Solicitation 70Z03024QCLEV0112 - Statement of Work.pdf

PDF 152 KB Posted

Attached to
70Z03024QCLEV0112 - USCG SECTOR NORTHERN GREAT LAKES HOUSING FLOORING REPLACEMENT PROJECT
Solicitation number
70Z03024QCLEV0112
Issued by

About this file

This document is a Statement of Work (SOW) for a carpet replacement project at three housing units of the US Coast Guard Sector Northern Great Lakes. The SOW outlines the scope of work, which includes removing existing carpet and padding, repairing the subfloor, and installing new stain-resistant padding and carpet per the specified manufacturer and styles. The project has an estimated total square footage of 4,061 across the three units. All materials will be supplied by the contractor, who will be financially responsible for any damages. The work is to be completed during normal business hours with minimal impact on the units' operations. The carpet installation for one unit must be completed by August 2, 2024, while the remaining units will be scheduled as housing becomes available, with a one-week window provided to the contractor. This project is associated with the federal contract opportunity 70Z03024QCLEV0112 for the USCG Sector Northern Great Lakes Housing Flooring Replacement Project, which is estimated to be less than $25,000 and falls under the NAICS code 238330 for Flooring Contractors.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Author: DC2 Ian R. Spaulding July 20, 2024

Department of Homeland Security

United States Coast Guard

Base Cleveland Housing Division

Scope of Work (SOW) Housing Site

Sault Sainte Marie, MI

For

Carpet Replacement

Point of Contact (POC)

DC2 Ian Spaulding

(920) 664-4708 or

DCC Coyet Carter (OHMC)

(443) 760-5034

Site Address

2563 Seminole Drive, Sault Sainte Marie MI 49783-1279. (2 Bedroom, 2 Story)

2658 Tahoma Way, Sault Sainte Marie MI 49783-1275. (2 Bedroom, 2 Story)

2543 Seminole Drive, Sault Sainte Marie MI 49783-1279. (3 Bedroom, 2 Story)

Scope of Work

Carpet Area

1.1 The contractor is to remove all carpet on stairs and on the First and second floor along with the padding to be replaced and dispose of all materials off the USCG property at the contractor expense to an approved disposal site.

1.2 The contractor will repair or replace any damaged or loose tack strips as needed;

inspect and repair the subfloor for any loose staples, screws, nails, etc.; identify and report any water, pet staining or odors, or any other abnormal damages that may cause further damage or odors to the USCG POC before continuing work.

1.3 All flooring will need to be cleaned of all loose debris, swept and/or vacuumed, before installing any new materials.

1.4 Install any needed rubber shims to level the carpet with any other flooring in use and install transitions to areas connecting to different flooring materials.

1.5 Install stain resistant padding and carpet following the manufacturer’s recommendations.

1.6 Carpet installation on stairs is to be tucked.

1.7 Carpeting Measurements:

1.7.1 2563 Seminole Drive – 1124 sq. ft./124 sq. yd.

1.7.2 2658 Tahoma Way – 1422 sq. ft./158 sq. yd.

1.7.3 2543 Seminole Drive – 1515 sq. ft./168 sq. yd.

Material/ Part Information

2.1 All materials will be supplied by the contractor.

2.2 8# 3/8” Spill guard padding is to be used.

2.3 Shaw Franchisee II 26 in the River Rock is to be used.

2.4 All rubber shims used will be Johnsonite LS-40-E (D or E according to thickness required).

2.5 All transitions and other exposed materials planned for use will have to be approved by the POC listed for quality and color. 25LR transition to be used.

2.6 Approximate square footage is listed below per unit per install area; contractor is to measure for accuracy and may do so prior to submitting a bid, padding, and carpeting measurements are to include stairs:

References

3.1 All work is to be completed shall comply with Federal, State and Local Laws, Codes and Regulations.

Liabilities

4.1 The contractor will be financially responsible for any and all damages incurred while working on Government property.

Coordination

5.1 All communications will go through the POC listed. No work can be modified or changed without their permission.

5.2 Work to be completed should have minimal impact on the unit’s operation. In the event any of the utilities need to be secured, these items should be well planned out.

5.3 Normal work hours for the unit is 8:00 AM to 4:00 PM, Monday-Friday, excluding all Federal Holidays. Any work outside these times needs to be worked out ahead of time.

5.4 All required License, Certificates, Accreditation Card, etc. will be submitted with the quote or bid.

Project Completion

6.1 All work completed is up to the POC’s approval. The site is to be at a minimum as clean of a condition it was found in. All trash, debris, materials removed, etc.

should be properly disposed by the contractor. There will be no on-site storage available for the duration of this project.

6.2 The Carpet installation for housing unit 2543 Seminole Drive is scheduled for completion no later than August 02, 2024. Upon delivery of materials work will commence immediately to insure completion of this unit

6.3 This contract will be awarded for multiple addresses, all with different start schedules; these will not run consecutively but as available units become vacant. The contractor will be given a one-week window to schedule and complete each job. The Coast Guard POC will attempt to provide a 30-day notice prior to the availability timeline as they have the ability to do so.