This is a Request for Proposals (RFP) for the design and installation of a new drinking water well at the Naval Research Laboratory (NRL) Pomonkey Facility in La Plata, Maryland. The solicitation number is N0017326Q5801, issued on March 30, 2026, with proposals due by April 30, 2026 at 11:00 AM local time. The contract is a firm fixed-price award with a 365-calendar-day performance period beginning within 14 days of award.
The project requires a qualified, State of Maryland-licensed well driller to provide complete turn-key services including decommissioning the existing well per Maryland state regulations and drilling a new 4.5-inch diameter well to a depth of 500-900 feet capable of sustained yield of 10 gallons per minute for five consecutive days. Deliverables include a fully operational well with specified casing meeting ASTM standards, new pump (1.5 or 2 H.P.), two pressure tanks, electrical wiring, and all required documentation including permits, water quality certifications, and completion reports. The contractor must comply with all applicable federal, state, and local codes including OSHA, EPA, Maryland Department of Environment, AWWA standards, and EM 385-1-1 safety requirements. Key milestones include a kick-off meeting within two weeks of award, pre-construction meeting coordination, and project schedule submission within three weeks. The contract incorporates numerous FAR and DFARS clauses including requirements for labor standards compliance, buy American provisions, cybersecurity maturity model certification (no FCI/CUI), small business subcontracting, and waste management with a 15-day post-completion reporting requirement. Award will be made to the lowest-priced technically acceptable proposal, with evaluation based on technical capability and price reasonableness. The magnitude of the project is estimated between $100,000 and $250,000.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Solicitation Amendment N0017326Q58010001 SF 30.pdf | ||
| NRL PoMonkey Facility Water Distribution__Site Map.pdf | ||
| Solicitation Amendment - N0017326Q58010001.pdf | ||
| Well Completion Report.pdf | ||
| Attachment_QA.pdf | ||
| REQUIREMENTS FOR ON-SITE CONTRACTORS_NOV 2023.docx | DOCX document | |
| Wage Determination.txt | TXT text file |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(See ).
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair) IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR
INFORMATION CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".
SOLICITATION
1. SOLICITATION NUMBER
5. REQUISITION/PURCHASE REQUEST NUMBER
CODE
6. PROJECT NUMBER
8. ADDRESS OFFER TO
4. CONTRACT NUMBER
7. ISSUED BY
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)
11. The contractor shall begin performance within
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES", indicate within how many calendar days after award in Item 12b.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and
b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d. Offers providing less than
STANDARD FORM 1442 (REV. 12/2022)
Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
is, is not required.
local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.
calendar days and complete it within calendar days after receiving
a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
12b. CALENDAR DAYS
2. TYPE OF SOLICITATION
SEALED BID (IFB)
INVITATION FOR BID
NEGOTIATED (RFP)
REQUEST FOR PROPOSAL
3. DATE ISSUED PAGE OF PAGES
AWARD (To be completed by Government)
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
OFFER (Must be fully completed by offeror)
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT
NUMBER
DATE
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)
CODE FACILITY CODE
15. TELEPHONE NUMBER (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14.)
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)
21. ITEMS ACCEPTED:
22. AMOUNT
26. ADMINISTERED BY
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)
31c. DATE
STANDARD FORM 1442 (REV. 12/2022) BACK
31b. UNITED STATES OF AMERICA
BY
31a. NAME OF CONTRACTING OFFICER (Type or print)
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30b. SIGNATURE 30c. DATE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
copies to issuing office.) Contractor agrees to furnish
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
23. ACCOUNTING AND APPROPRIATION DATA
ITEM
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES
CODE AT
27. PAYMENT WILL BE MADE BY
10 U.S.C. 3204(a) ( ) 41 U.S.C. 3304(a) ( )
20b. SIGNATURE 20c. OFFER DATE
Section A - Solicitation/Contract Form
New Well Installation - NRL POMONKEY
N0017326Q5801
Section B - Supplies or Services & Prices or Costs
Additional Information/Notes
Item Supplies/Service Quantity Unit Unit Price Amount
New Drinking Water Well - Pomonkey
(See Statement of Work "New Well Installation at NRL POMONKEY Facility)
Pricing Arrangement: Firm Fixed Price
1 Project
Section C - Description/Specifications/Statement of Work
SUBJECT TITLE: New Well Installation at NRL POMONKEY Facility
PW: 6707
NRL SITE POMONKEY Site, Maryland BLDG: Base wide
The statement of work is described below and is comprised of the following sections and attachments:
A. Introduction/Background B. General Contract Information C. Technical Criteria D. Project Point of Contact E. Service F. Waste Management G. Environment Management System Information H. Warranty I. Attachments
Offerors are expected to understand the general and local conditions that may affect the cost of the performance of work. All work executed under this task order shall provide a complete and usable system or facility. The Contractor will be working in and around an existing occupied Facility. The Contractor, sub-Contractor and their employees are required to present identification to gain access into the Facility in accordance with the current regulation, instructions and guidelines. The Contractor, sub-Contractors and their employees will not be allowed in the work area without prior approval of the Contracting Officer. Care shall be taken to prevent damage to the Facility features and equipment and to protect those features not involved in the contract.
Damage to or disfigurement of any components as a result of the execution of this task order shall be rectified by the Contractor to the satisfaction of the Contracting Officer and at no additional cost to the Government.
A. INTRODUCTION/ BACKGROUND:
The NRL Pomonkey Facility (NRL Code 8124) has a requirement of a qualified contractor to drill one new water well (bore hole) for a primary, potable water supply at the NRL Pomonkey Facility. The project site is located at 7425 Bumpy Oak Road, La Plata, MD.
The contractor will, in accordance with the terms and conditions set forth below, furnish all supervision, labor management, facilities, supplies, equipment and materials, and all required services necessary for the turn-key performance of the work. Well construction must be provided by a State of Maryland licensed well driller.
Provide service consisting of the following task:B. GENERAL CONTRACT INFORMATION:
a) Task: Provide all necessary labor, equipment, parts and supplies to:
Demolition / Decommission:
Decommission old well as required by Maryland state regulations, to include filling of old well with dry bentonite and properly cap or seals as per local state requirements. Prepare Water Well Abandonment-Sealing Report (electronic form found at New Well Abandonment form.pdf (maryland.gov)). The completed report must be signed by a licensed master well driller or supervising sanitarian.
Remove existing pump, pressure tanks, associated pipe connection and any device related to the existing well operation. Properly dispose any material.
Remove electrical connection back to point of connection.
Existing well cannot be demolished and disconnected from the water distribution system until the new well is ready to be connected to the existing water distribution.
New Work:
Well Location:
The well must be protected from the pollution of non-sanitary surroundings and should be located within 50 feet of the existing well (Well # CH-88-1739, water appropriation permit number CH1991G005(03)).
All required permits and certifications must be valid and exist before and during all work performed to construct the well. This includes a permit to drill a well under the COMAR 26.04.04
Pump Specifications:
The contractor shall provide a pump with footing and a protective screen sized to prevent the introduction of sand or silt into the suction line per American Water Works Association (AWWA) standards. It shall be capable of pumping water with 1 1/4 inch pipe, a minimum of 20 feet above the well head ground surface at any point on the Facility, while meeting volume of 10 gallons/min water flow with a 1 1/2 H.P.
pump. If static water pressure is too deep, a 2 H.P. pump is to be used. The electric cable shall be made for underwater use, as long as needed per IEC 502 code.
Pressure Tank Specifications:
The contractor shall provide two pressure tanks and all associated piping and fittings to appropriately match the pump and well specifications.
Well Specification:
The well depth is expected to be between 500 - 900 feet, depending on water volume, with a 4 1/2 inch diameter casing pipe, with a commercial pump screen material of Type 304 stainless steel.
Obtain all required licenses/permits to proceed with installation. Application for new well can be found at New Well Application Form.pdf (maryland.gov).
Drill a 4 1/2" well to a depth that tests show adequate yield of 10 gallons/min.
Development of drilling via rotary drilled. Complete drilling to estimated depth of usable groundwater and estimate safe yield for well prior to completion. Develop well to maximum yield per foot of drawdown.
Fill annular space from top to bottom with concrete grout and provide permanent casing with temporary well cap. Top of casing should be approximately 12" above ground level finished grade.
Purchase, install and connect new water well pipe to two new, contractor furnished pressure tanks.
Purchase adequate proposed pump capable of providing 10 gallons per minute. Install purchased pump and test for plumb and alignment per AWWA A100.
Purchase and install new pump electrical wire and connect to existing electrical panel. New pump electrical wire must be furnished by the contractor that meets the specifications of the manufacturer of the pump. Failure in correctly sizing the diameter of wire conductor will result in re-work at contractor's expense. Per National Electric Code (NEC) a properly sized ground wire should be part of the wire bundle leading from the pump in the well to the controller.
Conduct final pumping tests after well has been constructed, cleaned, and tested for plumb and alignment.
The pump must meet volume per day requirements for 5 sustained days. Contractor will be responsible for providing all flow meters necessary to provide well yield. After pump is installed, the water well shall be fully tested for compliance. The cost of this capacity test shall be included in the cost of this work.
Contractor will submit a completion report to the Approving Authority (Charles County Health Department). Completion Report can be found at New Well Completion Report.pdf (maryland.gov).
(https://mde.maryland.gov/programs/Water/BayRestorationFund/OnsiteDisposalSystems/Documents /New Well Completion Report.pdf) Perform lab tests to indicate that the water is safe for human consumption and obtain a Certificate of Potability (COP). Refer to this site (MDE Water Well Construction) for additional information on COP.
(https://mde.maryland.gov/programs/Water/BayRestorationFund/OnsiteDisposalSystems/Pages /WellConstruction.aspx#Contact%20Info Clean work site area after completion of the work each day.
Restore work site to pre-construction conditions.
Monitor any discrepancies and corrective action.
Deliverables:
Fully operational Well Water Well (Bore hole) with specified casing 4 1/2 inch inside diameter meeting ASTM standards for wall thickness to a depth that can meet a water demand of 10 gallons/min for 5 consecutive days.
New water pump, pressure tanks, piping and required fittings, electrical wiring and required fittings to connect to the Facility's existing main water supply piping and existing electrical panel.
All required documentation, including permits warranties and certifications needed.
b) Kick-Off Meeting: Coordinate virtual meeting within 2 week of contract award, at this meeting the government will provide additional documentation for construction activities.
c) Pre-Construction Meeting: No demo or construction activity can start prior the pre- construction meeting, Coordinate Meeting based on project execution schedule
d) Schedule: Provide project schedule within 3 weeks of contract award
e) Design/Shop drawing Submittal: *See Section L
f) RFI's/Submittals: *See Section L
g) Controlled Unclassified Information (CUI): (Not Applicable): When noted in the Task order that project data is classified as CUI "Controlled Unclassified Information", contractor shall handle, storage, reproduce and disposal of documents in accordance with 32 CFR Part 2002 and applicable agency policy.
h) Cost Proposal: Provide detailed cost break down, any exclusion has to be properly noted in the cost proposal.
C. TECHNICAL CRITERIA:
Contractor shall comply with all Federal, State and local codes and regulations which include but are not limited to the latest:
Unified Facility Criteria (UFC) and associate reference Environmental Protection Agency (EPA) Maryland Department of Environment (MDE) Insulated Cable Engineers Association (ICEA) Underwriter's Laboratories, Inc. (UL)
ASTM
ASHRAE
American Water Works Association (AWWA) National Fire Protection Association Standards (NFPA) American National Standards Institute (ANSI) National Electrical Manufacturers Association (NEMA) Illumination Engineering Society of North America (IESNA) National Electrical Installation Standards (NEIS) National Electrical Code (NEC) International, national, state, and municipal construction codes as adopted, unless the Contract Documents specify a different code is to be used.
EM 385-1-1 is a compliance document for this contract Operations involving the use of a crane will require a crane lift plan from the contractor for review and approval from Code 3523.
Accident Prevention Plan (APP) shall be in accordance with (IAW) Army Corp of Engineers EM-385 Latest Revision.
All work performed in accordance with the above specifications shall be in strict compliance with Occupational Safety and Health Administration (OSHA) regulation 29 CFR 1926. Particular attention is directed to "Safety Related Work Practice" 1926.416 and "lock and Tagging of Circuits," 1926.417
The Contractor shall comply with all Federal, State and Local safety and environmental regulations which include, but not limited to, OSHA standards, Environmental Protection Agency regulations and US Army Corps of Engineers EM 385-1-1 (USACE). The Government will accept no responsibility (neither legal nor financial) for any work or actions executed by the Contractor. The Contractor is responsible for coordinating this effort with the Contracting Officer.
The Contractor shall provide and Activity Hazard Analysis (AHA) for each definable feature of work. All AHA's shall be turned in with the project schedule submittal. The contractor is not permitted to start work until the AHA's are approved by the Contracting Officer's representative.
The Government points of contact for this project are as noted belowD. PROJECT POINT OF CONTACT:
a) Naval Research Laboratory, (NRL) Purchasing Agent, Code 1331 Yina Brooks Phone: 202-923-1546 Email: yina.brooks.cvi@us.navy.mil
b) Naval Research Laboratory, (NRL) Contract Officer, Code 133 Callan Walsh Phone: (484) 844-2641 Email: callan.t.walsh.mil@us.navy.mil
c) Naval Research Laboratory, (NRL) Construction Manager (CM), Code 3531 (Construction Manager and Contract Officer Representative, "COR")
(TBD)
d) Naval Research Laboratory, (NRL) Engineer in Charge (EIC), Code 3531
(TBD)
E. SERVICE:
a) Responsibility:
Contractor is responsible to provide the service outlined in this statement of work, which includes: decommissioning/demolishing of the original well and drilling/installing a new well. Contractor shall notify the contracting officer and NRL EIC/CM in writing once all the equipment, material and tools are available and ready to be installed in accordance with this contract.
The contractor shall provide and maintain work environments and procedures, which will:
Safeguard the public and Government personnel, property, materials, supplies, and equipment exposed to Contractor operations.
Avoid interruptions of Government operations and delays in project completion dates.
Control costs in the performance of this contract.
Contractor shall comply with all pertinent provisions of NRL Safety Requirements.
Contractor shall provide a working operational system free from defects before project turn over to the government.
b) Base Access/Contractor Badge:
For bid site visit: Contractor will coordinate site visit with NRL EIC.
c) Available Data:
Pertinent data in Naval Research Laboratory will be made available via the Engineering Branch when appropriate. Additional requirements may apply. Any data provided is for reference only.
Contractor is responsible to obtain accurate information not limited to: exact locations, existing dimensions, existing field conditions, existing above or below ground utilities, any temporary metering, any required testing, soil boring etc.
*Soil boring material will be safely stored in corresponding approved storage, properly closed and labeled, Provide in Label Project Name, PW #, Contractor Name, NRL EIC. Contractor shall notify NRL Environmental Code 3536 of location of the containers and the date that will be pick-up and removed from site.
NRL Environmental Code 3536 Contacts:
(TBD)
d) Field Investigations/Surveys/Site Visit:
Any field investigation/Site visit has to be coordinate via the NRL project EIC. Such request has to be made NLT 7 days prior the requested site visit.
Additional documentation will be required to fill and submitted directly to the visitor center office.
e) Photos:
Required pictures will be taken by the NRL EIC and will follow the NRL security screening process prior release. Contractor are not allow to take pictures.
f) Interruption of Utilities:
Contractor shall not interrupt any utility without written request for an outage request.
g) Permits:
Contractor is responsible to acquire all required local/State permits before any construction start.
h) Laydown Area:
Laydowns areas will be coordinated via Construction Manager, Reginald Hughley (reginald.a.hughley.civ@us.navy.mil)
i) Traffic Pattern:
If traffic pattern has to be temporary change, due to construction activities. Such plan has to be submitted to NRL Facility Service Desk Code 3523 for review and approval. Contractor is responsible to provide all the necessary traffic, detour and pedestrian signs for the time of the re-route.
j) Mean of Egress:
If constructions activities affect escape route, access to doors and stairs. Contactor is responsible to provide alternate route during construction activity and provide temporary signs. Any alternate plan has to be submitted for approval
k) Unexpected Field Conditions:
If during construction activities unexpected field conditions were noted that can affect the statement of work of this contract, contractor is responsible to notify in writing the contracting officer and NRL EIC for review and resolution.
l) Personnel Training:
Provide information available from the manufacture that is needed for use in training designated personnel to properly operate and maintain, and repair of components. Coordinate onsite training with NRL EIC
m) Stop of Work:
Only the contracting officer can issue a stop of work of this contract. Any presented issue on the field has to be referred to the NRL EIC for proper action
n) O & M Submittals:
Provide a copy of Operations and Maintenance Data
o) Material, Tools and Personnel:
As required under this contract, the contractor shall provide all the materials, tools, and equipment for proper installation and connection of the well, well pump, pressure tank, piping, piping fittings, electrical wiring, and electrical wiring fittings.
Contractor shall use a State of Maryland licensed well driller and comply with any additional licensing requirements of Charles County, the State of Maryland, and federal regulations for potable well drilling.
Licensed master well driller shall be covered by a performance bond and contractor's liability insurance as required by COMAR 26.05.02.05.
The contractor shall designate a point of contact or supervisor with phone numbers to contact during the period of performance
p) Final Inspection:
Contractor shall coordinate with NRL EIC for a final walkthrough, if any deficiency noted will be recorded on a push list for record and be distributed to the Contracting officer and the NRL EIC. Contractor would have 30 days to make any corrections for re-inspection.
F. WASTE MANAGEMENT:
The contractor shall ensure, to the maximum extent possible, that any waste generated by this project is reused or recycled. Waste, such as (but not limited to) metals, concrete, gypsum products, paper, cardboard, wood products, brick, plastics, mechanical products and equipment, and electrical products and equipment shall be diverted from landfills and incinerators through reusing or recycling. The Contractor is permitted to retain any funds from the sale of recycled or reused materials. The Contractor shall clean-up, remove and dispose of all concrete and work related debris off NRL property.
In the cases of lead-based paint and other hazardous waste generated by the demolition, the hazardous materials shall be inspected, and all associated paperwork and manifests shall be signed by the NRL Hazardous Waste Manager prior to leaving the construction site.
All construction debris and recyclable materials, in terms of amounts and pricing, shall be accounted and reported to NRL Environment.
NRL Hazardous Waste Manager
(TBD)
The contractor shall submit, within 15 days of completion of this project, all records indicating the disposition of waste generated by this project.
Records shall indicate weight, method, and location of the disposition of the waste. The Contractor shall comply with all applicable Federal, State, and local environmental laws and regulations. Final payment will not be made until records have been submitted to and approved by the COR - Reginald Hughley (reginald.a.hughley.civ@us.navy.mil)
G. ENVIROMENTAL MANAGEMENT SYSTEM INFORMATION:
The Contractor shall be aware that the Naval Research Laboratory has implemented an Environmental Management System (EMS) as directed by Executive Order 13423 Strengthening Federal Environmental, Energy and Transportation Management. EMS policy requires a reduction in hazardous waste disposal through alternate recycling and reclamation efforts. The Contractor shall be aware that the work activities related to this contract can cause real or potential significant environmental impact; thus, the Contractor shall competently perform all duties and responsibilities with a commitment to EMS policy. Pollution Prevention and Right - to - Know Information shall be observed during the duration of this contract
ENVIROMENTAL PROTECTION:
The Contractor shall comply with all applicable federal, state, and local laws, and with the regulations and standards as requested by the Contracting Officer or the COR. All environmental protection matters shall be coordinated with the Contracting Officer or the COR.
The Contractor shall promptly report and clean up any spills which result from the Contractor's operations.
The Contractor shall comply with the instructions of the local health department with respect to avoidance of conditions which create a nuisance or which may be hazardous to the health of military or civilian personnel.
In the event a regulatory agency assesses a monetary fine against the Government for violations resulting from the Contractor's conduct, the Contractor shall reimburse the Government for that fine and all other direct and indirect costs attributable to the fine.
H. WARRANTY:
List and explain the various warranties and clearly identify the servicing and technical precautions prescribed by the manufacturers or contract documents in order to keep warranties in force. Include warranty information for primary components of the system.
List all warranties for products, equipment, components, and sub-components whose duration exceeds one year. For each warranty listed, indicate the applicable specification section, duration, start date, end date, and the point of contact for warranty fulfillment. Also, list or reference the specific operation and maintenance procedures that must be performed to keep the warranty valid.
Provide a list that includes the name, address, and telephone number of the General Contractor and each Subcontractor who installed the product or equipment, or system. For each item, also provide the name address and telephone number of the manufacturer's representative and service organization that can provide replacements most convenient to the project site. Provide the name, address, and telephone number of the product, equipment, and system manufacturers.
I. ATTACHMENTS:
The attachments listed below provide additional guidance and/or requirements for this scope of work.
a) none
Requirements Decommission/Demolition and New Well Installation - NRL POMONKEY
Section D - Packaging and Marking
Delivery and shipping:
Ensure that the purchase order number: (TBD) is included in all correspondence, invoices, and shipping labels/documents. Failure to include this information can delay receipt of the order and payment processing. Warehouse hours of operation: Monday to Friday 6:30am - 11:30am and 12:30pm
- 3:00pm. For shipping/delivery questions or concerns, contact the NRL Shipping Department at: NRL_Shipping@us.navy.mil. Please cc yina.brooks.
civ@us.navy.mil and the Division POC.
**For software licenses only**
Email all software license keys, and Software updates to the Division POC: Hard copy/documentations shall be sent in accordance with this purchase order.
Performance Site:
U.S. Naval Research Laboratory - POMONKEY 7425 Bumpy Oak Road La Plata, Maryland 20670
Payment Information (WAWF):
**Please refer to WAWF POC and additional instructions in the purchase order**
Section E - Inspection and Acceptance
Overall Contract Inspection/Acceptance Locations
Inspection and Acceptance Location
Both Destination Instructions: Final Inspection: Contractor shall coordinate with NRL EIC for a final walkthrough, if any deficiency noted will be recorded on a push list for record and be distributed to the Contracting officer and the NRL EIC. Contract would have 30 days to make any corrections for re-inspection.
DoDAAC: N6695N CountryCode: USA
NAVAL RESEARCH LABORATORY
POMONKEY, 7425 BUMPY OAK ROAD
LA PLATA, MD 20646
UNITED STATES
(TBD), (TBD)
Email: (TBD)
Section F - Deliveries or Performance
Overall Contract Delivery Period
From date of lead time event to beginning of performance 14 Calendar Days Date of Award Receipt
From date of lead time event to completion of performance 365 Calendar Days Date of Award Receipt
Line Item Delivery Schedule Quantity Address and POC
Delivery After Delivery Date 01 May 2026
Period of Performance From 01 May 2026 To 30 Apr 2027
1 Project Place of Performance DoDAAC: N6695N CountryCode: USA
NAVAL RESEARCH LABORATORY
POMONKEY, 7425 BUMPY OAK ROAD
LA PLATA, MD 20646
UNITED STATES
(TBD), (TBD)
Email: (TBD)
Section G - Contract Administration Data
TYPE OF CONTRACT (52.216-1) (APR 1984)
The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.
DFARS Clauses Incorporated by Reference
Number Title Effective Date
Alternate/ Deviation
Variation Effective Date
252.201-7000 Contracting Officer's Representative. Dec 1991 252.232-7003 Electronic Submission of Payment Requests and Receiving Reports. Dec 2018 252.236-7000 Modification Proposals--Price Breakdown. Dec 1991
DFARS Clauses Incorporated by Full Text
252.232-7006 Wide Area WorkFlow Payment Instructions. (Jan 2023)
WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS (JAN 2023)
(a) As used in this clause- Definitions.
"Department of Defense Activity Address Code (DoDAAC)" is a six position code that uniquely identifies a unit, activity, or organization.
"Document type" means the type of payment request or receiving report available for creation in Wide Area WorkFlow (WAWF).
"Local processing office (LPO)" is the office responsible for payment certification when payment certification is done external to the entitlement system.
"Payment request" and "receiving report" are defined in the clause at 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.
(b) The WAWF system provides the method to electronically process vendor payment requests and receiving reports, as Electronic invoicing.
authorized by Defense Federal Acquisition Regulation Supplement (DFARS) 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.
(c) To access WAWF, the Contractor shall- WAWF access.
(1) Have a designated electronic business point of contact in the System for Award Management at https://www.sam.gov; and
(2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for self-registration available at this web site.
(d) The Contractor should follow the training instructions of the WAWF Web-Based Training Course and use the Practice WAWF training.
Training Site before submitting payment requests through WAWF. Both can be accessed by selecting the "Web Based Training" link on the WAWF home page at https://wawf.eb.mil/
(e) Document submissions may be via web entry, Electronic Data Interchange, or File Transfer WAWF methods of document submission.
Protocol.
(f) The Contractor shall use the following information when submitting payment requests and receiving reports in WAWF payment instructions.
WAWF for this contract or task or delivery order:
(1) The Contractor shall submit payment requests using the following document type(s): Document type.
(i) For cost-type line items, including labor-hour or time-and-materials, submit a cost voucher.
(ii) For fixed price line items-
(A) That require shipment of a deliverable, submit the invoice and receiving report specified by the Contracting Officer.
INVOICE
(B) For services that do not require shipment of a deliverable, submit either the Invoice 2in1, which meets the requirements for the invoice and receiving report, or the applicable invoice and receiving report, as specified by the Contracting Officer.
NOT APPLICABLE
(iii) For customary progress payments based on costs incurred, submit a progress payment request.
(iv) For performance based payments, submit a performance based payment request.
(v) For commercial financing, submit a commercial financing request.
(2) ) Fast Pay requests are only permitted when Federal Acquisition Regulation (FAR) 52.213-1 is included in the contract.
[Note: The Contractor may use a WAWF "combo" document type to create some combinations of invoice and receiving report in one step.]
(3) The Contractor shall use the information in the Routing Data Table below only to fill in applicable fields in WAWF Document routing.
when creating payment requests and receiving reports in the system.
Routing Data Table*
Field Name in WAWF Data to be entered in WAWF
Pay Official DoDAAC ____
Issue By DoDAAC ____
Admin DoDAAC ____
Inspect By DoDAAC ____
Ship To Code ____
Ship From Code ____
Mark For Code ____
Service Approver (DoDAAC) ____
Service Acceptor (DoDAAC) ____
Accept at Other DoDAAC ____
LPO DoDAAC ____
DCAA Auditor DoDAAC ____
Other DoDAAC(s) ____
(4) The Contractor shall ensure a payment request includes documentation appropriate to the type of payment request in Payment request.
accordance with the payment clause, contract financing clause, or Federal Acquisition Regulation 52.216-7, Allowable Cost and Payment, as applicable.
(5) The Contractor shall ensure a receiving report meets the requirements of DFARS Appendix F. Receiving report.
(g) WAWF point of contact.
(1) The Contractor may obtain clarification regarding invoicing in WAWF from the following contracting activity's WAWF point of contact.
(2) Contact the WAWF helpdesk at 866-618-5988, if assistance is needed.
(End of clause)
Section H - Special Contract Requirements
Section I - Contract Clauses Clauses listed by reference:
52.236-7 Permits and Responsibilities 252.203-7005 Representation Relating to Compensation of Former DoD Officials 252.204-7024 Notice on the Use of the Supplier Risk System 252.209-7021 Prohibition Relating to Conflicts of Interest in Consulting Services - Certification
FAR Clauses Incorporated by Reference
Number Title Effective Date
Alternate/ Deviation
Variation Effective Date
52.203-3 Gratuities. Apr 1984 52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements. Jan 2017 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards. (Deviation) Feb 2026 52.204-13 System for Award Management-Maintenance. (Deviation) Feb 2026 52.204-18 Commercial and Government Entity Code Maintenance. Aug 2020 52.204-19 Incorporation by Reference of Representations and Certifications. Dec 2014 52.204-21 Basic Safeguarding of Covered Contractor Information Systems. Nov 2021
52.209-6 Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, Proposed for Debarment, or Voluntarily Excluded. (Deviation)
Feb 2026
52.209-10 Prohibition on Contracting With Inverted Domestic Corporations. (Deviation) Feb 2026 52.212-4 Terms and Conditions-Commercial Products and Commercial Services. (Deviation) Feb 2026 52.219-6 Notice of Total Small Business Set-Aside. (Deviation) Feb 2026 52.219-33 Nonmanufacturer Rule. (Deviation) Feb 2026 52.222-3 Convict Labor. (Deviation) Feb 2026 52.222-6 Construction Wage Rate Requirements. (Deviation) Feb 2026 52.222-7 Withholding of Funds. (Deviation) Feb 2026 52.222-8 Payrolls and Basic Records. (Deviation) Feb 2026 52.222-9 Apprentices and Trainees. (Deviation) Feb 2026 52.222-10 Compliance with Copeland Act Requirements. (Deviation) Feb 2026 52.222-11 Subcontracts (Labor Standards). (Deviation) Feb 2026 52.222-12 Contract Termination-Debarment. May 2014 52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations. May 2014 52.222-14 Disputes Concerning Labor Standards. (Deviation) Feb 2026 52.222-15 Certification of Eligibility. May 2014 52.222-19 Child Labor-Cooperation with Authorities and Remedies. (Deviation) Feb 2026 52.222-36 Equal Opportunity for Workers with Disabilities. (Deviation) Feb 2026 52.222-41 Service Contract Labor Standards. (Deviation) Feb 2026 52.222-50 Combating Trafficking in Persons. (Deviation) Feb 2026 52.222-55 Minimum Wages for Contractor Workers Under Executive Order 14026. (Deviation) Feb 2026 52.222-62 Paid Sick Leave Under Executive Order 13706. (Deviation) Feb 2026 52.223-23 Sustainable Products. (Deviation) Feb 2026 52.225-1 Buy American-Supplies (Deviation) Feb 2026 52.226-8 Encouraging Contractor Policies to Ban Text Messaging While Driving. May 2024 52.232-1 Payments. Apr 1984 52.232-8 Discounts for Prompt Payment. Feb 2002 52.232-11 Extras. Apr 1984 52.232-23 Assignment of Claims. May 2014 52.232-27 Prompt Payment for Construction Contracts. Jan 2017 52.232-33 Payment by Electronic Funds Transfer-System for Award Management. Oct 2018 52.233-3 Protest after Award. (Deviation) Feb 2026 52.233-4 Applicable Law for Breach of Contract Claim. (Deviation) Feb 2026 52.236-2 Differing Site Conditions. (Deviation) Feb 2026 52.236-3 Site Investigation and Conditions Affecting the Work. (Deviation) Feb 2026 52.236-5 Material and Workmanship. (Deviation) Feb 2026 52.236-6 Superintendence by the Contractor. (Deviation) Feb 2026 52.236-8 Other Contracts. (Deviation) Feb 2026
52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements.
(Deviation)
Feb 2026
52.236-10 Operations and Storage Areas. (Deviation) Feb 2026
52.236-11 Use and Possession Prior to Completion. (Deviation) Feb 2026 52.236-12 Cleaning Up. (Deviation) Feb 2026 52.236-13 Accident Prevention. (Deviation) Feb 2026 52.236-14 Availability and Use of Utility Services. (Deviation) Feb 2026 52.236-15 Schedules for Construction Contracts. (Deviation) Feb 2026 52.236-17 Layout of Work. (Deviation) Feb 2026 52.236-21 Specifications and Drawings for Construction. (Deviation) Feb 2026 52.240-91 Security Prohibitions and Exclusions. (Deviation) Feb 2026 52.244-6 Subcontracts for Commercial Products and Commercial Services. (Deviation) Feb 2026 52.249-1 Termination for Convenience of the Government (Fixed-Price) (Short Form). Apr 1984
DFARS Clauses Incorporated by Reference
Number Title Effective Date
Alternate/ Deviation
Variation Effective Date
252.203-7000 Requirements Relating to Compensation of Former DoD Officials. Sep 2011 252.203-7002 Requirement to Inform Employees of Whistleblower Rights. Dec 2022
252.204-7012 Safeguarding Covered Defense Information and Cyber Incident Reporting.
(DEVIATION 2024-O0013 REVISION 1)
May 2024 Deviation 2024-O0013 May 2024
252.204-7018 Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services.
Jan 2023
252.204-7020 NIST SP 800-171 DoD Assessment Requirements. Nov 2023 252.204-7022 Expediting Contract Closeout. May 2021 252.204-7023 Reporting Requirements for Contracted Services. Jul 2021 252.205-7000 Provision of Information to Cooperative Agreement Holders. Oct 2024 252.211-7008 Use of Government-Assigned Serial Numbers. Sep 2010 252.216-7010 Postaward Debriefings for Task Orders and Delivery Orders. Oct 2025 252.219-7003 Small Business Subcontracting Plan (DoD Contracts). Dec 2019 252.223-7008 Prohibition of Hexavalent Chromium. Jan 2023 252.225-7001 Buy American and Balance of Payments Program. Feb 2024 252.225-7012 Preference for Certain Domestic Commodities. Apr 2022 252.225-7021 Trade Agreements. Feb 2024 252.225-7036 Buy American-Free Trade Agreements--Balance of Payments Program. Feb 2024 252.225-7048 Export-Controlled Items. Jun 2013 252.225-7056 Prohibition Regarding Business Operations with the Maduro Regime. Jan 2023
252.225-7060 Prohibition on Certain Procurements from the Xinjiang Uyghur Autonomous Region.
Jun 2023
252.227-7015 Technical Data-Commercial Products and Commercial Services. Jan 2025 252.227-7037 Validation of Asserted Restrictions on Technical Data. Jan 2025 252.232-7010 Levies on Contract Payments. Dec 2006 252.237-7010 Prohibition on Interrogation of Detainees by Contractor Personnel. Jan 2023 252.243-7002 Requests for Equitable Adjustment. Dec 2022 252.244-7000 Subcontracts for Commercial Products or Commercial Services. Nov 2023 252.247-7023 Transportation of Supplies by Sea. Oct 2024 252.247-7028 Application for U.S. Government Shipping Documentation/ Instructions. Jun 2012
FAR Clauses Incorporated by Full Text
52.212-5 Contract Terms and Conditions Required to Implement Statutes or Executive Orders - Commercial Products and Commercial Services.
(DEVIATION 2025-O0003 and 2025-O0004)
(Mar 2025) Deviation 2025-O0004 (Mar 2025)
Contract Terms and Conditions Required To Implement Statutes or Executive Orders-Commercial Products and Commercial Services (MAR 2025) (DEVIATION 2025-O0003 and 2025-O0004)
(a) The Contractor shall comply with the following Federal Acquisition Regulation (FAR) clauses, which are incorporated in this contract by reference, to implement provisions of law or Executive orders applicable to acquisitions of commercial products and commercial services:
(1) 52.203-19, Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (section 743 of Division E, Title VII, (Jan 2017) of the Consolidated and Further Continuing Appropriations Act, 2015 (Pub. L. 113-235) and its successor provisions in subsequent appropriations acts (and as extended in continuing resolutions)).
(2) 52.204-23, Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab Covered Entities (Dec (Section 1634 of Pub. L. 115-91).2023)
(3) 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment. (Section 889(Nov 2021) (a)(1)(A) of Pub. L. 115-232).
(4) 52.209-10, Prohibition on Contracting with Inverted Domestic Corporations .(Nov 2015)
(5) 52.232-40, Providing Accelerated Payments to Small Business Subcontractors (31 U.S.C. 3903 and 10 U.S.C. 3801).(Mar 2023)
(6) 52.233-3, Protest After Award (31 U.S.C. 3553).(Aug 1996)
(7) 52.233-4, Applicable Law for Breach of Contract Claim (Public Laws 108-77 and 108-78 ( 19 U.S.C. 3805 note)).(Oct 2004)
(b) The Contractor shall comply with the FAR clauses in this paragraph (b) that the Contracting Officer has indicated as being incorporated in this contract by reference to implement provisions of law or Executive orders applicable to acquisitions of commercial products and commercial services:
[ .]Contracting Officer check as appropriate
[ ] 52.203-6, Restrictions on Subcontractor Sales to the Government with (41 U.S.C. 4704 and 10 U.S.C. 4655).(1) (Jun 2020), Alternate I (Nov 2021)
[ ] 52.203-13, Contractor Code of Business Ethics and Conduct (41 U.S.C. 3509)).(2) (Nov 2021)
[ ] 52.203-15, Whistleblower Protections under the American Recovery and Reinvestment Act of 2009 (Section 1553 of Pub. L. 111-(3) (Jun 2010) 5). (Applies to contracts funded by the American Recovery and Reinvestment Act of 2009.)
[ ] 52.203-17, Contractor Employee Whistleblower Rights (41 U.S.C. 4712); this clause does not apply to contracts of DoD, NASA, (4) (Nov 2023) the Coast Guard, or applicable elements of the intelligence community-see FAR 3.900(a).
[X] 52.204-10, Reporting Executive Compensation and First-Tier Subcontract Awards (Pub. L. 109-282) ( 31 U.S.C. 6101 note).(5) (Jun 2020)
[ ] [Reserved].(6)
[ ] 52.204-14, Service Contract Reporting Requirements (Pub. L. 111-117, section 743 of Div. C).(7) (Oct 2016)
[ ] 52.204-15, Service Contract Reporting Requirements for Indefinite-Delivery Contracts (Pub. L. 111-117, section 743 of Div. C).(8) (Oct 2016)
[X] 52.204-27, Prohibition on a ByteDance Covered Application (Section 102 of Division R of Pub. L. 117-328).(9) (Jun 2023)
[ ] 52.204-28, Federal Acquisition Supply Chain Security Act Orders-Federal Supply Schedules, Governmentwide Acquisition Contracts, and (10) Multi-Agency Contracts. (Pub. L. 115-390, title II).(Dec 2023)
[ ] (11)
(i) 52.204-30, Federal Acquisition Supply Chain Security Act Orders-Prohibition. (Pub. L. 115-390, title II).(Dec 2023)
[ ] Alternate I of 52.204-30.(ii) (Dec 2023)
[X] (12) 52.209-6, Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, Proposed for Debarment, or Voluntarily Excluded. ( 2025) (31 U.S.C. 6101 note).Jan
[ ] 52.209-9, Updates of Publicly Available Information Regarding Responsibility Matters (41 U.S.C. 2313).(13) (Oct 2018)
[ ] [Reserved].(14)
[ ] 52.219-3, Notice of HUBZone Set-Aside or Sole-Source Award ( ) (15 U.S.C. 657a).(15) Oct 2022
[ ] 52.219-4, Notice of Price Evaluation Preference for HUBZone Small Business Concerns ( ) (if the offeror elects to waive the (16) Oct 2022 preference, it shall so indicate in its offer) (15 U.S.C. 657a).
[ ] [Reserved](17)
[X] (18) (i) 52.219-6, Notice of Total Small Business Set-Aside (Nov 2020) (15 U.S.C. 644).
[ ] Alternate I of 52.219-6.(ii) (Mar 2020)
[ ] (19)
(i) 52.219-7, Notice of Partial Small Business Set-Aside (15 U.S.C. 644).(Nov 2020)
[ ] Alternate I of 52.219-7.(ii) (Mar 2020)
[ ] 52.219-8, Utilization of Small Business Concerns (15 U.S.C. 637(d)(2) and (3)).(20) ( )Jan 2025
[ ] (21)
(i) 52.219-9, Small Business Subcontracting Plan (15 U.S.C. 637(d)(4)).( )Jan 2025
[ ] Alternate I of 52.219-9.(ii) (Nov 2016)
[ ] Alternate II of 52.219-9.(iii) (Nov 2016)
[ ] Alternate III of 52.219-9.(iv) (Jun 2020)
[ ] Alternate IV of 52.219-9.(v) ( )Jan 2025
[ ] (22)
(i) 52.219-13, Notice of Set-Aside of Orders (15 U.S.C. 644(r)).(Mar 2020)
[ ] Alternate I of 52.219-13.(ii) (Mar 2020)
[ ] 52.219-14, Limitations on Subcontracting ( ) (15 U.S.C. 657s).(23) Oct 2022
[ ] 52.219-16, Liquidated Damages-Subcontracting Plan (15 U.S.C. 637(d)(4)(F)(i)).(24) (Sep 2021)
[ ] 52.219-27, Notice of Set-Aside for, or Sole-Source Award to, Service-Disabled Veteran-Owned Small Business (SDVOSB) Concerns Eligible (25) Under the SDVOSB Program ( ) (15 U.S.C. 657f).Feb 2024
[X] (26)
(i) 52.219-28, Small Business Program Rerepresentation (15 U.S.C. 632(a)(2)).Postaward ( )Jan 2025
[ ] Alternate I of 52.219-28.(ii) (Mar 2020)
[ ] 52.219-29, Notice of Set-Aside for, or Sole-Source Award to, Economically Disadvantaged Women-Owned Small Business Concerns ((27) Oct ) (15 U.S.C. 637(m)).2022
[ ] 52.219-30, Notice of Set-Aside for, or Sole-Source Award to, Women-Owned Small Business Concerns Eligible Under the Women-Owned (28) Small Business Program ( ) (15 U.S.C. 637(m)).Oct 2022
[ ] 52.219-32, Orders Issued Directly Under Small Business Reserves (15 U.S.C. 644(r)).(29) (Mar 2020)
[X] 52.219-33, Nonmanufacturer Rule (15 U.S.C. 637(a)(17)).(30) (Sep 2021)
[X] 52.222-3, Convict Labor (E.O.11755).(31) (Jun 2003)
[X] (32) 52.222-19, Child Labor-Cooperation with Authorities and Remedies (E.O. 13126).(Jan 2025)
[ ] [Reserved](33)
[ ] [Reserved](34)
[X] (35)
(i) 52.222-35, Equal Opportunity for Veterans (38 U.S.C. 4212).(Jun 2020)
[ ] Alternate I of 52.222-35.(ii) (Jul 2014)
[X] (36)
(i) 52.222-36, Equal Opportunity for Workers with Disabilities (29 U.S.C. 793).(Jun 2020)
[ ] Alternate I of 52.222-36.(ii) (Jul 2014)
[X] 52.222-37, Employment Reports on Veterans ( ) (38 U.S.C. 4212).(37) Jun 2020
[ ] 52.222-40, Notification of Employee Rights Under the National Labor Relations Act (E.O. 13496).(38) (Dec 2010)
[X] (39)
(i) 52.222-50, Combating Trafficking in Persons (22 U.S.C. chapter 78 and E.O. 13627).(Nov 2021)
[ ] Alternate I of 52.222-50 (22 U.S.C. chapter 78 and E.O. 13627).(ii) (Mar 2015)
[ ] (40) 52.222-54, Employment Eligibility Verification (Executive Order 12989). (Not applicable to the acquisition of commercially (Jan 2025) available off-the-shelf items or certain other types of commercial products or commercial services as prescribed in FAR 22.1803.)
[ ] (41)
(i) 52.223-9, Estimate of Percentage of Recovered Material Content for EPA-Designated Items (May 2008) ( 42 U.S.C. 6962(c)(3)(A)(ii)). (Not applicable to the acquisition of commercially available off-the-shelf items.)
[ ] Alternate I of 52.223-9 (42 U.S.C. 6962(i)(2)(C)). (Not applicable to the acquisition of commercially available off-the-shelf items.)(ii) (May 2008)
[ ] 52.223-11, Ozone-Depleting Substances and High Global Warming Potential Hydrofluorocarbons (42 U.S.C. 7671, ).(42) (May 2024) et seq.
[ ] 52.223-12, Maintenance, Service, Repair, or Disposal of Refrigeration Equipment and Air Conditioners (42 U.S.C. 7671, ).(43) (May 2024) et seq.
[ ] 52.223-20, Aerosols (42 U.S.C. 7671, ).(44) (May 2024) et seq.
[ ] 52.223-21, Foams (42 U.S.C. 7671, ).(45) (May 2024) et seq.
[ ] 52.223-23, Sustainable Products and Services (MAR 2025) (DEVIATION 2025-O0004)) (7 U.S.C. 8102, 42 U.S.C. 6962, 42 U.S.C. 8259b, (46) and 42 U.S.C. 7671l).
[ ] (47)
(i) 52.224-3 Privacy Training (5 U.S.C. 552 a).(Jan 2017)
[ ] Alternate I of 52.224-3.(ii) (Jan 2017)
[X] (48)
(i) 52.225-1, Buy American-Supplies (41 U.S.C. chapter 83).(Oct 2022)
[ ] Alternate I of 52.225-1.(ii) (Oct 2022)
[X] (49)
(i) 52.225-3, Buy American-Free Trade Agreements-Israeli Trade Act (19 U.S.C. 3301 note, 19 U.S.C. 2112 note, 19 U.S.C. 3805 note, (NOV 2023) 19 U.S.C. 4001 note, 19 U.S.C. chapter 29 (sections 4501-4732), Public Law 103-182, 108-77, 108-78, 108-286, 108-302, 109-53, 109-169, 109-283, 110-138, 112-41, 112-42, and 112-43.
[ ] Alternate I [Reserved].(ii)
[ ] Alternate II of 52.225-3.(iii) (Jan 2025)
[ ] Alternate III of 52.225-3.(iv) (Feb 2024)
[ ] Alternate IV (Oct 2022) of 52.225-3.(v)
[ ] 52.225-5, Trade Agreements (19 U.S.C. 2501, ., 19 U.S.C. 3301 note).(50) (NOV 2023) et seq
[X] 52.225-13, Restrictions on Certain Foreign Purchases (E.O.'s, proclamations, and statutes administered by the Office of Foreign (51) (Feb 2021) Assets Control of the Department of the Treasury).
[ ] 52.225-26, Contractors Performing Private Security Functions Outside the United States (Oct 2016) (Section 862, as amended, of the National (52) Defense Authorization Act for Fiscal Year 2008; 10 U.S.C. Subtitle A, Part V, Subpart G Note).
[ ] 52.226-4, Notice of Disaster or Emergency Area Set-Aside (Nov 2007) (42 U.S.C. 5150).(53)
[ ] 52.226-5, Restrictions on Subcontracting Outside Disaster or Emergency Area (42 U.S.C. 5150).(54) (Nov 2007)
[X] 52.226-8, Encouraging Contractor Policies to Ban Text Messaging While Driving (E.O. 13513).(55) (May 2024)
[ ] 52.229-12, Tax on Certain Foreign Procurements .(56) (Feb 2021)
[ ] 52.232-29, Terms for Financing of Purchases of Commercial Products and Commercial Services (41 U.S.C. 4505, 10 U.S.C. (57) (Nov 2021) 3805).
[ ] 52.232-30, Installment Payments for Commercial Products and Commercial Services (41 U.S.C. 4505, 10 U.S.C. 3805).(58) (Nov 2021)
[X] 52.232-33, Payment by Electronic Funds Transfer-System for Award Management (31 U.S.C. 3332).(59) (Oct2018)
[ ] 52.232-34, Payment by Electronic Funds Transfer-Other than System for Award Management (Jul 2013) (31 U.S.C. 3332).(60)
[ ] 52.232-36, Payment by Third Party (31 U.S.C. 3332).(61) (May 2014)
[ ] 52.239-1, Privacy or Security Safeguards (5 U.S.C. 552a).(62) (Aug 1996)
[ ] 52.240-1, Prohibition on Unmanned Aircraft Systems Manufactured or Assembled by American Security Drone Act-Covered Foreign Entities (63) (Sections 1821-1826, Pub. L. 118-31, 41 U.S.C. 3901 note prec.).(Nov 2024)
[ ] 52.242-5, Payments to Small Business Subcontractors (15 U.S.C. 637(d)(13)).(64) (Jan 2017)
[ ] (65)
(i) 52.247-64, Preference for Privately Owned U.S.-Flag Commercial Vessels (46 U.S.C. 55305 and 10 U.S.C. 2631).(Nov 2021)
[ ] Alternate I of 52.247-64.(ii) (Apr 2003)
[ ] Alternate II of 52.247-64.(iii) (Nov 2021)
(c) The Contractor shall comply…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .