This is a solicitation (SPRDL1-24-R-0152) from DLA Land Warren for 477 Receiver Assembly units (NSN: 1005-01-172-7725, P/N: 6535480) with an option for an additional 477 units. The solicitation is a 100% Small Business Set-Aside for a Firm-Fixed-Price contract with DO-rated priority.

The contract requires First Article Testing (FAT) at the contractor's facility, which cannot be waived. The Government will provide test equipment and ammunition for FAT completion. Delivery is required within 420 days after contract award for the base quantity and 180 days for the option quantity if exercised. The contractor must follow Military Level B packaging requirements with Special Packaging Instructions. The product must be manufactured according to Government-owned technical specifications, with the contractor required to maintain ISO 9001:2015 quality standards (excluding paragraph 8.3). Proposals must be submitted electronically to the Contract Specialist, with submissions including both technical and pricing information.

View the file

Other files for this federal contract opportunity

Other files attached to Receiver Assembly, newest first.
File Type Posted
Amendment 0002 - SPRDL124R0152.pdf PDF
Amendment 0001 - SPRDL124R0152.pdf PDF
Special Packaging Instruction - 6535480.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION, OFFER AND AWARD 1. This Contract Is A Rated Order Under

DPAS (15 CFR 700)

Rating Page of Pages

2. Contract Number 3. Solicitation Number 4. Type of Solicitation 5. Date Issued 6. Requisition/Purchase Number Sealed Bid (IFB)

Negotiated (RFP)

7. Issued By Code 8. Address Offer To (If Other Than Item 7)

NOTE: In sealed bid solicitations ‘offer’ and ‘offeror’ mean ‘bid’ and ‘bidder’.

SOLICITATION

9. Sealed offers in original and copies for furnishing the supplies or services in the Schedule will be received at the place specified in item 8, or if handcarried, in the depository located in until (hour) local time (Date).

Caution - Late Submissions, Modifications, and Withdrawals: See Section L, Provision No. 52.214-7 or 52.215-1. All offers are subject to all terms and conditions contained in this solicitation.

10. For Information A. Name B. Telephone (No Collect Calls) C. E-mail Address

Call: Area Code Number Ext.

11. Table Of Contents

(X) Sec. Description Page(s) (X) Sec. Description Page(s)

Part I - The Schedule Part II - Contract Clauses A Solicitation/Contract Form I Contract Clauses

B Supplies or Services and Prices/Costs Part III - List Of Documents, Exhibits, And Other Attach.

C Description/Specs./Work Statement J List of Attachments D Packaging and Marking Part IV - Representations And Instructions E Inspection and Acceptance K Representations, Certifications, and F Deliveries or Performance Other Statements of Offerors G Contract Administration Data L Instrs., Conds., and Notices to Offerors H Special Contract Requirements M Evaluation Factors for Award

OFFER (Must be fully completed by offeror) NOTE: Item 12 does not apply if the solicitation includes the provisions at 52.214-16, Minimum Bid Acceptance Period.

12. In compliance with the above, the undersigned agrees, if this offer is accepted within _____ calendar days (60 calendar days unless a different period is inserted by the offeror) from the date for receipt of offers specified above, to furnish any or all items upon which prices are offered at the price set opposite each item, delivered at the designated point(s), within the time specified in the schedule.

13. Discount For Prompt Payment 10 Calendar Days (%) 20 Calendar Days (%) 30 Calendar Days (%) Calendar Days (%) (See Section I, Clause No. 52.232-8)

14. Acknowledgment of Amendments (The offeror acknowledges Amendment No. Date Amendment No. Date receipt of amendments to the SOLICITATION for offerors and related documents numbered and dated):

15A. Name and Code Facility 16. Name and Title of Person Authorized to Sign Offer Address of (Type or Print) Offeror

15B. Telephone Number 15C. Check if Remittance Address is 17. Signature 18. Offer Date Area Code Number Ext. Different From Above – Enter such

Address In Schedule

AWARD (To be completed by Government)

19. Accepted As To Items Numbered 20. Amount 21. Accounting And Appropriation

22. Authority For Using Other Than Full And Open Competition: 23. Submit Invoices To Address Shown In Item

10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( ) (4 copies unless otherwise specified)

24. Administered By (If other than Item 7) Code 25. Payment Will Be Made By Code

26. Name of Contracting Officer (Type or Print) 27. United States Of America 28. Award Date

(Signature of Contracting Officer)

IMPORTANT - Award will be made on this Form, or on Standard Form 26, or by other authorized official written notice.

AUTHORIZED FOR LOCAL REPRODUCTION Standard Form 33 (Rev. 9-97) Previous edition is unusable Prescribed By GSA-FAR (48 CFR) 53.214(c)

SPRDL1-24-R-0152

X

2025FEB20

SEE SOLICITATION

2025MAR2405:00pm

DOA4

2025FEB20 SEE SCHEDULE

SPRDL1

DLA LAND WARREN

WARREN, MI 48397-5000

JOHN MOSES

(586)467-1212

ZGBC

JOHN.MOSES@DLA.MIL

SEE CLAUSES

1 84

X 1

X 5 X 10

X 15 X 17 X 22

X 29

X 31

X 35

X 57

X 58

X 76

X 83

CONTINUATION SHEET

Reference No. of Document Being Continued Page of

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

SECTION A - SUPPLEMENTAL INFORMATION

Buyer Name: JOHN MOSES

Buyer Office Symbol/Telephone Number: ZGBC/(586)467-1212

Type of Contract 1: Firm Fixed Price

Kind of Contract: Supply Contracts and Priced Orders

*** End of Narrative A0000 ***

1. This procurement has been established as a 100% Total Small Business Set-Aside.

2. First Article Testing (FAT) at the contractor's facility is required for this procurement. Government Furnished Test Equipment and

Ammunition will be provided to complete the testing. See Sections C, E, and I for details.

3. See Exhibit A in Section J for the Contract Data Requirements List (DD1423), which includes the below data items:

A001 - Engineering Change Proposal (ECP)

A002 - Request for Variance (RFV)

A003 - Notice of Revision (NOR)

A004 - Acceptance Inspection Equipment (AIE) Report

A005 - Test Procedure - Heavy Phosphate Coating

A006 - First Article Test Report

A007 - Government Furnished Material (GFM) Consumption Report

4. Section J, Attachment 0001 references the Special Packaging Instruction (SPI) AM6535480 that will be issued under separate cover.

See the Section C Engineering Exceptions located with the Technical Data Package (TDP) in SAM.gov for updates to the SPI.

*** END OF NARRATIVE A0001 ***

AS7001

Acknowledgment of Amendments____________________________

Acknowledge all the amendments received from the Contracting Office by identifying the amendment number and its issue date below:

Amendment Number Date

************ End of Narrative ************

2 84

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

AS7311

Electronic Contracting Provision________________________________

(a) All DLA Land Warren solicitations will be publicized on the Contract Opportunities website https://SAM.gov . Any additional attachments, including Technical Data Packages (TDPs) when available electronically, will be separate attachments or referenced with instructions in the solicitation.

(b) As directed in Section L of this solicitation, interested vendors shall submit a quote or proposal via email to the Contract _________

Specialist listed on the solicitation. The email shall include subject header: Proposal Submission SPRDL1-XX-X-XXXX (company name) on the solicitation.

(c) Requirements for tracking solicitations and submitting bid submissions:

1. Vendors must be registered for a sam.gov account through https://login.gov in order to manage searches and track solicitations.

Using the Contract Opportunities search function in sam.gov, vendors will be able to view the Solicitation and any modifications or amendments made by the Contract Specialist.

2. Vendors may Request Access to controlled documents such as the Technical Data Package (TDP). Interested vendors must request TDPs as directed in Section C of this solicitation.

3. All bids and proposals must be submitted via email to the Contract Specialist on record. _________

(d) Note to offerors:

Please pay close attention to the solicitation closing date and time as stated on the cover page of this solicitation, local time (EST), for DLA Land Warren. In accordance with FAR 15.208(a), offerors are responsible for submitting proposals, and any revisions, and modifications, so as to be received by the Government office designated in the solicitation by the time specified.

It is Offeror's responsibility to ensure the proposal/quote is received by the Contract Specialist by the date and time specified on the cover page of this solicitation. In accordance with FAR 15.208, if the proposal/quote was not received at the initial point of entry to the Government infrastructure by the exact date and time specified on the cover page of this solicitation, it will be determined late.

Proposal/quote is defined to mean that ALL volumes or parts required in the solicitation are included in the electronic submission.

Note: There is no "expected" or "target" length of time for proposal submission; size and content may be factors, therefore offerors are strongly cautioned when submitting proposals to allow adequate time for submission.

Solicitations may remain posted on sam.gov after the solicitation closing date. If the response deadline has passed for the solicitation, vendors will need to send any late quotes, if applicable, directly to the Contract Specialist identified on the cover page of this solicitation.

(e) Any awards issued as a result of this solicitation will be distributed electronically. In the event of a FOIA request for a copy of any award issued as a result of this solicitation, or any subsequent modifications to the contract, the contract and modifications will be released, including the awarded unit price. This is the notice required by Executive Order 12600 (June 23, 1987) of our intention to release unit prices in response to any request under the Freedom of Information Act (FOIA), 5 USC 552. Unit price is defined as the contract price per unit or item purchased as it appears in Section B of the contract and is NOT referring to nor does it include Cost or

Pricing data/information. If you object to such release in the base contract or contract modifications, and you intend to submit an offer, notify the Procuring Contracting Officer in writing prior to the closing date identified in this solicitation and include the rationale for your objection consistent with the provisions of FOIA. A release determination will be made based on rationale given.

(f) Questions pertaining to this solicitation should be directed to the Contract Specialist identified on the cover page of this solicitation. For technical assistance in doing business with the Government, and doing business electronically, please visit the

Procurement Technical Assistance Center (PTAC) website at http://www.aptac-us.org/ to locate a regional center.

************ End of Narrative ************

AS7316

All or None____________

Offers in response to this solicitation must be submitted for the total quantity of the items identified in the solicitation.

(1) ONLY ONE AWARD WILL BE MADE AS A RESULT OF THIS SOLICITATION.

(2) OFFERS SUBMITTED FOR LESS THAN THE TOTAL QUANTITIES OF ALL THE ITEMS IN THIS SOLICITATION ARE INELIGIBLE FOR AWARD.

************ End of Narrative ************

3 84

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

AS8001

Notice of Requirement for Government Furnished Material (GFM)_____________________________________________________________

This solicitation includes the requirement for Government Furnished Material (GFM) which is defined as property in the possession of, or directly acquired by, the Government and subsequently furnished to the Contractor for performance of a contract.

The GFM list is attached to this solicitation. See the Section E narratives titled Government Furnished Ammunition and Government

Furnished Test Support Equipment for details. The GFM list identifies the part number(s), quantities, and delivery information for each unit of GFM to be provided to the Contractor in support of this contract in order to complete the first article test requirements.

The successful offeror is required to submit a written Property Management Plan to the Procuring Contracting Officer, in accordance with

DFARS 252.245-7003, CONTRACTOR PROPERTY MANAGEMENT SYSTEM ADMINISTRATION (provided in this solicitation), as part of the offer in response to this solicitation.

************ End of Narrative ************

*** END OF NARRATIVE A0002 ***

4 84

PIIN/SIIN

Page of

Name of Offeror or Contractor:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

Reference No. of Document Being Continued

MOD/AMD

SECTION B - SUPPLIES OR SERVICES AND PRICES/COSTS

0001 RECEIVER, CARTRIDGE

NSN: 1005-01-172-7725

Mfr CAGE: 19200

Mfr Part Number: 6535480

0001AA Production Quantity 477 EA $ $ ____________________ ______________ __________________

COMMODITY NAME: RECEIVER, CARTRIDGE

CLIN CONTRACT TYPE:

Firm Fixed Price

PRON: EH4C0688EH PRON AMD: 04

AMS CD: SM2B140000

Description/Specs./Work Statement _________________________________

TOP DRAWING NR: 6535480

DATE: 20-MAY-2024

See the technical data package for the list of drawings and specifications.

(End of narrative C001)

Packaging and Marking _____________________

PACKAGING/PACKING/SPECIFICATIONS:

SEE SECTION D AND SPI FOR PACKAGING DETAILS

UNIT PACK: 001

LEVEL PRESERVATION: Military

LEVEL PACKING: B

Inspection and Acceptance _________________________

INSPECTION: Origin ACCEPTANCE: Origin

Inspection/Acceptance at Origin means that you MUST contact the DCMA to arrange for a Government inspection BEFORE you ship the supplies called out in this order. Failure to have the items inspected and accepted will result in their rejection at the destination. The rejected supplies will be returned to you at your expense.

(End of narrative E001)

Deliveries or Performance _________________________

DOC SUPPL

REL CD MILSTRIP ADDR SIG CD MARK FOR TP CD ______ ________ ______ ______ ________ _____

001 W52H094114021V W562RP J 2

DEL REL CD QUANTITY DAYS AFTER AWARD __________ ______________ ________________

001 477 0420

5 84

Page of

Name of Offeror or Contractor:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

Reference No. of Document Being Continued

MOD/AMD

FOB POINT: Destination

SHIP TO:

(W562RP) SR W0LX ARMY GENERAL SUPPLY

DLA DISTRIBUTION ANNISTON

7 FRANKFORD AVE 362

ANNISTON,AL,36201-4199

6 84

Page of

Name of Offeror or Contractor:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

Reference No. of Document Being Continued

MOD/AMD

0001AB DATA ITEM: FIRST ARTICLE TEST REPORT 1 LO $ ** NSP ** ____________________________________ __________________

SERVICE REQUESTED: FIRST ARTICLE TEST REPORT

1 LO = 1 each Test Report on Contractor performed____

First Article Test (FAT)

NSP = Not Separately Priced___

(End of narrative B001)

FIRST ARTICLE TEST REPORT, PURSUANT TO THE

REQUIREMENTS OF THE CLAUSE ENTITLED "FIRST

ARTICLE APPROVAL - CONTRACTOR TESTING".

THE PRICE FOR FIRST ARTICLE TESTING IN THE

TOTAL AMOUNT OF $______________________, IS

INCLUDED IN THE TOTAL AMOUNT(S) FOR ITEM

0001AA.

The reason we are asking offerors to fill in the dollar amount in the preceding paragraph is so that we will know how much to subtract from the production CLIN if we waive the First

Article Test.

(End of narrative B002)

Inspection and Acceptance _________________________

INSPECTION: Origin ACCEPTANCE: Destination

DEL REL CD QUANTITY DAYS AFTER AWARD __________ ______________ ________________

001 1 0270

1. The First Article Test Report is due by 270 days after contract award.

2. Government Furnished Equipment and Ammunition is being provided for use in first article testing. See

Section E for details.

2. See the First Article Test Clause in Section I for details and distribution.

(End of narrative F001)

7 84

Page of

Name of Offeror or Contractor:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

Reference No. of Document Being Continued

MOD/AMD

0002 RECEIVER, CARTRIDGE

NSN: 1005-01-172-7725

Mfr CAGE: 19200

Mfr Part Number: 6535480

0002AA UNEXERCISED OPTION QUANTITY 477 EA $ $ ___________________________ ______________ __________________

COMMODITY NAME: RECEIVER, CARTRIDGE

CLIN CONTRACT TYPE:

Firm Fixed Price

OPTION QUANTITY, PURSUANT TO SECTION

I NARRATIVE ENTITLED "SEPARATELY PRICED

OPTION FOR INCREASED QUANTITY"

The quantity stated for the option CLIN

DOES NOT Form a part of the basic contractual quantity. Part or all of it may, however, be added to the contract by exercise of the option clause, at the discretion of the Government.

The option expiration date is 365 days __________ after contract award.

(End of narrative B001)

Description/Specs./Work Statement _________________________________

TOP DRAWING NR: 6535480

DATE: 20-MAY-2024

Packaging and Marking _____________________

PACKAGING/PACKING/SPECIFICATIONS:

SEE SECTION D AND SPI FOR PACKAGING DETAILS

UNIT PACK: 001

LEVEL PRESERVATION: Military

LEVEL PACKING: B

Inspection and Acceptance _________________________

INSPECTION: Origin ACCEPTANCE: Origin

Inspection/Acceptance at origin means that you MUST contact the DCMA to arrange for a Government inspection BEFORE you ship the supplies called out in this order. Failure to have the items inspected and accepted will result in their rejection at the destination. The rejected supplies will be returned to you at your expense.

(End of narrative E001)

8 84

Page of

Name of Offeror or Contractor:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

Reference No. of Document Being Continued

MOD/AMD

Deliveries or Performance _________________________

DOC SUPPL

REL CD MILSTRIP ADDR SIG CD MARK FOR TP CD ______ ________ ______ ______ ________ _____

DEL REL CD QUANTITY DAYS AFTER AWARD __________ ______________ ________________

001 477 0180

FOB POINT: Destination

SHIP TO:

(SPRDL1) DLA LAND WARREN

ZGA

6501 EAST ELEVEN MILE ROAD

WARREN,MI,48397-5000

The shipping destination for CLIN 0002AA has not been determined. Please reference the Section L narrative

LS7326 - Destination for Option Quantities for details.

(End of narrative F001)

9 84

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

SECTION C - DESCRIPTION/SPECIFICATIONS/WORK STATEMENT

CS6100

Drawings - Specifications_________________________

In addition to the drawing(s) and/or specifications listed below, other documents which are part of this procurement and which apply to Preservation/Packaging/Packing and Inspection and Acceptance are contained elsewhere.

Drawings and Specifications in accordance with Technical Data Package/Technical Data Package Listing 6535480, with revisions in effect as of 20 May 2024, are applicable to this procurement with the following exceptions:

Vendors to access this information with the technical data posted on Contract Opportunities.

************ End of Narrative ************

CS6334

Technical Data Package Information (Contract Opportunities in SAM.gov) Version_______________________________________________________________________________

The following Xd item applies to this solicitation:

[ ] 1. There is no Technical Data Package (TDP) included with this solicitation.

[ ] 2. This solicitation contains one or more web-located TDPs. If multiple Contract Line-Item Numbers (CLINS) are listed below, each one will have its own URL just under the CLIN listing. The URL will take you to that CLINs Web-located TDP. To access the TDP, you will have to copy or type the links URL to your web browser address bar at the top of the screen.

Note: To copy a link from a .pdf file, click on the Text Select Tool, then highlight the URL, copy and paste it into your browser, and hit the Enter key.

CLIN: N/A

TDP Link (URL): N/A

[ X ] 3. The TDP for this solicitation resides within sam.gov under the Contract Opportunities search function https://sam.gov , ___ and is associated with this solicitation number and can be accessed via this URL:

https://sam.gov/opp/788f3e6b67d5441e88b8edc1d12b599a/view

a. Log on to the SAM.gov website.

b. Select Contract Opportunities in the search bar and search by solicitation number.

(1) TDPs that have an Export Control Warning Notice are subject to the Arms Export Control Act (Title 22, U.S.C., Sec

2751, et.seq.) or the Export Administration Act of 1979, as amended, Title 50, U.S.C, App. 2401 et. seq..

(2) Further dissemination must be in accordance with provisions of DoD Directive 5230.25. This also applies to distribution of the TDP to all SUBCONTRACTORS at every level.

(3) To obtain these TDPs, vendors and Contractors must have a current DD 2345, Militarily Critical Technical Data

Agreement on file with Defense Logistics Information Service (DLIS).\~ If you are currently certified, your MPIN will be verified and you may proceed to the next step.\~ To obtain certification, login to the Joint Certification Program (JCP) https://www.dla.mil/Logistics-Operations/Services/JCP/ . Click on documents and follow instructions provided.\~ Processing time is estimated at six (6) to ten (10) weeks after receipt. Contract Opportunities will allow you to access export controlled TDPs once certification is confirmed.

(4) Upon completion of the purposes for which Government Technical Data has been provided, the Contractor is required to destroy all documents, including all reproductions, duplications, or copies thereof as may have been further distributed by the Contractor. Destruction of this technical data shall be accomplished by: shredding, pulping, burning, or melting

10 84

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

any physical copies of the TDP and/or deletion or removal of downloaded TDP files from computer drives and electronic devices, and any copies of those files.

c. If technical data is otherwise restricted, click the document title to request access. A window will pop-up, select Request

Access to controlled documents and enter the Reason for Access. This will generate an email to the Contract Opportunities system administrator at DLA Warren with all the information needed for them to grant you access. Contract Opportunities will subsequently automatically generate an email stating when you have permission to view or download TDP items. Allow 2 3 working days to complete this Contract Opportunities-TDP access/approval process through sam.gov.

d. Only one individual in your company can request access to the Technical Data Package (TDP) for a solicitation. That individual must be registered as the Data Custodian, as identified in the JCP, and be granted approval to view the Technical

Data Package (TDP) for a solicitation. The Data Custodian MUST be registered for a sam.gov account through https://login.gov

. Any individual(s) no longer with the company should be deleted. Questions related to registration in https://login.gov should be directed to https://login.gov/help/ . Questions related to accounts in sam.gov should be directed to https://sam.gov/content/help . Vendors are responsible for placing correct information in login.gov and sam.gov accounts.

e. It is strongly suggested that you submit an access request and provide the Contract Specialist with the completed Use and

Non-Disclosure Agreement at the same time if the solicitation requires both to gain access to view the TDP.

[ ] 4. The Government requires a Use and Non-Disclosure Agreement (NDA) to be signed by the Data Custodian of your firm, as identified in the JCP, before access is granted to the technical data. The appropriate Agreement is titled N/A, and is:

[ ] available by emailing the Contract Specialist listed on page 1 of this solicitation.

[ ] available as an attachment to this solicitation.

Follow the instructions on the Agreement and email it to the Contract Specialist at N/A. The Contract Specialist will notify the

Contract Opportunities administrator upon receiving the NDA. The Administrator will grant approval to view/download the TDP. An email stating approval has been granted will be sent to the vendor. It can take up to 24 hours after approval before you are able to view the

TDP. If you have any questions/problems viewing the TDP contact the Contract Specialist.

************ End of Narrative ************

CS6510

Heavy Phosphate Coating Requirement___________________________________

The following requirements regarding heavy phosphate coatings are applicable to this solicitation and any resultant contract in addition to those requirements set forth in specification MIL-DTL-16232G.

a. Paragraph 3.1 of MIL-DTL-16232G refers to "Preproduction Inspection." The heavy phosphate coating procedures should be sent by the

Contractor to the Contracting Office, DLA Land Warren, at DLAWarrenPostAward@dla.mil. The contract number must be cited on all phosphate coating procedures being submitted to DLA Land Warren for review and approval. Procedures shall include product name and manufacturer of all chemicals/materials to be used. All processes, equipment, controls along with testing and test frequencies used for phosphating including application of supplemental finishes shall be described in detail.

b. Paragraph 3.2.5-c of MIL-DTL-16232G refers to the "Chromic acid rinse, (Classes 1, 2 and 3)." The final rinse shall be checked by a standard free and total acid titration along with a pH reading "prior to starting production and at least every 8 hours thereafter."

c. Paragraph 4.7.3 of MIL-DTL-16232G refers to "Weight per unit area of phosphate coatings." The frequency for testing coating weight is "per lot, at least every 8 hours."

d. Paragraph 4.7.5 of MIL-DTL-16232G refers to "Accelerated corrosion resistance." Accelerated corrosion resistance shall be determined in accordance with 4.7.5.1. The frequency for testing accelerated corrosion resistance per ASTM B117 is "per lot, at least every 8 hours."

e. The "product name" along with the manufacturer of the supplemental dry film lubricant or CARC paint (primer/topcoat) shall be stated in the procedure and shall be traceable to the applicable Qualified Products List (QPL) or Qualified Products Database (QPD) at Assist

Online. QPD products may be obtained at the quick search site, type the specification number (i.e., 3150) in the second block and click the "Submit" button. Then click on the specification (i.e., MIL-PRF-3150). In the next screen, click on the word "Qualification".

To obtain MIL Specs, MIL Standards, QPL and QPD products see http://quicksearch.dla.mil/ . To obtain MIL Specs, MIL Standards, QPD products see https://assist.dla.mil/online/start/ .

f. A thickness range for the supplemental dry film lubricant or CARC paint (primer/topcoat) shall be stated in the procedure along with

11 84

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

a frequency for testing. A daily frequency is required.

g. Heat cured dry film lubricant shall be air dried for 1.0 hour (until dry to touch) after dipping/spraying or flash dried at 155-175 degrees F for 10-30 minutes and then heat cured at a temperature of 375-425 degrees F for 55-65 minutes per paragraph 4.3.2.3 of MIL-PRF-

46010.

h. Air cure dry film lubricant shall be air dried at room temperature for 24 hours minimum.

i. Adhesion testing shall be stated in the procedure for a supplemental coating of dry film lubricant per ASTM D2510 or CARC paint per

ASTM D3359, method B along with the frequency for testing. A daily frequency is required.

j. Salt spray testing of parts with phosphate and supplemental dry film lubricant per ASTM B117 for 100 hours shall be stated in the procedure along with the frequency for testing. The frequency for testing is "per lot or weekly." Parts shall show no more than 3 rust spots per 3" x 6" area with none larger than 1.0mm in diameter. Salt spray testing of parts with phosphate and primer per ASTM B117 for

336 hours shall be included in the procedure for supplemental coatings of CARC paint along with a frequency for testing. The frequency for salt spray testing is "per lot or monthly." Parts shall show no visible rust exceeding rust grade no. 9 per ASTM B610, no more than

5 blisters per 4" x 6" area with none larger than 3/64 inch in diameter. Underfilm attack at the scribe shall not exceed 1/8 inch.

k. Topcoat color shall be visual/equipment checked against the specified chip no. of FED-STD-595 per paint batch. The procedure shall include the specified color chip number.

l. Cure of the paint shall be checked daily by solvent wipe per paragraph 4.2.3.2 of MIL-DTL-53072. The manufacturer of the MEK solvent shall be stated in the procedure.

************ End of Narrative ************

CS7002

Drawing Limitations___________________

(a) The drawings supplied with this contract are not shop or process drawings. They are engineering design drawings. They are ___ adequate to permit manufacture, and:

(1) depict the completed (item(s), and

(2) serve as the basis for inspection of the completed item(s).

(b) These drawings DON'T cover intermediate drawings/specifications or steps in the manufacturing process. As a result, even if you meet all the dimensions and tolerances specified in the engineering design drawing for each individual part, a cumulative unacceptable fit for the contract item could result.

(c) The Contractor is responsible for producing the shop or process drawings needed to cover intermediate steps in the _____________________________ manufacturing process.

(d) The Contractor is responsible for obtaining all specifications and drawings necessary to manufacture the items being solicited _____________________________ in accordance with the TDP including all incorporated specifications and drawings. Delivery delays are not excusable where the

Contractor asserts that it did not have a specification or drawing and has failed to request, in writing, the specification from either the Procuring Contracting Officer or Contract Specialist prior to the solicitation closing date.

(e) If you fail to produce an end item with a cumulative fit that conforms to Government drawings, specifications or other supplemental manufacturing documentation, you'll be responsible for correcting this condition at no additional cost to the Government and no delivery schedule extension.

************ End of Narrative ************

CS7004

Configuration Control Engineering Changes__________________________________________

(a) The Contractor may submit Engineering Change Proposal(s) (ECPs) and Request for Variance(s) (RFVs) for the requirements in the

Government provided Technical Data Package (TDP). If a Value Engineering Change Proposal(s) (VECPs) clause is included on this contract, VECPs shall be submitted in the same manner as ECPs.

(1) ECPs - The Contractor may request a permanent change to the requirements specified in the TDP or any other baseline documentation by submitting an ECP. ECPs shall be submitted to include all Notice of Revisions (NORs) necessary to completely define the requested change. Each ECP shall be accompanied with at least one NOR per affected document. The Contractor shall not present any production

12 84

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

items for acceptance that incorporate any change to the TDP or other baseline documentation until notified by the Government the ECP has been approved and incorporated in the contract.

(i) Page 1 of DD Form 1692 (or equivalent) shall be submitted for all ECPs. Pages 2-7 of DD Form 1692 shall be submitted when required to properly explain all the potential logistics and technical impacts of the proposed change. DD Form 1695 NOR or DD

Form 1695-1 Tabulated NOR (or equivalents) shall be submitted to completely describe the desired change on each affected document.

(ii) All ECPs submitted by the Contractor will be routine priority unless otherwise justified. If the Contractor considers the ECP to be emergency or urgent, they shall include justification within 48 hours of submittal of the ECP.

(2) RFVs - The Contractor may request to temporarily depart from a requirement specified in the TDP or any other baseline documentation, by submitting an RFV. RFVs may be submitted either pre-production (formerly known as Request for Deviation (RFD)) or post-production and prior to acceptance by the Government (formerly known as Request for Waiver (RFW)). DD Form 1694 (or equivalent) shall be submitted for all RFVs. The Contractor shall not present any production items for acceptance with any nonconformance to the requirements in the TDP or other baseline documentation until notified by the Government the RFV has been approved and incorporated in the contract.

(b) Submission of requested changes - The submission of an ECP or RFV by the Contractor does not affect the required delivery dates specified within the contract, shall not constitute excusable delay in the performance of this Contract by the Contractor or in any way relieve the Contractor from compliance with the contract delivery schedule. If a delivery date change is needed, it must be negotiated with the Procuring Contracting Officer and documented via modification to the contract. The submission of an ECP and/or RFV by the

Contractor shall not preclude the Government from exercising its rights under any clause of the Contract.

(c) Specifications - Permanent proposed changes to specifications which are part of the TDP or baseline documentation shall be requested with an ECP and NOR (i.e. Specification Change Notices (SCNs) are not required).

(d) Forms If any of the above listed forms are not included with the solicitation or contract, the Contractor may locate forms on the

DOD Forms Website https://www.esd.whs.mil/Directives/forms/dd1500_1999/ or contact the Contract Specialist listed on page 1 of the solicitation or contract for copies of the forms.

************ End of Narrative ************

CS7151

Use of Class 1 Ozone Depleting Substances (CIODS)_________________________________________________

(a) Definitions.

(1) Class I and Class II Ozone-Depleting Substances (CIODS) refers to the class of substances identified in Section 602(a) of the Clean Air Act, (42 U.S.C. 7671a(a)), complete list provided at: https://www.epa.gov/clean-air-act-overview/clean-air-act-title-vi-stratospheric-ozone-protection

(2) Directly requires the use of CIODS means that the Government's specification or technical data package, at any tier, explicitly requires the use of any Class I Ozone-Depleting Substance (CIODS) in performance of the contract.

(3) Indirectly requires the use of CIODS means that the Government's specification or technical data package, while not explicitly requiring the use of any CIODS, does require a feature that you can meet or produce only by the use of CIODS.

(b) No CIODS shall be used in meeting the requirements of this contract. If the use of CIODS is required in the performance of this contract, please notify the Procuring Contracting Officer immediately in writing.

(a)\*()No Class II Ozone Depleting Substances shall be required in the performance of this contract without Government approval. If the use of Class II ODS is required in the performance of this contract, please notify the Procuring Contracting Officer immediately in writing.

************ End of Narrative ************

CS8001

Contractor Retention of Supply Chain Traceability Documentation________________________________________________________________

1) By submitting a quotation or offer, the Contractor, is confirming it currently has, or will obtain before delivery, and shall retain supply chain traceability documentation, as described in paragraph (2) below, demonstrating the item conforms to the technical requirements, and for part numbered items, is from an approved manufacturer.

13 84

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

2) Supply Chain Traceability Documentation

i. \*. Supply chain traceability documentation shall include: basic item description, part number; drawing or specification;

national stock number, manufacturing source, manufacturing sources Commercial and Government Entity (CAGE) code, and clear identification of the name and location of all supply chain intermediaries between the manufacturer to the contractor to

Government acceptance. The documentation should also include, if available, the manufacturer's batch identification for the item(s), such as date codes, lot codes, or serial numbers.

ii. Supply chain traceability documentation shall also include, if available, the manufacturer's batch identification for the item(s), such as date codes, lot codes, or serial numbers. For part numbered items, contractors can find examples of acceptable supply chain traceability documentation at the Counterfeit Detection and Avoidance Program (CDAP) website http://www.dla.mil/LandandMaritime/Business/Selling/Counterfeit-Detection-Avoidance-Program/ .

iii. In addition, the contractor will obtain, retain, and provide to the contracting officer written documentation of all inspections and tests necessary to substantiate that the supplies furnished under this contract conform to contract requirements, including any applicable technical requirements for specified manufacturers parts. Such records shall include, without limitation, test reports, test data, material certification, and manufacturing process sheets, in addition to any other information identified in the technical specifications applicable to the item.

3) The contractor shall make supply chain traceability documentation available to the contracting officer within three business days upon the contracting officers request. The contracting officer determines the acceptability and sufficiency of documentation.

The contractor shall retain supply chain traceability documentation for ten years after final payment under this contract for audit and other valid government purposes. If the contractor fails to retain or provide the documentation, or the contracting officer finds the documentation to be unacceptable, the contracting officer may take corrective action, including, but not limited to, cancellation of undelivered orders or rejection of delivered supplies.

************ End of Narrative ************

*** END OF NARRATIVE C0001 ***

14 84

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

SECTION D - PACKAGING AND MARKING

DS6419

Packaging Requirements (Special Packaging Instructions)_______________________________________________________

A. Military preservation, packing, and marking for the item identified above shall be accomplished in accordance with the specific requirements identified below, all the applicable requirements of, MIL-STD-2073-1 and the Special Packaging Instruction (SPI) contained in the TDP.

PRESERVATION: Military ________

LEVEL OF PACKING: B ___

QUANTITY PER UNIT PACKAGE: 001 ___

SPI NUMBER: AM6535480 _________

B. Unitization: Shipments of identical items going to the same destination shall be palletized if they have a total cubic displacement of 50 cubic feet or more unless skids or other forklift handling features are included on the containers. Pallet loads must be stable, and to the greatest extent possible, provide a level top for ease of stacking. A palletized load shall be of a size to allow for placement of two loads high and wide in a conveyance. The weight capacity of the pallet must be adequate for the load. The pallet shall be a 40 x 48 inch, 4-way entry pallet although variations may be permitted as dictated by the characteristics of the items being unitized. The load shall be contained in a manner that will permit safe handling during shipment and storage.

C. Marking: In addition to any special markings called out on the SPI;

C.1. All unit packages, intermediate packs, exterior shipping containers, and, as applicable, unitized loads shall be marked in accordance with MIL-STD-129 including bar coding and a MSL label. The Contractor is responsible for application of special markings as discussed in the Military Standard regardless of whether specified in the contract or not. Special markings include, but are not limited to, Shelf-life markings, structural markings, and transportation special handling markings. The marking of pilferable and sensitive materiel will not identify the nature of the materiel. Passive RFID tagging is required in all contracts that contain DFARS clause

252.211-7006. Contractors must check the solicitation and/or contract for this clause. For details and most recent information, see http://www.acq.osd.mil/log/sci/ait.html for the current DoD Suppliers Passive RFID Information Guide and Supplier Implementation Plan.

If the item has Unique Item Identifier (UII) markings then the concatenated UII needs to be 2D bar coded and applied on the unit package, intermediate and exterior containers, and the palletized unit load.

D. Heat Treatment and Marking of Wood Packaging Materials: All non-manufactured wood used in packaging shall be heat treated to a core temperature of 56 degrees Celsius for a minimum of 30 minutes. The box/pallet manufacturer and the manufacturer of wood used as inner packaging shall be affiliated with an inspection agency accredited by the board of review of the American Lumber Standard Committee. The box/pallet manufacturer and the manufacturer of wood used as inner packaging shall ensure tractability to the original source of heat treatment. Each box/pallet shall be marked to show the conformance to the International Plant Protection Convention Standard.

Boxes/pallets and any wood used as inner packaging made of non-manufactured wood shall be heat-treated. The quality mark shall be placed on both ends of the outer packaging, between the end cleats or end battens; on two sides of the pallet. Foreign manufacturers shall have the heat treatment of non-manufactured wood products verified in accordance with their National Plant Protection Organizations compliance program. In addition, wood used as dunnage for blocking and bracing, to include ISO containers, shall be ordered with ALSC certified marking for dunnage or the markings may be applied locally at two foot intervals.

E. This SPI has been validated and the method of preservation/packing has proven successful in meeting the needs of the military distribution system, including indeterminate storage and shipment throughout the world. Special instructions and/or tailoring of the

SPI is detailed in the Supplemental Instructions below. A prototype package is required to validate the sizes and fit requirements of the SPI. Minor dimensional and size changes are acceptable provided Contractor provides the PCO and ACO with notification 60 days prior to delivery. Any design changes or changes in the method of preservation that provide a cost savings without degrading the method of preservation or packing or affecting the serviceability of the item will be considered and responded to within 10 days of submission to

PCO and ACO. Government reserves the right to require testing to validate alternate industrial preservation methods, materials, alternate blocking, bracing, cushioning, and packing.

F. Hazardous Materials (as applicable):

F.1. Hazardous Materials is defined as a substance, or waste which has been determined by the Secretary of Transportation to be capable of posing an unreasonable risk to health, safety, and property when transported in commerce and which has been so designated. (This includes all items listed as hazardous in Titles 29, 40 and 49 CFR and other applicable modal regulations effective at the time of shipment.)

F.2. Unless otherwise specified, packaging and marking for hazardous material shall comply with the requirements for the mode of transport and the applicable performance packaging contained in the following documents:

--International Air Transport Association (IATA) Dangerous Goods Regulations

--International Maritime Dangerous Goods Code (IMDG)

15 84

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

--Code of Federal Regulations (CFR) Title 29, Title 40 and Title 49

--Joint Service Regulation AFJMAN24-204/TM38-250/NAVSUPPUB 505/MCO

P4030.19/DLAM 4145.3 (for military air shipments).

F.3. If the shipment originates from outside the continental United States, the shipment shall be prepared in accordance with the United

Nations Recommendations on the Transport of Dangerous Goods in a manner acceptable to the Competent Authority of the nation of origin and in accordance with regulations of all applicable carriers.

F.4. When applicable, a Product Safety Data Sheet (SDS) is required to be included with every unit pack and intermediate container and shall be included with the packing list inside the sealed pouch attached to the outside of the package.

G. SUPPLEMENTAL INSTRUCTIONS: See Section C exceptions for changes/updates to the SPI. ________________________________________________________

************ End of Narrative ************

*** END OF NARRATIVE D0001 ***

16 84

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

SECTION E - INSPECTION AND ACCEPTANCE

ES6019

Use of MIL-STD 1916___________________

a. The Government will not accept lots whose samples submitted for acceptance contain non-conformances unless appropriately documented and approved by the Procuring Contracting Officer (PCO). The Contractor shall use MIL-STD 1916, DOD Preferred Methods of Acceptance of

Product. The Verification Level (VL) shall be VL IV for major characteristics and VL II for minor characteristics.

b. MIL-STD HDBK-1916 provides guidance on the use of MIL-STD 1916. This handbook is not contractually binding.

************ End of Narrative ************

ES6026

First Article Test (Contractor Testing)_______________________________________

a. The first article shall be examined and tested in accordance with contract requirements, the item specification(s), Quality Assurance

Provisions (QAPs) and all drawings listed in the Technical Data Package.

b. The first article shall be representative of items to be manufactured using the same processes and procedures and at the same facility as contract production. All parts and materials, including packaging and packing, shall be obtained from the same source of supply as will be used during regular production. All components, subassemblies, and assemblies in the first article sample shall have been produced by the Contractor (including subcontractors) using the technical data package applicable to this procurement.

c. The first article shall be inspected and tested by the Contractor for all requirements of the drawing(s), the QAPs, and specification(s) referenced thereon, except for:

(1) Inspections and tests contained in material specifications provided that the required inspection and tests have been performed previously and certificates of conformance are submitted with the First Article Test Report.

(2) Inspections and tests for Military Standard (MS) components and parts provided that inspection and tests have been performed previously and certifications for the components and parts are submitted with the First Article Test Report.

(3) Corrosion resistance tests over 10 days in length provided that a test specimen or sample representing the same process has successfully passed the same test within 30 days prior to processing the first article, and results of the tests are submitted with the

First Article Test Report.

(4) Life cycle tests over 10 days in length provided that the same or similar items manufactured using the same processes have successfully passed the same test within 1 year prior to processing the first article and results of the tests are submitted with the

First Article Test Report.

(5) Onetime qualification tests, which are defined as a one-time on the drawing(s), provided that the same or similar item manufactured using the same processes has successfully passed the tests, and results of the test are on file at the Contractor's facility and certifications are submitted with the First Article Test Report.

d. Those inspections which are of a destructive nature shall be performed upon additional sample parts selected from the same lot(s) or batch(es) from which the first article was selected.

e. A First Article Test Report shall be compiled by the Contractor documenting the results of all inspections and tests (including supplier's and vendor's inspection records and certifications, when applicable). The First Article Test Report shall include actual inspection and test results to include all measurements, recorded test data, and certifications (if applicable) keyed to each drawing, specification and QAP requirement and identified by each individual QAP characteristic, drawing/specification characteristic and unlisted characteristic. Evidence of the QAR's verification will be provided. One copy of the First Article Test Report will be copy furnished to Contract Specialist john.moses@dla.mil, PCO timothy.nichols@dla.mil and usarmy.ria.devcom-ac.mbx.rdar-qep@army.mil.

f. Notwithstanding the provisions for waiver of first article, an additional first article sample or portion thereof, may be ordered by the Procuring Contracting Officer in writing when (i) a major change is made to the technical data, (ii) whenever there is a lapse in production for a period in excess of one year, or (iii) whenever a change occurs in place of performance, manufacturing process, material used, drawing, specification or source of supply. When conditions (i), (ii), or (iii) above occurs, the Contractor shall notify the Procuring Contracting Officer so that a determination can be made concerning the need for the additional first article sample or portion thereof, and instructions provided concerning the submission, inspection, and notification of results. Costs of the additional first article testing resulting from any of the causes listed herein that were instituted by the Contractor and not due to changes directed by the Government shall be borne by the Contractor.

17 84

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

************ End of Narrative ************

ES6055

Government Furnished Ammunition_______________________________

a. \*.Ammunition has been programmed to support contractual test requirements as follows:

(1) Rounds: 12,000

Cartridges: M33 Ball

National Stock Number: 1305-00-028-6574

Department of Defense Identification Code: A555

(2) Rounds: 20

Cartridges: Dummy Rounds

National Stock Number: 1305-01-557-7022

Department of Defense Identification Code: AB36

Applicable Data Item Descriptions (DIDs) for this solicitation are available on the website using https://quicksearch.dla.mil

DI-MGMT-80554

DI-MGMT-80503

DI-MISC-80914B

DI-MGMT-80438B

b. Requests for all ammunition shall be submitted electronically to the Contract Specialist listed on the contract using DD Form 1348 no later than 90 days prior to desired delivery dates. The completed request may be submitted via electronic mail to the Procuring

Contracting Officer and usarmy.detroit.tacom.mbx.ilsc-mca@army.mil

c. The Contractor shall be responsible for reporting on the status of ammunition expenditures throughout the life of the contract as follows:

1. Every 90 days after the initial receipt of Government furnished ammunition, the Contractor shall provide an ammunition consumption report in accordance with the CDRL.

2. No later than 30 days after completion of the contract, the Contractor shall report to the Procuring Contracting Officer on the remaining ammunition. The Contractor shall request disposition instructions for the remaining ammunition. The Contractor shall execute the disposition instructions and provide confirmation to the Procuring Contracting Officer.

d. The Contractor shall furnish a copy of the above ammunition reports and disposition requests to the cognizant Defense…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .