Solicitation 70Z03025QCLEV0067 - Statement of Work.pdf
PDF 722 KB Posted
- Attached to
- 70Z03025QCLEV0067 - U. S. Coast Guard Station St. Ignace Family Housing Painting Project
- Solicitation number
- 70Z03025QCLEV0067
About this file
This Statement of Work (SOW) details a painting project for the U.S. Coast Guard housing units in St. Ignace, Michigan. The project involves interior painting of five residential properties located on Keightley Street, ranging from 3-4 bedrooms and approximately 1,801-1,905 square feet each. Contractors are required to perform comprehensive surface preparation, including repairing wall damages, removing hardware, applying primer and paint (Sherwin Williams PrepRite ProBlock & ProMar 200 in Extra White), and reinstalling accessories. The scope includes thorough cleaning, sanding, caulking, and careful painting of walls, ceilings, and trim with specific requirements for coverage and finish.
The project will be executed on a varied timeline between January and October, with units becoming available sequentially. Contractors must complete work within five working days of unit availability, commencing within five days of notification. Key requirements include using specified painting materials, following EPA waste disposal regulations, conducting a pre-work walkthrough to document existing conditions, and coordinating all communications through the designated Point of Contact (DC1 Onalee Rohl). The solicitation is estimated to be under $25,000, classified under NAICS code 238320 for Painting and Wall Covering Contractors, with a small business size standard of $19.0 million.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Solicitation 70Z03025QCLEV0067 - SF 1442.pdf | ||
| Wage Determinations - Mackinac County MI.txt | TXT text file | |
| Solicitation 70Z03025QCLEV0067.docx | DOCX document | |
| Reference Information Sheet.pdf | ||
| Request for Information (RFI).pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Department of Homeland Security
United States Coast Guard
Base Cleveland Housing Division
Scope of Work (SOW)
Housing Site
Coast Guard Housing
Saint Ignace, MI
For
Interior Prep, prime, and paint
Point of Contact (POC)
DC1 Onalee Rohl
(906) 440-0946
Onalee.m.rohl@uscg.mil
Site Address
220 Keightley Street, St. Ignace, MI 49781
286 Keightley Street, St. Ignace, MI 49781
210 Keightley Street, St. Ignace, MI 49781
274 Keightley Street, St. Ignace, MI 49781
278 Keightley Street, St. Ignace, MI 49781
Solicitation 70Z03025QCLEV0067 USCG Station St. Ignace Housing Painting Project
Scope of Work
1.1 The contractor is to prepare all surfaces to protect from paint spatter, drips, or accidental contact with the brush or roller, by the use of drop cloths, masking tape or other appropriate means.
1.2 Remove any interference, (i.e., electrical cover plates, window cranks, window treatments, towel bars, stair handrails, light covers, smoke detectors, etc.). Stoves and refrigerators should be moved out far enough to facilitate painting behind them, but should remain hooked up to power, water, and gas connections.
1.3 All surfaces to be painted shall be properly prepared, (i.e., cleaned, sanded, feathered, puttied, primed, etc.) as necessary. Surface preparations will include the repair of damage to walls and ceilings, (i.e., splits, cracks, nail holes, chips, indentations, and holes less than eight inches in diameter). Damage greater than two inches in size shall be repaired by means of wall board plug with backer, taped and mudded, filled, sanded, and smooth; all other damaged areas will be repaired with wall mud as needed. All surfaces shall be free of dirt, grease, loose debris, and any other foreign matter that would adversely affect the appearance.
1.4 Where caulking is required, such as the kitchen/bathroom counters, trim work, and wall to ceiling joints, should be accomplished along with all other preparation work. Caulk will be furnished by the contractor and will be white in color and made of siliconized latex.
1.5 Contractor shall notify the POC listed upon completion of all preparation work before applying paint. After the POC has inspected and accepted the preparation work, paint may be applied.
1.6 A primer coat will be required on walls with different finishes or color change before any finish paint can be applied. Example: homes that have a semi-gloss finish will need a primer coat before applying an eggshell paint finish. The old color scheme was tan / beige walls with white trim, the new colors are Extra White without pigment all around.
1.7 Contractor shall paint all previously painted surfaces which include, but not limited to, walls, ceilings, and the trim around doors, windows, stairways, and baseboard heater covers with a minimum of two coat of paint for any area that has a paint color change and one coat for any area where the paint being applied matches existing color of the walls.
Paint shall be applied carefully with clean rollers and brushes to produce a complete and even coverage with a smooth finish, free of runs and other defects. Window sashes should be removed and/or positioned to ensure no contact with the window frames until the paint is cured.
1.8 Spraying paint to surfaces is not allowed except for baseboard heat covers and trim pieces, this is not to be performed within the home.
1.9 After painting is completed, the POC needs to be notified to inspect and approve job completion is satisfactory prior to any items being reinstalled.
1.10 The contractor shall ensure that each home painted is left in a clean and orderly condition. All hardware, electrical, and plumbing accessories, to include items listed in
1.2, shall be reinstalled.
1.11 The contractor shall dispose of all waste materials properly and IAW EPA regulations at the contractor’s expense.
1.12 Approximate unit sizes are as listed:
• 220 Keightley Street, St. Ignace, MI -3BR, 2.5 bath 1,801 sq. ft. home, est. 2,300 sq.
ft. of walls and ceilings. Laundry room included.
• 286 Keightley Street, St. Ignace, MI -4BR, 2.5 bath 1,905 sq. ft. home, est. 2,400
sq. ft. of walls and ceilings. Laundry room included.
• 210 Keightley Street, St. Ignace, MI -4BR, 2.5 bath 1,905 sq. ft. home, est. 2,400
• 274 Keightley Street, St. Ignace, MI -4BR, 2.5 bath 1,905 sq. ft. home, est. 2,400
• 278 Keightley Street, St. Ignace, MI -4BR, 2.5 bath 1,905 sq. ft. home, est. 2,400
1.14 All units will become available on a VARIED TIMELINE roughly between the months of January to October; all units WILL NOT be available at the same time for work to be performed and contractor cannot wait until all units are available before starting work.
There are currently 2 units available for immediate work. All contractors work in the unit must commence within five days of notice from the units to the contractor. Each unit must be completed within a one-week (five working days) timeframe from the start date of that unit. If possible, the POC will give the contractor a 30-day notice prior to the availability date.
1.15 5.2 A site visit is highly encouraged to provide valuable insight into homes.
Allowing the assessment of needs and condition of each unit to ensure quality and precise work. To schedule a site visit prior to commencing work and to accurately quote work needed, please contact the POC listed.
CG Personnel to complete
2.1 Moving the stove and refrigerator back into its normal operating position.
Material/ Part Information
3.1 All paint and tools shall be supplied by the Contractor. (Paint and Primer is Sherwin
Williams brand: PrepRite ProBlock & ProMar 200 – Egg Shell finish for majority of the home and Semi-gloss or similar if above product is discontinued for bathrooms, utility rooms and kitchens. All Full Paint areas are transitioning to the color Extra White without pigment added.)
References
4.1 All work is to be completed shall comply with Federal, State and Local Laws, Codes and
Regulations.
4.2 Manufactures’ requirements and recommendations shall be followed for all products used.
Liabilities
5.1 The contractor will be financially responsible for damages incurred while working on
Government property. There will be a pre-work walkthrough with each contractor at each job site prior to the contract start and contractor must identify any damages in their work area that are pre-existing, or along their access route to their work area. (Doorways, Doors, Walls, Jambs, Flooring, etc.) Contractor must identify the pre-existing damage to the Local Housing Representative in writing and provide a copy of the signed document by both the contractor and the local housing representative dated for the start date of the work performed in said unit or they can be held liable for the damages.
Coordination
6.1 All communications will go through the Local POC listed. No work can be modified or changed without their permission.
6.2 Work to be completed should have minimal impact on the unit’s operation. In the event any of the utilities need to be secured, these items should be well planned out.
6.3 Normal work hours for the unit is 8:00 AM to 4:00 PM, Monday-Friday, excluding all
Federal Holidays. Any work outside these times needs to be worked out ahead of time with any change in cost being highlighted upfront and confirmation by contracting officer will have to be approved as an amendment to the contract.
6.4 All required License, Certificates, Accreditation Card, etc. will be submitted with the quote or bid. There is also a minimum of two references being requested for submission with these documents.
Project Completion
7.1 All work completed must meet the local POC’s standard and be in accordance with this
SOW. The site is to be at a minimum as clean of a condition it was found in. All trash, debris, materials removed, etc. should be properly disposed of by the contractor.
7.2 All units will become available on a VARIED TIMELINE roughly between the months of January to October; units WILL NOT be available at the same time for work to be performed and contractor cannot wait until all units are available before starting work.
There are currently 3 units available for immediate work. All contractors work in the unit must commence within five days of notice from the units POC to the contractor of the unit’s availability. All work must be completed within a one-week (five working days) timeframe from the start date of that unit. If at all possible, the POC will give the contractor a 30-day notice prior to the availability date.