Solicitation - W911SG26RA025re.pdf
PDF 442 KB Posted
- Attached to
- Removal and Replacement of Dishwasher BLDG 20226
- Solicitation number
- W911SG26RA025
About this file
This is a sealed bid solicitation for construction services issued by the U.S. Army Corps of Engineers at Fort Bliss, Texas. The project involves removal and replacement of a commercial dishwasher, food tray accumulator, and water heat booster at Building 20226 dining facility. This is a 100% competitive set-aside for Service-Disabled Veteran-Owned Small Businesses (SDVOSB) under NAICS 238210 with a small business size standard of $19 million. The estimated project magnitude is between $250,000 and $500,000, with a firm fixed-price (FFP) contract structure. Sealed proposals are due by 10:00 a.m. MST on August 26, 2026, and should be emailed to the contracting officer. A mandatory site visit is scheduled for August 19, 2026, at 10:00 a.m. MST, limited to two attendees per company. Written questions must be submitted by August 21, 2026, by 4:00 p.m. MST.
Award will be made using the Lowest Price Technically Acceptable (LPTA) evaluation method based on three non-price factors evaluated as acceptable or unacceptable: Technical (most significant), Past Performance (significantly more important than price), and Price (least significant). The contractor must demonstrate experience as a prime contractor on at least three construction projects of equal or greater size and complexity within the last five years. Performance and payment bonds equal to 100% of the awarded price are required, along with an offer guarantee. The contract period of performance is 180 calendar days after issuance of the Notice to Proceed. The contractor must provide a superintendent at all times during work, which is a key non-subcontractable position. All work must comply with International Code Council standards, Unified Facilities Criteria, NFPA 101 Life Safety Code, OSHA regulations, and Fort Bliss regulations. The facility will remain occupied during construction, and coordination with the Contracting Officer is required before utility shutdowns, with a minimum three-week advance notice required.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(See ).
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair) IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR
INFORMATION CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".
SOLICITATION
1. SOLICITATION NUMBER
5. REQUISITION/PURCHASE REQUEST NUMBER
CODE
6. PROJECT NUMBER
8. ADDRESS OFFER TO
4. CONTRACT NUMBER
7. ISSUED BY
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)
11. The contractor shall begin performance within
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES", indicate within how many calendar days after award in Item 12b.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and
b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d. Offers providing less than
STANDARD FORM 1442 (REV. 12/2022)
Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
is, is not required.
local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.
calendar days and complete it within calendar days after receiving
a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
12b. CALENDAR DAYS
2. TYPE OF SOLICITATION
SEALED BID (IFB)
INVITATION FOR BID
NEGOTIATED (RFP)
REQUEST FOR PROPOSAL
3. DATE ISSUED PAGE OF PAGES
W911SG26RA025 14 AUG 2026 1 88
LOG 10146 6J
W6QM MICC-FT BLISS
BLDG 111, 111 PERSING RD
FORT BLISS, TX 79916-6812
UNITED STATES
CHARLES JOHNSON, EMAIL: CHARLES.D.JOHNSON12.CIV@ARMY.MIL
TELEPHONE: 9155685150
W911SG
CHARLES JOHNSON 9155685150
PROJECT TITLE: REMOVAL AND REPLACEMENT OF DISHWASHER BLDG 20226
PROJECT LOCATION: FT. BLISS TX
PROJECT TITLE: REMOVE AND REPLACE DISHWASHER AT BLDG 20226
LOCATION: FORT BLISS TX
PROJECT INCLUDES THE REMOVAL AND REPLACEMENT OF THE EXISTING COMMERCIAL DISHWASHER, FOOD TRAY ACCUMULATOR, AND WATER HEAT BOOSTER AT THE EXISTING DINING FACILITY, BUILDING 20226. THE CONTRACTOR SHALL PROVIDE A NEW COMMERCIAL DISHWASHER, THAT MEETS OR EXCEEDS THE
EXISTING UNIT.
THE CONTRACTOR SHALL PROVIDE ALL WORK, LABOR, MATERIALS, RELATED FEES, AND RELATED SERVICES FOR CONSTRUCTION REQUESTED HEREIN UNTIL COMPLETION AND ACCEPTANCE OF THE ENTIRE WORK, EXCEPT FOR ANY COMPLETED UNIT OF WORK WHICH MAY HAVE BEEN ACCEPTED UNDER THE CONTRACT, BY THE GOVERNMENT IN A PROFESSIONAL AND COLLABORATIVE ENVIRONMENT TO SUSTAIN MISSION REQUIREMENTS. CONSTRUCTION SERVICES AND FINISHED PRODUCTS SHALL BE DELIVERED ON SCHEDULE, SAFELY, AND COMPLIANT WITH REGULATORY CODES AND STANDARDS.
THIS IS A 100% COMPETITIVE SET-A SIDE FOR SERVICE-DISABLED VETERAN OWNED SMALL BUSINESS. NAICS 238210 WITH A SMALL BUSINESS SIZE STANDARD
OF $19 MILLMILLION.
THE ESTIMATED MAGNITUDE OF CONSTRUCTION FOR THIS PROJECT IS BETWEEN $250,000.00 AND $500,000.00.
THE AWARDEE OF THIS CONTRACT WILL BE REQUIRED TO PROVIDE A SUPERINTENDENT AT ALL TIMES WORK IS BEING PERFORMED ON THE PROJECT (SEE CLAUSE AT FAR 52.236-6). THE SUPERINTENDENT IS CONSIDERED A KEY POSITION. THIS POSITION SHALL NOT BE SUBCONTRACTED AND MUST WORK DIRECTLY
FOR THE PRIME CONTRACTOR. ALL WORK SHALL BE PERFORMED SIMULTANEOUSLY .
RESULTING CONTRACT WILL BE FRIM FIXED PRICED (FFP)
5 180
FAR 52.211-10
10:00 AM
26 AUG 2026
AWARD (To be completed by Government)
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
OFFER (Must be fully completed by offeror)
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT
NUMBER
DATE
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)
CODE FACILITY CODE
15. TELEPHONE NUMBER (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14.)
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)
21. ITEMS ACCEPTED:
22. AMOUNT
26. ADMINISTERED BY
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)
31c. DATE
STANDARD FORM 1442 (REV. 12/2022) BACK
31b. UNITED STATES OF AMERICA
BY
31a. NAME OF CONTRACTING OFFICER (Type or print)
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30b. SIGNATURE 30c. DATE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
copies to issuing office.) Contractor agrees to furnish
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
23. ACCOUNTING AND APPROPRIATION DATA
ITEM
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES
CODE AT
27. PAYMENT WILL BE MADE BY
10 U.S.C. 3204(a) ( ) 41 U.S.C. 3304(a) ( )
20b. SIGNATURE 20c. OFFER DATE
W911SG26RA025
1. POINT OF CONTACT:
Charles D. Johnson Contract Specialist
Email: charles.d.johnson12.civ@army.mil
2. This procurement is a Small Business set-aside acquisition SDVOSB set-aside acquisition.
3. The Government has scheduled a one-day site visit at BLDG 20226 Ft. Bliss TX SITE VISIT:
at 10:00 a.m. MST on 19 August 2026.
a. We will meet at the:
The parking lot of Bldg. 20226 Ft. Bliss, TX
Work is located at Building 20226.
b. Contractors who wish to attend the site visit shall provide the name(s), company name, position title, telephone number, email address and mailing address of all attendees via email to charles.d.
johnson12.civ@army.mil no later than 4:00 p.m. MST on 18 August 2026.
c. The site visit is limited to a maximum of two (2) attendees per company. Contractor representatives should be prepared to furnish identification if requested.
d. Individual or group questions will not be answered during the site visit. Potential offerors may submit written questions in accordance with number 4 (below) of these instructions to offerors section.
Note: Remarks and explanations made by the Government representatives during the course of the site visit, whether orally or in writing, shall not change or qualify any of the terms or conditions of this solicitation. The solicitation can only be changed by a formal, written amendment issued by the Contracting Officer (KO).
4. All offeror inquiries or questions shall be submitted in REQUEST FOR INFORMATION (RFI)
Writing electronically at charles.d.johnson12.civ@army.mil no later than 21 August 2026 by 4:00 p.
m. MST. An amendment will then be issued with all questions and answers. **After the due date no additional RFI's will be answered**
5. Proposals are due no later than 10:00 a.m. MST on 26 August 2026. PROPOSAL DUE DATE:
Proposals shall be emailed to charles.d.johnson12.civ@army.mil. Proposals SHALL include the following in order to be considered (failure to include all line items shall be subject for rejection of the offer):
a. Cover sheet on company letterhead with your DUNS number, CAGE code, Tax ID, and primary point of contact information;
b. Signed and completed Standard Form 1442 along with any amendments;
c. Letter from bonding company indicating offeror's ability to obtain payment bonds in the amount of their offer;
d. Past Performance per Evaluation Factors.
Please note that all correspondence via e-mail shall contain a subject line that reads, "Removal and Installation of Dishwasher BLDG 20226, Company Name". If sending attachments via e-mail, ensure only .pdf, .doc or .xls documents are sent. In the body of the email please ensure to list the number of attachments submitted. It is the Contractor's responsibility to verify all emails along with all attachments are received by the Contract Specialist listed above.
6. BONDNG REQUIREMENTS:
a. Payment Bonds:
(1) The penal amount of the bonds shall be 100 percent of the awarded price.
(2) The Government may require additional bond protection when a contract price is increased.
The increase in protection shall generally equal 100 percent of the increase in contract price. The Government may secure additional protection by directing the contractor to increase the penal amount of the existing bond or obtain an additional bond.
b. Offer Guarantee:
(1) An Offer Guarantee is required.
7. Offeror must be registered in the database SYSTEM FOR AWARD MANAGEMENT (SAM):
IAW FAR 52.204-7 in order to be awarded a contract and have the applicable NAICS code listed in FAR 52.219-1(c), Small Business Program Representations (Alternate I), Representations.
Evaluation FACTORS
EVALUATION FACTORS FOR AWARD
The Government will award a contract resulting from this solicitation using the evaluation method "Lowest Price Technically Acceptable." This method is appropriate when best value is expected to result from selection of the technically acceptable offer with the lowest evaluated reasonable price.
Offers will be evaluated for acceptability but not ranked using the non-price factors. Evaluation factors and significant sub factors that establish the requirements of acceptability are set forth below. Award will be made on the basis of the lowest evaluated reasonable price of proposals meeting the acceptability standards for non-price factors (RFO FAR 15.103-2). The Government intends to evaluate proposals and award a contract without discussions with offerors (except clarifications as described in RFO FAR 15.202(a)(2)). Therefore, the offeror's initial proposal should contain the offeror's best terms from technical, past performance, and price. The Government reserves the right to conduct discussions if the Contracting Officer later determines them to be necessary. The Government reserves the right to waive informalities and minor irregularities in offers received. If a minor clerical error has occurred, then the offeror may be given an opportunity to correct the minor error within the constraints of the "clarifications" process.
This solicitation is for a firm, fixed price construction contract. Award shall be made to the technically acceptable offer that provides the lowest reasonable price. The Government intends to award a contract to one offeror deemed responsible in accordance with Federal Acquisition Regulation (FAR 9.1).
Offerors are required to submit technical proposals addressing the Evaluation Factors and Sub- Factors identified. The procurement is being conducted utilizing the Lowest Price Technically Acceptable (LPTA) source selection process in accordance with RFO FAR 15.103-2. Proposal will be evaluated for acceptability, but not ranked, using the non-price evaluation factors. Award will be made on the basis of the lowest evaluated reasonable price of proposals meeting the acceptability standards for non-price factors. There shall be no trade-offs. Offers evaluated as not Technically Acceptable will not be eligible for award, regardless of price. The proposal must set forth full, accurate and complete information as required by the solicitation. The Government will rely on such information for the award of the contract. By submission of the offer, the Offeror agrees that all items proposed will be utilized for the duration of the contract and any substitutions will require prior Contracting Officer's approval. The offeror shall be held responsible for the validity of all information supplied in the proposal, including the information provided by potential subcontractors. Should subsequent investigation disclose that the facts and conditions were not as stated, the proposal may be rejected. To ensure timely and equitable evaluation of proposals, offerors must follow the instructions contained herein. Offerors are required to meet all solicitation requirements, including terms and conditions, representations and certifications, and technical requirements, in addition to those identified as evaluation factors or subfactors. Offerors must clearly identify any exception to the solicitation terms and conditions and provide complete accompanying rationale. The response shall consist of three (3) separate parts; Part I -Technical Proposal - Part II -Past Performance-Part III Price Proposal.
The Government's technical evaluation team will evaluate the technical proposals on an acceptable or unacceptable basis, assigning one of the ratings described below for each subfactor.
Any subfactor evaluated as "Unacceptable" will render the entire proposal unacceptable and, therefore, awardable.
Only those proposals determined to be technically acceptable, at time of award, will be considered for award. However, the offeror is reminded that the Government reserves the right to award this effort based on the initial proposal, as received, without discussion.
Rating Description
Acceptable Proposal clearly meets the minimum requirements for solicitation. Unacceptable Proposal does not clearly meet the minimum requirements for solicitation. This solicitation requires the evaluation of price and the following non-price factors:
Factor 1: Technical - Significantly more Important than past performance and price. Evaluation of this factor will be based on the offeror's submission of a project schedule that demonstrates the offeror's understanding of the work requirement including estimated timeframes for ordering supplies and completing construction. Capable of handling specialized commercial kitchen equipment installations. Meet or exceed the performance requirements of the existing unit (model STERO STPCW-ER-18, Hobart WPS-122, Hobart CLP86).
a. Experience - Previous experience will be evaluated as "Acceptable or Non-Acceptable". To be acceptable, offerors must provide information demonstrating they have successfully performed as prime contractors within the last FIVE (5) years* on at least THREE (3) construction project of equal or greater size and complexity and magnitude within the same or similar scope of work as identified in this solicitation. Past performance information shall be obtained by the Contract Specialist from any other sources available to the Government to include, but not limited to, PPIRS or other databases.
Rating Description
Acceptable
Based on the offeror's performance record, the Government has a reasonable expectation that the offeror will successfully perform the required effort, or the offeror's performance record is unknown.
(see note below)
Unacceptable
Based on the offeror's performance record, the Government has no reasonable expectation that the offeror will be able to successfully perform the required effort.
TECHNICAL RATINGS
*The FIVE (5) years shall be calculated from the solicitation issue date.
Factor 2: Past Performance Evaluation: Significantly more important than price, but less important than technical. The Past Performance evaluation results are an assessment of the offeror's probability of meeting the minimum past performance solicitation requirements. This assessment is based on the offeror's record of relevant and recent past performance information that pertains to the requirements outlined in the solicitation. A qualified contractor capable of handling specialized commercial kitchen equipment restaurant-type projects similar in size, scope, and complexity to large-scale DFAC dishwasher or tray conveyor replacements.
Factor 3: Price - Prices will be evaluated for reasonableness through a comprehensive comparison of each proposal received. Reasonableness will be determined based on prices submitted by the competition, current market conditions, and comparison to the Government estimate. Prices will also be evaluated to determine if they are either excessive or insufficient for the effort to be accomplished, and for any unbalanced areas within the offeror's pricing proposal. A price that is too low or too high may endanger the proposal's opportunity for award of a contract.
Evaluation factors: Technical is more significant than both Past Performance and Price. Past Performance is significantly more important than Price but not more than Technical. Price is less significant than the factors of Technical and Past Performance.
Each proposal shall be evaluated to ensure that all information provided in the RFP has been addressed, is accurate and complete.
STATEMENT OF WORK
PART 1 - DESCRIPTION OF WORK
1.1. Scope of work includes the removal and replacement of the existing commercial Objectives.
dishwasher, food tray accumulator, and water heat booster at the existing Dining Facility, building 20226. The Contractor shall provide a new commercial dishwasher, food tray accumulator, and water heat booster, and all associated components with a capacity that meets or exceed the existing units. The Contractor shall provide all work, labor, materials, related fees, and related services for construction requested herein until completion and acceptance of the entire work, except for any completed unit of work which may have been accepted under the contract, by the Government in a professional and collaborative environment to sustain mission requirements.
Construction services and finished products shall be delivered on schedule, safely, and compliant with regulatory codes and standards.
1.2. . The period of performance shall be [hundred and eighty (180)] Period of Performance calendar days after issuance of Notice to Proceed (NTP).
1.2.1.The Contractor shall not commence work unless authorized by the Contracting Officer (KO).
All technical questions shall be addressed to the Contracting Officer's Representative (COR) for resolution and clarification.
1.3. The work to be performed under this contract will be performed in Place of Performance.
Building 20226, located within the Fort Bliss TX Installation.
1.3.1 : Facility will be occupied during construction. Do not enter the facility without Occupancy prior approval of the KO.
1.3.2. All work shall adhere to and comply with the most current International Code Council (ICC), the Unified Facilities Criteria (UFC) https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc [military amended codes], NFPA 101 Life Safety Code, the Architectural Barriers Act (ABA) and all other Local, State and Federal Regulations, Codes, and Standards. All Unified Facilities Guide Specifications (UFGS) shall be used for this project (https://www.wbdg.org/guides specifications).
1.4 Specific Work Requirements.
1.4.1. Contractor shall ensure safe access to and egress from building and other adjacent occupied or used facilities during construction and shall provide all required barricades, fencing, covered walkways, planking, lighting, bracing, shoring, warning signs, etc. as required by OSHA and Fort Bliss Regulations for the protection of workmen, staff and Users.
1.4.2. The exact location and quantity of existing ductwork, penetrations, and equipment shall be field verified by the Contractor. Contractor shall examine existing structures, note all conditions as to character and extent of all work involved, validate and Bid accordingly.
1.4.3.Contractor shall field verify all dimensions, exact locations and quantities before commencing Work.
1.4.4. Electric Kitchen Equipment.
1.4.5. Prior to the removal and installation of the new tray accumulator, dishwasher and water heater booster coordinate with the COR and customer before utility shut down. Provide a minimum of 3-weeks' notice prior to the schedule utility shutdown.
1.4.6. The contractor shall disconnect all connecting utilities, then remove and dispose of the existing commercial dishwasher, tray accumulator and water heater.
1.4.7. Remove existing dishwasher, tray accumulator, soiled dish table and water heater booster.
Install new dishwasher, tray accumulator and water heater booster. Disconnect existing plumbing and electrical components to the dishwasher, water heater booster and tray accumulator if necessary. Contractor is responsible for verifying all existing equipment type, size, dimensions, and electrical and plumbing conditions.
1.4.8 Disconnect, remove and replace copper plumbing connections for the soiled dishtable station. Provide all new water and drain copper piping and fiberglass, ASJ facing tube insulation.
New piping shall be equal in size to existing and new shut oof insulation valves. Soiled dishtable shall be move back to original location and reconnect to the existing location.
1.4.9.Remove any ceiling tile if new tile if necessary and replace it with new ceiling tile to match existing.
1.4.10. New dishwasher shall have 76.1 Amps, 3-phase, 480 volts, 60 cycle, cold water size 3/4, direct drain size 2 inches, and direct drain size above finish floor 7 inches or approve equal.
Contractor shall field verify all electrical components, plumbing and equipment connections as per industry standards. Existing dishwasher is manufactured by STERO Company with model number STPCW-ER-18 and serial number 75764-4-08. Dishwasher shall be UL 921 with detergent dispenser. Provide dishwasher that is energy stat labeled. Provide automatic control to cycle machine through wash, rinse, dry or heat, and stop phases. Include manual setting to repeat or skip phases of cycle. Dishwasher shall have a safety switch that automatically stops spraying action when door is open. Install kitchen equipment in accordance with manufacture's instructions.
1.4.11The contractor shall be responsible for verifying the electrical requirements of the existing dishwasher and tray accumulator and determine if the new dishwasher and tray accumulator will require additional circuit breakers at Panel KN5 (208Y/120V 3PH 4W).
1.4.12. The contractor shall provide and install all piping and fittings, gate valves shock arrestors, tail pieces, traps, water line strainers, gas valves, regulators, etc. As necessary for all equipment where these items are not provided as standard by the equipment manufacturer.
1.4.13. Provide chemical pumps for detergent and rinse and ensure the lines are connected to the proper chemical container as per the manufacturer's recommendations.
1.4.14.Provide a new tray accumulator STERO Company or approved equal with NSF/ANSI 2, factory assembled, under counter model with welded steel channel frame, polished stainless steel enclosure, removable accel panel on three sides, and minimum 4 inch diameter chrome plated.
Existing tray accumulator is manufactured by STERO Company with model STAC-15 and serial number 75763-4-08. Provide manufacturer's standard dispenser mechanism to maintainORK the dispensing height at a constant level with stainless steel carriers. Tray accumulator shall have minimum of 7 Amps 1- phase, 60HZ, 120 volts and 1/2 HP. Contractor shall field verify all electrical components, plumbing and equipment connections as per industry standards. Tray accumulator shall accommodate existing size tray and shall hold five tray per carrier. Accumulator shall be provided with anti-jam switches with quick brakes. Ensured the dishwasher and tray conveyer are properly secured to prevent any movement.
1.4.15. New tray accumulator shall have conveyor belt to consist of low friction polycarbonate compound and replaceable without the use of special tool and disassembling of entire belt.
Conveyor bed to be 14 gauge stainless steel bed with longitudinal intersection rounded on 3/4 radius. Contractor must field verify all electrical components, plumbing and equipment connections as per industry standards. Stainless steel channel cross braces on approximately 5' 0" centers to be provided supporting the bed and side track. Motor to be controlled manually by an on/off switch and automatically through a limit switch as required by application. All wired to the watertight SCR solid state D.C. controller with overload protection in NEMA 4 enclosure.
1.4.16 The Contractor shall provide a commercial water heater booster with all associated components with the capacity the meets or exceeds the existing units. The water heater booster shall meet the recommendations of the dishwasher manufacturer. Contractor is responsible for verifying in person all existing equipment type, size, dimensions, and electrical, mechanical and plumbing conditions. Existing booster heater is rated 18kW, 480V, 3-Phase with a current draw of
21.7 Amps.
1.4.17 Contractor shall perform operation tests on each piece of equipment to determine that components, including controls, safety devices, and attachments, operate properly and in accordance with specified requirements. Ensure that all components are properly installed and function as per the manufacture recommendations.
1.4.17.1. Contractors shall review the Fire Prevention Construction Guide 2025 prior to construction work. Contractor to field verify existing fire alarm conditions in the Work Area and take photo documentation for record purposes prior to construction. Contractor to coordinate fire alarm test with Fort Bliss Fire and DPW PM prior to construction and once construction is complete to ensure all devices are working properly. Temporarily strap and protect all existing fire devices, light fixtures and diffusers to allow for construction at the ceilings. Fire alarm work shall be done by a certified fire alarm contractor.
1.4.17.2. Furnish incidental work and materials to disconnect, remove, store, secure, protect, and reinstall applicable roof telecommunication equipment, connections, and features. Protect temporary terminations. Any communication cable either Fiber or Copper coming in aerially into the building will need to be decommissioned, prevented from being damaged, and re-installed per the current Installation Information Infrastructure Architecture (I3A) and UFC Army regulations and standards. Any damage or cut cables will be reported to The Project Manager Network Enterprise Center (NEC). Operations & Plans Branch via the COR.
1.4.17.3 Current I3A Army Communication Standards 2010. If any communication lines, equipment, or hardware is disturbed, it will need to be reinstalled IAW the most current 3 UFC 580- 01 ISP Communication Standards.
1.4.17.4. If any communication lines need to be moved, please do so IAW I3A and UFC standards.
If trenching or marking is required, please submit requests to usarmy.bliss.106-sig-bde.mbx.nec dig-permits@mail.mil as we are not tied in with 811. Please contact the Network Enterprise Center (NEC) before disturbing any communications equipment the contractor may come across (network switches, fiber lines, etc.). Please do not dispose of any communications equipment the contractor may come across. Please request a site visit by the NEC NLT 7 days prior to work start date and NLT 7 days prior to project completion to ensure surveys and inspections ensuring communication lines are operational. If fiber needs to be pulled through duct banks, please ensure pathways have been checked and cleared.
1.4.18. . Mechanical/Plumbing/HVAC
1.5 Attachments.
A. Environmental Review Form
B. ESD-RFI Template
C. Drawing sets -Asbuilts
D. Eng_Form_4288-R, Submittal Register
E. Fort Bliss Solid Waste Program
F. Fort Bliss Fire Prevention Construction Guide 2025
G. iWatch Training for Contractors<
H. TRADOC Form 928-R-E, Material Approval Submittal
I. Specifications: All Unified Facilities Guide Specification (UFGS) shall be used for this project including but not limited to those listed below. All specifications can be found at https://www.wbdg.
org/guides-specifications)
UFC 3-110-03 ROOFING, WITH CHANGE 5
UFGS 01 45 00.00 20 QUALITY CONTROL (HVAC)
UFGS 01 45 00.00 40 QUALITY CONTROL (PROCESS)
UFGS 01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
UFGS 01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
UFGS 01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT
UFGS 01 75 00.00 40 STARTING AND ADJUSTING
UFGS 01 78 00 CLOSEOUT SUBMITTALS
UFGS 02 41 00 DEMOLITION AND DECONSTRUCTION
UFGS 05 05 23.16 STRUCTURAL WELDING
UFGS 05 12 00 STRUCTURAL STEEL
UFGS 05 50 13 MISCELLANEOUS METALS
UFGS 05 50 14 STRUCTURAL METAL FABRICATIONS
UFGS 06 10 00 ROUGH CARPENTRY
UFGS 07 22 00 ROOF AND DECK INSULATION
UFGS 07 54 23 THERMOPLASTIC-POLYOLEFIN ROOFING
UFGS 07 60 00 FLASHING AND SHEET METAL
UFGS 07 92 00 JOINT SEALANTS
UFGS 09 90 00 PAINTS AND COATINGS
UFGS 11 31 13 ELECTRIC KITCHEN EQUIPMENT
UFGS 23 03 00.00 20 BASIC MECHANICAL MATERIALS AND METHODS
UFGS 26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS
UFGS 26 05 00.00 40 COMMON WORK RESULTS FOR ELECTRICAL
.PART 2 - GENERAL REQUIREMENTS
2.1 . Basic Guidelines
2.1.1. . Prior to the start of any construction work an authorized Preconstruction Conference representative of the KO will schedule and conduct a preconstruction conference. The notification will include specific details regarding the date, time, and location of the conference, any need for attendance by sub-Contractors, and information regarding the items to be discussed.
2.1.1.1. The Contractor's Project Manager (PM), Superintendent, and Quality Control Manager (QCM) shall attend this meeting. Minutes of the meeting will be prepared and signed by the Contractor. The minutes shall be sent to the COR for review and approval no later than 24 hours after the meeting.
2.1.2. Contractor shall have a copy of the [Paving IDIQ Contract,] Scope Construction Documents.
of Work (SOW), Drawings, and specifications at the construction site at all times.
2.1.3. . The Contractor shall verify all dimensions and investigate existing site Licenses and Permits conditions prior to submitting proposal. The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses and permits. The Contractor shall comply with all applicable laws and regulations, including but not limited to Building Codes, Federal Law, Texas State Law, Occupational Safety and Health Administration (OSHA) regulations, Army and installation regulations.
2.1.4. . Everything included in this paragraph and its subparagraphs is Contractor Furnished Items basic to the contract and should be included in the contract price.
2.1.4.1.The Contractor shall provide all labor, supervision, transportation, vehicles, supplies, equipment, materials and services required to perform work under this contract. The Contractor shall, as necessary, provide all equipment needed to perform the work safely and to meet the requirements herein.
2.1.5. . Contractor shall exercise extreme caution to protect building finishes, Installation Property private property, military property, historic material, cultural resources, etc., from damage during the performance of these contract requirements. Contractor shall be responsible for all loss or damage to Government and private property while executing contract requirements as a result of negligence on behalf of the Contractor, subcontractors, or any representatives of the Contractor or subcontractors."
2.1.6. . Contractor's personnel, whose tasks involve operation of any vehicles, Contractor Vehicles shall possess a valid U.S. state driver's license, certificates and permits, applicable for the type and class of vehicle being operated.
2.1.6.1. Limited Access. The Contractor shall only use existing roadways when transporting personnel and/or material during the execution of the contract. The Contractor shall strictly adhere to the foregoing and shall not develop new ingress or egress roads.
2.1.6.2. Parking. The Contractor shall ensure that its personnel use designated parking areas only.
Personal and non-construction related vehicles shall not be parked on grassy, gravel, or landscaped areas (unless identified as acceptable in drawings).
2.1.6.7. . Construction Materials. Applying to contracts for the construction, Buy American Act alteration, or repair of any public building or public work in the United States, the Contractor shall utilize commercially available off-the-shelf (COTS) construction materials in accordance with Executive Order 10582 and 41 U.S.C. chapter 83, Buy American.
2.2. The personnel listed below are considered essential to the work being Key Personnel.
performed under this contract. Prior to substituting, removing, replacing, or diverting any of the specified individuals, the Contractor shall notify the KO fifteen (15) working days in advance and shall submit a written request and justification (including proposed substitutions) in sufficient detail to permit evaluation of the impact on this Contract. The proposed substitution of personnel must meet or exceed the experience and other technical requirements of the personnel being replaced.
No change in personnel shall be made by the Contractor without the prior written consent of the KO. However, in urgent situations, as determined or agreed to by the KO, an oral request to substitute key personnel may be approved and subsequently ratified by the KO in writing. Such ratification shall constitute the consent of the KO required by this paragraph. The KO will notify the Contractor within ten (10) working days after receipt of all required information of the decision on the substitution(s). In the event the proposed substitution of key personnel does not meet or exceed the experience and other technical requirements of the personnel being replaced, substitution of acceptable replacements for the individuals as specified below. The key personnel listed below may, with the consent of the contracting parties, be amended during the course of the Contract to either add or remove personnel as necessary.
PM
Superintendent
Site Safety and Health Officer (SSHO)/ QCM
2.2.1. . The Contractor shall provide a PM. PM
2.2.1.1. The role of the Construction PM is to be the Government's Point of Contact (POC) for projects and administration of construction. Per project, the PM is accountable for:
2.2.1.1.1. Management of performance of all trade Contractors, review and analysis of SOW, architectural and engineering drawings and specifications; ensuring contract documents and regulations are comprehended and followed; supervision of Construction Superintendent(s), reviewing and approving their reports, submittals, monitor reported difficulties, and correcting safety violations/ deficiencies; developing, tracking, updating and controlling construction schedule; project management plan, and associated costs to achieve completion of project;
coordinating the closure of a project.
2.2.1.2. The PM shall possess the following:
2.2.1.2.1. Language. Full professional working proficiency at speaking, listening, reading, and writing in English.
2.2.1.2.2. Experience. Five (5) years of experience (within the last ten (10) years) working as a Construction PM (or in a position with equivalent responsibilities) managing multiple construction projects simultaneously related to the project.
2.2.2 . The Contractor shall assign one competent superintendent for each task Superintendent project. The superintendent shall be accountable for overall supervision and management of job site coordination, day-to-day operations, schedule adherence, enforcement of safety and quality, managing subcontractors, has authority to act for the Contractor, and shall be on site at all times during Construction. The superintendent is required to attend facility turnover meetings (Red Zone meetings), partnering meetings, and quality control meetings. The qualification requirements for the alternate superintendent are the same as for the superintendent.
2.2.2.1. The Superintendent shall possess the following:
2.2.2.1.1. Language. Full Professional working proficiency at speaking, listening, reading, and writing in English.
2.2.2.1.2. Experience. Five (5) years' experience (within the last ten (10) years) working as a Construction Superintendent (or in a position with equivalent responsibilities), managing multiple construction projects simultaneously related to the project. The superintendent must be familiar with the requirements of Engineering Manual (EM) 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The KO may request proof of the superintendent's qualifications at any point in the project if the performance of the superintendent is in question.
2.2.3. . The SSHO shall be accountable for overall supervision and management of the SSHO Contractor's safety program(s) and plan(s). Contractor shall assign one SSHO for each who will work simultaneously as the SSHO and QCM The SSHO shall be on site at all times during construction to implement and administer the Contractor's safety program and Government accepted Accident Prevention Plan. An alternate shall be identified in the Construction Safety Plan to serve in the event of the SSHO's absence. The requirements for the alternate are the same as the SSHO. The SSHO shall meet the requirements of EM 385-1-1 Chapter 2 Safety and Occupational Health Program management for Contractors. The SSHO must ensure that the requirements of 29 CFR 1926.16 are met for the project. It is responsibility of the Contractor to express to the KO in the event that due to the complexity of the project, one employee will be required for each position.
2.2.3.1. The SSHO shall be the Government's POC for all aspects relating to safety. The SSHO responsibilities include, but are not limited to facilitating and ensuring the completion of facility safety assessments/investigations of reportable and non-reportable mishaps involving personal injury accidents, property damage, and cases of occupational illnesses; recording accident reports in an accurate, complete, and timely manner; assuring that claims for injuries and illnesses are posted in the Occupational Safety and Health Administration log; promoting and furnishing applicable safety and health, accident prevention, and investigation training for Contractor's employees; assessing and evaluating work environment, identifying potential hazards, and aiding Contractor, Construction PM, and Construction Superintendent during work place inspections;
supporting Contractor, Construction PM(s), and Construction Superintendents in investigating accidents and developing measures to prevent recurrences.
2.2.3.2.The Safety Manager shall possess the following:
2.2.3.2.1. Language. Full professional working proficiency at speaking, listening, reading, and writing in English.
2.2.3.2.2 Experience. Five (5) years' experience (within the last ten (10) years) working as a SSHO (or in a position with equivalent responsibilities), identifying potential risks and hazards, investigating accidents, and promote occupational safety on multiple construction projects, simultaneously, related to the project.
2.2.2.2.3. Certification. SSHO shall possess active credentials as a Certified Safety and Health Official (CSHO) in construction or Master Certification (MC) from an OSHA Training Institute Education Centers.
2.2.4. . The QCM shall be accountable for overall supervision and management of the QCM construction's quality control and management program(s) and plan(s). Contractor shall assign one QCM for each project who will work simultaneously as SSHO and QCM. The QCM shall be on site at all times during construction and alternate shall be identified in the Construction Quality Control Plan to serve in the event of the QCM's absence. The requirements for the alternate are the same as the QCM. It is the responsibility of the Contractor to express to the KO in the event that due to the complexity of the project, one employee will be required for each position.
2.2.4.1. The QCM is to be the Government's POC for all aspects relating to quality control. the QCM responsibilities include but are not limited to the supervision and management of the Contractor's quality control and management program(s) and plan(s) in accordance with specifications; inspecting work for conformance to project plans and specifications identifying issues arising during construction and verifying that deficiencies have been corrected; recording and notifying the PM and/or Superintendent of problems on a timely basis so that corrections can be made without impact to the project schedule; creating, updating and maintaining the project submittal log and all other project specific quality control reports; reviewing shop drawings and submittals for conformance with project specifications by direct review and by leveraging the knowledge and experience of others in the project team when necessary; scheduling, reviewing, certifying, and managing submittals, including those of subcontractors, designers of record, consultants, manufacturers, offsite fabricators, suppliers, and purchasing agents; tracking preparatory, initial, and follow-up control phases and control, verification, and acceptance tests including documentation; continuing development of the project Quality Control Plan to address the specific needs of task orders, as required; examining the work area to assure that all required preliminary work has been completed and is in compliance with the contract; reviewing drawings and each paragraph of applicable specifications, reference codes, and standards applicable to work being performed in the field.
2.2.4.2. The QCM shall possess the following:
2.2.4.2.1. Language. Full professional working proficiency at speaking, listening, reading, and writing in English.
2.2.4.2.2. Experience. Five (5) years' experience (within the last ten (10) years) working as a QCM (or in a position with equivalent responsibilities), managing multiple construction projects simultaneously related to the project.
2.3. . The Government will provide electricity and water for Contractor use in conjunction Utilities with this contract where available, and commodities will be at no cost to the Contractor. The Contractor shall instruct employees in utilities conservation practices. The Contractor shall be responsible for operating under conditions that preclude the waste of utilities. Contractor shall meter all utilities used and report them to Sustainability & Energy and Engineering Services Division. To coordinate the use of utilities please contact the COR. The Contractor shall provide its own sources of utilities (water, electricity, etc.) needed to complete the work in the SOW at locations where Government utilities are not available.
2.3.1 . All anticipated utility outages shall be coordinated with . Utilities Cutovers and Interruptions DPW through the COR. A minimum advance notice of fourteen (14) calendar days shall be provided by the Contractor. Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays unless directed otherwise. Conform to procedures required in paragraph Work Outside Regular Hours.
2.3.2 . The Contractor shall be responsible for furnishing portable latrines as . Portable Latrines required by OSHA and American National Standards Institute (ANSI), for the use of employees at such locations as designated by the KO or COR.
2.4. . Hours of Operation
2.4.1. . The Contractor shall perform all work during normal work hours. Normal Work Hours Normal work hours are defined as the time period from 0730 hours (7:30 AM) to 1630 hours (4:30 PM) MDT/MST, Mondays through Fridays except on Federal holidays or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings. The Contractor shall not be reimbursed when the Government facility is closed for the above reasons.
2.4.1.1. . For Government holidays visit https://www.opm.gov/policy-Federal Government Holidays data oversight/pay-leave/federal-holidays/#url=Overview .
2.4.1.2. This list of holidays relates to Government duty days and is not intended to supplement or otherwise alter the provisions of any Wage Determination regarding applicable paid holidays.
2.4.1.3. It is understood and agreed between the Government and the Contractor that observance of such days by Government personnel will not be a reason for an additional period of performance, or entitlement of compensation except as set forth within the contract. In the event the Contractor's personnel work during the holiday, the Contractor may reimburse them; however, no form of holiday or other premium compensation will be reimbursed either as a direct or indirect cost, other than their normal compensation for the time worked, unless stipulated otherwise. This provision does not preclude reimbursement for authorized overtime work if applicable. When the Department of Defense grants excused absence to its employees, the Contractor agrees to continue to provide sufficient personnel to perform critical tasks already in operation or scheduled, and shall be guided by the instructions issued by the KO or the COR. If Government personnel are furloughed, the Contractor shall contact the KO or the COR to receive direction. It is the Government's decision as to whether the contract price/cost will be affected as a result of Government shutdown and/or furloughed Government employees. In the event that Government shutdown and/or furloughed Government employee does impact contract price/cost, a negotiated settlement will be reached as deemed appropriate by the KO. 2.4.2. 2.5. 2.6.
2.4.2. . Work outside regular working hours requires Approval of Work Outside Normal Work Hours KO approval. Make application fifteen (15) calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the KO may approve work outside regular hours. During periods of darkness, the different parts of the work must be lighted in a manner approved by the KO.
2.5. Approval of work other than normal work-hours of the military reservation will be based upon the requirements of the task, technical or safety factors and not for the convenience of the Contractor. This is not intended to restrict the Contractor to an 8-hour day if the segment of project requires continuous work until completed because of mission requirements, the technical nature thereof, in the interest of safety, or to prevent damage to the project or other property. The Contractor shall give prior notice of such requirements to the KO. The KO may authorize the Contractor to perform work outside of normal working hours and/or working days. When the Government requires the Contractor to work outside normal hours, the Contractor shall be notified at the onset of the project, but not less than 24 hours in advance.
2.6 . The Contractor shall perform all work in such a manner as to minimize the Environmental polluting of air, water, or land and shall, within reasonable limits, control noise and the disposal of solid waste material, as well as other pollutants. The Contractor shall comply with AR-420-47 Solid & Hazardous Waste Management, Title 40 CFR Part 260 through 273 and with all Federal, State, and local laws and regulations concerning environmental pollution control. Compliance by Subcontractors shall be the responsibility of the Contractor.
2.6.1. Permits.
2.6.1.1. Hazardous Material Abatement. The Contractor shall coordinate all hazardous material removal with the DPW-ED through the COR and execute all projects in strict adherence to the latest installation, Federal, state, and local regulations. Copies of the ten (10) day notification shall be required prior to any abatement. Copies of all clearance reports, air monitoring, and waste manifests shall be required at the completion of the project. All notifications and records pertaining to hazardous materials shall be submitted to the Fort Bliss Safety Office, Industrial Hygiene Services, COR, and DPW-ED Asbestos and Lead Program Manager.
2.6.1.2. Air Emissions. Construction Operating Permits may be required prior to the installation of a significant, stationary, and/or air emissions source. Possible sources include but are not limited to:
boilers, generators, paint booths, baghouses, cyclones, painting operations, wood working operations, welding operations, de-painting or blasting operations, engine test cells, solvent baths /degreasers, fuel storage tanks, or fueling operations. The air emission units listed above may also require a modification to the installation's Title V Permit and cannot be installed nor operated until a permit is issued is issued by the state permitting authority as applicable. Coordinate with the Air Program Manager via the COR for further guidance.
2.62. Products
2.6.3. Hazardous Materials Requirements
2.6.3.1. . Texas House Bill 1927, effective September Certification of Asbestos Free Construction 2001, requires a Safety Data Sheet and a signed statement by an architect, engineer or Texas Department of Health Inspector identifying presence of asbestos containing material in all…