SEE ADDENDUM

(No Collect Calls)

W911N220Q0051 13-Jul-2020

b. TELEPHONE NUMBER

717-267-8357

8. OFFER DUE DATE/LOCAL TIME

12:00 PM 27 Jul 2020

5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

STANDARD FORM 1449 (REV. 2/2012)

Prescribed by GSA – FAR (48 CFR) 53.212

(TYPE OR PRINT)

(SIGNATURE OF CONTRACTING OFFICER)

ADDENDA ARE

26. TOTAL AWARD AMOUNT (For Gov t. Use Only )

23.

CODE 10. THIS ACQUISITION IS

SUCH ADDRESS IN OFFER

17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT

BELOW IS CHECKED

TELEPHONE NO.

W911N29. ISSUED BY

18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a. UNLESS BLOCK

7. FOR SOLICITATION

INFORMATION CALL:

a. NAME

JONATHAN K. CARROLL

2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NUMBER

(TYPE OR PRINT)

30b. NAME AND TITLE OF SIGNER 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER

30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a.UNITED STATES OF AMERICA

0 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1. 52.212-4. FAR 52.212-3. 52.212-5 ARE ATTACHED.

25. ACCOUNTING AND APPROPRIATION DATA

1. REQUISITION NUMBER

20.

ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.

OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS

W25G1Q016300EE

ARE NOT ATTACHED

27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED

(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE

SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:

. YOUR OFFER ON SOLICITATION

28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN

% FOR:SET ASIDE:UNRESTRICTED OR X

SMALL BUSINESSX

17a.CONTRACTOR/ CODE FACILITY

OFFEROR CODE

LETTERKENNY ARMY DEPOT

LETTERKENNY CONTRACTING OFFICE - ACC-RSA-LEAD

1 OVERCASH AVENUE, ATTN: CCAM-MLK, BLDG 2S

CHAMBERSBURG PA 17201-4150

18a. PAYMENT WILL BE MADE BY CODE

RATED ORDER UNDER

DPAS (15 CFR 700)

13a. THIS CONTRACT IS A

13b. RATING

CODE15. DELIVER TO CODE W25G1Q 16. ADMINISTERED BY

12. DISCOUNT TERMS11. DELIVERY FOR FOB DESTINA-

TION UNLESS BLOCK IS

MARKED

SEE SCHEDULE

14. METHOD OF SOLICITATION

RFQ IFB RFPX

DIRECTORATE OF OPS PLANNING & SUPPORT

BLDG 370 ASRS DOOR 18 AMLD-PLX

LETTERKENNY ARMY DEPOT

CHAMBERSBURG PA 17201-4150

TEL: FAX:

717-2679834FAX:

TEL: SERVICE-DISABLED

VETERAN-OWNED

SMALL BUSINESS

8(A)

HUBZONE SMALL

BUSINESS

SIZE STANDARD:

NAICS:

335129

X

OFFER DATED

29. AWARD OF CONTRACT: REF.

DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY

COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND

EMAIL:

TEL:

31c. DATE SIGNED

SEE SCHEDULE

SCHEDULE OF SUPPLIES/ SERVICESITEM NO. QUANTITY UNIT UNIT PRICE AMOUNT

24.22.21.19.

WOMEN-OWNED SMALL BUSINESS (WOSB)

ELIGIBLE UNDER THE WOMEN-OWNED

SMALL BUSINESS PROGRAM

EDWOSB

32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS

(CONTINUED)

PAGE 2 OF23

ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED: ______________________________________________________

32a. QUANTITY IN COLUMN 21 HAS BEEN

RECEIVED INSPECTED

32b. SIGNATURE OF AUTHORIZED GOVERNMENT

REPRESENTATIVE

32c. DATE 32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT

REPRESENTATIVE

32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f . TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE

37. CHECK NUMBER

FINALPARTIALCOMPLETE

36. PAYMENT35. AMOUNT VERIFIED

CORRECT FOR

34. VOUCHER NUMBER

FINAL

33. SHIP NUMBER

PARTIAL

38. S/R ACCOUNT NUMBER 39. S/R VOUCHER NUMBER 40. PAID BY

41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT

41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE

42a. RECEIVED BY (Print)

42b. RECEIVED AT (Location)

42c. DATE REC'D (YY/MM/DD) 42d. TOTAL CONTAINERS

STANDARD FORM 1449 (REV. 2/2012) BACK

Prescribed by GSA – FAR (48 CFR) 53.212

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

SEE SCHEDULE

20.

SCHEDULE OF SUPPLIES/ SERVICES

21.

QUANTITY UNIT

22. 23.

UNIT PRICE

24.

AMOUNT

19.

ITEM NO.

W911N220Q0051

Section SF 1449 - CONTINUATION SHEET

SOLICITATION NOTES

S OLICITATION NOTES

1. System for Award Management (SAM): In accordance with FAR 4.1102, Offerors shall be registered in the SAM database in order to be eligible for contract award. No award will be made to an Offeror not registered.

Registration can be accomplished at h ttps://www.sam.gov/portal/public/SAM/. Registration in this database shall remain active.

2. Annual Representations and Certifications: In accordance with FAR 4.1201, Offerors shall complete electronic annual representations and certifications within SAM as part of required registration. Registration in this database shall remain active and can be accessed at h ttps://www.sam.gov/portal/public/SAM/.

3. Questions: Questions regarding this solicitation shall be submitted to the Contracting Officer, in writing, at least 5 calendar days prior to the closing date. Questions submitted after this time will be answered at the discretion of t he Contracting Officer. The Contracting Officer for this action is Thomas C. Hall, thomas.c.hall111.civ@mail.mil. The Contract Specialist for this action is Jonathan K Carroll. Please copy jonathan.k.carroll.civ@mail.mil on all questions.

4. Award without Discussions: The Government intends to award without discussions, offerors should submit their best prices in their initial offer. If FAR Provision 52.212-2, Evaluation-Commercial Items, is included, Offerors must submit all information requested therein in order for the Government to determine technical acceptability.

5. Amendments: The Offeror shall submit to the Contracting Officer signed copies of all amendments issued to this solicitation. Failure to comply may cause your proposal to be rejected.

6. Payment: Payment for this action will be made by Electronic Funds Transfer (EFT) through the Defense Finance and Accounting Services (DFAS) utilizing Wide Area Work Flow (WAWF). See 252.232-7006 for more information.

7. Period for Acceptance of Offers: The Offeror agrees to hold the prices in its offer firm for 60 calendar days from the date specified for receipt of offers.

8. Set- Aside: The proposed contract is 100% set-aside for small business concerns.

9. F OB Destination: Unless otherwise stated in the solicitation, Offerors shall provide FOB Destination prices.

10. Site Visit: Site visit attendance is urged but is not mandatory; however, failure to attend a site visit shall not be a reason for price increases to the contract after contract award. In order to obtain access to the site visit, please submit the name and date of birth of all attendees to Jonathan K. Carroll at jonathan.k.carroll.civ@mail.mil. Submit this information no later than Thursday, 16 July 2020, at 12:00 P.M. Eastern Standard Time (EST). Offerors who do not submit this information will be denied access to the site. All attendees will meet at Building 2S, Letterkenny Contracting Office, 1 Overcash Avenue, Letterkenny Army Depot, Chambersburg, PA. Offerors are required to obtain a visitor’s pass from Building 2S Security/Badge Office prior to arriving at Building 2S. Please allow at least 45 minutes for this process. You must provide a current picture identification, vehicle registration and proof of insurance to obtain a pass. The documentation you receive with your visitor pass shall remain with you during the site visit and returned to the Badge Office upon completion of the site visit and prior to departure of the Depot.

**NOTE: FOR THIS SITE VISIT, ATTENDEES SHALL WEAR THE FOLLOWING: STEEL TOED SHOES, HEARING PROTECTION, SAFETY GLASSES, AND CLOTH FACE COVERINGS (DUE TO THE COVID-19

PANDEMIC)

11. Insurance (Fixed Price): Pursuant to the requirements of FAR clause 52.228-5 Insurance-Work on a Government Installation, the contractor shall obtain and maintain at least the following kinds of insurance and minimum liability coverage during any period of contract performance:

a. Workmen's Compensation and occupational disease coverage as required by law except that, if this contract is to be performed in a state which does not require or permit private insurance, then compliance with the statutory or administrative requirements in any such state will be satisfactory. The required Workmen's Compensation Insurance shall extend to cover employers' liability for accidental bodily injury or death and for occupational disease with a minimum liability limit of $100,000.

b. Comprehensive General Liability Insurance in the minimum limit of $500,000 per occurrence for bodily injury liability.

c. Comprehensive Automotive Liability Insurance with minimum limits of $200,000 per person and $500,000 per occurrence for bodily injury, and a minimum limit of $200,000 per occurrence for property damage.

PURCHASE DESRIPTION

LETTERKENNY ARMY DEPOT

PURCHASE DESCRIPTION

BUILDING 320 PAINT BOOTH 4378 LIGHTS UPGRADE

1.0 General Information:

1.1 Scope: Request the purchase of thirty four (34) light fixtures, wiring panel, and 3 way interlock. This specification establishes the minimum requirements for the purchase of contractor installed lights in paint booth at Letterkenny Army Depot (LEAD). The contractor shall provide installation and testing services for the completion of this project. The lights shall be installed turnkey in accordance with Original Equipment Manufacturer specification and standards. Specifications are based upon commercially available products and shall meet or exceed the minimum requirements specified in section 4.0 Specifications.

1.2 Place and Performance of Installation: All work shall be performed in building 320 between the hours of

6:00 AM and 3:30 PM, Monday thru Thursday, exclusive of Federal Holidays and special depot closures (typically the Monday before or Thursday after Federal Holidays that fall on a Saturday, Sunday, Tuesday or Thursday). Other hours, weekend, and holiday work will be considered separately as requested by the contractor with adequate advanced notice and approved by the Contracting Officer.

1.3 Security Requirements: Contractor and all associated sub-contractor’s employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Risk Management or Security Office. Contractor workforce shall comply with all personal identity verification requirements as directed by DOD, HQDA and/or local policy.

Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes. The contractor and all associated subcontractor employees shall also comply with adjudication standards and processes using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014- 05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

1.3.1 Security, Safety and Fire Protection: All work shall comply with LEAD Regulation 385-1 and Pamphlet 385-4. The equipment and the installation shall also meet all the safety criteria set forth in OSHA 1926.501 and ANSI/ASSE Z359.

1.3.2 Media Devices: All pictures shall be taken by LEAD representative and approved before release.

1.3.3 AT Level I Awareness Training: All contractor employees, to included subcontractor employees, requiring access to Army Installations, facilities, and controlled access areas shall complete AT Level 1 awareness training within 30 calendar days after contract start date and within 30 calendar days of new employees commencing performance. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer, if a COR is not assigned, within 15 calendar days after completion of training. AT level 1 awareness training is available on the Letterkenny Army Depot homepage – www.lead.army.mil.

1.3.4 Physical Security: The contractor shall safeguard all Government property provided for contractor use. At the close of each work period, Government facilities, equipment and materials shall be secured.

1.3.5 iWATCH Training: The contractor and all associated sub-contractors with an area of performance within an Army-controlled installation, facilities or area shall brief all employees on the local iWATCH program.

This local developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR or contracting officer. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance. The contractor shall report completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer, if a COR is not assigned, within 15 calendar days after completion of training. iWATCH training is available on the Letterkenny Army Depot homepage – www.lead.army.mil.

1.3.6 OPSEC Training: Per AR 530-1, Operations Security, new contractor employees and associated sub-contractor employees shall complete Level I OPSEC training within 30 calendar days of their reporting for duty and annually thereafter. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer, if a COR is not assigned, within 15 calendar days after completion of training. Level 1 OPSEC training is available on the Letterkenny Army Depot homepage – www.lead.army.mil.

2.0 Government Responsibilities:

2.1 Government Furnished Property and Materials: The Government will provide the facilities, equipment, materials and/or services listed below:

2.1.1 Facilities: The Government will provide clear access to all working areas necessary for the contractor to perform the installation outlined, during the specified hours listed in section 1.2.

2.1.2 Equipment: none

2.1.3 Materials: none

2.1.4 Services: none

2.2 Site Preparation: Letterkenny Army Depot will provide a clear area for installation of the lights.

2.3 Utilities: Utilities provided will be that from replaced fixtures. LEAD will also provide temporary utilities for the operation of equipment required for the installation of the lights.

2.4 Delivery and Storage: The Government will not be responsible for loading, unloading, or providing any extended storage, prior to installation, of materials or equipment as part of this contract.

3.0 Contractor Responsibilities: The contractor shall be responsible to inform all of his workers, direct or contracted, and ensure they follow the information within this specification. The contractor shall also have a representative onsite to manage the project and be the point of contact (POC) to communicate and coordinate with Letterkenny’s POC.

3.1 Post Processor: none

3.2 Project Schedule: Contractor will supply a schedule with start and duration of project. Contractor will submit schedule within 15 working days after award.

3.3 Utility Requirements: The contractor shall provide utility requirements within 15 days after receipt of the purchase order.

3.4 Field Verification: It shall be the responsibility of the contractor to verify, in the field, all measurements, locations of structures and utilities, and any other physical conditions which would affect the progress, or quantity of work. Any errors by the contractor, due to omission of field verification, shall not be the basis for any increase in contract price. Where existing utilities or other obstructions interfere with the progress of the contract, the contractor shall provide all materials and labor to relocate all obstructions as required and approved by the Contracting Officer.

3.5 Special Foundation: None.

3.6 Utility Installation: Existing utilities and connections for the old fixtures must be used for the new lights.

3.7 Disposal Of Materials And Equipment: All salvageable materials and equipment removed by the contractor shall be delivered to the Depot Property Disposal Yard, Facilities Engineering Division warehouse, or other sites as directed by the Contracting Officer, or his representative and shall remain the property of the Government. Delivery shall be made during normal operating hours of the receiving activity. No Government materials or equipment shall be removed from the reservation by the contractor.

All packing, packaging, and scrap material accumulated during the performance of the contract shall be removed and disposed of properly by the contractor.

3.8 Dust Control: The contractor shall control the amount of dust generated during the installation of the system foundation and components, and shall prevent the spread of dust to occupied portions of the building. Use of water will not be permitted when it will result in, or create, hazardous or objectionable conditions such as ice, flooding or pollution.

3.9 Protection of Existing Structures and Equipment: The contractor shall take all necessary precautions to insure against damage to existing structures and equipment to remain in place.

3.10 Installation of New Equipment: The contractor shall be responsible for supplying all parts, material, equipment, tools, and labor required to install the equipment provided under this contract. This shall include off-loading equipment, moving it to the installation site, positioning and installing. The contractor shall make all connections to existing utilities necessary for proper operation. The contractor shall remove and dispose all packaging and preservative material. Removed components shall not be taken from the Depot property. Removed components shall be placed in a location designated by the TPOC.

3.11 Wiring: All electrical work and materials shall be in compliance with the National Electrical Code and

National Electrical Manufacturers Association. All electrical installations shall be inspected and accepted by a certified electrician. All work shall be subject to inspection by LEAD electricians.

3.12 Pipe: none

3.13 Fluids: none

3.14 Permits: The contractor shall be responsible for determining and obtaining all necessary permits, fees, licensing, insurance, and bonding to perform and complete this installation.

4.0 Requirements: This requirement is for the purchase of thirty four (34) light fixtures, a light panel, and a shutoff solenoid for paint booth 4378 in building 320.

This equipment is for the upgrade of paint booth lights which will be changed from rear access to inside access fixtures. All of the equipment is for the upgrade of one paint booth, 4378.

4.1 Equipment and features: The equipment shall consist of light fixtures, electrical panel, interlock, and any necessary materials for complete installation of the equipment. The panel shall connect together the light fixtures and the paint booth to create an explosion proof environment where if any light fixture cover is not fully closed and sealed, the solenoid will shut off the compressed air supply for spraying to the paint booth.

All equipment shall meet applicable NFPA standards for spraying paint and electrical.

4.1.1 Light fixtures: The light fixtures shall replace the existing light fixtures and use the same locations as the existing ones. Also, each new light shall be 18” x 48”, nominal, be retrofitted into the same openings (panels) and include a retro-fit kit will all necessary material and parts to mount the new light into the existing mountings flush and have a tight seal. Each light fixture shall have a tempered glass cover.

34 – 4 tube wall fixtures T-8 LED tubes 32 watt electronic ballasts Run on 120V 60 Hz Interlock safety switch Inside booth access to lights Flush mount to inside wall surface Twist in lamp install/removal NFPA standards, Class 1, Division 2, Groups A-D

4.1.2 Lighting panel: The panel shall be a NEMA 12 enclosure and meet NFPA standards. The lighting panel shall be used to interlock every light fixture in the booth and the paint air via a solenoid to ensure that all fixture covers are closed and sealed to create an explosion proof environment in the booth

4.1.3 Air Solenoid: The solenoid will be used in the paint booth to connect the lighting fixtures to the compressed air to create an explosion proof environment while spraying paint. The solenoid and installation will meet all applicable NFPA standards

4.1.4 Documentation: One set (each) of paper and one (each) CD of operator instruction manuals, maintenance service manuals, and parts listing manuals shall be provided for the furnished systems. These manuals shall be written in the English language.

4.1.5 Warranty: The contractor shall furnish with the equipment a standard commercial warranty or full one-year warranty (parts, labor, and shipping, at minimum), whichever is greater. The contractor shall provide commercial warranties for any subcontracted components that will be underwritten. The contractor shall supply all corresponding warranty contact names and phone numbers before the end of the project. The warranty shall be effective beginning immediately after final acceptance of the equipment and not before that time.

4.2 Machine Control System:

4.2.1 Control Features: none

4.2.2 Control Software Compatibility: none

4.3 Machine Features: none

4.4 General Requirements:

4.4.1 Painting: All surfaces to be painted shall be cleaned of all foreign matter. The equipment shall be painted

IAW standard commercial practice that shall not be less than one coat of primer and one coat of finish color.

4.4.2 Lubrication: none

4.4.3 Power Requirements: The power used shall be the power available from the existing fixtures that will be replaced.

4.4.4 Automatic Lubrication: none

4.4.5 Energy Efficiency: All equipment that directly consumes energy in normal operation shall be designed and constructed for the highest degree of energy efficiency as governed by the latest developments available within industry.

4.4.6 Preservation, Packaging and Delivery: The contractor shall utilize standard commercial methods for preservation and packaging appropriate for each unit and acceptable to commercial carriers. As a minimum, all areas susceptible to damage from exposure to the elements shall be preserved and/or packed to prevent damage. The contractor shall be responsible for ensuring the equipment is delivered to LEAD in good condition.

4.4.7 Inspection and Acceptance: The equipment shall be examined for design, construction, materials, components, and workmanship to determine compliance with the contract and this specification. Any deviation from these requirements shall be cause for rejection.

4.5 Safety and Environmental Requirements:

4.5.1 Equipment Hazards: Guards shall be easily removable to facilitate inspection, maintenance, or repair.

4.5.2 Mercury Restriction: The equipment shall not contain mercury compounds nor be exposed to free mercury during manufacture.

4.5.3 Asbestos Restriction: Asbestos and materials containing asbestos shall not be used in or on the equipment.

4.5.4 PCB Restriction: Equipment and materials containing Polychlorinated Biphenyl (PCB) shall not be shipped to Letterkenny Army Depot.

4.6 Installation Requirements:

4.6.1 Design and Installation: The contractor shall provide all parts, labor, and services for the design, fabrication and installation of the lights and accessory equipment. The contractor shall provide competent English speaking personnel to place the equipment in operation and to conduct the acceptance tests and training of depot personnel. The contractor, through his service personnel, shall be fully responsible for the offloading, installation, activation, and testing of the equipment and the service personnel shall remain until system activation and testing has successfully been completed. Under no circumstances should the contractor plan on gratuitous Depot assistance during installation, activation, and testing such as diagnosis, troubleshooting, or repair of the equipment.

4.6.2 Badges: Identification badges will be issued for admittance of personnel before performing work or service on this contract. The identification badge is the property of the US Government and must be returned upon termination or demand. The contractor/vendor agrees that he will ensure all badges issued to employees are returned to the Badge and Identification Section, Security Division, Letterkenny Army Depot promptly on termination of need or on expiration, which occurs first. The badge room is located in Bldg 2, phone # 717- 267-5301. Hours of operation are 7:30 AM to 3:30 PM, Monday thru Friday, exclusive of Federal Holidays.

4.6.3 Fire Extinguishers: The LEAD R 385-1 designates the type and number of fire extinguishers required to perform the contracted work. The LEAD Fire Department will not provide any extinguisher support. The contractor can gain the above information through a pre-construction conference, visiting the fire department, or phone 717-267-8231.

4.6.4 Use of Portable Gas or Arc Equipment: The contractor shall obtain a permit, from the LEAD Fire

Department, to use portable gas or arc equipment for cutting, welding or open flame operations. The Fire Department will require one day advance notice to permit necessary inspection before actually starting work, and notification when work is finished to allow for re-inspection. The Fire Department can be notified by calling ext. 8231. The contractor shall take necessary precautions to prevent fires IAW NFPA Standard No.

51B and LEAD R 420-13.

4.6.5 Spills: Any spills or releases of materials or wastes must be reported immediately to the site supervisor, the

LEAD Fire Department, and the LEAD Environmental Office per the LEAD Installation spill Contingency Plan (ISCP). Any such spills or releases generated by the contractor shall be contained, cleaned and disposed of by the contractor per the direction of the LEAD on-scene coordinator.

5.0 Applicable Documents:

OSHA Safety and Health Standards 29 CFR 1910 Occupational Safety and Health Standards (copies may be obtained at http://www.osha.gov)

Letterkenny Army Depot (LEAD) Publications:

LEAD Regulation 385-1: LEAD Safety and Occupational Health Program LEAD Pamphlet 385-4 – Safety Requirements for Security, Safety, and Fire Prevention for Contractors Performing Work on LEAD (Copies may be obtained at LEAD Directorate of Contracting, Bldg 2)

National Fire Protection Association:

NFPA Standard 70 – National Electric Code NFPA Standard 79 – Electrical Standard for Industrial Machinery (copies may be obtained from http://www.nfpa.org/)

National Electrical Manufacturer’s Association (NEMA) NEMA 250 Enclosures for Electrical Equipment

(Copies may be obtained at www.nema.org)

6.0 Quality Assurance:

6.1 Quality Conformance Inspection: The lights and all accessory components shall be subject to a quality conformance inspection, performed by a designated Depot representative, to determine compliance with this specification.

6.2 Tests:

6.2.1 Accuracy: The contractor shall be responsible for developing test procedures to demonstrate the accuracy and operation of the equipment to be in compliance with the requirements of this specification. All test procedures shall be submitted to and approved by Depot Technical Point of Contact (TPOC) prior to the start of testing. The contractor shall prove out all problems.

6.2.2 Post Processing Verification: none

6.3 Technical Instruction: The contractor shall be responsible for providing technical instruction of four (4) Depot personnel in the operation and maintenance of the equipment supplied under this contract. All instructions, oral and written, shall be in the English language. The project LEAD TPOC will coordinate with individuals to be trained upon successful completion of all installation and test specifications.

7.0 none

8.0 Final Acceptance: Once all conditions of this contract are met, final acceptance will be after 100 hours of continuous operation without a breakdown or failure, or 14 days, whichever comes first. If the equipment has a failure or breakdown and it is determined that is the fault of the machine hardware or software, the operating time and 14 days timeframe start over each time this happens. After the 100 hour operating time or 14 days have been met, final payment of this contract will be made.

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Each

LIGHT UPGRADE FOR BLDG 320 PAINT BOOTH

FFP

PAINT BOOTH LIGHT UPGRADE IN ACCORDANCE WITH THE

PURCHASE DESCRIPTION

FOB: Destination

NSN: LABW12-4LED:3GX14

MILSTRIP: W25G1Q016300EE

SPEC NR: LABW12-4LED:3GX

PURCHASE REQUEST NUMBER: W25G1Q016300EE

PSC CD: 6210

NET AMT

INSPECTION AND ACCEPTANCE TERMS

Supplies/services will be inspected/accepted at:

CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY

0001 Destination Government Destination Government

DELIVERY INFORMATION

CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /

CAGE

0001 180 dys. ADC 1 DIRECTORATE OF OPS PLANNING &

SUPPORT

BLDG 370 ASRS DOOR 18 AMLD-PLX

LETTERKENNY ARMY DEPOT

CHAMBERSBURG PA 17201-4150

FOB: Destination

W25G1Q

CLAUSES INCORPORATED BY REFERENCE

52.204-7 System for Award Management OCT 2018 52.204-9 Personal Identity Verification of Contractor Personnel JAN 2011 52.204-10 Reporting Executive Compensation and First-Tier

Subcontract Awards

JUN 2020

52.204-13 System for Award Management Maintenance OCT 2018 52.204-16 Commercial and Government Entity Code Reporting JUL 2016 52.204-18 Commercial and Government Entity Code Maintenance JUL 2016 52.204-19 Incorporation by Reference of Representations and

Certifications.

DEC 2014

52.204-21 Basic Safeguarding of Covered Contractor Information Systems

JUN 2016

52.209-6 Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, or Proposed for Debarment

JUN 2020

52.209-10 Prohibition on Contracting With Inverted Domestic Corporations

NOV 2015

52.211-17 Delivery of Excess Quantities SEP 1989 52.212-1 Instructions to Offerors--Commercial Items JUN 2020 52.212-3 Alt I Offeror Representations and Certifications--Commercial

Items (JUN 2020) Alternate I

OCT 2014

52.212-4 Contract Terms and Conditions--Commercial Items OCT 2018 52.219-6 Notice Of Total Small Business Set-Aside MAR 2020 52.222-3 Convict Labor JUN 2003 52.222-19 Child Labor -- Cooperation with Authorities and Remedies JAN 2020 52.222-21 Prohibition Of Segregated Facilities APR 2015 52.222-26 Equal Opportunity SEP 2016 52.222-36 Equal Opportunity for Workers with Disabilities JUN 2020 52.222-37 Employment Reports on Veterans JUN 2020 52.222-50 Combating Trafficking in Persons JAN 2019 52.223-5 Pollution Prevention and Right-to-Know Information MAY 2011 52.223-18 Encouraging Contractor Policies To Ban Text Messaging

While Driving

JUN 2020

52.232-33 Payment by Electronic Funds Transfer--System for Award Management

OCT 2018

52.232-39 Unenforceability of Unauthorized Obligations JUN 2013 52.232-40 Providing Accelerated Payments to Small Business

Subcontractors

DEC 2013

52.233-3 Protest After Award AUG 1996

52.233-4 Applicable Law for Breach of Contract Claim OCT 2004 52.237-1 Site Visit APR 1984 52.237-2 Protection Of Government Buildings, Equipment, And

Vegetation

APR 1984

52.242-15 Stop-Work Order AUG 1989 52.242-17 Government Delay Of Work APR 1984 52.247-34 F.O.B. Destination NOV 1991 252.203-7000 Requirements Relating to Compensation of Former DoD

Officials

SEP 2011

252.203-7002 Requirement to Inform Employees of Whistleblower Rights SEP 2013 252.203-7005 Representation Relating to Compensation of Former DoD

Officials

NOV 2011

252.204-7003 Control Of Government Personnel Work Product APR 1992 252.204-7008 Compliance With Safeguarding Covered Defense Information

Controls

OCT 2016

252.204-7012 Safeguarding Covered Defense Information and Cyber Incident Reporting

DEC 2019

252.204-7015 Notice of Authorized Disclosure of Information for Litigation Support

MAY 2016

252.204-7016 Covered Defense Telecommunications Equipment or Services -- Representation

DEC 2019

252.204-7017 Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services -- Representation

DEC 2019

252.204-7018 Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services

DEC 2019

252.223-7006 Prohibition On Storage, Treatment, and Disposal of Toxic or Hazardous Materials

SEP 2014

252.223-7008 Prohibition of Hexavalent Chromium JUN 2013 252.225-7001 Buy American And Balance Of Payments Program-- Basic DEC 2017 252.225-7002 Qualifying Country Sources As Subcontractors DEC 2017 252.225-7035 Buy American--Free Trade Agreement--Balance Of Payments

Program Certificate--Basic

NOV 2014

252.225-7048 Export-Controlled Items JUN 2013 252.232-7003 Electronic Submission of Payment Requests and Receiving

Reports

DEC 2018

252.232-7010 Levies on Contract Payments DEC 2006 252.243-7001 Pricing Of Contract Modifications DEC 1991 252.244-7000 Subcontracts for Commercial Items JUN 2013 252.247-7023 Transportation of Supplies by Sea FEB 2019

CLAUSES INCORPORATED BY FULL TEXT

52.209-11 REPRESENTATION BY CORPORATIONS REGARDING DELINQUENT TAX LIABILITY OR A

FELONY CONVICTION UNDER ANY FEDERAL LAW (FEB 2016)

(a) As required by sections 744 and 745 of Division E of the Consolidated and Further Continuing Appropriations Act, 2015 (Pub. L. 113-235), and similar provisions, if contained in subsequent appropriations acts, the Government will not enter into a contract with any corporation that--

(1) Has any unpaid Federal tax liability that has been assessed, for which all judicial and administrative remedies have been exhausted or have lapsed, and that is not being paid in a timely manner pursuant to an agreement with the authority responsible for collecting the tax liability, where the awarding agency is aware of the unpaid tax liability, unless an agency has considered suspension or debarment of the corporation and made a determination that suspension or debarment is not necessary to protect the interests of the Government; or

(2) Was convicted of a felony criminal violation under any Federal law within the preceding 24 months, where the awarding agency is aware of the conviction, unless an agency has considered suspension or debarment of the corporation and made a determination that this action is not necessary to protect the interests of the Government.

(b) The Offeror represents that--

(1) It is [ ] is not [ ] a corporation that has any unpaid Federal tax liability that has been assessed, for which all judicial and administrative remedies have been exhausted or have lapsed, and that is not being paid in a timely manner pursuant to an agreement with the authority responsible for collecting the tax liability; and

(2) It is [ ] is not [ ] a corporation that was convicted of a felony criminal violation under a Federal law within the preceding 24 months.

(End of provision)

52.211-8 TIME OF DELIVERY (JUN 1997)

(a) The Government requires delivery to be made according to the following schedule:

REQUIRED DELIVERY SCHEDULE

(Contracting Officer insert specific details)

Within Days

After Date

Item No. Quantity of Contract

The Government will evaluate equally, as regards time of delivery, offers that propose delivery of each quantity within the applicable delivery period specified above. Offers that propose delivery that will not clearly fall within the applicable required delivery period specified above, will be considered nonresponsive and rejected. The Government reserves the right to award under either the required delivery schedule or the proposed delivery schedule, when an offeror offers an earlier delivery schedule than required above. If the offeror proposes no other delivery schedule, the required delivery schedule above will apply.

OFFEROR'S PROPOSED DELIVERY SCHEDULE

Within Days

After Date

Item No. Quantity of Contract

(b) Attention is directed to the Contract Award provision of the solicitation that provides that a written award or acceptance of offer mailed, or otherwise furnished to the successful offeror, results in a binding contract. The Government will mail or otherwise furnish to the offeror an award or notice of award not later than the day award is dated. Therefore, the offeror should compute the time available for performance beginning with the actual date of award, rather than the date the written notice of award is received from the Contracting Officer through the ordinary mails. However, the Government will evaluate an offer that proposes delivery based on the Contractor's date of receipt of the contract or notice of award by adding (1) five calendar days for delivery of the award through the ordinary mails, or (2) one working day if the solicitation states that the contract or notice of award will be transmitted electronically. (The term "working day" excludes weekends and U.S. Federal holidays.) If, as so computed, the offered delivery date is later than the required delivery date, the offer will be considered nonresponsive and rejected.

(End of clause)

52.212-1 INSTRUCTIONS TO OFFERORS--COMMERCIAL ITEMS (JUN 2020)

ADDENDUM TO FAR 52.212-1, INSTRUCTIONS TO OFFERORS--COMMERCIAL ITEMS:

Paragraph (c) is changed to read: Period for acceptance of offers. The Offeror agree to hold the prices in its offer firm for 60 calendar days from the date specified for receipt of offers, unless another time period is specified in an addendum to the solicitation.

52.212-2 EVALUATION--COMMERCIAL ITEMS (OCT 2014)

(a) The Government will award a contract resulting from this solicitation to the responsible offeror whose offer conforming to the solicitation will be most advantageous to the Government, price and other factors considered. The following factors shall be used to evaluate offers:

(b) Options. The Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. The Government may determine that an offer is unacceptable if the option prices are significantly unbalanced. Evaluation of options shall not obligate the Government to exercise the option(s).

(c) A written notice of award or acceptance of an offer, mailed or otherwise furnished to the successful offeror within the time for acceptance specified in the offer, shall result in a binding contract without further action by either party. Before the offer's specified expiration time, the Government may accept an offer (or part of an offer), whether or not there are negotiations after its receipt, unless a written notice of withdrawal is received before award.

ADDENDUM TO FAR 52.212-2, BASIS OF AWARD:

A. General Information:

1. The basis of award will be the Lowest Priced, Technically Acceptable offer. Offerors must receive a rating of Technically Acceptable in all factors/subfactors in order for their overall proposal to be determined Technically Acceptable.

2. By submission of its offer, the offeror accedes to all solicitation requirements, including terms and conditions, and technical requirements.

3. The Government intends to make award without discussions, unless the Contracting Officer determines that discussions are necessary. Offerors should provide their most favorable prices in their initial offers.

B. Non-Price Evaluation Factors and Subfactors:

1. Factor 1- Technical:

(a) Subfactor 1 Equivalence: The offerer shall provide the following to the Government POC:

a. A written summary of the project to evaluate possible equivalents.

b. Information including, but is not limited to: brochures, videos, and drawings pertaining to all equipment included in their proposal.

c. Any equipment specifications with regard to their proposal that can be used to evaluate possible equivalents.

(b) Subfactor 2 – Past Experience: The Offerors shall provide three recent and relevant Government or private sector projects completed within the past three years that demonstrates the ability to perform the requirements in this solicitation. The Offeror shall identify the contract title, contract number, dollar value, client name and address, location of work, point of contact with telephone number, and an explanation of how each project related to the work requirements of this solicitation.

C. Price Evaluation Factor: Offerors shall complete the Schedule B with pricing for each Contract Line Item Number (CLIN).

D. Proposals will be evaluated initially independently of the price to determine the Offerors’ ability to meet the Government’s requirement set forth in the solicitation. The Government may make a final rating determination based on the proposal as submitted without requesting any further information. For all proposals determined to be Technically Acceptable, the offer providing the lowest price will receive the contract award.

1. Offerors’ technical proposals will receive an overall rating based on the following:

(a) Technically Acceptable: Offeror meets all requirements or technical specifications or has submitted all documentation requested in any technical evaluation criteria and all documentation meets the standard set forth in the solicitation.

(b) Technically Unacceptable: Offerer fails to meet all requirements or technical specifications or has failed to comply in submitting requested documentation in any technical evaluation criteria or the submitted documentation fails to meet the standard set forth in the solicitation.

(End of Addendum)

52.212-5 CONTRACT TERMS AND CONDITIONS REQUIRED TO IMPLEMENT STATUTES OR

EXECUTIVE ORDERS—COMMERCIAL ITEMS (DEVIATION 2018-O0021) (JUN 2020)

(a) Comptroller General Examination of Record. The Contractor shall comply with the provisions of this paragraph

(a) if this contract was awarded using other than sealed bid, is in excess of the simplified acquisition threshold, and does not contain the clause at 52.215-2, Audit and Records—Negotiation.

(1) The Comptroller General of the United States, or an authorized representative of the Comptroller General, shall have access to and right to examine any of the Contractor’s directly pertinent records involving transactions related to this contract.

(2) The Contractor shall make available at its offices at all reasonable times the records, materials, and other evidence for examination, audit, or reproduction, until 3 years after final payment under this contract or for any shorter period specified in FAR Subpart 4.7, Contractor Records Retention, of the other clauses of this contract. If this contract is completely or partially terminated, the records relating to the work terminated shall be made available for 3 years after any resulting final termination settlement. Records relating to appeals under the disputes clause or to litigation or the settlement of claims arising under or relating to this contract shall be made available until such appeals, litigation, or claims are finally resolved.

(3) As used in this clause, records include books, documents, accounting procedures and practices, and other data, regardless of type and regardless of form. This does not require the Contractor to create or maintain any record that the Contractor does not maintain in the ordinary course of business or pursuant to a provision of law.

(b)(1) Notwithstanding the requirements of any other clauses of this contract, the Contractor is not required to flow down any FAR clause, other than those in this paragraph (b) (1) in a subcontract for commercial items. Unless otherwise indicated below, the extent of the flow down shall be as required by the clause—

(i) 52.203-13, Contractor Code of Business Ethics and Conduct (OCT 2015) (41 U.S.C. 3509).

(ii) 52.203-19, Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (JAN 2017) (section 743 of Division E, Title VII, of the Consolidated and Further Continuing Appropriations Act, 2015 (Pub. L.

113-235) and its successor provisions in subsequent appropriations acts (and as extended in continuing resolutions)).

(iii) 52.204-23, Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab and Other Covered Entities (Jul 2018) (Section 1634 of Pub. L. 115-91).

(iv) 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment. (AUG 2019) (Section 889(a)(1)(A) of Pub. L. 115-232).

(v) 52.219-8, Utilization of Small Business Concerns (OCT 2018) (15 U.S.C. 637(d)(2) and (3)), in all subcontracts that offer further subcontracting opportunities. If the subcontract (except subcontracts to small business concerns) exceeds $700,000 ($1.5 million for construction of any public facility), the subcontractor must include 52.219-8 in lower tier subcontracts that offer subcontracting opportunities.

(vi) 52.222-17, Nondisplacement of Qualified Workers (MAY 2014) (E.O. 13495). Flow down required in accordance with paragraph (l) of FAR clause 52.222-17.

(vii) 52.222-21, Prohibition of Segregated Facilities (APR 2015).

(viii) 52.222-26, Equal Opportunity (SEP 2016) (E.O. 11246).

(ix) 52.222-35, Equal Opportunity for Veterans (OCT 2015) (38 U.S.C. 4212).

(x) 52.222-36, Equal Opportunity for Workers with Disabilities (JUL 2014) (29 U.S.C. 793).

(xi) 52.222-37, Employment Reports on Veterans (FEB 2016) (38 U.S.C. 4212).

(xii) 52.222-40, Notification of Employee Rights Under the National Labor Relations Act (DEC 2010) (E.O.

13496). Flow down required in accordance with paragraph (f) of FAR clause 52.222-40.

(xiii) 52.222-41, Service Contract Labor Standards (AUG 2018) (41 U.S.C. chapter 67).

(xiv)(A) 52.222-50, Combating Trafficking in Persons (Mar 2015) (22 U.S.C. chapter 78 and E.O. 13627).

(B) Alternate I (Mar 2015) of 52.222-50 (22 U.S.C. chapter 78 and E.O. 13627).

(xv) 52.222-51, Exemption from Application of the Service Contract Act to Contracts for Maintenance, Calibration, or Repair of Certain Equipment-Requirements (MAY 2014) (41 U.S.C. chapter 67).

(xvi) 52.222-53, Exemption from Application of the Service Contract Act to Contracts for Certain Services- Requirements (MAY 2014) (41 U.S.C. chapter 67).

(xvii) 52.222-54, Employment Eligibility Verification (OCT 2015) (E.O. 12989).

(xviii) 52.222-55, Minimum Wages Under Executive Order 13658 (DEC 2015).

(xix) 52.222-62 Paid Sick Leave Under Executive Order 13706 (JAN 2017) (E.O. 13706).

(xx)(A) 52.224-3, Privacy Training (JAN 2017) (5 U.S.C. 552a).

(B) Alternate I (JAN 2017) of 52.224-3.

(xxi) 52.225-26, Contractors Performing Private Security Functions Outside the United States (OCT 2016) (Section 862, as amended, of the National Defense Authorization Act for Fiscal Year 2008; 10 U.S.C. 2302 Note).

(xxii) 52.226-6, Promoting Excess Food Donation to Nonprofit Organizations (MAY 2014) (42 U.S.C. 1792). Flow down required in accordance with paragraph (e) of FAR clause 52.226-6.

(xxiii) 52.247-64, Preference for Privately Owned U.S.-Flag Commercial Vessels (FEB 2006) (46 U.S.C. Appx.

1241(b) and 10 U.S.C. 2631). Flow down required in accordance with paragraph (d) of FAR clause 52.247-64.

(2) While not required, the contractor MAY include in its subcontracts for commercial items a minimal number of additional clauses necessary to satisfy its contractual obligations.

52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (MAY 2020)

(a) Definitions. As used in this clause--

Long-term contract means a contract of more than five years in duration, including options. However, the term does not include contracts that exceed five years in duration because the period of performance has been extended for a cumulative period not to exceed six months under the clause at 52.217-8, Option to Extend Services, or other appropriate authority.

Small business concern means a concern, including its affiliates, that is independently owned and operated, not dominant in the field of operation in which it is bidding on Government contracts, and qualified as a small business under the criteria in 13 CFR part 121 and the size standard in paragraph (d) of this clause. Such a concern is ``not dominant in its field of operation'' when it does not exercise a controlling or major influence on a national basis in a kind of business activity in which a number of business concerns are primarily engaged. In determining whether dominance exists, consideration shall be given to all appropriate factors, including volume of business, number of employees, financial resources, competitive status or position, ownership or control of materials, processes, patents, license agreements, facilities, sales territory, and nature of business activity.

(b) If the Contractor represented that it was any of the small business concerns identified in 19.000(a)(3) prior to award of this contract, the Contractor shall rerepresent its size and socioeconomic status according to paragraph (f) of this clause or, if applicable, paragraph (h) of this clause, upon occurrence of any of the following:

(1) Within 30 days after execution of a novation agreement or within 30 days after modification of the contract to include this clause, if the novation agreement was executed prior to inclusion of this clause in the contract.

(2) Within 30 days after a merger or acquisition that does not require a novation or within 30 days after modification of the contract to include this clause, if the merger or acquisition occurred prior to inclusion of this clause in the contract.

(3) For long-term contracts--

(i) Within 60 to 120 days prior to the end of the fifth year of the contract; and

(ii) Within 60 to 120 days prior to the date specified in the contract for exercising any option thereafter.

(c) If the Contractor represented that it was any of the small business concerns identified in 19.000(a)(3) prior to award of this contract, the Contractor shall rerepresent its size and socioeconomic status according to paragraph (f) of this clause or, if applicable, paragraph (h) of this clause, when the Contracting Officer explicitly requires it for an order issued under a multiple-award…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .