This solicitation package requests proposals for a garage door replacement project at a federal facility in North Dakota. The General Services Administration seeks to replace one failing overhead garage door and operator located in the Vehicle and Cargo Inspection System non-intrusive inspection building at the Port of Entry in Portal, North Dakota. Offerors must provide all labor, materials, and equipment to remove the existing door and install a new insulated steel door with windows, tracks, springs, and an electric operator by January 2024. The project also requires cleaning and fire sprinkler protection.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation Package
47PJ0024R0017
Overhead Garage Door & Operator Replacement Portal, North Dakota
Table of Contents
SF1442 Solicitation, O�er, & Award ……………………………………………………………. 2
The Agreement …………………………………………………………………………………………….. 5
Construction Scope of Work ……………………………………………………………… 8
3 in 1 Energy Specifications ………………………………………………………………. 16
Wage Determination …………………………………………………………………………. 17
The Solicitation ……………………………………………………………………………………………. 47
Representations & Certifications ………………………………………………………………… 62
** O�ers due by 4pm CT on 1/4/2024
** O�ers MUST be submitted via email to laura.funk@gsa.gov
** Site Visit: 12/19/23, 10:00 AM - 12:00 PM Central Time
(See ).
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair) IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".
SOLICITATION
1. SOLICITATION NUMBER
5. REQUISITION/PURCHASE REQUEST NUMBER
CODE
6. PROJECT NUMBER
8. ADDRESS OFFER TO
4. CONTRACT NUMBER
7. ISSUED BY
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)
11. The contractor shall begin performance within
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES", indicate within how many calendar days after award in Item 12b.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and
b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d. Offers providing less than
STANDARD FORM 1442 (REV. 8/2014)
Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
is, is not required.
local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.
calendar days and complete it within calendar days after receiving
a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
12b. CALENDAR DAYS
2. TYPE OF SOLICITATION
SEALED BID (IFB)
NEGOTIATED (RFP)
3. DATE ISSUED PAGE OF PAGES
47PJ0024R0017
GSA PBS NORTH DAKOTA FIELD OFFICE 8PMPN
657 2ND AVE N RM 244
Fargo, ND 58102 USA
In accordance with the Scope of Work dated 11/20/2023, the contractor will replace the failing overhead garage door and operator.
8PQ
GSA PBS Acquisition Division 8PQ 1 Denver Federal Center PO Box 25546, Building 41 Denver, CO 80225-0546 USA
EQ8PSMMN-24-0010
8PMPN
Laura Funk 701-566-6114
24-006
2 7112/14/2023
1/4/2024
4:00 PM (CST)
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
OFFER (Must be fully completed by offeror)
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT
NUMBER
DATE.
AWARD (To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)
CODE FACILITY CODE
15. TELEPHONE NUMBER (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14.)
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)
21. ITEMS ACCEPTED:
22. AMOUNT
26. ADMINISTERED BY
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)
31c. DATE
STANDARD FORM 1442 (REV. 8/2014) BACK
31b. UNITED STATES OF AMERICA
BY
31a. NAME OF CONTRACTING OFFICER (Type or print)
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30b. SIGNATURE 30c. DATE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
copies to issuing office.) Contractor agrees to furnish
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
23. ACCOUNTING AND APPROPRIATION DATA
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
27. PAYMENT WILL BE MADE BY
10 U.S.C. 2304(c) ( ) 41 U.S.C. 3304(a) ( )
20b. SIGNATURE 20c. OFFER DATE
PAGE
GENERAL SERVICES ADMINISTRATION
OF
ITEM NO.
(a)
SUPPLIES OR SERVICES
(b)
QUANTITY
ORDERED
(c)
UNIT
(d)
UNIT PRICE
(e)
AMOUNT
(f)
0001 __________
Place of Performance: Non-Instrusive Inspection NII Hwy 52
Port of Entry. The door is located in the VACIS
PoP: 01/22/2024 - 05/21/2024
Replace one failing garage door and operator at the Portal
Contract Type: Firm Fixed Price
Replace Overhead Garage Door and Operator
PSC: Z2AA -- REPAIR OR ALTERATION OF OFFICE BUILDINGS
Deliverable
LS
at Canadian Border Portal, ND 58772-9998
Non-Intrusive Inspection Building
Sol. Reference No. 47PJ0024R0017 GSA Contract No. TBD
Simplified Acquisition Construction Contract for: Garage Door Replacement located at US Hwy 52 At Can Bdr, Portal, ND, 58772.
The Agreement
Table of Contents
I. Project Information I.A. Project Summary I.B. The Contract I.C. Period of Performance I.D. Work Conditions/Site Requirements I.E. Authorized Representatives I.F. Contract Liquidated Damages Rate I.G. Buy American Exceptions I.H. Statement of Work, Specifications, Drawings, Exhibits, and Other Attachments
II. Prices II.A. Basis of Pricing II.B. Contract Price Form
III. Terms and Conditions III.A. Commencement, Prosecution, and Completion of Work III.B. Contractor Responsibilities III.C. Material and Workmanship III.D. Project Schedule III.E. Interpretation of Specifications and Drawings III.F. Submittals III.G. Government’s Right to Stop Work for Non-Compliance III.H. Other Contracts III.I. Use and Possession Prior to Substantial Completion III.J. Finality of Contract Modifications III.K. Liquidated Damages III.L. Insurance Requirements [CO Instruction: See FAR 28.306(b) and edit amounts if needed III.M. Administrative Matters III.N. Bonds III.O. Requirements for GSA Information Systems
IV. Contract Clauses IV.A. Clauses Incorporated in Full Text
(1) (FAR 52.223-2 Affirmative Procurement of Biobased Products Under Service and Construction Contracts (SEPT 2013)
(2) FAR 52.223-9 Estimate of Percentage of Recovered Material Content for EPA-Designated Items (MAY 08)
(3) FAR 52.225-9 Buy American—Construction Materials (OCT 2022)
(4) FAR 52.228-13 Alternative Payment Protections (July 2000)
(The Agreement) Last Revised 06/2023
(5) GSAR 552.204-9 Personal Identity Verification Requirements (APR 2023)
(6) GSAR 552.252-6 Authorized Deviations in Clauses (NOV 2021) (Deviation FAR 52.252-6)
(7) FAR 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment (NOV 2021)
(8) FAR 52.232-40 Providing Accelerated Payments to Small Business Subcontractors
(MAR 2023)
(9) FAR 52.228-11, Pledges of Assets (FEB 2021) (DEVIATION APR 2020)
(10) FAR 52.204-27 Prohibition on a ByteDance Covered Application
(11) Additional clauses
IV.B. Clauses Incorporated by Reference
I. Project Information
I.A. Project Summary
The purpose of this project is to replace one failing garage door and operator at the Portal North Dakota Land Port of Entry.
I.B. The Contract
(1) The Contract consists of the SF1442, the Agreement, the Statement of Work, Specifications, Drawings, Exhibits, Amendments, Modifications, and other Attachments identified herein (collectively, the Contract Documents). The Contract contains the entire agreement of the Parties, and no prior written or oral agreement, express or implied, shall be admissible to contradict or modify any part of the Contract.
(2) The Contractor shall provide and pay for all labor, materials, equipment, tools, water, heat, utilities, transportation, and other facilities and services necessary for the proper execution of the work described in and reasonably inferable from the Contract Documents (the Work), whether temporary or permanent. In consideration for, and upon condition of, the Contractor's completion of the Work, GSA shall pay the Contractor the price or prices established in Section II, subject to the terms and conditions set forth in this Contract.
I.C. Period of Performance
(1) Commencement. The Contractor shall commence performance of the Work within 10 days after the Contractor receives the Notice to Proceed (NTP).
(2) Substantial Completion. The Contractor shall achieve Substantial Completion of the Work, as that term is defined in this Agreement, no later than 110 calendar days from issuance of Notice to Proceed (NTP).
(3) Contract Completion. The Contractor shall achieve Contract Completion, as the term is defined in this Agreement, within 10 calendar days of Substantial Completion.
I.D. Work Conditions/Site Requirements
Work is located in and out of the Vehicle and Cargo Inspection System (VACIS) building located at the Land Port of Entry in Portal, North Dakota.
(The Agreement)
I.E. Authorized Representatives
(1) This Contract is between the United States of America, acting by and through the Administrator of General Services (GSA), and the Contractor (the Parties). References in this Contract to "the Owner" or "the Government" shall be understood to refer to GSA. The following individual is designated as the only authorized GSA representative under this Contract, unless other warranted contracting officers are designated in writing:
Authorized Representative Information:
Contracting Officer’s Information
Name: Laura Funk
Telephone: (701) 566-6114
Email: laura.funk@gsa.gov
(2) For the applicable authorities and limitations see Section IV of this Agreement, GSAR 552.236-70.
I.F. Contract Liquidated Damages Rate
In accordance with GSAR 552.211-12, Liquidated Damages – Construction, in Section IV of this Agreement, liquidated damages shall be calculated at the rate of $0 per calendar day.
I.G. Buy American Exceptions
For the applicable Buy American clause and any exceptions, see Section IV of this Agreement.
I.H. Statement of Work, Specifications, Drawings, Exhibits, and Other Attachments
The following documents are incorporated by reference into this Contract.
(1) Scope of Work dated November 20, 2023
(2) Wage Determination ND20230035 dated October 20, 2023
(3) Product Specifications
(4) Universal Scope Requirements V3.9 dated November 13, 2023
(Remainder of Page Intentionally Blank)
(The Agreement)
CONSTRUCTION SCOPE OF WORK
U.S. GENERAL SERVICES ADMINISTRATION, ROCKY MOUNTAIN REGION 8
Date: November 20, 2023
Revision Date: n/a
Section 1: Project Title
24-006 525 Portal VACIS Garage Door Replacement
Section 2: Project Location, Building Name, & Building Number
Portal: GSA Storage Garage 301 W. Railway Ave P.O. Box 39 Portal ND, 58772
Building Number: ND0523AM
Section 3: Contact List
Contracting Officer (CO)
Name: Laura Funk
Email: laura.funk@gsa.gov
Address: 657 2nd Ave N. #244
Fargo, ND 58102
Phone (O): (701) 566-6114
Project Manager
Name: Curtis Schumaier
Email: curtis.schumaier@gsa.gov
Address: 100 1st Street SW
Minot, ND 58701
Phone (O): 701-552-9852
Phone (C): 701-340-5954
Property Manager
Name: Curtis Schumaier
Email: curtis.schumaier@gsa.gov
Address: 100 1st Street SW
Minot, ND 58701
Phone (O): 701-552-9852
Phone (C): 701-340-5954
(Scope of Work)
Section 4: Project Background & Project Description
The General Services Administration needs to replace one failing garage door and operator at the Portal Port of
Entry. The door is located in the VACIS Non-Intrusive Inspection Building
Section 5: Project Objectives
The contractor shall provide labor, materials, equipment, and supervision necessary to perform:
1) Remove and replace existing door, tracks, springs, and cables.
2) Doors shall be a Midland Garage Door, Model 3” ENERGYSAVER see attached Specification or an approved equal. The door shall be the appropriate size to fit the current opening.
a. Current door measures 146 1/8 inches wide and 192 ½ inch high.
b. It is the contractor’s responsibility to verify the measurements before parts are ordered.
3) Each door shall have 2 windows installed, with a minimum of ½” insulated glass. Windows shall match the size and shape of the adjacent door.
4) Door R-value shall exceed 17.0 with closed cell polystyrene insulation.
5) Exterior Door Panel Color shall be Coffee. The Interior Door Panel shall be white. New door shall match the interior and exterior of the adjacent door.
6) Doors are to be double style, track to be 3”, and springs shall have no less than 25,000 cycle springs. Spring shaft line to have pillow block bearing on the end plates.
7) Rails shall be installed in a manner as not to block the fire sprinkler heads when the door is in the raised position.
8) Door cable shall be the maximum size allowed on the cable drums.
9) Contractor to remove and replace miller edge (Safety Strip) with new.
10) Exterior weather seals shall be replaced with new and match the adjacent door.
11) Contractor to remove existing commercial operator and replace it with a new operator, to include brakes and wall station. New operator shall be sized in accordance with the manufacturer's recommendation for the new door.
12) A staging area will be determined by mutual agreement after contract award.
13) The following information is provided for bidding purposes only. The contractor is advised to conduct a site visit and field-verify the exact information required for use in completing the work and submitting an offer.
14) No asbestos or lead containing materials shall be used.
15) All work shall comply with codes and standards applicable to each type of work through the course of this project including the National Electric Code (NFPA 70). Contractor shall also comply with the requirements of GSA Build Green Standards, and PBS P-100.
16) The Contractor is responsible for locating all utilities in the project area, both public and private. GSA will make any existing drawing available for reference purposes only, actual location is still the contractor's responsibility.
17) The contractor is responsible for the protection of all existing building property surfaces from damage due to work performed under this contract. Damages to existing surfaces caused by the performance of this contract shall be repaired to match the existing surface finish at no additional cost to the Government.
18) The Contractor shall remove all debris generated in the performance of this contract daily.
19) The contractor shall take all necessary precautions to prevent any dust or debris from filtering into other parts of the building including but not limited to mechanical systems. Should dust or debris filter into other parts of the building the contractor shall take immediate steps to clean the area (no equipment or supplies will be furnished by GSA).
20) At the completion of the project, the project area shall be cleaned to building standards as determined by the
GSA Property Manager. Should the contractor fail to clean the project limits in a timely manner, GSA will contract for said cleaning and the cost will be deducted from the contract. Ensure that all penetrations are sealed with fire rated approved material as required by the International Building Code.
21) The CO has the right to reject any unsatisfactory or unsuitable material or workmanship.
Section 6: Proposal Pricing & Site Walk
1) Pre-proposal Site Visit Meeting:
a. The site visit shall consist of a meeting to review construction requirements followed by a walk-thru of the project site. The meeting shall be attended by the contractor and GSA project personnel, and appropriate sub-contractors.
b. Review existing conditions of the project area including any field verification.
c. Review the solicitation/evaluation requirements.
d. Bidders are to arrange a pre-proposal site visit by contacting the Property Manager.
2) Cost Proposal Requirements:
a. When submitting a proposal, provide a cost breakdown for each task into the following categories:
Materials, equipment, labor hours, subcontractor's quotes, overhead, profit, and bond broken down into shell, tenant improvement (TI) (by tenant), Building- Specific Amortized Capital (BSAC), and environmental (as applicable). Follow P120 guidelines for tier level 3 based on project triage tool.
Pricing shall be broken down by Construction Specification Institute (CSI) divisions.
Section 7: Period of Performance
Once notice to proceed has been issued, the contractor has 120 calendar days to complete the project. The contractor must also promptly begin the badging process at the time of notice to proceed. Please allow a minimum of
30 days to complete the badging process. Because this work will be located on a port of entry, the CBP may require the contractor to provide additional clearance information before work can begin on site. Extensions will be granted for unforeseen conditions and other factors outside of the contractor’s control at the Contracting Officer’s discretion.
Section 8: Universal Scope Requirements
ALL of the requirements in this section are MANDATORY
● See the attached Universal Scope Requirements document for the full details outlining each item
● Failure to comply with any and all of the requirements will result in the project not being accepted as complete
Section 9: Submittals
1) Contractor shall submit a Method of Procedures (MOP) to the GSA Delivery Project Manager (PM) for approval prior to commencement of work. At a minimum, the MOP shall include:
a. Brief narrative describing method of accomplishment, construction techniques, etc
b. b) Project schedule (to include critical path, major milestones, long lead time items, mobilization & demobilization, inspection dates, substantial completion, and occupancy dates)
c. Service/Utility Outages (if necessary)
d. Phasing schedule (if necessary)
e. Any building infrastructure/BAS equipment that may be impacted
2) All new equipment and anything requiring a preventative maintenance plan shall be inputted into Maximo upload template.
3) Submittals:
a. Manufacturer's specifications, instructions, and material specification sheets in original form
b. Shop drawings showing size and hardware locations
c. Warranty information
4) Submittal response by the government shall be (14) calendar days or less.
Section 10: General Requirements
1) Contractor Use of the Premises
a. During the period of the project, the contractor will have access to the site only during business hours of 7:00 am -5:00 pm, Monday through Friday. No on-site work shall be performed outside these hours or on holidays unless otherwise directed by the Contracting Officer. The contractor will need to coordinate with the Contracting Officer to arrange access to the parking lot. The contractor shall make every effort to cause a minimum of damage to parking lots, any other paved areas, any items that need to be moved during the course of the project, and any areas not included in this scope of work. Any damage caused will be repaired at the contractor’s expense.
b. Contractor to coordinate a staging area, if needed, with the building manager prior to mobilizing to the site.
2) Progress Meetings
Progress meetings are not required for this project. The project manager and building team representative shall make daily inspections of the work progress.
3) Equipment
The contractor shall provide all equipment associated with the entire project, operate in a safe manner and adhere to all OSHA and GSA standards.
4) Equipment and Material Storage
The contractor shall provide and store all equipment, the materials specified above, and any other materials required completing the project. The materials are required to be kept clean and dry throughout the duration of the project. Contractor to coordinate with building manager for location of storage sheds.
5) Electricity, Water, and Gas
GSA will pay for electricity, water, and gas during the course of this project. The contractor is responsible for making connections to the existing systems. Temporary electrical work shall meet the requirements of NFPA
70-1996 (NEC), Article 305. When temporary connections are removed, restore existing utility services to their original condition.
6) Fire Watch
Contractor shall be responsible for providing fire watch if required per attached GSA fire watch guidelines.
7) Fire Alarm Impairment and Hot Work
When a fire suppression or alarm system impairment is required, the contractor shall provide a written outage request to GSA for approval in advance of impairing any systems. Contractor shall be responsible for having a GSA approved NICET certified fire alarm contractor perform all system impairments. During fire alarm/suppression impairments or hot work procedures, the contractor shall provide a fire watch per the
GSA Regional Fire Watch Guidelines.
8) Protection of Public
The building site will continue to be used by tenants. The contractor shall fence, barricade, or otherwise block off the immediate work area to prevent unauthorized entry. The contractor shall illuminate barricades and obstructions at night and maintain safe building access and egress for tenants.
9) Housekeeping
The project site shall be kept in a neat, orderly, and safe condition at all times. The contractor shall provide enough containers for collecting construction debris and construction materials to be recycled. The contractor shall wet down dry materials and rubbish to prevent blowing dust and keep volatile wastes in covered containers.
10) Transportation and Deliveries
The contractor shall arrange deliveries of materials in accordance with construction schedules; coordinate with COR to avoid conflict with other tenants and other work conditions at the site. Contractor must make
GSA PM & CO aware of any lead times that may affect the project schedule.
11) Cleaning
Before scheduling the final inspection, the Contractor shall accomplish six items: (1) Remove all tools, equipment, surplus material, and rubbish; (2) Restore or refinish, to original condition, surfaces that are damaged due to the work of this contract; (3) Remove grease, dirt, stains, foreign materials, and labels from finished surfaces; (4) Thoroughly clean building interiors; (5) Pickup all construction debris from the site; and
(6) At time of final inspection, project shall be thoroughly cleaned and ready for use.
12) Disruptive Work
All painting, staining, or other activity which may cause noxious or undesirable fumes and/ or any noisy work that may be disruptive to the tenants/ public must be performed after normal working hours. The use of paint or stain that does not generate odors is preferred and may be required if the space will be occupied the following day with prior written approval from GSA.
Section 11: Badging & Security
1) Contractor is responsible to follow GSA’s security and badging requirements as detailed upon contract award.
2) US Access shared enrollment centers can be found at fedidcard.gov. Travel distances to the nearest center should be accounted for during the badging process.
3) All contract employees working onsite shall have a favorable Tier 1 or SAC background investigation.
● Personnel who have not received a favorable determination will not be permitted to work on this project.
● Escorting of employees that have not received a favorable determination through GSA’s security requirements or local agencies background check is not permitted.
● The contractor may be subjected to additional background checks by the local agency for any border station projects or services.
● At the discretion of the Port Director and GSA Facility Manager, background checks for escorted personnel may be conducted by Customs and Border Protection.
Section 12: Payments
Information regarding payment requests and payment is in the solicitation/ contract. Please contact the CO if you have any questions regarding payments.
Section 13: Substantial Completion & Final Inspection
1) When a project, or designated portion of the project is complete, request a final inspection. Upon receipt of a request that the project is substantially complete, the Contracting Officer will proceed with the inspection within ten days of receipt of request or will advise the contractor of items that prevent the project from being designated substantially complete.
2) The contractor shall provide O&M manuals. The O&M manuals shall contain the following:
● Executed Warranties (at project completion)
● Maintenance and operation manuals
Section 14: Attachments
1) Universal Scope requirements
2) 3 in Energy Saver Specifications
PICTURES
FINISH OPTIONS
Standard Colors White, Almond, Sandtone, Tera-Bronze, Beige, Green And Coffee
ColorSelect Select Custom Color
Powder Coat Select Custom Color
ARCHITECTURAL SPECIFICATIONS
MODEL 3” ENERGYSAVER™
MIDLANDGARAGEDOOR.COM | 800. 473. 4056
STEEL STANDARDS SPECIFICATIONS
Thickness ASTM A653 25 Ga.
20 Ga. (Available)
Embossing Pebble Texture
Hot Dipped ASTM A924 Galvanized Coating
16 Ga.
13 Ga.
STILES MATERIAL SPECIFICATIONS
End Stiles HDG Steel
Center Stiles HDG Steel 16 Ga.
13 Ga.
THERMAL BREAKS TYPE LOCATION
Top/Bottom Extrusions PVC Top/Bottom Of Sections
Alcryn Thermoplastic Elastomer Bottom Of Sections
Seal Stripes Polypropylene Face Side End Of Stiles
FINISH TYPE SPECIFICATIONS
Prime Coat Urethane Primer 0.2 mil
Top Coat Baked On Polyester 0.8 mil
SECTION INFORMATION
FEATURE STANDARDS SPECIFICATIONS
Wind Guard Package* ANSI/DASMA A102 IBC 2015 Exposure B Or C Building Category II Or III
Installed U-Factor ANSI/DASMA 105 0.15 BTU/HR-FT2-ºF
R-Value ASTM C236 R17.05
ANSI/DASMA 105
ASTM E283
AIR INFILTRATION STANDARDS COMPLIANCE
15 mph 0.08 cfm/ft2
25 mph 0.13 cfm/ft2ANSI/DASMA 105
ASTM E283
PERFORMANCE DATA
10,000 Cycle Standard 25,000 Cycle Available 50,000 Cycle Available 100,000 Cycle Available
HARDWARE FEATURES SPECIFICATIONS
Hinges ASTM A123 G60
Rollers Floating, Bearing Nylon Steel
COUNTERBALANCE STANDARDS COMPLIANCE
Helical Wound ASTM A229 Coil Springs
Lift Cables Galvanized Aircraft Type
Cross Header Shaft ANSI/DASMA 102 Designed for Appropriate
SF
SPRING
HARDWARE & COUNTERBALANCE
LOCK TYPE SPECIFICATIONS
Slide Lock Interior Mounted
Keyed Lock Optional
WEATHERSTRIP MOUNTING LOCATION
U-Shape Astragal Aluminum Retainer Bottom Of Door
TRACK STANDARDS SPECIFICATIONS
2 Inch Track ASTM A1008/A1010 Angle Mount
3 Inch Track ASTM A1008/A1010 Angle Mount
TRACKS, LOCK & WEATHERSTRIP
OPERATOR TYPE
Pull Rope Standard Equipment
Chain Hoist or Optional Electric Operators
OPERATION
*OPTIONAL **Not available in all sizes, consult factory for unusual requirements.
As manufactured by Midland Garage Door Mfg. Co. Related structure work, opening preparation, field painting, electrical work falls to the responsibility of other trades.
Garage doors should be installed in compliance with Midland Garage Door Mfg.Co.
instructions by authorized Midland Garage Door installation professionals.
ADD-ONS
• Thermal Glazing
• High Cycle Springs
• Jamb Weatherstrip
• Electric Operators
• Chain Hoist
DOOR OPTIONS
• Bottom Sensing Edge
• Flexible PVC Dual Flap Header Seal
• Full Vision Aluminum Sections (White Standard With Optional Anodized, Powder Coat, Or ColorSelect Custom Colors)
DOOR TYPE: POLYSTYRENE INSULATED PANEL THICKNESS: 2.875 INCH R-VALUE: R17.05 INSTALLED U-FACTOR: 0.15 BTU/HR-FT2-ºF
3-INCH ENERGYSAVER HIGHLIGHTS
U-Factor is tested per ANSI-DASMA 105. Installed U-Factor and calculated U-Value are NOT equivalent.
U-Factor is tested per ANSI-DASMA 105. Installed U-Factor and calculated U-Value are NOT equivalent.
| ����������� | ���������������� |
| ���� | �� |
| ���� | �� |
| ��(")*+ | *����,�� -)� *,��'-,./� ��0� |
��������#���1����!� �����#�2��� ����3(� ������4� ����� �5��6"�
��7 ������#�������!��8������� �������������9�#��������8������������/:� ���5��,������2��;� ���5��,�������;�<('������� ���5��,����������!��
5����
��!�����1�������# 5�������������������4� ����� �5��6"�
��7 �������1$������
������4� ����� �5��6"�
��-�������7 �������1 ��������=��>-��(�0�30�360;�3(??????????????????????????????????????????????????????????????@*1�����
���5��,������2��;������@@��� ���1����.�����!���$��@��#�������!����������
�(������������������@@����9��� ���:�������0�(#($����@(� ���
����3�
5�����9 �������������@@�1����.�����!���$�������������@��������A�;(�������� ���0 �����9�#���������@@������������������������������@��������� �������9�#���������@@������������������������������@������������� �$��1����������@@������������������������������@����#���3�1 ���������@@������������������������������@�����������1
���������(����������@@??????????????????????????????@?????????????????????????????@@*1�����
��9����9������ ���5��,�������;�<������@@ �����9����.�����!��$���������@��#�������!����������
������9���
���1����.�����!��@��
5�����9 �����������������@@��$���������������������������@��A��(�������� ���0 �����9�#�������������@@������������������������������@�� �������9�#������������� �$@@������������������������������@���1���������#���3�1 �������������1
���5��,�������������9�#�������9��������4�������������!(�*1������
5������!� 1����/:� ���5��,������������ �����1�
�����!�1 ����1 1�9
������9�#�������������
�1 ����8����(7����� ������1
����8��������������9 ���5��,����������5�����������������999(� 5�9���#
��1�
(Wage Determination)
| ��� | �������������������������������������������������������������������������� | |||
| ������������������������������ � | ����������������!� | ��������������������������������������������������������������������"#������� | ��������������������������������������������������������������������� | |
| $���%������������������������� ���������������������� | ��������������������������������������������������������������������$��� | ��������������������������������������������������������������������������$&� |
| �()*+�����,-���.,)�����/�����0������������������ ����! | ����������12��� | �������������������������������������������������������������������"3 |
| �� | !�����������������������������������������������������������������������4�/����56 |
4��"&��4���&��7���'�,))��0������������������������� �������������������!� "3��"#���8&�6$&6���0���������������������� ����!���������������������������������������������������������������������������������������������� ���������������������������������������������������������������������������������$��9������&��+�������������� ��������������������� �����$,::,��,��3�����)����������� ��������������������� ����������������������������������������������������������������;�4��8���������������������������������������������������������������������������$���"&���8�"�$�"$��&��� 8<����� ������������������� � ������������������������������������������������������������������4�6����������������������������������������������������������������������������4�6������������������������������ ����
������������������������������������������������������������������4�6����������������������������������������������������������������������������
| �������������������������������������������������������������������� | ������ | ||||||||||
| ����� | ���������� | ����� | ������������ | ���� | !"�#�� | $�%�& | '()� | �����**���+� | "�*,-���������������� | ��� | |
| � | � |
| .���������������������������������������������������������������� | �/0'�� | |
| ����1 | ��� |
| 1 | ����� | �������&����0���������������������������� | � | |||
| ��� | �� | |||||
| . | �"�� | !"�#������������������������� |
� ���1 �0�/ ��"� � ��&��0�&� $'()�2 ��3� 4 ��)5���)�* �,���6 ���(*���+�-����������������
| � | �� | |||||||||
| � | "�����"�7 | 8�)95+���:)�;��+�����)95+��������� | ����� | 1��� | "�����"�7 | 8+<)����9�= | �������9�= | +�=������������������� | � |
| ���. | "�����"�7 | &���������������������� | ����� |
| .��. | "�����"�7 | �+�9*�>���������������� | ���1� |
| �.� | "�����"�7 | +�=������������������� | � |
��1. ���0��� $8�(�5 ��= �+**��-��������
| � | ���� | ��/&# | '��%��7 | '(63 | ��()9��������� | ����. | ��������������������������������������������������������������������!� '��� | � | ��)��;� | ���� | 3���)��<�= | >+� | )��>� | 3��>+�6���+3�����+� | �+ | ?5�)5 | ?�*=��� | �� | ��)�=����*�@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@0+��7 | �:�)(��;� | "�=�� | $�"- | |||||||||||||||||||||||||||
| ���2 | ����<*��5��� | ���= | ��)9 | ��;�>+� | ��=���* | &+����)�+�� | �33*��� | �+ | �** | )+����)�� | �(<A�)� | �+ | �5�'�;���8�)+� | �)� | >+� | ?5�)5 | �5� | )+����)� | �� | �?��=�= | $��= | ��,�+*�)�����+� | ?�� | ���(�=- | +� | +� | �>��� | B��(��, | |||||||||||||||||||||
| 2 | �� | ||||||||||||||||||||||||||||||||||||||||||||||||
| �� | �> | �5��)+����)� | �� | )+;���= | <, | �5� | �"2 | �5� | )+����)�+� | 6(�� | 3�+;�=��63*+,��� | ?��5 | |||||||||||||||||||||||||||||||||||||
| 5+(� | +> | 3��= | ��)9 | *��;� | >+� | �;��, | |||||||||||||||||||||||||||||||||||||||||||
| � | 5+(���5�, | ?+�92 | (3 | �+ | .� | 5+(�� | +> | 3��= | ��)9 | *��;� | ��)5 | ,�����63*+,��� | 6(�� | <� | 3��6����= | �+ | (�� | 3��= | ��)9 | *��;� | >+� | �5���+?� | �**����2 | ��A(�, | +� | +�5�� | 5��*�5���*���= | ���=�2 | ��)*(=���3��;����;� | )���C | �+ | ������ | � | >�6�*, | 6�6<�� | $+� | 3���+� | ?5+ | ��*�9� | >�6�*, | �+ | �5� | �63*+,��- | ?5+ | �� | �**2 | ��A(��=2 | +� | 5�� |
| �������!� �� | �+, |
| �"��-./%01��2�11��1341�4�1�5 | �./%0� |
�"�����!������.�!����� �1��2
| � | $�.�!������/�� | |
| ��1��2 | �������,���!����$11�� |
�� �1341�4�1�5� ��6!����$�1�5 %�
�����������7'���� ���
| ��� | �+, |
| �"��-�(%/'�1���113��4�84�1�5 | �(%� |
9�� ��1��� ��� �������,���!����$�113 �� ��4�84�1�5�
9��
���:����� ��$��11;��������� �+<'0./+-�%')*�=>�11�1124��4�1�5 �%')*� �� �������,���!����$�11�1� �� �124��4�1�5�
| � | �� |
| ����� ������������ |
����!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!�������������������"��#�$#%#&'()�%(*)��++#�,-�+&*�#--.�/�0
����1�%�����
��23��
��4���� 3�� 3��
��0����$������ ����3��
���5
����6�����������
��0���) �7�/�
��8�/����� ������� �����"�������
����"�������2��������������
��0����$������ ���������������799��� ��$��797.97�/�(������
������������6������
����5������
���6�����������
��0������ � ���5-���7:��;&�+
��7:��;&�+ ���=/��"�������2������������"
��0������ � ���������������799��� ��$��797.9%�����6��������� �����
�5� ��������6���������
���������������8�/�(�������������
���5��� �� ������" ��/���"�������2�������������� � ���������������799��� ��$��797.9@�/�� ��������
II. Prices
II.A. Basis of Pricing
(1) Contract Prices. All Contract prices set forth in this Section include all costs necessary to complete the work for which the price is established (e.g., Base Contract, Unit Price, Options) in accordance with the Contract Documents, including, but not limited to, the cost of work performed by subcontractors and consultants, indirect costs, fees, expenses, taxes, and profit.
(2) Knowledge of Conditions Affecting Price. FAR 52.236-3, Site Investigations and Conditions Affecting the Work, is incorporated by reference in this Contract. The Contractor shall be presumed to have established all prices with knowledge of general and local conditions that may affect the cost of Contract performance at the site where the Work is to be performed, to the extent that such information is reasonably obtainable.
(3) Unit Prices and Allowances. If any portion of the Work is to be performed on a unit price basis, the Unit Price shall include all costs of coordinating and incorporating the unit-priced portion of the Work into the Base Contract Work. The Contractor shall only be obligated to perform unit-priced work to the extent that an Allowance has been established. The Contractor shall be obligated to perform such work in excess of a unit quantity for which an Allowance is established only if directed by the Contracting Officer in writing. The Contractor shall be bound to the unit price or prices set forth herein in all equitable adjustments for changes including unit priced work, and no markups shall be applied to such unit prices.
II.B. Contract Price Form
Standard Form (SF) 1442
III. Terms and Conditions
III.A. Commencement, Prosecution, and Completion of Work
FAR 52.211-10, Commencement, Prosecution, and Completion of Work and GSAR 552.211-10, Commencement, Prosecution and Completion of Work is supplemented as follows:
The Contractor shall diligently prosecute the Work so as to achieve Substantial Completion of the Work, as defined in GSAR 552.211-70 Substantial Completion (Mar 2019) and the time specified in Section I (Project Information), “Period of Performance” clause. If the Contract specifies different completion dates for different phases or portions of the Work, the Contractor shall diligently prosecute the Work so as to achieve Substantial Completion of such phases or portions of the Work within the times specified.
III.B. Contractor Responsibilities
GSAR 552.236-71, Contractor Responsibilities is located in Section IV.A. of this Agreement and is supplemented as follows:
(1) The Contractor shall secure and pay for all necessary permits and governmental fees, licenses, and inspections that are customarily secured after award of the Contract and that are legally required at the time of award. The Contractor shall provide a copy of the permits required for execution of the work to the Contracting Officer prior to commencement of any related work.
(The Agreement)
III.C. Material and Workmanship
All equipment, material, and articles incorporated into the Work shall be new and of the most suitable grade for the purpose intended, unless otherwise specified in this Contract. References in the specifications to equipment, material, articles, or patented processes by trade name, make, or catalog number shall be regarded as establishing a standard of quality and performance and shall not be construed as limiting competition. Unless specifically directed by the Contracting Officer, the Contractor may use any equipment, material, article, or process that is equal to that named in the specifications, so long as it is of comparable quality and meets specified characteristics, or, if no such characteristics are specified, the relevant performance characteristics of the specified item.
III.D. Project Schedule
(1) The Project Schedule shall be a rational, reasonable and realistic plan for completing the Work, and conform to requirements specified in this clause and elsewhere in this Contract.
(2) The Contractor understands and acknowledges that the preparation and proper management of the Project Schedule is a material component of the Work, and that the Contract price includes all costs of compliance with Project Schedule requirements.
(3) The Project Schedule shall depict all major activities necessary to complete the Work.
(4) Prior to NTP, the Contractor shall submit its Project Schedule to the Contracting Officer. The Contractor shall submit the Project Schedule in PDF and hardcopy print format.
(5) The Project Schedule shall incorporate both major tasks as well as milestone events specified in the Contract, including, as applicable, NTP, Substantial Completion, and milestones related to specified work phases and site restrictions. The Project Schedule shall also include Contractor-defined milestones to identify target dates for critical events, based upon the Contractor's chosen sequence of work and be linked to the tasks that drive those milestones.
(6) Unless a shorter period for updates is specified elsewhere, the Contractor shall update the Project Schedule weekly to reflect its actual progress in completing the Work, and submit the updated Project Schedule to the Contracting Officer.
(7) If the Contractor revises the Project Schedule after initial submission, the Contractor shall provide in writing to the Contracting Officer a narrative describing the substance of the revision, the rationale for the revision, and the impact of the revision on the projected substantial completion date.
(8) If at any time the Contracting Officer finds that the Project Schedule does not comply with any Contract requirement, the Contractor shall, upon written notice of exceptions taken by the Contracting Officer, revise the Project Schedule, adjust activity progress, or provide sufficient information demonstrating compliance.
(9) If the Contractor fails to sufficiently address the Contracting Officer's exceptions to the Project Schedule within 5 calendar days of written notice of the same, the Contracting Officer may withhold retainage until the Project is Substantially Complete or until such time as the Contractor has complied with Project Schedule requirements.
(The Agreement)
(10) The Contracting Officer shall be entitled, but not required, to rely upon the Project Schedule to evaluate the Contractor's progress, evaluate entitlement to extensions of time, and determine the criticality or float of any activities described in such Project Schedule.
III.E. Interpretation of Specifications and Drawings
(1) The specifications and drawings shall be interpreted to complement each other.
Requirements set forth in the specifications and not shown on the drawings, or shown on the drawings and not set forth in the specifications, shall be of like effect as if shown or set forth in both.
(2) Different requirements within the Contract Documents shall be deemed inconsistent only if compliance with both cannot be achieved.
(3) If a requirement set forth in one location is more restrictive than that set forth elsewhere in the Contract Documents, requirements set forth in specifications shall govern over requirements set forth in drawings; otherwise, the more restrictive shall govern.
(4) In case of inconsistent requirements within the drawings, the following order of precedence shall apply:
(a) Requirements indicated in large-scale drawings shall govern over inconsistent requirements indicated in small-scale drawings.
(b) Requirements indicated in schedules shall govern over inconsistent information shown in drawings.
(5) Unless otherwise noted, the drawings shall be interpreted to provide for a complete construction, assembly, or installation of the Work, without regard to the detail with which material components are shown in the drawings.
(6) If any inconsistency within the drawings or specifications cannot be reconciled by reference to this clause, the Contractor shall promptly request a determination from the Contracting Officer as to which requirement shall govern. Election by the Contractor to follow either requirement without a determination from the Contracting Officer shall be at the Contractor's risk; should the Contracting Officer subsequently determine that the requirement not followed by the Contractor governs, the Contractor shall be responsible for all cost and time required to comply with the Contracting Officer's determination.
III.F. Submittals
(1) The Contractor shall prepare and submit to the Contracting Officer shop drawings, samples, calculations, product information, mockups, and other submittals (collectively, "submittals") demonstrating compliance with Contract requirements for all Work components as specified elsewhere in this Contract. If particular submittal requirements are not specified for a component of the Work, the Contractor shall prepare submittals for such Work as directed by the Contracting Officer.
(2) Prior to submission, the Contractor shall review all submittals for accuracy, completeness, compliance with Contract requirements, and coordination between different trades and subcontractors. The Contractor shall indicate its approval on all submittals as evidence of such review and coordination. Submittals submitted to the Contracting Officer without evidence of the Contractor’s approval may be rejected without further review.
(The Agreement)
(3) The Contractor shall not proceed with work or procure products or materials described or shown in submittals until the Contracting Officer has indicated approval of the submittal. If the Contracting Officer disapproves of a submittal, the Contractor shall be entitled to an explanation of the reasons for disapproval.
Any work or activity undertaken prior to approval shall be at the Contractor’s risk; should the Contracting Officer subsequently determine that the work or activity does not comply with the Contract, the Contractor shall be responsible for all cost and time required to comply with the Contracting Officer's determination. The Contracting Officer shall have the right to order the Contractor to cease execution of work for which submittals have not been approved. The Government shall not be liable for any cost or delay incurred by the Contractor attributable to the proper exercise of this right.
(4) Approval by the Contracting Officer of any submittal required under this Contract shall not relieve the Contractor from responsibility for any errors or omissions in such submittals, or from responsibility for complying with the requirements of this Contract, except with respect to variations described and approved as changes in accordance with the following Paragraph (5).
(5) The Contractor shall be entitled to rely upon approval of submittals containing variations from the requirements of the Contract as a change to the Contract only if the Contractor separately requests approval of the variation at the time of submission and the Contracting Officer has approved the request for variation. Such requests shall fully describe the substance of the variation reflected in the Contractor's submittal. This provision shall not be interpreted as limiting the right of the Government to treat non-conforming work as a change where the Contractor has failed to request a variation in accordance with this paragraph.
(6) The Contractor shall be entitled to receive notice of action on submittals within a reasonable time, given the volume or complexity of the submittals and the criticality of the affected activities to Substantial Completion. The Contractor shall not be entitled to receive notice of action on submittals containing variations from Contract requirements in less than twenty working days for all Work components as specified elsewhere in this Contract.
III.G. Government’s Right to Stop Work for Non-Compliance
If the Contractor, after receiving written notice from the Contracting Officer of non-compliance with any requirement of this Contract, fails to promptly initiate action to achieve compliance within a reasonable time, the Contracting Officer shall have the right to order the Contractor to stop work under the Contract until the Contractor has complied. The Contractor shall not be entitled to any extension of Contract time or payment for any costs incurred as a result of being ordered to stop work for such cause. Possession of this right by the Contracting Officer shall not relieve the Contractor of its obligation to comply with the Contract, regardless of whether this right is exercised.
III.H. Other Contracts
The Government may enter into other contracts to be performed at the Project site including, but not limited to, construction management services. The Contractor shall not impede site access for these other contractors and shall notify GSA immediately if the activities of other contractors interfere with performance of the Contract.
(The Agreement)
III.I. Use and Possession Prior to Substantial Completion
Upon notice by the Contracting Officer, the Government shall have the right to take possession of, use, or operate with Government employees or other contractors, any completed or partially completed part of the Work prior to Substantial Completion. Exercise by the Government of the right shall not relieve the Contractor of responsibility for completing any unfinished components of the Work.
III.J. Finality of Contract Modifications
As set forth elsewhere in this Contract, the Contractor is entitled to additional consideration under certain conditions, including the issuance of change orders. It is the Contractor's duty to include in proposals for equitable adjustment or other consideration all compensation to which it may be entitled, including cost and time. Unless otherwise explicitly stated in a modification to the Contract providing such consideration, adjustments to the Contract price or time agreed upon therein shall be deemed to provide all compensation to which the Contractor is entitled, and shall constitute final settlement of the Contractor's entitlement to compensation on account of the change or other condition giving rise to the modification.
III.K. Liquidated Damages
The Contractor acknowledges that time is of the essence for the performance of the Work, and that determining actual damages from delay would be extremely difficult and impractical. If the Contractor fails to achieve Substantial Completion of the Work in accordance with FAR 52.211-12, Liquidated Damages and GSAR 552.211-12, Liquidated Damages and the time specified in this Contract, the Contractor shall be liable to the Government for liquidated damages at the rate specified in Section I (Project Information), paragraph entitled, “Liquidated Damages Rate,” for each calendar day following the required completion date that the Work is not Substantially Complete. (CO Note: N/A if not applicable)
III.L. Insurance Requirements [CO Instruction: See FAR 28.306(b) and edit amounts if needed
(1) The Contractor shall obtain and maintain for the entire life of the Contract, in addition to any insurance required by law, the following minimum kinds and amounts of insurance required pursuant to FAR clause 52.228-5, Insurance – Work on a Government Installation, and GSAR 552.228-5, Government as Additional Insured.
(a) Workers' compensation insurance in the amount required by the jurisdiction in which the Contract is performed. The Contractor shall obtain Employers' liability coverage of at least $100,000.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .