating to Compensation of Former DoD
Officials
NOV 2011
252.204-7016 Covered Defense Telecommunications Equipment or Services -- Representation
DEC 2019
252.204-7017 Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services -- Representation
DEC 2019
52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (JAN 2020)
(a)(1) The North American Industry Classification System (NAICS) code for this acquisition is 237990.
(2) The small business size standard is $39,500,000.
(3) The small business size standard for a concern which submits an offer in its own name, other than on a construction or service contract, but which proposes to furnish a product which it did not itself manufacture, is 500 employees.
(b)(1) If the provision at 52.204-7, System for Award Management, is included in this solicitation, paragraph (d) of this provision applies.
(2) If the provision at 52.204-7, System for Award Management, is not included in this solicitation, and the Offeror has an active registration in the System for Award…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .