This Invitation to Bid (ITB) is issued by the City of Milton, Florida, for the construction of the 2026.15 Effluent Discharge System Downtown Plant Pump Station project. The solicitation requests sealed bids from qualified and properly licensed contractors to furnish all labor, materials, equipment, supervision, and services necessary to complete the project. The scope of work involves constructing an effluent discharge system and associated pump station infrastructure at the downtown plant facility. Sealed bids must be submitted by the deadline specified in the solicitation documents, with evaluation and award to follow upon completion of the bid review process. Prospective bidders are encouraged to attend a pre-bid meeting or conduct site visits to familiarize themselves with project conditions and requirements prior to submission.
The solicitation requires bidders to provide detailed pricing proposals covering all costs associated with labor, materials, equipment, and project administration necessary for successful completion of the effluent discharge system construction. Contractors must demonstrate proper licensure and qualifications appropriate to the scope of work. Funding for this municipal infrastructure project is provided through the City of Milton's capital improvement budget or related water utility revenues. Award will be made to the lowest responsive and responsible bidder meeting all technical and administrative requirements established in the ITB documents.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
INVITATION TO BID (ITB)
CITY OF MILTON
MILTON, FL
BID NO 2016.15
2026.15 Effluent Discharge System
Downtown Plant Pump Station
Publish Date: Pre-Bid Conference:
11/05/2026 11/19/2026 9:00 AM (CST)
Question Due by: Answers Posted by:
12/03/2026 at 2:00 PM (CST) 12/10/2026
Submittal Deadline: Where to Deliver Bid:
12/17/2026 by 2:00 PM (CST) Milton City Hall
6738 Dixon Street
Milton, FL 32570
City of Milton
Purchasing Department
(850) 983-5400 mwilliams@miltonfl.org mailto:mwilliams@miltonfl.org
ITB No.: 2026.15
Contents
ADVERTISEMENT FOR BIDS
Section I – Authority
Section 2 - Definitions
Section 3 – General Information
3.1 Solicitation Overview
3.2 Issuing Office
3.3 Administrative Details and Dates
3.4 Addenda
3.5 Bid Validity
3.6 Communications Restrictions
3.7 Form of Agreement
3.8 No Negotiation
Section 4 – Scope of Work
4.1 Scope of Work
4.2 Work Included
4.3 Plans and Specifications
4.4 Permits and Regulatory Compliance
4.5 Safety and Worksite Conditions
4.6 Standards of Performance
4.7 Supervision
4.8 Work Hours
4.9 Protection of Property and Coordination
4.10 Unauthorized Work
Section 5 – Compensation and Pricing
5.1 Contract Price
5.2 Bid Quantities
Section 6 – Minimum Qualifications
6.1 Minimum Requirements
Section 7 – Special Requirements
7.1 Business Tax Receipts
7.2 Insurance
7.3 Minimum Insurance Coverages and Limits
7.4 Federal Funding and Federal Requirements
7.5 Bid Bond
7.6 Bid Bond Return and Validity
7.7 Performance and Payment Bonds
7.8 Public Records
7.9 Local Vendor Preference
Section 8 – Evaluation and Basis of Award
8.1 Evaluation
8.2 Responsiveness
8.3 Responsibility
8.4 Clarifications
8.5 Rejection of Bids
8.6 Tie Bids
Section 9 – Award Process and Contract
9.1 Notice of Intended Award
9.2 Protest Procedures
9.3 Notice of Award
9.4 Contract Execution and Bond Submission
9.5 Failure to Execute or Provide Required Bonds
9.6 Notice to Proceed
9.7 Contract Term
9.8 Contract Time
Section 10 – Bid Submittal Requirements
10.1 Bid Submittal Deadline
10.2 Bid Submittal Location
10.3 Public Bid Opening
10.4 Required Bid Contents
10.5 Addendum Acknowledgement
10.6 Withdrawal or Modification
10.7 Required Envelope Markings
10.8 Responsibility for Delivery
Section 11 – Instructions to Bidder
11.1 General
11.2 Official Posting Platforms
11.3 Proposal Forms
11.4 Signature Requirements
11.5 Addenda
11.6 Examination of Solicitation Documents and Site
11.7 Pre-Bid Conference
11.8 Pre-Bid Questions and Interpretations
11.9 Bid Quantities (If Unit Price Contract)
11.10 Compliance with Applicable Laws
11.11 Mathematical Errors
11.12 Word vs. Figure Discrepancy
11.13 Americans with Disabilities Act (ADA)
11.14 Reservation of Rights
APPENDIX A
BIDDER SITE EXAM CERTIFICATION
BIDDER CERTIFICATION AND ADDENDA ACKNOWLEDGEMENT
APPENDIX B
SUBCONTRACTOR LIST
Major Subcontractors
Certification
Affidavit of Compliance with Human Trafficking Laws
CERTIFICATION REGARDING NONDISCRIMINATION
CONFLICT-OF-INTEREST CERTIFICATION
1. Vendor Information
2. Acknowledgement
3. Conflict Disclosure
4. Ongoing Duty to Disclose
5. Certification
DRUG-FREE WORKPLACE CERTIFICATION
E-VERIFY COMPLIANCE CERTIFICATION
NON-COLLUSION AFFIDAVIT
PROMPT PAYMENT COMPLIANCE CERTIFICATION
PUBLIC ENTITY CRIMES AFFIDAVIT
SCRUTINIZED COMPANIES CERTIFICATION
APPENDIX C
APPENDIX D
ADVERTISEMENT FOR BIDS
2026.15 Effluent Discharge System
Downtown Plant Pump Station
SECTION I – AUTHORITY
The City of Milton ("City") issues this Invitation to Bid ("ITB") as a competitive sealed bid pursuant to § 255.20, F.S.; Article VIII, § 2(b), Fla. Const.; Chapter 166, F.S., including § 166.021, F.S.; the City of Milton Purchasing Policy 9.0, as amended; and, because the Project is funded in whole or in part with federal financial assistance, the procurement standards at 2 C.F.R. §§ 200.318–200.327, including the sealed-bid requirements of 2 C.F.R. § 200.320(b)(1), and the terms of the Federal Award identified in § 7.3. Where federal, state, and City requirements differ, the most restrictive requirement applies.
This ITB solicits sealed bids from qualified and properly licensed contractors to furnish all labor, materials, equipment, supervision, and services necessary to complete the Work described in the Contract Documents (the “Work”).
The Work constitutes public construction subject to the bidding thresholds and the payment and performance bond requirements of §255.05, F.S.
Bidders shall hold all licenses required under Chapter 489, F.S., in the appropriate classification at the time of bid submission and shall maintain such licensure throughout the term of the Contract.
Award, if made, shall be a firm-fixed-price contract awarded in writing to the lowest responsive and responsible Bidder in accordance with 2 C.F.R. §
200.320(b)(1)(ii)(D), § 255.20, F.S., and the City's Purchasing Policy. The City reserves the right to reject any or all Bids and to waive minor irregularities that do not affect price, competition, or substantive rights. The City will document and justify each Bid it rejects, as required by 2 C.F.R. § 200.320(b)(1)(ii)(E).
SECTION 2 - DEFINITIONS
For purposes of this Invitation to Bid and the resulting Contract, the following terms shall have the meanings set forth below:
2.1 “ITB” or “Solicitation” means this Invitation to Bid and all addenda issued by the City prior to Bid opening.
2.2 “Addendum” means a written clarification, modification, or revision to the
ITB issued by the City prior to Bid opening.
2.3 “Bid” means the written offer submitted by a Bidder in response to this ITB to perform the Work described in the Contract Documents for the price(s) stated therein.
2.4 “Bidder” means a firm, partnership, corporation, or other legal entity properly licensed under Chapter 489, F.S., that submits a Bid in response to the
ITB and is legally authorized to perform public construction in the State of
Florida.
2.5 “Base Bid” means the Bidder’s stated lump sum or unit price amount for performing the Work described in the ITB exclusive of any Add Alternates.
2.6 “Add Alternate” or “Alternative Bid Item” means a separately identified portion of the Work described in the ITB for which the Bidder provides a separate price, to be added to or deducted from the Base Bid at the City’s sole discretion in determining award.
2.7 “Responsive Bid” means a Bid that conforms in all material respects to the requirements of this ITB and the Contract Documents, including submission of all required forms, pricing, acknowledgments, bonds, certifications, and other required documentation, without material deviation, reservation, or irregularity.
2.8 “Responsible Bidder” means a Bidder who has the capability, integrity, financial capacity, experience, equipment, and personnel necessary to fully perform the Contract requirements and to assure good faith performance.
2.9 “Bid Bond” means the security submitted with a Bid to guarantee that the
Bidder will enter into the Contract and furnish required Performance and
Payment Bonds if awarded.
2.10 “Performance and Payment Bonds” means the bonds required under
§255.05, F.S., to secure faithful performance of the Contract and payment to subcontractors and suppliers.
2.11 “Notice of Award” means the written notice issued by the City informing the successful Bidder that it has been selected for award of the Contract.
2.12 “Agreement” or “Contract” means the written agreement executed between the City and the successful Bidder, including all Contract Documents incorporated therein.
2.13 “City” means the City of Milton, Florida.
2.14 “Contractor” means the Bidder to whom the Contract is awarded and who executes the Agreement with the City.
2.15 “Work” means all labor, materials, equipment, supervision, services, and other items necessary to construct and complete the Project in accordance with the Contract Documents.
2.16 “Contract Documents” means the documents identified in Article IV, § 4.1 of the Form of Agreement, subject to the limited incorporation provisions of
Article IV, § 4.2.
2.17 “Contract Time” means the number of calendar days stated in the
Contract Documents within which the Work must achieve Substantial
Completion and Final Completion.
2.18 “Notice to Proceed” means the written authorization issued by the City directing the Contractor to commence the Work and establishing the
Contract Time.
2.19 “Substantial Completion” means the stage in the progress of the Work when the Work, or a designated portion thereof, is sufficiently complete in accordance with the Contract Documents so that the City can occupy or utilize the Work for its intended purpose.
2.20 “Final Completion” means the point at which the Work has been fully completed in accordance with the Contract Documents, all punch list items have been corrected, all required closeout documentation has been submitted and accepted, and the City has issued written final acceptance.
2.21 “Liquidated Damages” means the predetermined amount stated in the
Contract Documents that the Contractor shall pay to the City for each
Calendar Day the Work remains incomplete beyond the time required for
Substantial Completion or Final Completion, as applicable, representing the parties’ reasonable estimate of damages that would be difficult to ascertain at the time of contracting.
2.22 “Unit Price” means the price stated in the Bid for a single unit of Work, including all labor, materials, equipment, overhead, and profit necessary to complete that unit of Work as specified.
2.23 “Lump Sum” means a single fixed price stated in the Bid for completion of a defined portion of the Work, regardless of the actual quantities required, except as adjusted by Change Order.
2.24 “Change Order” means a written amendment to the Contract executed by the City and the Contractor authorizing a change in the Work, Contract
Price, Contract Time, or any combination thereof.
2.25 “Field Order” means a written order issued by the City or Engineer that clarifies or interprets the Contract Documents or orders minor changes in the
Work that do not change the Contract Price or Contract Time.
2.26 “Subcontractor” means an individual or entity having a direct contract with the Contractor to perform a portion of the Work at the Project site.
2.27 “Engineer” means the professional engineer or engineering firm identified in the Contract Documents that prepared the plans and specifications for the
Project and may provide technical review, inspections, or recommendations regarding the Work. The Engineer is not the Contract Administrator and does not have authority to modify the Contract unless expressly authorized in writing by the City.
2.28 “Calendar Day” means every day shown on the calendar, including weekends and legal holidays.
2.29 “Business Day” means any day other than a Saturday, Sunday, or legal holiday observed by the City of Milton.
2.30 Capitalized terms not defined in this Section, including "Federal Award,"
"Federal Awarding Agency," "Federal Requirements," "Funding Agency," "Pass-
Through Entity," and "Wage Determination," have the meanings given in Article
I of the Form of Agreement.
SECTION 3 – GENERAL INFORMATION
3.1 SOLICITATION OVERVIEW
The City is soliciting sealed bids from qualified and properly licensed contractors to furnish all labor, materials, equipment, supervision, and services necessary to construct the project described in the Contract Documents (the “Project”).
The Project generally consists of:
THE DOWNTOWN PLANT PUMP STATION WILL CONSIST OF CONSTRUCTION OF A NEW CAST-IN-PLACE
CONCRETE WET WELL, INSTALLATION OF FOUR (4) PUMPS, PIPING, ELECTRICAL, GRAVITY PIPING AND
EFFLUENT MAIN INSTALLATION CONNECTING TO EXISTING EFFLUENT PIPELINE FOR A COMPLETE AND
OPERATIONAL QUADRAPLEX PUMP STATION AT THE EXISTING MILTON DOWNTOWN PLANT.
3.2 ISSUING OFFICE
This solicitation is issued by the City of Milton Purchasing Division.
All communications regarding this ITB shall be directed only to the designated
Procurement Contact identified below in §3.3.
3.3 ADMINISTRATIVE DETAILS AND DATES
Bid No.: 2026.15
Bid Title: 2026.15 ITB Effluent Discharge System
(Downtown Plant)
Date of Issuance: 11/05/2026
Project Description and Scope of Work: The Downtown Plant Pump Station will consist of construction of a new cast-in-place concrete wet well, installation of four
(4) pumps, piping, electrical, gravity piping and effluent main installation connecting to existing effluent pipeline for a complete and operational quadraplex pump station at the existing Milton Downtown Plant.
Project Location: Milton Downtown Plant Pump Station
Procurement Contact: Name: Michele Williams
Phone: (850) 983-5480
Email: mwilliams@miltonfl.org
Engineer: Donovan Hill Group
Pre-Bid Conference:
Pre-Bid Conference is Mandatory.
Date: 11/19/2026
Time: 10:00 am
Location: Milton City Hall
Reference: Instructions to Bidder: Section 11
(Pre-Bid Conference)
Questions Due By: 12/03/2026
Bid Submittal Deadline: 12/17/2026 by 2:00 PM
Site Visit:
Site Visit will be Mandatory.
Date: 11/19/2026
Time: Following the Pre-Bid Conference
Location: Milton Downtown Plant Station
If applicable, the site inspection form included herein must be signed and submitted with bids. Bids received from
Bidders not submitting the mandatory site inspection form will be considered non-responsive and will be rejected.
Reference: Instructions to Bidder: Section 11
(Examination of Solicitation Documents and
Site)
3.4 ADDENDA
All changes shall be issued by written addendum. Verbal statements are not binding. Bidders are responsible for acknowledging receipt of all addenda in the Bid Form.
mailto:mwilliams@miltonfl.org
3.5 BID VALIDITY
Bids shall remain valid for ninety (90) calendar days after bid opening, unless extended by mutual written agreement of the parties.
3.6 COMMUNICATIONS RESTRICTIONS
From the date of advertisement of this Solicitation until the City issues a Notice of
Award, or otherwise withdraws, all communications regarding this Solicitation shall be directed solely to the Procurement Contact identified in §3.3.
Violation of this provision may result in the Bid being deemed non-responsive or the Bidder being determined non-responsible, if the City determines that such contact has resulted in an unfair competitive advantage or otherwise compromised the integrity of the procurement process.
3.7 FORM OF AGREEMENT
Form of Agreement. The Construction Services Contract attached as Appendix
C, including Exhibits M through O, is the form of contract the City intends to execute with the successful Bidder. Its federal provisions are material terms of this
Solicitation, and Bidders shall price their Bids accordingly.
Reserved Modifications. Before execution, the City reserves the right to revise the
Form of Agreement to:
a. Complete blanks, exhibits, and project-specific information, including
Contract Price, Contract Times, liquidated damages, and the awarded
Bidder's information;
b. Incorporate any addenda issued under this ITB;
c. Incorporate Funding Agency requirements issued or changed after the Bid opening;
d. Conform to Applicable Laws, including changes in law taking effect before execution;
e. Incorporate requirements of the City Attorney, City Manager, or City Council as a condition of approval; and
f. Make non-material clarifications, corrections, and conforming changes.
No Material Change to Bid Basis. No revision under this Section shall materially change the scope of Work, the bid pricing, or the allocation of risk on which bids were submitted, except by mutual written agreement with the awarded Bidder or as required by law or by a funding agency.
Bidder's Acceptance. By submitting a bid, the Bidder agrees to execute a contract substantially in the form of the Form of Agreement, as revised under this
Section.
3.8 NO NEGOTIATION
This is a competitive sealed bid. Except as permitted by law, the City shall not negotiate price with the lowest responsive and responsible Bidder.
SECTION 4 – SCOPE OF WORK
4.1 SCOPE OF WORK
The Project will require a qualified and properly licensed contractor to furnish all labor, materials, equipment, supervision, and services necessary to construct the project described in the Contract Documents (the “Project”).
The Scope of Work generally consists of:
The Downtown Plant Pump Station will consist of construction of a new cast-in-place concrete wet well, installation of four (4) pumps, piping, electrical, gravity piping and effluent main installation connecting to existing effluent pipeline for a complete and operational quadraplex pump station at the existing Milton
Downtown Plant.
The complete plans and technical specifications are set forth in the Engineer’s
Plans and Technical Specifications.
4.2 WORK INCLUDED
The Contractor shall provide all labor, materials, equipment, tools, supervision, transportation, permits, testing, and incidentals necessary to fully complete the
Work in accordance with the Contract Documents, whether or not specifically enumerated, as required for a complete and operational project.
4.3 PLANS AND SPECIFICATIONS
The Work shall be performed in strict accordance with the plans, drawings, technical specifications, and other Contract Documents issued with this ITB, including any addenda. The complete plans and technical specifications are set forth in the Engineer’s Plans and Technical Specifications.
Where the Solicitation Documents identify a product by brand name, the reference establishes the minimum salient characteristics required and shall be read as "or approved equal." Equivalent products will be considered under the substitution provisions of the Form of Agreement.
In the event of a conflict among Contract Documents, the order of precedence set forth in the Agreement shall govern.
4.4 PERMITS AND REGULATORY COMPLIANCE
Unless otherwise expressly stated in the Contract Documents, the Contractor shall obtain and pay for all permits, inspections, and approvals required for the performance of the Work and shall comply with all applicable federal, state, and local laws, codes, ordinances, and regulations.
4.5 SAFETY AND WORKSITE CONDITIONS
The Contractor shall be solely responsible for initiating, maintaining, and supervising all safety precautions and programs in connection with the Work and shall comply with all applicable occupational safety and health requirements.
The Contractor shall maintain the Project site in a safe condition and take all necessary precautions to protect persons and property.
4.6 STANDARDS OF PERFORMANCE
All Work shall be performed in a good and workmanlike manner, consistent with industry standards and in accordance with the Contract Documents.
Materials and equipment incorporated into the Work shall be new and of suitable quality unless otherwise specified.
4.7 SUPERVISION
The Contractor shall designate a competent on-site superintendent authorized to act on behalf of the Contractor and shall maintain adequate supervision of the Work at all times during performance.
4.8 WORK HOURS
Work shall be performed during the hours of:
7:00am – 4:30pm
Work outside of permitted hours may require prior written approval from the City.
4.9 PROTECTION OF PROPERTY AND COORDINATION
The Contractor shall protect existing facilities, utilities, public and private property, and adjacent improvements from damage arising from the performance of the Work.
The Contractor shall coordinate the Work with the City, utility providers, and other contractors as necessary to ensure orderly and timely completion of the
Project.
4.10 UNAUTHORIZED WORK
The Contractor shall not perform any work beyond the scope of the Contract
Documents without prior written authorization from the City. The City shall not be responsible for payment for unauthorized work.
SECTION 5 – COMPENSATION AND PRICING
5.1 CONTRACT PRICE
a. Firm-Fixed-Price Contract. This Solicitation is issued as identified in the Bid
Form. Whether issued on a Lump Sum or Unit Price basis, the resulting
Contract will be a firm-fixed-price contract. The Lump Sum and each Unit
Price bid are fixed for the duration of the Contract, subject to adjustment only by Change Order executed in accordance with the Form of
Agreement.
b. Lump Sum. If issued on a Lump Sum basis, the Contract Price shall be the
Base Bid amount, plus any Add Alternates awarded under § 8.1, as adjusted by approved Change Orders.
c. Unit Price. If issued on a Unit Price basis, payment shall be based on the actual quantities of Work performed and accepted by the City at the Unit
Prices stated in the Bid Schedule. Estimated quantities are provided for bid evaluation only and are not guaranteed.
d. Add Alternates. Add Alternates awarded under § 8.1 shall be incorporated into the Contract Price at the prices stated in the Bid Form.
e. Allowances. Each allowance identified in the Bid Schedule is a fixed amount established by the City and included in the Bid total. The Bidder's overhead, profit, and other costs associated with allowance Work shall be included in its other Bid prices and not in the allowance. Allowance funds may be expended only upon the City's written authorization, based on documented cost of the authorized Work. Any unexpended allowance balance shall be deducted from the Contract Price by Change Order before Final Payment.
No allowance or Change Order shall be priced on a cost-plus-a-percentage-of-cost or percentage-of-construction-cost basis (2 C.F.R. § 200.324(d)).
5.2 BID QUANTITIES
Where the Bid includes estimated quantities for unit price items, such quantities are approximate and are provided solely for evaluation purposes. Actual quantities may increase or decrease as required for completion of the Work.
SECTION 6 – MINIMUM QUALIFICATIONS
6.1 MINIMUM REQUIREMENTS
☒ Shall Apply. ☐ Shall Not Apply.
To be considered for award, the Bidder must meet the following minimum qualifications at the time of Bid submission:
a. Legal Authorization
The Bidder must be legally authorized to conduct business in the State of
Florida, including registration with the Florida Department of State, Division of
Corporations, where required by Chapter 605, 607, or 620, F.S., no later than execution of the Contract. Failure to obtain such authorization within the time stated in the Notice of Award constitutes a failure to execute the Contract under § 9.5.
b. Licensure
The Bidder must hold a current and active contractor license issued pursuant to Chapter 489, Florida Statutes, in the classification required for the Work described in this ITB.
The license must be active and in good standing at the time of Bid submission and shall remain active throughout the duration of the Contract. The City reserves the right to verify licensure status.
c. Experience
The Bidder must have successfully completed, as prime contractor, at least three (3) projects of similar size, scope, and complexity within the past five (5) years. For purposes of this requirement, "similar" means projects involving construction of a wastewater effluent disposal system with a contract value of at least $10,000,000.00.
d. References
The Bidder must provide a minimum of three (3) references for comparable projects performed within the past five (5) years. Each reference shall include the project name, location, description of work performed, contract value, and owner contact information.
e. Bonding Capacity
The Bidder must be capable of providing Performance and Payment Bonds in the full amount of the Contract Price in accordance with §255.05, Florida
Statutes.
f. Insurance Capability
The Bidder must be capable of obtaining and maintaining the insurance coverage required in Section 7 of this ITB and the resulting Contract.
g. Statutory Eligibility
The Bidder must:
a. Not be disqualified from public contracting pursuant to §§287.133–
287.135, Florida Statutes;
b. Comply with §448.095, Florida Statutes; and
c. Must not be excluded or disqualified in SAM.gov under 2 C.F.R. Part
180.
Failure to meet any of the above minimum qualifications may result in the Bidder being determined non-responsible and ineligible for award.
SECTION 7 – SPECIAL REQUIREMENTS
7.1 BUSINESS TAX RECEIPTS
☒ Shall Apply.
The successful Bidder shall obtain all required business tax receipts or local occupational licenses required to perform the work within the City prior to issuance of a Purchase Order or execution of the Contract, as applicable.
Submission with the Bid is not required.
7.2 INSURANCE
☒ Shall Apply.
The successful Bidder shall procure and maintain, at its own expense, the insurance required by Article V of the Form of Agreement (Appendix C), including the minimum coverages and limits listed below. Coverage shall run from the Effective Date through Final Acceptance and for any longer period stated in the Form of Agreement. Certificates of insurance and all required endorsements shall be submitted to and approved by the City before Contract execution and issuance of the Notice to Proceed. If this Section conflicts with
Article V of the Form of Agreement, Article V controls.
7.3 MINIMUM INSURANCE COVERAGES AND LIMITS
A. Commercial General Liability (occurrence form), including products-completed operations, personal and advertising injury, and contractual liability:
i. Each Occurrence: $1,000,000
ii. General Aggregate: $2,000,000
iii. Products-Completed Operations Aggregate: $2,000,000, maintained for three (3) years after Final Acceptance
B. Automobile Liability, covering any auto (owned, non-owned, and hired):
i. Combined Single Limit: $1,000,000 per accident
C. Workers' Compensation and Employer's Liability:
i. Workers' Compensation: statutory, in compliance with Chapter 440, F.S.
ii. Employer's Liability – Each Accident: $1,000,000
iii. Employer's Liability – Disease, Policy Limit: $1,000,000
iv. Employer's Liability – Disease, Each Employee: $1,000,000
D. Umbrella/Excess Liability:
i. $5,000,000 per occurrence, excess of the coverages in A, B, and C
(Employer's Liability)
E. Contractor's Pollution Liability:
i. $1,000,000 per occurrence / $2,000,000 aggregate
F. Builder's Risk (all-risk / special form):
i. 100% of the replacement cost of the Work, including fire, named windstorm, flood, theft, vandalism, and debris removal
ii. City, Contractor, and all subcontractors named as insureds
iii. Deductibles not to exceed $25,000 per occurrence ($100,000 for flood and named windstorm), borne by the Contractor
iv. Loss proceeds payable to the City as trustee
v. Waiver of subrogation in favor of all insureds
vi. Maintained until Final Acceptance
G. Additional Requirements:
i. All liability policies (except Workers' Compensation) shall name the City and its officials, officers, employees, and agents as additional insureds for ongoing and completed operations, on a primary and non-contributory basis.
ii. The Contractor and its insurers shall waive all rights of subrogation against the City and its officials, officers, employees, and agents.
iii. Each policy shall provide thirty (30) days' prior written notice to the City of cancellation, non-renewal, or material reduction in coverage (ten
(10) days for non-payment of premium).
iv. Insurers shall be authorized to do business in Florida and rated no less than A-, Class VII by A.M. Best Company.
7.4 FEDERAL FUNDING AND FEDERAL REQUIREMENTS
Shall Apply.
a. Federal Funding. The Project is funded in whole or in part with federal financial assistance awarded by U. S. Treasury under RESTORE Act Direct
Component, Assistance Listing No. (ALN) – 21.015. The resulting Contract will include the Federal Requirements set forth in Article XXIV and Exhibits M
(Federal Contract Provisions), N (Federal Certifications), and O (Funding
Agency Supplemental Requirements and Wage Determination) of the Form of Agreement in Appendix C. Bids shall include all costs of complying with those requirements.
b. Prevailing Wages. Work is subject to the Davis-Bacon Act, 40 U.S.C. §§ 3141–
3148, and 29 C.F.R. Parts 1, 3, and 5. U.S. Department of Labor Wage
Determination No. FL20260132, Modification 05/18/2026, is attached as
Appendix E and incorporated into this ITB. A modification issued at least ten
(10) calendar days before bid opening applies and will be issued by addendum (29 C.F.R. § 1.6(c)(2)(ii)(A)). If the Contract is not awarded within ninety (90) days after bid opening, any modification issued before award applies (29 C.F.R. § 1.6(c)(2)(ii)(D)). Award is conditioned upon the Bidder's acceptance of the Wage Determination (2 C.F.R. Part 200, App. II(D)).
c. Buy America. The Project is an infrastructure project subject to the Buy
America Preference of § 70914 of the Infrastructure Investment and Jobs Act, Pub. L. 117-58, and 2 C.F.R. Part 184, as set forth in Exhibit M, § M-11(b) of the
Form of Agreement. Bids shall be based on compliant iron and steel, manufactured products, and construction materials. Waivers may be requested only through the City and are granted only by the Federal
Awarding Agency under 2 C.F.R. § 184.7. The City does not represent that any waiver will be sought or granted.
d. Small, Minority, Women's, and Veteran-Owned Businesses. The City encourages participation by small businesses, minority businesses, women's business enterprises, veteran-owned businesses, and labor surplus area firms.
A Bidder that intends to subcontract shall take and document the steps in 2
C.F.R. § 200.321(b)(1)–(5), as required by Exhibit M, § M-12.
e. Federal Certifications. Each Bidder shall submit with its Bid the Federal
Certifications in Appendix B.
f. Exclusion Verification. Before award, the City will verify in SAM.gov that the apparent lowest responsive Bidder and its principals are not excluded or disqualified (2 C.F.R. § 180.300). An excluded Bidder is ineligible for award.
g. Organizational Conflicts. Any firm that developed or drafted the specifications, requirements, statement of work, or this ITB is excluded from competing (2 C.F.R. § 200.319(b)).
h. Funding Agency Requirements. Additional Funding Agency requirements are set forth in Exhibit O of the Form of Agreement.
7.5 BID BOND
☒ Shall Apply.
Each Bid must include Bid Security in the amount of not less than five percent
(5%) of the total Bid amount, payable to the City of Milton, Florida.
Bid Security shall be in the form of:
1. A Bid Bond issued by a surety authorized to conduct business in the State of Florida and accompanied by a current and valid Power of Attorney; or
2. A certified check or cashier’s check drawn on an FDIC-insured financial institution.
3. Failure to submit acceptable Bid Security in the required form and amount at the time of Bid opening shall render the Bid non-responsive.
7.6 BID BOND RETURN AND VALIDITY
☒ Shall Apply.
a. Each Bid shall remain firm and shall not be withdrawn for a period of ninety
(90) calendar days after Bid opening.
b. Bid Security of Bidders not under consideration for award shall be returned within a reasonable time after Bid opening. The Bid Security of the apparent successful Bidder shall be retained until the Contract has been executed and required Performance and Payment Bonds have been furnished and approved.
c. If the successful Bidder fails to execute the Contract or furnish required bonds within the time specified, the Bid Security may be forfeited in accordance with Section 9.
7.7 PERFORMANCE AND PAYMENT BONDS
☒ Shall Apply.
a. The successful Bidder shall furnish a Performance Bond and a Payment Bond, each in the amount of one hundred percent (100%) of the Contract Price, where required by § 255.05, F.S., and in all cases where the Contract Price exceeds the federal simplified acquisition threshold (currently $350,000), as required by 2 C.F.R. § 200.326.
b. The bonds shall: Be issued by a surety authorized to conduct business in the
State of Florida; Be issued by a surety listed in the current U.S. Department of the Treasury Circular 570; Be accompanied by a current and valid Power of
Attorney; and Comply with the requirements of §255.05, F.S.
c. The required bonds shall be furnished within ten (10) calendar days after issuance of the Notice of Award, unless otherwise authorized by the City, and shall be a condition precedent to Contract execution and issuance of the
Notice to Proceed.
d. Failure to furnish acceptable bonds shall constitute grounds for withdrawal of award and forfeiture of Bid Security as provided in Section 9.
7.8 PUBLIC RECORDS
a. Pursuant to Chapter 119, Florida Statutes, all documents submitted in response to this ITB are subject to public inspection and copying unless exempt from disclosure by law.
b. Sealed bids are exempt from public disclosure until the City provides notice of an intended decision or as otherwise provided by §119.071(1)(b), Florida
Statutes.
c. If a Bidder claims that any portion of its Bid is exempt from disclosure, the
Bidder shall identify the specific information claimed to be exempt and cite the applicable statutory basis. The City shall determine whether any claimed exemption applies.
d. By submitting a Bid, the Bidder acknowledges that the City is subject to
Chapter 119, Florida Statutes, and cannot guarantee the confidentiality of submitted information.
e. IF THE RESPONDENT HAS QUESTIONS REGARDING THE APPLICATION OF
CHAPTER 119, FLORIDA STATUTES, TO THE RESPONDENT’S DUTY TO PROVIDE
PUBLIC RECORDS RELATING TO ANY RESULTING CONTRACT, CONTACT THE
CUSTODIAN OF PUBLIC RECORDS AT: Molly Turnes; Phone: (850) 983-5402;
Email: mturnes@miltonfl.org;
Address: 6738 Dixon Street, Milton, FL 32570
7.9 LOCAL VENDOR PREFERENCE
Pursuant to the City of Milton Purchasing Policy 9.0, the City encourages participation by local vendors and may consider a Local Vendor Preference in determining the lowest responsive and responsible Bidder, provided such preference is not prohibited by applicable state or federal law or funding requirements.
For purposes of this Solicitation, a “Local Vendor” means a business entity that maintains a physical business location within the corporate limits of the City of
Milton.
mailto:mturnes@miltonfl.org
Bidders seeking consideration as a Local Vendor must identify such status in their
Bid and provide documentation sufficient to establish eligibility.
SECTION 8 – EVALUATION AND BASIS OF AWARD
8.1 EVALUATION
This Solicitation is issued as a competitive sealed bid pursuant to §255.20, Florida
Statutes. Award, if made, shall be to the lowest responsive and responsible
Bidder whose Bid conforms in all material respects to the requirements of this ITB.
If issued on a Lump Sum basis, the lowest responsive and responsible Bidder shall be determined based on the Base Bid amount stated in the Bid Form.
If issued on a Unit Price basis, the lowest responsive and responsible Bidder shall be determined based on the Total Evaluated Bid Amount calculated by applying the submitted Unit Prices to the estimated quantities provided for evaluation purposes.
Estimated quantities are approximate and are provided solely for comparison of
Bids. Actual quantities may increase or decrease as required for completion of the Work, and payment shall be based on actual quantities incorporated into the Work at the Unit Prices bid.
Where Add Alternates are included, the lowest responsive and responsible
Bidder shall be determined on the Base Bid (or Total Evaluated Bid Amount) plus the Add Alternates the City elects to award, taken only in the numerical order of priority listed in the Bid Form and to the extent of funds available. The City will announce the amount of funds available for award at the Bid opening, before any Bid is opened.
8.2 RESPONSIVENESS
The City will review each Bid to determine whether it is responsive to the requirements of this ITB.
A responsive Bid is one that conforms in all material respects to the Solicitation
Documents without material deviation, reservation, or irregularity.
Failure to submit required forms, failure to acknowledge addenda, failure to include required bonds, or failure to comply with material requirements of this ITB may result in the Bid being deemed non-responsive.
8.3 RESPONSIBILITY
The City shall determine whether the lowest responsive Bidder is responsible.
In determining responsibility, the City may consider factors including, but not limited to:
• Relevant experience on projects of similar size and scope
• Financial capacity and bonding capability
• Availability of equipment and personnel
• Safety record
• Past performance on public construction projects
• Compliance with applicable statutory requirements
• Ability to obtain required insurance and permits
• Integrity and compliance with public policy (2 C.F.R. § 200.318(h))
• Exclusion status in SAM.gov, including any debarment for violations of federal labor standards (2 C.F.R. § 180.300)
The City may request additional information to assist in its responsibility determination. Failure to provide requested information within the time specified may result in a determination of non-responsibility.
8.4 CLARIFICATIONS
The City may request clarification of information submitted in a Bid for the purpose of resolving ambiguities or confirming compliance with the requirements of this ITB. Clarifications shall not constitute negotiations and shall not permit modification of price, scope, or other material terms of the Bid.
Clarifications shall not cure a material defect or omission.
8.5 REJECTION OF BIDS
The City reserves the right to:
• Reject any or all Bids for a sound, documented reason (2 C.F.R. §
200.320(b)(1)(ii)(E)).
• Reject a Bid determined to be mathematically or materially unbalanced.
• Waive minor irregularities or informalities that do not affect price, competition, or substantive rights.
• Verify references and qualifications.
• Conduct investigations as permitted by law.
The City’s determination of responsiveness and responsibility shall be final, subject to applicable protest procedures set forth in the City of Milton
Purchasing Policy 9.0.
8.6 TIE BIDS
In the event of a tie between two or more lowest responsive and responsible
Bidders, the tie shall be resolved in accordance with the City of Milton
Purchasing Policy 9.0, applying any tie-break preference required by Florida law where applicable. If the tie remains unresolved, the City shall resolve it by a drawing of lots conducted publicly in the presence of at least two City employees and documented in the procurement file. For a federally funded
Solicitation, no local or geographic preference shall be used to resolve a tie.
SECTION 9 – AWARD PROCESS AND CONTRACT
9.1 NOTICE OF INTENDED AWARD
Following completion of the evaluation described in Section 8, the City will post a Notice of Intended Award identifying the lowest responsive and responsible
Bidder.
The Notice of Intended Award shall be posted in accordance with the City of
Milton Purchasing Policy 9.0.
9.2 PROTEST PROCEDURES
Any actual or prospective Bidder who is aggrieved in connection with this
Solicitation or the intended award may file a protest in accordance with the procedures and timeframes set forth in the City of Milton Purchasing Policy 9.0.
The protest period shall commence upon posting of the Notice of Intended
Award. Failure to timely file a protest in accordance with Purchasing Policy 9.0 shall constitute a waiver of all protest rights.
For a federally funded Solicitation, the City alone is responsible for resolving protests (2 C.F.R. § 200.318(k)), and the City will provide notice of any protest to the Funding Agency or Pass-Through Entity where the Federal Award requires it.
9.3 NOTICE OF AWARD
If no timely protest is filed, or upon resolution of any timely protest, the City may issue a Notice of Award to the successful Bidder.
Issuance of the Notice of Award does not authorize commencement of the
Work and does not constitute a binding contract between the parties.
9.4 CONTRACT EXECUTION AND BOND SUBMISSION
Within the time specified in the Notice of Award, the successful Bidder shall:
• Execute the Form of Agreement;
• Furnish the required Performance and Payment Bonds in accordance with
§255.05, Florida Statutes; and
• Provide all required insurance documentation.
Execution of the Agreement and submission and approval of required bonds and insurance are conditions precedent to issuance of the Notice to Proceed.
9.5 FAILURE TO EXECUTE OR PROVIDE REQUIRED BONDS
Failure of the successful Bidder to timely execute the Agreement or furnish required bonds and insurance may result in withdrawal of the award and forfeiture of the Bid Bond as permitted by law.
The City may, at its discretion, award the Contract to the next lowest responsive and responsible Bidder or reject all Bids and re-solicit.
9.6 NOTICE TO PROCEED
The Contractor shall not commence Work until the City issues a written Notice to
Proceed. The Contract Time shall commence as stated in the Notice to
Proceed.
9.7 CONTRACT TERM
The Contract shall become effective upon execution by both parties and shall remain in effect until Final Completion has been achieved, all closeout requirements have been satisfied, and final payment has been made, unless terminated earlier in accordance with the Contract Documents.
9.8 CONTRACT TIME
Substantial Completion shall be achieved within 510 Calendar Days after issuance of the Notice to Proceed.
Final Completion shall be achieved within 570 Calendar Days after issuance of the Notice to Proceed.
9.9 LIQUIDATED DAMAGES
☒ Shall Apply.
Failure to achieve Substantial Completion within the Contract Time shall result in assessment of Liquidated Damages in the amount of $2,700.00 per Calendar
Day for each day the Work remains incomplete beyond the required completion date.
Failure to achieve Final Completion within the Contract Time shall result in assessment of Liquidated Damages in the amount of $2,700.00 per Calendar
Day for each day the Work remains incomplete beyond the required completion date.
Liquidated Damages for Final Completion shall apply only after Substantial
Completion has been achieved and shall not be assessed concurrently with
Liquidated Damages for Substantial Completion.
SECTION 10 – BID SUBMITTAL REQUIREMENTS
10.1 BID SUBMITTAL DEADLINE
Bids must be received no later than the date and time stated in Section 3. Bids received after the stated deadline will not be accepted and will be returned unopened.
10.2 BID SUBMITTAL LOCATION
Bids shall be submitted in a sealed envelope, one (1) electronic copy, one (1) original and one (3) copy, to:
City of Milton
Attn: Purchasing Department
6738 Dixon Street
Milton, Florida 32570
10.3 PUBLIC BID OPENING
Bids will be publicly opened and read aloud at the beginning at 2:00 pm Milton
City Hall, 6738 Dixon Street, Milton, FL 32570.
10.4 REQUIRED BID CONTENTS
The Bidder shall include the following fully completed and executed documents in its sealed Bid submission:
1. Appendix A:
a. Bid Form
b. Bid Schedule
c. Bidder’s Qualification Statement
d. Site Examination Certification
e. Bidder’s Certification and Addenda Acknowledgement
2. Appendix B:
a. Subcontractor List
b. Anti-Human Trafficking Compliance Affidavit
c. Certification Regarding Nondiscrimination
d. Conflict-of-Interest Disclosure and Certification
e. Drug-Free Workplace Certification
f. E-Verify Compliance Certification
g. Non-Collusion Affidavit
h. Prompt Payment Compliance Certification
i. Public Entity Crime Affidavit
j. Scrutinized Companies Certification
k. Federal Certifications (Debarment and Suspension; Anti-Lobbying and Standard Form LLL, if the Bid exceeds $100,000; Covered
Telecommunications; Federal Antidiscrimination Compliance, if required)
l. Buy America Certification
3. Additional Items:
a. Bid Bond (as required in Section 7)
b. Contractor’s License
All required forms shall be properly executed. Forms requiring notarization must be notarized.
Failure to submit all required documents at the time of Bid opening may result in the Bid being deemed non-responsive.
10.5 ADDENDUM ACKNOWLEDGEMENT
Failure to properly acknowledge receipt of all issued addenda in the Bid Form may result in the Bid being deemed non-responsive.
10.6 WITHDRAWAL OR MODIFICATION
Bids may be modified or withdrawn prior to the submission deadline by written notice.
10.7 REQUIRED ENVELOPE MARKINGS
The sealed envelope shall clearly display:
10.8 RESPONSIBILITY FOR DELIVERY
It is the sole responsibility of the Bidder to ensure that its Bid is received at the designated location on or before the stated deadline. The City shall not be responsible for delays caused by mail, courier service, or other delivery methods.
Bids submitted by telephone, email, facsimile, or other electronic transmission will not be accepted unless expressly authorized in this Solicitation.
Failure to comply with the submission requirements of this ITB may result in the Bid being deemed non-responsive.
SECTION 11 – INSTRUCTIONS TO BIDDER
11.1 GENERAL
This Invitation to Bid (“ITB”) is issued as a competitive sealed bid for a public construction project. The Work is fully described in the Solicitation Documents.
Bidders shall submit sealed Bids in strict accordance with the requirements of this
ITB.
To: C i ty of Milton
VENDOR Name:
SEALED BID * DO NOT OPEN
Sealed ITB #2026.15
Title: 2026.15 ITB Effluent Discharge System (City of Milton Downtown Pump Plant)
DUE DATE/TIME: Thursday, December 17, 2026 / 2:00 p.m. (CST)
All documents issued in connection with this Solicitation, including the ITB, plans, specifications, appendices, exhibits, and addenda, collectively comprise the
Solicitation Documents and are complementary to one another.
It is the responsibility of each Bidder to monitor the City’s designated solicitation platforms and website for the issuance of addenda. Failure to acknowledge addenda as required may result in the Bid being deemed non-responsive.
11.2 OFFICIAL POSTING PLATFORMS
The City utilizes BidNet Direct, DemandStar, and the City’s official website for publication of solicitation opportunities and addenda. Bidders are solely responsible for monitoring these platforms and ensuring receipt of any addenda issued.
11.3 PROPOSAL FORMS
Bidders shall submit their Bid on the forms furnished by the City. All blank spaces shall be completed in ink or typed. Where required, amounts shall be stated in both words and figures.
Bidders shall not modify, alter, or substitute the City’s Bid Form. Submission of a
Bid on any form other than that provided may result in the Bid being deemed non-responsive.
All documents required by this ITB, including bid security, certifications, affidavits, and other required attachments, shall be submitted with the Bid. Such required attachments shall not be considered modifications to the Bid Form.
If additional space is necessary for completion of any required form, clearly labeled supplemental pages may be attached.
11.4 SIGNATURE REQUIREMENTS
The Bid shall be signed by an individual authorized to bind the Bidder.
If the Bid is submitted by a corporation, limited liability company, partnership, or other legal entity, the person signing the Bid shall certify that they are authorized to execute the Bid on behalf of the entity.
If the Bid is signed by an agent, written evidence of the agent’s authority to bind the Bidder shall be submitted with the Bid.
Electronic signatures are accepted unless otherwise stated in this ITB.
11.5 ADDENDA
Addenda may be issued to clarify, modify, or revise the Solicitation Documents.
Addenda shall be issued in writing and posted on the City’s designated solicitation platforms.
Verbal statements, interpretations, or clarifications shall not be binding.
Each Bidder is responsible for determining whether any addenda have been issued and for acknowledging receipt of all addenda in the Bid Form.
11.6 EXAMINATION OF SOLICITATION DOCUMENTS AND SITE
Each Bidder is responsible for:
• Thoroughly examining the Solicitation Documents;
• Visiting the Project site to become familiar with existing conditions that may affect the Work;
• Reviewing applicable federal, state, and local laws, regulations, permits, and ordinances that may affect performance of the Work;
• Studying and correlating observations with the Contract Documents; and
• Promptly notifying the City of any conflicts, errors, or discrepancies discovered in the Solicitation Documents.
Submission of a Bid constitutes representation that the Bidder has satisfied itself as to all conditions affecting the Work and that the Bid is based upon performance in accordance with the Contract Documents.
11.7 PRE-BID CONFERENCE
If a pre-bid conference is scheduled, the date, time, and location shall be as stated in this ITB. Attendance shall be mandatory as indicated in Section 3.
Statements made at a pre-bid conference are not binding unless confirmed by written addendum.
11.8 PRE-BID QUESTIONS AND INTERPRETATIONS
All questions regarding the meaning or intent of the Solicitation Documents shall be submitted in writing to the Procurement Representative as identified in
Section 3.
Questions must be received no later than the deadline stated in this ITB.
Responses deemed necessary by the City shall be issued by written addendum.
Only written addenda issued by the City shall be binding. No verbal interpretation or clarification shall modify the Solicitation Documents.
11.9 BID QUANTITIES (IF UNIT PRICE CONTRACT)
Bidders shall not modify the estimated quantities provided in the Bid Schedule but shall insert a unit price for each item listed.
11.10 COMPLIANCE WITH APPLICABLE LAWS
Bidders shall comply with all applicable federal, state, and local laws, rules, and regulations in the preparation and submission of their Bid.
11.11 MATHEMATICAL ERRORS
In the event of discrepancy between the Bid Form total and the sum of individual line items, the sum of the individual line items shall govern.
11.12 WORD VS. FIGURE DISCREPANCY
In the event of discrepancy between words and figures, the amount stated in words shall govern.
11.13 AMERICANS WITH DISABILITIES ACT (ADA)
The City of Milton complies with the Americans with Disabilities Act (ADA).
Any person requiring special accommodations to participate in this solicitation process should contact the City’s Purchasing Department at least seventy-two
(72) hours prior to the scheduled event.
11.14 RESERVATION OF RIGHTS
The City reserves the right to waive minor irregularities, request clarifications, verify information, reject any or all Bids, cancel or re-advertise the Solicitation, and take any action authorized by applicable law, consistent with Section 8.
No contractual relationship shall exist until a written Agreement is executed by authorized representatives of both parties.
APPENDIX A
• Bid Form
• Bid Schedule
•…