Solicitation_Checklist_Summary.xlsx
XLSX spreadsheet 19 KB Posted
- Attached to
- Legacy Island Phase II
- Solicitation number
- ITB 26-029
- Issued by
- Lee County, Fort Lauderdale City, Florida
About this file
This document is a procurement checklist and workflow guide used by the City of Fort Myers, Florida, to manage Invitation to Bid (ITB) and Request for Proposal/Request for Qualifications (RFP/RSQ) solicitations, particularly those involving grant funding from sources such as the Florida Department of Transportation (FDOT). The checklist outlines the complete procurement process for the Legacy Island Phase II project, an ITB for construction of a five-slip docking facility, overwater observation pier, two 16' x 16' gazebos, and interpretive signage at Legacy Island Park in the Caloosahatchee River. The procurement requires submission of lump-sum bids across nine base bid line items and two alternate bid items through the OpenGov electronic portal by March 24, 2026, at 2:00 p.m. A non-mandatory pre-submittal meeting is scheduled for March 2, 2026, at 10:00 a.m., with contractor questions due by March 12, 2026. City Council approval is anticipated on April 6, 2026, and the contract term requires substantial completion within 180 calendar days and final completion within 210 calendar days after Notice to Proceed.
The checklist identifies multiple funding sources including FDOT Local Agency Program, FEMA Public Assistance, Florida Fish and Wildlife Conservation Commission Florida Boating Improvement Program (contributing $330,241.00 or 83.24 percent of the $396,756.00 total estimated project cost), HUD Community Development Block Grant-Disaster Recovery, and Hazard Mitigation Grant Program. The City provides a minimum cost share of $66,515.00 or 16.76 percent of total project costs. Contractors must submit a five percent bid bond, obtain FDOT prequalification if work exceeds $250,000, maintain $1,000,000 minimum insurance coverage, and comply with a 15 percent Minority Business Enterprise participation goal. Liquidated damages range from $904 to $1,685 per day depending on contract value, and the successful contractor must provide Performance and Payment Bonds equal to 100 percent of the contract price within ten days of award. The workflow includes multiple approval and coordination steps with grant sources, internal departments, the selection committee, and the Clerk's office prior to contract execution and posting under contract management in OpenGov.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ITB- incl Grants checklist
| Date completed | Title: |
| Intake request received | |
| Obtain grant and read entire Agreement | |
| Create solicitation in OpenGov | |
| Meet with Proj Mgr to discuss any questions/review contract | |
| Send for internal approvals (in OpenGov) | |
| *Procurement | |
| *Dept Manager | |
| *Dept Director | |
| *Legal | |
| * Grants Manager | |
| Email solicitation grant source for approval (have Thaddeus upload to GAP if FDOT) | |
| Receive concurrance from the grant source | |
| Finalize timeline | |
| Send calendar invites to committee and Project Manager for prebid, opening, selection committee | |
| * create Teams links for pre-submittal, opening,& selection committees | |
| Send email to Bernice Vono, Michele Ingresol, and Mary Hagemann annoucing public meetings (prebid, opening, Selection committee) | |
| Email newspaper ad to (ganlegpubnotice4@gannett.com) | |
| Pay for ad by calling in your P-Card | |
| Mark GL account on receipt (see intake) and send to Kim Beaber | |
| Set up solicitation to auto release on desired date/time | |
| Create Pre-Submittal paperwork | |
| * print out sign-in sheet | |
| *create agenda (H:/Procurement Solicitation Templates/Pre-Submittal Meeting) | |
| Conduct Pre-Submittal meeting | |
| *record meeting through Teams link (during the meeting) | |
| *save recording in file file | |
| *save and post sign-in sheet, agenda, & recording to bid file and OpenGov | |
| If site Visit, record, save in bid file and post to OpenGov as a Notice | |
| Answer Questions in OpenGov/send to Proj Mgr if you cannot answer | |
| Send Q&A to funding source for approval. ( Zoe.Giannopoulos@dot.state.fl.us) | |
| Record the Solicitation Opening via Teams and post to Notices in OpenGov | |
| Save submittals & recording in bid file | |
| Mark pass/fail for each response in OpenGov | |
| Save bid tabulation (after pass/fail selection) in bid file | |
| Post tabulation & recording under Notices in OpenGov | |
| Check SAM.gov and State Suspended Vendor list for each responsive proposal | |
| Send external email to project Manager and committee with bidtab and submittal link, asking for recommendation | |
| When recommendation is received… | |
| Create contract and send to grant source for approval (have thaddeus upload to GAP) | |
| Once concurrance is received from grant source, send to Contractor for signature | |
| Create a Notice of Intent in OpenGov / save NOI to bid file. | |
| Simutaneously, create an agenda item (green sheet) | |
| Once signed, attach to agenda item and print copy for the Clerk's office. | |
| * in upper right of cover, write the Peak # and meeting date | |
| * hand deliver to the Clerk's office | |
| Once executed, Clerk's office will send link & save executed contract by "Contract_exec" in bid file | |
| Send a copy of the executed contract to the grant source | |
| See "H:/FDOT/FDOT docs to upload to GAP" and send Thaddeus those docs to upload to GAP | |
| Send a copy of the contract to the Supplier and the Project Manager | |
| Post under Contract Management in OpenGov | |
| ITB COMPLETED |
ITB Checklist
&Z&F
RFP-RSQ Grants checklist
| Date completed | Title |
| Intake request received | |
| Obtain grant and read entire Agreement | |
| Create solicitation in OpenGov | |
| Meet with Proj Mgr to discuss any questions/review contract | |
| Send for internal approvals (in OpenGov) | |
| *Procurement | |
| *Dept Manager | |
| *Dept Director | |
| *Legal | |
| * Grants Manager | |
| Email solicitation grant source for approval (have Thaddeus upload to GAP if FDOT) | |
| Receive concurrance from the grant source | |
| Finalize timeline | |
| Before publishing, setup a meeting with the Selection Committee to review responsibilities, the scope, and send them "Evaluation Committee Requirements" to sign beore publishing. found in H:/Procurement Solicitation templates/selection committee templates (copy entire file to bid file) | |
| * add title and bid number to "Evaluation Committee Requirements" and attached to meeting invite | |
| * add any notes to "Pre-Selection committee agenda" and use at this meeting | |
| Send calendar invites to committee and Project Manager for prebid, opening, selection committee | |
| * create Teams links for pre-submittal, opening, & selection committees | |
| Send email to Bernice Vono, Michele Ingresol, and Mary Hagemann annoucing public meetings (prebid, opening, Selection committee) | |
| Email newspaper ad to (ganlegpubnotice4@gannett.com), if over $200k or grant funded | |
| Pay for ad by calling in your P-Card | |
| Mark GL account on receipt (see intake) and send to Kim Beaber | |
| Set up solicitation to auto release on desired date/time | |
| Create Pre-Submittal paperwork | |
| * print out sign-in sheet | |
| *create agenda (H:/Procurement Solicitation Templates/Pre-Submittal Meeting) | |
| Conduct Pre-Submittal meeting | |
| *record meeting through Teams link (during the meeting) | |
| *save recording in file file | |
| *save and post sign-in sheet, agenda, & recording to bid file and OpenGov | |
| If site Visit, record, save in bid file and post to OpenGov as a Notice | |
| Answer Questions in OpenGov/send to Proj Mgr if you cannot answer | |
| Send Q&A to funding source for approval. ( Zoe.Giannopoulos@dot.state.fl.us) | |
| OPENING: Record the Solicitation Opening via Teams and post to Notices in OpenGov | |
| Save submittals & recording in bid file | |
| Mark pass/fail for each response in OpenGov | |
| Save bid tabulation (after pass/fail selection) in bid file | |
| Post tabulation & recording under Notices in OpenGov | |
| Check SAM.gov and State Suspended Vendor list for each responsive proposal (See SAM.gov SOP under H:/Procurement Policy/SOPs/SAM.gov check) | |
| Set up evaluation in OpenGov (see intake for list of selection committee members) | |
| Broadcast Evaluation to committee members | |
| Send sharepoint link of downloaded submittals to committee members. Reminding them the when/where the selection committee in scheduled. | |
| Send external email to project Manager and committee with bidtab and submittal link | |
| Selection committee Prep: copy documents from H:/Procurement Solicitation Documents/Selection committee templates to bid file | |
| * Modify "Agenda script" for the meeting and print for meeting | |
| * Modify "Sign-In Sheet" and print for meeting | |
| Selection Committee: record the meeting through a teams link | |
| * discuss Pros and cons | |
| * reveal scoring / make recommendation to Council (at least 3) | |
| create an agenda (greens sheet) giving approval to negotiate | |
| Procurement staff will be included, record all negotiation meetings, & save recording in bid file | |
| Create contract and send to grant source for approval (have thaddeus upload to GAP, if FDOT) | |
| Once concurrance is received from grant source, send to Contractor for signature | |
| Create a Notice of Intent in OpenGov / save NOI to bid file. | |
| Simutaneously, create an agenda item (green sheet) | |
| Once signed, attach to agenda item and print copy for the Clerk's office. | |
| * in upper right of cover, write the Peak # and meeting date | |
| * hand deliver to the Clerk's office | |
| Once executed, Clerk's office will send link & save executed contract by "Contract_exec" in bid file | |
| Send a copy of the executed contract to the grant source | |
| If FDOT, See "H:/FDOT/FDOT docs to upload to GAP" and send Thaddeus those docs to upload to GAP | |
| Send a copy of the contract to the Supplier and the Project Manager | |
| Post under Contract Management in OpenGov | |
| RFP-RSQ COMPLETED |
RFP/RSQ Checklist
&Z&F
File details come from the government source that posted it. Updated .