Solicitation 70Z03025QCLEV0038 - SOW.pdf
PDF 155 KB Posted
- Solicitation number
- 70Z03025QCLEV0038
About this file
This Statement of Work details fuel farm repair requirements for the U.S. Coast Guard Station Erie. The scope includes replacing an existing GASBOY model #9153atw2l fuel dispenser with a new dual-sided unit for gasoline and diesel fuel, replacing hose reels with 125-foot hoses and nozzle gallon counters, repairing cement cracks in the containment area, replacing a 2-inch ball valve for rainwater drainage, and installing an emergency stop outside the building. The work requires a one-year material and labor warranty.
The contractor must coordinate with Station Erie's Engineering Petty Officer to work between 7am-4pm with minimal impact on operations. Basic utilities (electricity, water, bathrooms) will be provided on-site. The contractor is responsible for work site safety, including providing PPE and safety barriers, and must comply with all federal, state and local safety regulations. The base is located at 1 Coast Guard Rd, Erie, PA 16505, with designated parking available for work crews. The COR will review deliverables, with contractors having 30 business days to correct any rejected work.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Solicitation 70Z03025QCLEV0038 - SF 1442.pdf | ||
| Reference Information Sheet.pdf | ||
| Request for Information (RFI).pdf | ||
| Solicitation 70Z03025QCLEV0038 - RFQ.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work
FUEL FARM REPAIR
COAST GUARD STATION ERIE
TABLE OF CONTENTS
1.0 GENERAL
Replace Fuel dispenser and hose reels.
2.0 SCOPE OF WORK
1. Replace existing fuel dispenser with new equivalent shall have two sides one for gasoline and one for diesel fuel, shall include replaceable fuel filters. Current dispenser is
GASBOY model# 9153atw2l serial number 490519.
2. Replace both hoses and hose reels with new equivalent to include 125 feet of hose, nozzles and a gallon counter at the nozzle.
3. Repair all cracks in cement located containment area to ensure it is watertight
4. Replace 2in ball valve used to drain rainwater.
5. Install emergency stop outside the building near the dispenser.
6. Provide A one-year material and labor warranty commencing on the date of substantial completion.
3.0 BACKGROUND
The units fuel farm continually malfunctions due to old age and faulty components. Currently the gasoline switch is broken and continuously malfunctions. Sector EM’s installed temporary switch inside the building to turn it on however fueling evolutions take 4 personnel to complete because of a cation tag stating I member remains at each breaker and switch while fueling in case of emergency. Also, the gasoline side hose is cracked so cannot be used and is tagged out.
During the fall and spring months there are no commercial fuel docks open, and the Station relies on the fuel farm for all operations.
4.0 COORDINATION
1. COORDINATION
2. INTERFERENCE WITH COAST GUARD OPERATIONS: Accomplish work in a manner that causes minimal impact on normal operations. Notify the Contracting
Officer’s Technical Representative prior to beginning construction. Arrange work hours
7am to 4pm directly with Station Erie’s Engineering Petty Officer, John Piskura at
(814)838-2098. Work will not affect the Stations normal operations
5.0 TEMPORARY UTILITIES
1. TEMPORARY UTILITIES
2. GENERAL: Most utilities will be provided on site. (Electricity, Water and Bathroom facilities). Any other service necessary to complete the project has to be provided by the contractor.
1.0 SAFETY PROGRAM
1.1 SAFETY PROGRAM
5.2 GENERAL: The Contractor is wholly responsible for work site safety. The Contractor shall implement a safety program that protects the lives and health of personnel in the construction area, prevents damage to property, and avoids work interruptions. The contractor shall provide and necessary PPE for workers and station personnel in the area.
The Contractor shall provide appropriate safety barricades, signs, signal lights, etc. (see
SECTION 01570) as well as complying with the requirements of all applicable Federal, State and Local safety laws, rules and regulations.
2. COMPLIANCE: The Contractor is specifically required to comply with the requirements of the U. S. Army Corps of Engineers "Safety and Health Requirements Manual" (EM
385-1-1, latest version available) and the “Accident Prevention” clause (FAR 52.236-13).
Once accepted, this safety plan shall become part of the contract requirements. Note:
This review/acceptance does not in any way relinquish the Contractor from responsibility for work site safety nor the obligation to comply with the OSHA regulations found in 29
CFR 1910 & 1926 or any other State or Local safety law, rule or regulation applicable to the contract work. The Coast Guard will fully cooperate with the Department of Labor
(Occupational Safety and Health Administration) in their enforcement of OSHA regulations.
6.0 CONTRACTOR PERSONNEL
It is the responsibility of the contractor to propose qualified contractor personnel to perform all requirements specified in the SOW.
6.1 QUALIFIED PERSONNEL
The Contractor shall provide qualified personnel to perform all requirements specified in this
SOW.
6.2 CONTINUITY OF SUPPORT
The Contractor shall ensure that the contractually required level of support for this requirement is maintained at all times. The Contractor shall ensure that all contract support personnel are present for all hours of the workday. If for any reason the Contractor staffing levels are not maintained due to vacation, leave, appointments, etc., and replacement personnel will not be provided, the Contractor shall provide e-mail notification to the Contracting Officer’s
Representative (COR) prior to employee absence. Otherwise, the Contractor shall provide a fully qualified replacement.
6.3 EMPLOYEE CONDUCT
Contractor’s employees shall comply with all applicable Government regulations, policies and procedures (e.g., fire, safety, sanitation, environmental protection, security, “off limits” areas, wearing of parts of DHS uniforms, and possession of weapons) when visiting or working at
Government facilities. The Contractor shall ensure Contractor employees present a professional appearance at all times and that their conduct shall not reflect discredit on the United States or the Department of Homeland Security. The Project Manager shall ensure Contractor employees understand and abide by Department of Homeland Security established rules, regulations and policies concerning safety and security.
6.4 REMOVING EMPLOYEES FOR MISCONDUCT OR SECURITY REASONS
The Government may, at its sole discretion (via the Contracting Officer*), direct the Contractor to remove any Contractor employee from DHS facilities for misconduct or security reasons.
Removal does not relieve the Contractor of the responsibility to continue providing the services required under the contract. The Contracting Officer will provide the Contractor with a written explanation to support any request to remove an employee.
7.0 ACCESS ROADS AND PARKING
1. ACCESS ROADS AND PARKING
2. ACCESS: The base is located at the end of Presque Isle State Park 1 Coast Guard Rd.
Erie, PA 16505.
3. PARKING: is available and will be designated for the work crew.
8.0 GOVERNMENT ACCEPTANCE PERIOD
The COR will review deliverables prior to acceptance and provide the contractor with an e-mail that provides documented reasons for non-acceptance. If the deliverable is acceptable, the COR will send an e-mail to the Contractor notifying it that the deliverable has been accepted.
8.1 The COR will have the right to reject or require correction of any deficiencies found in the deliverables that are contrary to the information contained in the Contractor’s accepted proposal. In the event of a rejected deliverable, the Contractor will be notified in writing by the COR of the specific reasons for rejection. The Contractor may have an opportunity to correct the rejected deliverable and return it per delivery instructions.
8.2 The Contractor shall have 30 business days to make corrections and redeliver.