This is a Request for Quotation (RFQ) issued by Watervliet Arsenal for the manufacture of breech ring forgings for 155mm M284 cannons.

The solicitation requests quotations for 15 body breech ring forgings per drawing 11579761, Revision E, with the government intending to make only one award. Two contract line items are offered: CLIN 0001 with first article requirement and CLIN 0002 with first article waived. The contractor must provide contract data per DD Form 1423, including chemical and physical properties analysis, inspection records, and certificates of conformance. All responses must be submitted electronically to evan.j.caulfield.civ@army.mil. The quotation deadline is 12 AUG 2026. Delivery is scheduled 120 calendar days from award receipt for two units, followed by 90 calendar days from first article test approval for the remaining 13 units under CLIN 0001, or 180 calendar days from award receipt for all 15 units under CLIN 0002. Inspection and acceptance occur at the contractor's plant, with FOB destination and contractor-paid transportation. The manufacturer's cage code is 19206, part number 00X974048, under NAICS 331110 with a DPAS priority rating of DO-A5. The solicitation includes restrictions on export-controlled technical data access, requiring current DD 2345 certification, and contains critical military technology disclosures prohibiting foreign distribution. A first article inspection cost of $1,200 will be added to offers that cannot waive first article testing. Award will be made to the lowest evaluated responsive offer meeting all material requirements and responsibility criteria.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR QUOTATION

(THIS IS NOT AN ORDER)

THIS RFQ IS IS NOT A SMALL BUSINESS SET-ASIDE

15. DATE OF QUOTATION

16. SIGNER

a. NAME (Type or print)

c. TITLE (Type or print)

b. TELEPHONE

AREA CODE

NUMBER

STANDARD FORM 18 (REV. 6-95)

Prescribed by GSA-FAR (48 CFR) 53.215-1(a)

AUTHORIZED FOR LOCAL REPRODUCTION

Previous edition not usable

8. TO:

b. COMPANYa. NAME

c. STREET ADDRESS

d. CITY e. STATE f. ZIP CODE

9. DESTINATION

a. NAME OF CONSIGNEE

b. STREET ADDRESS

c. CITY

d. STATE e. ZIP CODE

7. DELIVERY

FOB DESTINATION

OTHER

(See Schedule)

10. PLEASE FURNISH QUOTATIONS TO THE

ISSUING OFFICE IN BLOCK 5a ON OR BEFORE CLOSE OF BUSINESS (Date)

IMPORTANT: This is a request for information and quotations furnished are not offers. If you are unable to quote, please so indicate on this form and return it to the address in Block 5a. This request does not commit the Government to pay any costs incurred in the preparation of the submission of this quotation or to contract for supplies or service. Supplies are of domestic origin unless otherwise indicated by quoter. Any representations and/or certifications attached to this Request for Quotation must be completed by the quoter.

11. SCHEDULE (Include applicable Federal, State and local taxes)

ITEM NO.

(a)

SUPPLIES/ SERVICES

(b)

QUANTITY

(c)

UNIT

(d)

UNIT PRICE

(e)

AMOUNT

(f)

12. DISCOUNT FOR PROMPT PAYMENT

a. 10 CALENDAR DAYS (%) b. 20 CALENDAR DAYS (%) c. 30 CALENDAR DAYS (%) d. CALENDAR DAYS

NUMBER PERCENTAGE

NOTE: Additional provisions and representations are are not attached.

13. NAME AND ADDRESS OF QUOTER

a. NAME OF QUOTER

b. STREET ADDRESS

c. COUNTY

d. CITY e. STATE f. ZIP CODE

14. SIGNATURE OF PERSON AUTHORIZED TO

SIGN QUOTATION

PAGE OF PAGES

1. REQUEST NO. 2. DATE ISSUED 3. REQUISITION/PURCHASE REQUEST NO. 4. CERT. FOR NAT. DEF.

UNDER BDSA REG. 2

AND/OR DMS REG. 1

RATING

5a. ISSUED BY 6. DELIVER BY (Date)

5b. FOR INFORMATION CALL (NO COLLECT CALLS)

NAME TELEPHONE NUMBER

AREA CODE NUMBER

Section A - Solicitation/Contract Form

Breech RingsInstrument Name:

Product Service Code : 1025

THE GOVERNMENT INTENDS TO MAKE ONLY ONE AWARD FOR A TOTAL QUANTITY OF 15

EACH OF DRAWING # 11579761, REV. E, EITHER WITH THE FIRST ARTICLE REQUIREMENT

(CLIN 0001) OR WITHOUT THE FIRST ARTICLE REQUIREMENT (CLIN 0002). PLEASE PRICE

ACCORDINGLY.

LOCAL NARRATIVES - Section A

REQUEST FOR QUOTE RESPONSES

ALL RESPONSES MUST BE ELECTRONIC. YOU MUST SUBMIT YOUR QUOTE RESPONSES

USING

THE FOLLOWING METHODS:

(a) Email to: evan.j.caulfield.civ@army.mil

(b) Request for Quotes must be filled out completely and sent in its entirety to be considered responsive.

DISTRIBUTION AND DESTRUCTION OF EXPORT CONTROL TECHNICAL DATA PACKAGE

(a) This solicitation and resulting contract contains technical data whose export is restricted by the Arms Export Control Act (Title 22, U.S.C., Sec 2751, et. seq.) or the Export Administration Act of 1979, as amended, Title 50, U.S.C, App. 2401 et. seq. Violations of these export laws are subject to severe criminal penalties. Disseminate in accordance with provisions of DoD Directive 5230.25.

This also applies to distribution of the TDP to all SUBCONTRACTORS at every level.

(b) To be eligible to gain access to this export controlled TDP (via FedBizOpps) an offeror must have a current DD 2345, "Militarily Critical Technical Data Agreement" certification on file with the Defense Logistics Information Service (DLIS). To obtain certification, go to http://www.dlis.dla.mil /jcp/, click on documents, and follow instructions provided. Processing time is estimated at six (6) to ten (10) weeks after receipt. FBO will allow access to export controlled TDPs once certification is confirmed. Upon receipt of certification, an offeror may request the TDP in accordance with the instructions stated in the solicitation's Section C.

W911PT26QA108

(c) Upon completion of the purposes for which Government Technical Data has been provided, the offeror, and all subcontractors, vendors, and sub-vendors of the offeror, are required to destroy all documents, including all reproductions, duplications, or copies thereof as may have been further distributed.

(d) Destruction of this technical data shall be accomplished by: shredding, pulping, burning, or melting any physical copies of the TDP and/or deletion or removal of downloaded TDP files from computer drives and electronic devices, and any copies of those files.

Disclosure of Unit Price Information

This constitutes notification pursuant to Executive Order 12600, Pre-Disclosure Notification Procedures for Confidential Commercial Information (June 23, 1987), of our intention to release unit prices of the awardee in response to any request under the Freedom of Information Act, 5 USC 552. Unit price is defined as the contract price per unit or item purchased. We consider any objection to be waived unless the contracting officer is notified of your objection to such release prior to submission of initial proposals.

*** END OF NARRATIVE ***

Section B - Supplies or Services & Prices or Costs

Additional Information/Notes

LOCAL NARRATIVES - Section B

NOTICE OF WATERVLIET ARSENAL INFORMATION/REQUIREMENTS

(a) IMPORTANT DELIVERY/QUALITY REQUIREMENTS:

(1) ALL OFFERORS MUST CAREFULLY REVIEW THE DELIVERY REQUIREMENT IN THE

REQUEST FOR QUOTE OR SOLICITATION. WHEN SUBMITTING AN OFFER/BID, PLEASE

ENSURE THAT YOU CAN MEET THE DELIVERY SCHEDULE.

(2) ON TIME DELIVERY IS VERY CRITICAL. THEREFORE, YOU MUST ADHERE TO THE

DELIVERY REQUIREMENTS INDICATED IN ANY RESULTANT AWARD. FAILURE TO

COMPLY WITH THE CONTRACTUAL DELIVERY SCHEDULE, MAY RESULT IN

TERMINATION OF THE ORDER OR REQUIRE CONSIDERATION IF THE GOVERNMENT

ELECTS TO EXTEND DELIVERY. (NOTE: Non-availability of raw materials, subcontractor issues, scheduling conflicts, should be considered at the time you are submitting your offer/bid.

They are not acceptable excuses for failing to meet the delivery after award).

(3) PROVIDING QUALITY PRODUCTS THAT CONFORM TO THE CONTRACT ARE JUST

AS IMPORTANT AS MEETING THE REQUIRED DELIVERY. DELIVERY OF NON-

CONFORMING PRODUCTS RESULTS IN DELIVERY DELAYS AND INCREASED COSTS

TO THE ARSENAL.

(4) PAST PERFORMANCE FOR QUALITY AND DELIVERY MAY BE A MAJOR

CONSIDERATION IN MAKING DETERMINATIONS FOR FUTURE CONTRACT AWARDS.

NOTICE: Throughout this document we may use the terms "we" and "you", the term "we" means the government of the United States of America, and the term "you" means the contractor.

(b) WATERVLIET ARSENAL INFORMATION FOR CONTRACTORS:

"Watervliet Arsenal Information for Contractors" document is incorporated by reference in all solicitations and contracts. The full text version of the instructions is available at Internet address:

http://www.wva.army.mil/Documents/Contracting/WAIC.pdf Upon request, the contracting officer will make its full text available."

POC - CONTRACT SPECIALIST/BUYER: Evan Caulfield

TELEPHONE NUMBER: 518-266-4813

E-MAIL ADDRESS: evan.j.caulfield.civ@army.mil

CONTRACTOR UEI NUMBER/CAGE CODE/FAX NUMBER:

Please provide the following information for your company.

VENDOR NAME: _________________________

VENDOR POC: __________________________

POC PHONE: ____________________________

E-MAIL ADDRESS (see note below): __________________________

UNIQUE ENTITY ID: _______________________

CAGE CODE (if known) __________________

TAX ID NUMBER ________________________

VENDOR FAX NUMBER ________________

NOTE: Your e-mail address is required so that in the event you receive the resultant award, we can e-mail it to you. If we experience difficulties with e-mail, it will be data faxed.

(c) POSTERS:

(1) Contracts for Material, Supplies, Articles and Equipment Exceeding $15,000/Service Contract Labor Standards. Orders subject to these Acts require contractors to post WH Publication 1313, "Employee Rights on Government Contracts".

(2) Construction Orders. Orders for construction require contractors to post WH Publication 1321, "Employee Rights under the Davis Bacon" and the Office of Federal Contract Compliance poster on "Equal Employment Opportunity is the Law."

(3) These posters can be accessed electronically at http://www.dol.gov .

(4) Hard copies of the posters will be made available upon request to the contracting officer.

(d) PAYMENTS:

Any vendor that receives an award (except those paid by credit card or accommodation check) can view invoice payments made by DFAS at https://wawf.eb.mil/ using the "my invoice" system.

You will be required to register in order to view payments. Payment information is maintained for 120 days from invoice payment. Vendors can find out when invoices have been paid by Electronic Funds Transfer (EFT), etc. This website can save valuable time and frustration over billing questions and it is a free service.

(e) RELEASE OF INFORMATION:

The contractor shall not release or authorize release of DoD specifications; acceptance test results; information involving critical military technology; or any other information in which the DoD maintains proprietary rights, or is otherwise confidential or classified. This restriction includes any endorsement by the Department of Army of a contractor. Release of information under the circumstances referenced above requires the prior written approval of the Contracting Officer responsible for this contract. It is the contractor's responsibility to be familiar with, and comply with the requirements of Chapter 5, page 22, paragraph 5-48, of AR 360-1 may be found at http://www.

usapa.army.mil/pdffiles/r360_1.pdf

*** END OF NARRATIVE ***

Item Supplies/Service Quanti ty

Unit Unit Price Amount

0001 FIRST ARTICLE REQUIRED -

BODY, BREECH RING FORGING

PER DWG. #11579761 REV. E;

FOR: 155MM M284 CANNON. To include contract data prepared and delivered in accordance with

CONTRACT DATA

REQUIREMENTS LIST (DD FORM

1423) which is attached hereto as EXHIBIT A; along with general data drawings attachment A.

*INSPECTION REQUIRED. WBS #

EH24UWV331EHM71

NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall

15 Each provide DoD unique identification, or a DoD recognized unique identification equivalent.

Manufacturer's CAGE: 19206

Manufacturer's Part Number:

00X974048

CLIN only - Requisition Document Number (MILSTRIP, DLMS, FEDSTRIP): W16H1F6152015R

Product Service Code: 1025

North American Industry Classification System (NAICS):

331110

Defense Priorities Allocation System (DPAS) Priority Rating: DO- A5

Weapon System Code: 000

Bill to Party: W16H1F

Claimant Program Code: A5

Pricing Arrangement: Firm Fixed Price

0002 FIRST ARTICLE WAIVED - BODY,

BREECH RING FORGING PER

DWG. #11579761 REV. E; FOR:

155MM M284 CANNON. To include contract data prepared and delivered in accordance with

CONTRACT DATA

REQUIREMENTS LIST (DD FORM

1423) which is attached hereto as EXHIBIT A; along with general data

15 Each drawings attachment A.

*INSPECTION REQUIRED. WBS #

EH24UWV331EHM71

NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification, or a DoD recognized unique identification equivalent.

Manufacturer's CAGE: 19206

Manufacturer's Part Number:

00X974048

CLIN only - Requisition Document Number (MILSTRIP, DLMS, FEDSTRIP): W16H1F6152015R

Product Service Code: 1025

North American Industry Classification System (NAICS):

331110

Defense Priorities Allocation System (DPAS) Priority Rating: DO- A5

Weapon System Code: 000

Bill to Party: W16H1F

Claimant Program Code: A5

Pricing Arrangement: Firm Fixed Price

Section C - Description/Specifications/Statement of Work

LOCAL NARRATIVES - Section C

IDENTIFICATION OF CASTING/FORGING MANUFACTURER

If the offeror intends to subcontract the manufacture of a casting/forging required by this solicitation, he must indicate herein who will furnish the basic casting/forging. After award of a contract, any change of this subcontractor will not be made without prior approval of the contracting officer.

TECHNICAL DATA PACKAGE INFORMATION

The following "X"d item applies to this solicitation:

[ ] 1. There is no Technical Data Package (TDP) included with this solicitation.

[X] 2. The TDP for this solicitation resides within SAM (https://www.SAM.gov), associated with this solicitation number, and can be accessed via this URL: Attached in Sam

-1-

To access the data through SAM:

a. Log on to the SAM web site.

b. Search for the solicitation number.

c. The solicitation and TDP documents will be attached in the "Attachments/Links" section of the posting. Access to documents in this section will be marked either "Public" or ""Controlled"

d. Public documents can be viewed right away. To access controlled documents, click on the document link and select "Request Access." This will generate an email to the contracting specialist or contracting officer responsible for the solicitation to notify them a contractor is requesting access. Access will be granted to contractors with an active DD2345 on file. SAM will subsequently automatically generate an email stating when the requesting contractor has permission to view or download TDP items. Allow two (2) to three (3) working days to complete this TDP access/approval process through the SAM system.

f. If multiple individuals in the contractor's organization need access to the Technical Data Package (TDP) for a solicitation and an explicit access request is required, each individual MUST submit an explicit access request to be granted approval to view the TDP. Those same individuals MUST be registered in SAM. Any individuals no longer with the company should be deleted.

g. It is strongly suggested that contractors submit the explicit access request and provide the buyer with the completed "Use and Non-Disclosure Agreement" at the same time if the solicitation requires both to gain access to view the TDP.

ACCESS AND GENERAL PROTECTION/SECURITY POLICY AND PROCEDURES

(a) The contractor and all associated subcontractors' employees shall comply with applicable installation, facility, and area commander installation and facility access and local security policies and procedures (provided by the Government representative). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the installation Provost Marshal Office, Director of Emergency Services, or Security Office. The contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9 "Personal Identity Verification of Contractor Personnel") as directed by DoD, HQDA, and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.

(b) For contractors requiring Common Access Card (CAC). Before CAC issuance, the contractor employee requires, at a minimum, a favorably adjudicated National Agency Check with Inquiries (NACI) or an equivalent or higher investigation in accordance with Army Directive 2014-05, The contractor employee will be issued a CAC only if duties involve one of the following: (1) Both physical access to a DoD facility and access, via logon, to DoD networks on-site or remotely; (2) Remote access, via logon, to a DoD network using DoD-approved remote access procedures; or

(3) Physical access to multiple DoD facilities or multiple non-DoD federally controlled facilities on behalf of the DoD on a recurring basis for a period of six (6) months or more. At the discretion of the sponsoring activity, an initial CAC may be issued on a favorable review of the FBI fingerprint check and a successfully scheduled NACI at the Office of Personal Management.

(c) For contractors that do not require CAC, but require access to a DoD facility or installation.

Contractor and all associated sub-contractors employees shall comply with adjudication standards, and procedures using the National Crime Information Center Interstate Identification Index (NCIC- III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures elsewhere in Section C; Non-disclosure Statement; for OCONUS locations, refer to the Status of Forces Agreement and other theater regulations.

EXHIBIT A

CONTRACT DATA REQUIREMENT LIST - DD Form 1423 Form Approval OMB No. 0704-0188

Public reporting burden for this collection of information is estimated to average 440 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.: 0001; 0002

B. EXHIBIT A

C. CATEGORY

D. SYSTEM/ITEM

E. CONTRACT/PR NO.:

F. CONTRACTOR

1. DATA ITEM NO: A001

2. TITLE OF DATA ITEM: Chemical and Physical Properties for Forging or Casting Analysis Report

3. SUBTITLE: Record of Treatment and Test, Major Forgings/Castings (CN1)

4. AUTHORITY: DI-FORG-81196

5. CONTRACT REFERENCE: Applicable Drawing or Material Specification

6. REQUIRING OFFICE: TAWV-CQD-E

7. DD250 REQUIRED: No

8. APP CODE:

9. DISTRIBUTION STATEMENT REQUIRED: B Test and Evaluation

10. FREQUENCY: With Each Submission

11. AS OF DATE:

12. DATE OF FIRST SUBMISSION: With First Shipment

13. DATE OF SUBSEQUENT SUBMISSIONS: With Each Shipment

14. DISTRIBUTION:

A. ADDRESSEES: DEPARTMENT OF THE ARMY, Attn TAWV-CQD-E Bldg. 35-E, Watervliet Arsenal, 1 Buffington Street, Watervliet NY 12189-4000

B. COPIES:

DRAFT: 0

FINAL: 1

15. TOTAL: 1

16. REMARKS: Submit SMCWV Form 1155 for each component or lot. A computerized version of SMCWV Form 1155 may be used with prior approval of the procuring office. Data Item Descriptions (DID) referenced in block 4 can be accessed at: http//assist.daps.mil.

17. PRICE GROUP:

18. ESTIMATED TOTAL PRICE:

G. PREPARED BY: Julie Cannon

H. DATE: 6Mar 2025

I. APPROVED BY: William Potter, TAWV- CQD-E

J. DATE: 10 Mar 2025

CONTRACT DATA REQUIREMENT LIST - DD Form 1423 Form Approval OMB No. 0704-0188

Public reporting burden for this collection of information is estimated to average 440 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.: 0001

B. EXHIBIT A

C. CATEGORY

D. SYSTEM/ITEM

E. CONTRACT/PR NO.:

F. CONTRACTOR

1. DATA ITEM NO: A002

2. TITLE OF DATA ITEM: Test/Inspection Report

3. SUBTITLE: Inspection Records - First Article Sample WVA FORM 702-61-R-E, 16 March 2016 702-CQD-E 61 8 Jan 2025(CN 3)

4. AUTHORITY: DI-NDTI-80809B

5. CONTRACT REFERENCE: First Article Clause

6. REQUIRING OFFICE: TAWV-CQD-C CQD-E

7. DD250 REQUIRED: *See Block 16

8. APP CODE:

9. DISTRIBUTION STATEMENT REQUIRED: B Test and Evaluation

10. FREQUENCY: ONE/P

11. AS OF DATE:

12. DATE OF FIRST SUBMISSION: With First Article

13. DATE OF SUBSEQUENT SUBMISSIONS: With First Article

14. DISTRIBUTION:

A. ADDRESSEES: As specified in contract or purchase order

B. COPIES:

DRAFT: 0

FINAL: 1

15. TOTAL: 1

16. REMARKS: Delete paragraph 10.2 of referenced DID (Block 4). Submit WVA Form 702-61-R- E showing results of inspections. Also submit DD Form 1222. Computerized versions of these forms may be used with prior approval of the procuring office. See QAP-APPX-WVA paragraph 10 for requirements. * Inspection/acceptance requirements specified in the contract. Data Item Description (DID) referenced in block 4 can be accessed at: http//assist.daps.mil.

17. PRICE GROUP:

18. ESTIMATED TOTAL PRICE:

G. PREPARED BY: J Cannon

H. DATE: 3 Mar 2025

I. APPROVED BY: William Potter, TAWV-CQD-E

J. DATE: 3 March 2025

CONTRACT DATA REQUIREMENT LIST - DD Form 1423Form Approval OMB No. 0704-0188

Public reporting burden for this collection of information is estimated to average 440 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.: 0001; 0002

B. EXHIBIT A

C. CATEGORY

D. SYSTEM/ITEM

E. CONTRACT/PR NO.:

F. CONTRACTOR

1. DATA ITEM NO: A003

2. TITLE OF DATA ITEM: Certification/Data Report

3. SUBTITLE: Certificate of Conformance (COC), NDT Applications (CN 9)

4. AUTHORITY: DI-MISC-80678

5. CONTRACT REFERENCE: QAP-APPX-WVA and applicable drawing or material specification

6. REQUIRING OFFICE: TAWV-CQD-E

7. DD250 REQUIRED: No

8. APP CODE:

9. DISTRIBUTION STATEMENT REQUIRED: B Test and Evaluation

10. FREQUENCY: With Each Submission

11. AS OF DATE:

12. DATE OF FIRST SUBMISSION: With First Shipment

13. DATE OF SUBSEQUENT SUBMISSIONS: With Each Shipment

14. DISTRIBUTION:

A. ADDRESSEES: DEPARTMENT OF THE ARMY, Attn: TAWV-CQD-E Bldg. 35-E, Watervliet Arsenal, 1 Buffington Street, Watervliet NY 12189-4000

B. COPIES:

DRAFT: 0

FINAL: 1

15. TOTAL: 1

16. REMARKS:

a. Paragraph 10.3, 10.4 of referenced DID (Block 4) is not applicable. See QAP-APPX- WVA paragraph 4.6 and 9 for the general requirements. The COC will also contain specific references to a specification or drawing for the acceptance standards, procedure and personnel qualifications. Data Item Description (DID) referenced in block 4 can be accessed at: http//assist.

daps.mil.

b. The required Technique Sheet is specific to the part and gives details of the process on that part, for example:

1. Method of establishing the magnetizing current (Head Shot, Coil. Prods, Yoke Cable wrap etc.); 2. Amperages used in the inspection on both fields, sequencing included. (Head shot first at 500amps/Coil shot second 800 amps); 3.

Pictures/Sketches of the part and its orientation; 4. Where on the part are they checking for proper minimum gauss readings (30- 60); what are they using to check this reading, QQI, Hall Effect Probe; 5. Type of Inspection Medium (Wet Fluorescent/Dry Particles, Continuous Method/Residual)

17. PRICE GROUP:

18. ESTIMATED TOTAL PRICE:

G. PREPARED BY: J. Cannon

H. DATE: March 3, 2025

I. APPROVED BY: William Potter, TAWV-CQD-E

J. DATE: March 3, 2025

CONTRACT DATA REQUIREMENT LIST - DD Form 1423 Form Approval OMB No. 0704-0188 response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.: 0001; 0002

B. EXHIBIT A

C. CATEGORY

D. SYSTEM/ITEM

E. CONTRACT/PR NO.:

F. CONTRACTOR

1. DATA ITEM NO: A004

2. TITLE OF DATA ITEM: Test/Inspection Report

3. SUBTITLE: Inspection Records, Production Components (CN12)

4. AUTHORITY: DI-NDTI-80809B

5. CONTRACT REFERENCE: QAP-APPX-WVA

6. REQUIRING OFFICE: TAWV-CQD-E

7. DD250 REQUIRED: No

8. APP CODE:

9. DISTRIBUTION STATEMENT REQUIRED: B Test and Evaluation

10. FREQUENCY: With Each Submission

11. AS OF DATE:

12. DATE OF FIRST SUBMISSION: With First Shipment

13. DATE OF SUBSEQUENT SUBMISSIONS: With Each Shipment

14. DISTRIBUTION:

A. ADDRESSEES: DEPARTMENT OF THE ARMY, Attn: TAWV-CQD-E Bldg. 35-E, Watervliet Arsenal, 1 Buffington Street, Watervliet NY 12189-4000

B. COPIES:

DRAFT: 0

FINAL: 1

15. TOTAL: 1

16. REMARKS: Delete paragraph 10.2 through 10.2.8 of referenced DID (Block 4).

Submit all records for production components. See QAP-APPX-WVA paragraph 4.2 and 4.5 for the requirement.

Data Item Description (DID) referenced in block 4 can be accessed at: http//assist.daps.mil.

17. PRICE GROUP:

18. ESTIMATED TOTAL PRICE:

G. PREPARED BY: J. Cannon

H. DATE: March 3, 2025

I. APPROVED BY: William Potter, TAWV-CQD-E

J. DATE: March 3, 2025

CONTRACT DATA REQUIREMENT LIST - DD Form 1423 Form Approval OMB No. 0704-0188 and maintaining the data needed, and completing and reviewing the collection of information.

Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.: 0001; 0002

B. EXHIBIT A

C. CATEGORY

D. SYSTEM/ITEM

E. CONTRACT/PR NO.:

F. CONTRACTOR

1. DATA ITEM NO: A005

2. TITLE OF DATA ITEM: Test Procedure

3. SUBTITLE: Magnetic Particle Inspection Procedures (CN 23)

4. AUTHORITY: DI-NDTI-80603

5. CONTRACT REFERENCE: QAP-APPX-WVA and ASTM-E1444

6. REQUIRING OFFICE: TAWV-CQD-E

7. DD250 REQUIRED: No

8. APP CODE: A

9. DISTRIBUTION STATEMENT REQUIRED: B Test and Evaluation

10. FREQUENCY: ONE/R

12. DATE OF FIRST SUBMISSION: *See Block 16

13. DATE OF SUBSEQUENT SUBMISSIONS: With Each Revision

14. DISTRIBUTION:

A. ADDRESSEES: DEPARTMENT OF THE ARMY, Attn: TAWV-CQD-E Bldg. 35-E, Watervliet Arsenal, 1 Buffington Street, Watervliet NY 12189-4000

B. COPIES:

DRAFT: 0

FINAL: 1

15. TOTAL: 1

16. REMARKS: Delete paragraph 10.2 through 10.2.2.8 of referenced DID (Block 4). Submit written procedures for review and approval by the procuring office. The minimum elements of the procedure are detailed in paragraphs 5.3 thru 5.3.1.15 of ASTM-E1444. Specific heat treatment requirements will be per QAP-APPX-WVA paragraph 9.1. *With First Article or no later than 30 days prior to first production shipment when First Article is not required. Government requires 15 days to review/approve. Data Item Description (DID) referenced in block 4 can be accessed at:

http//assist.daps.mil.

17. PRICE GROUP:

18. ESTIMATED TOTAL PRICE:

G. PREPARED BY: J Cannon

H. DATE: 3 Mar 2025

I. APPROVED BY: William Potter, TAWV-CQD-E

J. DATE: 3 March 2025

CONTRACT DATA REQUIREMENT LIST - DD Form 1423 Form Approval OMB No. 0704-0188 and maintaining the data needed, and completing and reviewing the collection of information.

Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.: 0001; 0002

B. EXHIBIT A

C. CATEGORY

D. SYSTEM/ITEM

E. CONTRACT/PR NO.:

F. CONTRACTOR

1. DATA ITEM NO: A006

2. TITLE OF DATA ITEM: Chemical and Physical Properties for Forging or Casting Analysis Report

3. SUBTITLE: Major Forging/Casting with Value Difference (CN 27)

4. AUTHORITY: DI-FORG-81196

5. CONTRACT REFERENCE: Applicable drawing or material specification

6. REQUIRING OFFICE: TAWV-CQD-E

7. DD250 REQUIRED: No

8. APP CODE:

9. DISTRIBUTION STATEMENT REQUIRED: B Test and Evaluation

10. FREQUENCY: AS REQ

12. DATE OF FIRST SUBMISSION: With First Shipment

13. DATE OF SUBSEQUENT SUBMISSIONS: With Each Shipment

14. DISTRIBUTION:

A. ADDRESSEES: DEPARTMENT OF THE ARMY, Attn: TAWV-CQD-E, Bldg. 35-E, Watervliet Arsenal, 1 Buffington Street, Watervliet NY 12189-4000

B. COPIES:

DRAFT: 0

FINAL: 1

15. TOTAL: 1

16. REMARKS: Determine the Value Difference and report on the Record of Treatment and Test, SMCWV Form 1155. Redetermine Value Difference when a material and/or process change is made. Data Item Description (DID) referenced in block 4 can be accessed at: http//assist.daps.mil.

17. PRICE GROUP:

18. ESTIMATED TOTAL PRICE:

G. PREPARED BY: J Cannon

H. DATE: 3 March 2025

I. APPROVED BY: William Potter, TAWV-CQD-E

J. DATE: 3 March 2025

*** END OF NARRATIVE ***

Requirements

FORGING, BREECHRING

Section E - Inspection and Acceptance

INSPECTION/ACCEPTANCE CRITERIA

PLACE OF INSPECTION AND ACCEPTANCE

Government inspection/acceptance will be made by the authorized Government Representative located at:

Inspection Acceptance

[ ] Watervliet Arsenal [ ] Watervliet Arsenal

[X] Contractor's Plant [X] Contractor's Plant

CHEMISTRY (Apr 1998) (ACC-WRN(WVA))

Offeror shall list in the spaces provided below, the chemistry of the steel which he proposes to use for producing the forgings herein. Chemistry will not be changed during production without prior approval of the Contracting Officer.

(END OF CLAUSE)

GENERAL REQUIREMENTS FOR QUALITY ASSURANCE (DEC 2001) (ACC-WRN(WVA))

Contractor requirements and inspection provisions are required in accordance with QAP-APPENDIX-BL and item QAP (s), if applicable.

(END OF CLAUSE)

52.209-3 Alt I FIRST ARTICLE APPROVAL- CONTRACTOR TESTING (Sept 1989) - ALTERNATE I (Jan 1997)

(a) The contractor shall test __ Two BODY, BREECH RING FORGING, 11579761, shall be furnished for 100% inspection to assure compliance with QAP(s), specification(s), drawing(s) and contract.

One BODY BREECH RING FORGING shall be destructively tested for mechanical properties. The properties shall be determined utilizing tensile and charpy specimens taken from discs located as specified on sheet 3 of drawing

11579761 and the procedures in MIL-R-10185.

___ unit(s) of Lot/Item _________________ as specified in this contract. At least 15 calendar days before the beginning of first article tests, the contractor shall notify the contracting officer, in writing, of the time and location of the testing so that the government may witness the tests.

(b) The contractor shall submit the first article test report within ____ calendar days from the date of this contract to:

WATERVLIET ARSENAL

VENDOR QUALITY & GAGE CALIBRATION WORK GROUP

BLDG #35E, ATTN: TAWV-CQD-C

WATERVLIET, NY 12189-4050

Marked "FIRST ARTICLE TEST REPORT: Contract No. ______________ Lot/Item No. __________."

Within calendar days after the Government receives the test report, the contracting officer shall notify the 30 contractor, in writing, of the conditional approval, approval or disapproval of the first article. The notice of conditional approval or approval shall not relieve the contractor from complying with all requirements of the specifications and all other terms and conditions of this contract. A notice of conditional approval shall state any further action required of the contractor. A notice of disapproval shall cite reasons for the disapproval.

(c) If the first article is disapproved, the Contractor, upon Government request, shall repeat any or all first article tests.

After each request for additional tests, the Contractor shall make any necessary changes, modifications, or repairs to the first article or select another first article for testing. All costs related to these tests are to be borne by the Contractor, including any and all costs for additional tests following a disapproval. The Contractor shall then conduct the tests and deliver another report to the Government under the terms and conditions and within the time specified by the Government. The Government shall take action on this report within the time specified in paragraph (b) of this subsection. The Government reserves the right to require an equitable adjustment of the contract price for any extension of the delivery schedule, or for any additional costs to the Government related to these tests.

(d) If the Contractor fails to deliver any first article report on time, or the Contracting Officer disapproves any first article, the Contractor shall be deemed to have failed to make delivery within the meaning of the Default clause of this contract.

(e) Unless otherwise provided in the contract, and if the approved first article is not consumed or destroyed in testing, the Contractor may deliver the approved first article as part of the contract quantity if it meets all contract requirements for acceptance.

(f) If the Government does not act within the time specified in paragraph (b) or (c) of this subsection, the Contracting Officer shall, upon timely written request from the Contractor, equitably adjust under the changes clause of this contract the delivery or performance dates and/or the contract price, and any other contractual term affected by the delay.

(g) Before first article approval, the acquisition of materials or components for, or the commencement of production of, the balance of the contract quantity is at the sole risk of the Contractor. Before first article approval, the costs thereof shall not be allocable to this contract for (1) progress payments, or (2) termination settlements if the contract is terminated for the convenience of the Government.

(h) The Government may waive the requirement for first article approval test where supplies identical or similar to those called for in the schedule have been previously furnished by the offeror/contractor and have been accepted by the Government. The offeror/contractor may request a waiver.

(i) The Contractor shall produce both the first article and the production quantity at the same facility.

(End of clause)

LATENT MATERIAL DEFECT (Oct 1993) (ACC-WRN(WVA))

When the contractor certifies that the material delivered under this order conforms to the material specified herein, the Government may within a reasonable time from receipt of material, and notwithstanding previous acceptance, perform a physical/chemical analysis of the material to assure conformance to specification requirement. Failure of the material to meet the physical/chemical requirements will be a cause for rejection as a Latent Material Defect and will necessitate replacement of the material at the contractor's expense when so directed by the Contracting Officer.

(END OF CLAUSE)

*** END OF NARRATIVE ***

Overall Contract Inspection/Acceptance Locations

0001 Inspection and Acceptance Location

Both Destination Instructions: Inspection/Acceptance. 30 Days.

DoDAAC: W16H1F CountryCode: USA

W0K9 OSC WVA-STOCK RECORD ACCT

1 BUFFINGTON ST BLDG 35, WATERVLIET NY 12189-4050

WATERVLIET, NY 12189-4050

UNITED STATES

0002 Inspection and Acceptance Location

Both Destination Instructions: Inspection/Acceptance. 30 Days.

DoDAAC: W16H1F CountryCode: USA

W0K9 OSC WVA-STOCK RECORD ACCT

1 BUFFINGTON ST BLDG 35, WATERVLIET NY 12189-4050

WATERVLIET, NY 12189-4050

UNITED STATES

Section F - Deliveries or Performance

LOCAL NARRATIVES - Section F

DELIVERY INFORMATION

Effective March 1, 2020, all commercial carriers must request an appointment for delivery to Watervliet Arsenal through the Carrier Appointment System (CAS). Carriers can register for CAS at https://eta.sddc.army.mil/. In the event that a carrier is either unable to register for CAS, or if CAS is down, carriers must call the transportation desk at 518-266-5858 to schedule an appointment

Note(s):

Late/early arrivals may be rescheduled to the next available appointment date.

This will not apply to small package carriers such as FEDEX, UPS, or DHL.

(b) Notice: Normal delivery hours for receipt of supplies at Watervliet Arsenal are as follows:

Monday through Thursday Business Hours: 6:30 A.M. EST to 3:30 P.M. EST

Friday Business Hours: Every other Friday from 6:30 A.M. EST to 2:00 P.M. EST

Fridays will be staggered with every other Friday being a closed business day. The first Friday of 2026 to be closed is January 9, 2026.

BASED ON THE ABOVE, CONTRACTORS SHOULD CALL THE CONTRACT/PURCHASE

ORDER ADMINISTRATOR IN ADVANCE IF DELIVERY IS SCHEDULED FOR A FRIDAY TO

FIND OUT IF THE ARSENAL WILL BE OPEN FOR BUSINESS.

Also, when a federal holiday is normally observed on a Friday, the Arsenal may be closed on the preceding Thursday. In these instances, please contact the contract/purchase order administrator in advance of delivery if Thursday delivery is anticipated to determine if the arsenal will be open for business.

THE ABOVE INFORMATION SHOULD BE NOTED WHEN SCHEDULING DELIVERIES AS

WATERVLIET ARSENAL WILL NOT BE LIABLE FOR ANY STORAGE, DEMURRAGE OR

SHIPPER LABOR COSTS INCURRED AS A RESULT OF CONTRACTOR ATTEMPTED

DELIVERIES ARRIVING DURING NON-BUSINESS HOURS.

ITEM DESCRIPTION:

The material delivered hereon must be tagged or otherwise identified by placing the purchase order /contract number on the packing slip or it will be returned at the contractor's expense. If more than one item is involved, material must be segregated by item and must be tagged or otherwise identified by item number. National stock number, when applicable, must be shown on all vendor's documents, such as Bill of Lading, Notice of Shipment, delivery or packing slip, etc.

*** END OF NARRATIVE ***

0001 Delivery Schedule From date of lead time event to delivery 120 Calendar Days

Date of Award Receipt 2 Each Delivery Schedule From date of lead time event to delivery 90 Calendar Days

Date of First Article Test Approval 13 Each

15 EachQuantity

Address and POC Ship To DoDAAC: W16H1F CountryCode: USA

W0K9 OSC WVA-STOCK RECORD ACCT

1 BUFFINGTON ST BLDG 35, WATERVLIET NY 12189-4050 WATERVLIET, NY

12189-4050 UNITED STATES

Special Handling/Notes FoB Details

Party to Pay Transportation Cost: Contractor

Point Type: Destination

0002 Delivery Schedule

From date of lead time event to delivery 180 Calendar Days

Date of Award Receipt 15 EachQuantity

Address and POC Ship To DoDAAC: W16H1F CountryCode: USA

W0K9 OSC WVA-STOCK RECORD ACCT

1 BUFFINGTON ST BLDG 35, WATERVLIET NY 12189-4050 WATERVLIET, NY

12189-4050 UNITED STATES

Special Handling/Notes FoB Details

Party to Pay Transportation Cost: Contractor

Point Type: Destination

FAR Clauses Incorporated by Reference

Number Title Effective Date

Alternate Deviation

Variation Effective Date

52.242-17 Government Delay of Work. 1984-04

52.247-34 F.o.b. Destination. 1991-01

52.247-48 F.o.b. Destination-Evidence of Shipment.

1999-02

Section G - Contract Administration Data

DFARS Clauses Incorporated by Reference

Number Title Effective Date

Alternate Deviation

Variation Effective Date

252.232-7003 Electronic Submission of Payment Requests and Receiving Reports.

2018-12

DFARS Clauses Incorporated by Full Text

Number Title Effective Date

Alternate Deviation

Variation Effective Date

252.232-7006 Wide Area WorkFlow Payment Instructions. (Tailored)

2023-01

WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS (JAN 2023)

(a) As used in this clause- Definitions.

"Department of Defense Activity Address Code (DoDAAC)" is a six position code that uniquely identifies a unit, activity, or organization.

"Document type" means the type of payment request or receiving report available for creation in Wide Area WorkFlow (WAWF).

"Local processing office (LPO)" is the office responsible for payment certification when payment certification is done external to the entitlement system.

"Payment request" and "receiving report" are defined in the clause at 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.

(b) The WAWF system provides the method to electronically process Electronic invoicing.

vendor payment requests and receiving reports, as authorized by Defense Federal Acquisition Regulation Supplement (DFARS) 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.

(c) To access WAWF, the Contractor shall- WAWF access.

(1) Have a designated electronic business point of contact in the System for Award Management at https://www.sam.gov; and

(2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for self-registration available at this web site.

(d) The Contractor should follow the training instructions of the WAWF WAWF training.

Web-Based Training Course and use the Practice Training Site before submitting payment requests through WAWF. Both can be accessed by selecting the "Web Based Training" link on the WAWF home page at https://wawf.eb.mil/

(e) Document submissions may be via web WAWF methods of document submission.

entry, Electronic Data Interchange, or File Transfer Protocol.

(f) The Contractor shall use the following information when WAWF payment instructions.

submitting payment requests and receiving reports in WAWF for this contract or task or delivery order:

(1) The Contractor shall submit payment requests using the following Document type.

document type(s):

(i) For cost-type line items, including labor-hour or time-and-materials, submit a cost voucher.

(ii) For fixed price line items-

(A) That require shipment of a deliverable, submit the invoice and receiving report specified by the Contracting Officer.

Invoice and Receiving Report (Combo)

(B) For services that do not require shipment of a deliverable, submit either the Invoice 2in1, which meets the requirements for the invoice and receiving report, or the applicable invoice and receiving report, as specified by the Contracting Officer.

N/A

(iii) For customary progress payments based on costs incurred, submit a progress payment request.

(iv) For performance based payments, submit a performance based payment request.

(v) For commercial financing, submit a commercial financing request.

(2) ) Fast Pay requests are only permitted when Federal Acquisition Regulation (FAR) 52.213-1 is included in the contract.

(3) The Contractor shall use the information in the Routing Data Document routing.

Table below only to fill in applicable fields in WAWF when creating payment requests and receiving reports in the system.

Routing Data Table*

Field Name in WAWF Data to be entered in WAWF

Pay Official DoDAAC

TBD

Issue By DoDAAC

W911PT

Admin DoDAAC

TBD

Inspect By DoDAAC

TBD

Ship To Code W16H1F

Ship From Code

Mark For Code

Service Approver (DoDAAC)

Service Acceptor (DoDAAC)

Accept at Other DoDAAC

LPO DoDAAC

DCAA Auditor DoDAAC

Other DoDAAC(s)

(4) The Contractor shall ensure a payment request includes Payment request.

documentation appropriate to the type of payment request in accordance with the payment clause, contract financing clause, or Federal Acquisition Regulation 52.216-7, Allowable Cost and Payment, as applicable.

(5) The Contractor shall ensure a receiving report meets the Receiving report.

requirements of DFARS Appendix F.

(g) WAWF point of contact.

(1) The Contractor may obtain clarification regarding invoicing in WAWF from the following contracting activity's WAWF point of contact.

Evan Caulfield, 518-266-4813, evan.j.caulfield.civ@army.mil

(2) Contact the WAWF helpdesk at 866-618-5988, if assistance is needed.

(End of clause)

Section H - Special Contract Requirements

LOCAL NARRATIVES - Section H

CRITICAL MILITARY TECHNOLOGY

The documents, drawings (microfilms) listed herein contain critical military technology that is owned by the United States Government, Watervliet Arsenal. These documents, drawings (microfilm) are not to be used for any purpose other than the purpose for which they are furnished, nor shall they be distributed or reproduced for any purpose, nor any part of their contents revealed in any manner, to persons other than the individuals or organizations specified to receive it, or their employees, without written consent of the Watervliet Arsenal.

LIST OF DOCUMENTS/DRAWING NO.

11579761, Rev. E

DISCLOSURE OF WATERVLIET ARSENAL TECHNOLOGY

In accordance with, Title 10 of the U.S. Code Section 4542, no Cannon Production Technology as defined herein, may be furnished to any foreign source or representative thereof. Therefore, solicitations and subsequent contracts for this requirement will be confined only to United States, Puerto Rico, and Canada which are considered part of the United States Industrial Base.

Cannon Production Technology (as defined below) or other technology on any defense item being manufactured or developed at Watervliet Arsenal, will not be released outside the offeror's /contractor's firm and/or the United States of America (the latter prohibition includes, but is not limited to, disclosure to the offeror's/contractor's foreign subsidiaries, affiliates, etc.) nor will such technology be used to manufacture cannon (as defined below) or other defense items being manufactured or developed at Watervliet Arsenal, in response to requests from anyone other than Watervliet Arsenal, without prior written approval of Watervliet Arsenal (WVA).

The offeror/contractor is hereby notified that any breach by him/her of the above provision may legally be pursued by the Government as a breach of implied contract (with respect to an offeror) or breach in contract (with respect to the firm awarded the contract). The offeror/contractor is hereby also placed on written notice that any damages the Government chooses to pursue for such breach may include any consequential damages for which the offeror/contractor would be liable. In addition, injunctive relief may be pursued in the event of violation of the above provision.

If prior approval of Watervliet Arsenal has been obtained, as required by the above provision, any subcontract is involved, the contractor shall insert the substance of this provision (that is, the first three full paragraphs above) in such subcontract. Failure of the contractor to include this provision in any subcontract may be pursued by the Government as a breach of contract by the contractor whereby he/she may be liable for any damage, to include consequential damages, caused Watervliet Arsenal due to unauthorized release or use of the data by the subcontractor.

Additionally, any drawings, specifications, or other technical data furnished with this solicitation need not be returned to the Watervliet Arsenal, but should be disposed of by the offeror, however care must be taken to assure disposal of the data is made in a manner which will comply with the terms of this provision.

DEFINITIONS

1. CANNON: is defined as a complete assembly consisting of a tube, breech mechanism, firing mechanism, and all integral components. It may include tube attachments and muzzle appendages. It is a component of a weapon system of 40mm Bore or over such as tank guns, towed and selfpropelled howitzers, naval guns, mortars, and recoilless guns.

2. CANNON PRODUCTION TECHNOLOGY: is defined as the technical data package and manufacturing technology.

a. TECHNICAL DATA PACKAGE: cannon engineering drawings, specifications and standards.

b. MANUFACTURING TECHNOLOGY: is technical knowledge, documentation, assistance, and equipment and machines used and useful in the manufacture of cannon.

(1) TECHNICAL KNOWLEDGE: is the know-how collected, trade secrets, production experience and special skills necessary for the production of cannon and is the technical information and inventions necessary for the manufacture of cannon and relating to the manufacture of cannon.

(2) TECHNICAL DOCUMENTATION: is manufacturing technical data; comprising drawings, specifications, schemes, composition, descriptions, methods of calculations, instructions, and other information necessary and sufficient for the manufacture of cannon.

(3) TECHNICAL ASSISTANCE: is all assistance required to make practical and economical use of the technology required to manufacture cannon, such as delivery of documentation, training of personnel, instructions, consultations and acquainting of specialists with the most economical method of using this technology in the manufacture of cannon.

(4) EQUIPMENT AND MACHINES: are production machines, machine accessories, apparatuses, spare parts and tooling, complete and in such quantity and quality as to secure the proper operation of a plant for cannon manufacture.

*** END OF NARRATIVE ***

Section I - Contract Clauses

LOCAL NARRATIVES - Section I

PROMPT PAYMENT NOTICE TO FAR 52.232-25

(a)(5)(i) For the purposes of this clause referenced elsewhere herein, Government acceptance shall be deemed to have occurred constructively on the 30th day after the contractor delivered the supplies or performed the services.

*** END OF NARRATIVE ***

FAR Clauses Incorporated by Reference

Number Title Effective Date

Alternate Deviation

Variation Effective Date

52.203-19 Prohibition on Requiring Certain Internal Confidentiality…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .