Solicitation_12363N26Q4188.pdf
PDF 1 MB Posted
- Solicitation number
- 12363N26Q4188
- Issued by
-
Department of Agriculture Forest Service
About this file
This is a commercial construction solicitation issued by USDA-FS Stewardship Contracting for the Bear Gulch Post-Fire Adit Safety Closure project in Mason County, Washington. The solicitation number is 12363N26Q4188, issued July 2, 2026, with offers due July 16, 2026, at 10:00 AM Mountain Time. The project involves three line items: (1) Project Workplan preparation including equipment, materials, work methods, fire prevention procedures, project schedule, and a Health & Safety Plan addressing underground work hazards and emergency communications in a remote post-wildfire burn area near Lake Cushman; (2) Portal Closure installation of a bat-friendly steel gate at a historical adit adjacent to Copper Creek trail #876 with minimum 5¾-inch spacing using ¾" X ¾" square steel tubing, 1/8" or 3/16" thickness, permanently anchored to bedrock and restricting public access while allowing wildlife ingress/egress; and (3) a Work Report documenting actions taken, results, field notes, and photographs. The project magnitude is less than $25,000 with an estimated performance period from July 20, 2026, to September 21, 2027.
Award will be made on a firm fixed-price basis to the highest technically rated offeror, provided their price is fair and reasonable and past performance is acceptable or neutral. Evaluation criteria include Planned Technical Approach addressing site access, adit closure, emergency communications, and post-fire field work; Schedule Compliance Statement; and Contractor Performance Assessment Reporting System review. All quotes must be submitted via email in lump-sum pricing format for all three items. The contract is a commercial construction acquisition subject to FAR and AGAR clauses including Construction Wage Rate Requirements, Buy American-Construction Materials, Progress Payments for Commercial Construction, and Anti-Discrimination and Diversity, Equity, and Inclusion Compliance certifications. Invoicing will be submitted to the Department of Treasury's Invoice Processing Platform. Small business set-aside applies with limitations on subcontracting.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION, OFFER,
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
7. ISSUED BY CODE 8. ADDRESS OFFER TO
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO. 3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION CALL
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
FOR
SEALED BID (IFB)
NEGOTIATED (RFP)
1172878
USDA-FS STEWARDSHIP CONTRACTING BR
1400 INDEPENDENCE AVE SW
MS-1138
WASHINGTON DC 20250-1138
363N
CHAD.BULLOCK@USDA.GOV
JAMES.KAMINSKI@USDA.GOV
D__QUOT.eqd2wnl433zqtojx@u.box.com
JAMES KAMINSKI 573-453-8424
07/02/2026
12363N26Q4188 INVITATION FOR BID
REQUEST FOR PROPOSAL
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
Bear Gulch Post-Fire Adit Safety Closure
Olympic National Forest
Mason County, WA
The magnitude of this project is Less than $25,000.
Estimated Period of Performance - July 20, 2026, to September 21, 2027
SEE ATTACHED SCHEDULE OF ITEMS AND STATEMENT OF WORK
11. The Contractor shall begin performance within
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and is not required.is, b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
d. Offers providing less than
12b. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in Item 12b.)
0 0 calendar days and complete it within ________________ ________________ calendar days after receiving
07/16/2026
NSN 7540-01-155-3212
x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________
STANDARD FORM 1442 (Rev. 12/2022)
Prescribed by GSA
FAR(48 CFR) 53.236-1(d)
12363N26Q4188 Bear Gulch Post-Fire – Adit Safety Closure Page 1 of 27
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than item 14.)
CODE FACILITY CODE
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
OFFER (Must be fully completed by offeror)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES CODE AT
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this document solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE
BY
USDA-FS STEWARDSHIP CONTRACTING BR
1400 INDEPENDENCE AVE SW
MS-1138
WASHINGTON DC 20250-1138
363N
CHAD A. BULLOCK
28. NEGOTIATED AGREEMENT 29. AWARD
and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations,certifications, and specifications incorporated by reference in or attached to this contract.
copies to issuing office.) Contractor agrees to furnish
10 U.S.C. 3204(a) 41 U.S.C. 3304(a)
STANDARD FORM 1442 (REV. 12/2022) BACK
Continued...
and return
(Contractor is not required to sign this document.) Your offer on this
12363N26Q4188 Bear Gulch Post-Fire – Adit Safety Closure Page 2 of 27
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED
12363N26Q4188
ALL QUOTES SHALL BE EMAILED TO:
CHAD.BULLOCK@USDA.GOV;
JAMES.KAMINSKI@USDA.GOV,D__QUOT.eqd2wnl433zqtojx@u
.box.com on or BEFORE
July 16, 2026, 10:00 AM MOUNTIAN TIME.
Since all documents will be submitted to me electronically. Follow this naming convention for your attachments and keep the subject line the same or just reply all to this email.
Be sure to fill out all required documentation.
Required to be filled in below:
Company Name:___________________________________
POC Name:_______________________________________
Phone number:___________________________________
Email:__________________________________________
BPA/IDIQ/MATOC Contract #_______________________
UEI SAM #______________________________________
Contractual POC: Chad A.T. Bullock Contracting
Officer, chad.bullock@usda.gov 385-368-5300
Contractual Technical: James Kaminski APSO, 573-453-8424
Delivery: 09/21/2026
Delivery Location Code: 05G3
USDA FS OLYMPIC NATIONAL FOREST
HOOD CANAL RANGR DIST HOODSPORT OFC
150 N CUSHMAN RD PO BOX 68
HOODSPORT WA 98548 US
FOB: Destination
Period of Performance: 07/27/2026 to 09/21/2026
0001 Project Workplan: 1 EA
Must include a description of all equipment and materials to be used, work methods, fire prevention procedures, and a project schedule.
Shall include a Health & Safety Plan (HASP). The
Site is in a remote location near Lake Cushman, Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
12363N26Q4188 Bear Gulch Post-Fire – Adit Safety Closure Page 3 of 27
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED
12363N26Q4188
WA in area within a Post-Wildfire burn scar and having sporadic cell phone coverage. The HASP shall address alternative forms of emergency communication for on-site personnel as well the mitigation of physical hazards that may be encountered.
The Health & Safety Plan shall address safety concerns with performing work underground.
1. Description of workers conducting field work and their certifications (relevant to this work), equipment and materials to be used, work methods, and proposed project schedule.
2. A Health & Safety Plan (HASP) shall be prepared prior to conducting field operations.
The HASP shall describe, at minimum, certifications for personnel conducting field work (e.g. Hazwoper), a job hazard analysis to identify and mitigate potential hazards at the site (including work conducted inside the portals), personnel protective equipment (PPE) to be utilized, an emergency evacuation plan, and alternative forms of emergency communication for on-site personnel.
0002 Portal Closure: Install a bat-friendly wildlife 1 EA gate at the historical adit adjacent to the
Copper Creek trail #876. Adequate closure of the adit would consist of installing ¿bat friendly¿ steel gate that is permanently anchored to the bedrock and restricts public access yet allowing ingress and egress for bats and other wildlife species that inhabit the mine feature. There is no design requirement to facilitate human entry with this historical adit closure.
1. Adequate closure of the adit shall consist of installing a ¿bat friendly¿ steel non-functioning gate that restricts public access and human entry into the adit, yet allows ingress and egress for bats. The gate must have a minimum spacing of 5
¾¿ inches, utilizing ¾¿ X ¾¿ square steel tube, 1/8¿ or 3/16¿ thickness. All waste material and equipment shall be removed at the end of project.
Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
12363N26Q4188 Bear Gulch Post-Fire – Adit Safety Closure Page 4 of 27
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED
12363N26Q4188
The portal dimensions are approximately 10¿ by
10¿ (Height x Width at entrance), however, dimensions will vary depending on where the idea location for the steel gate will be located during installation. Schedule shall be coordinated such that project COR can be on-site for the work.
2. The existing steel gate may be repaired to accomplish the performance of this work. Any remaining steel that was unused for the final product must be removed from the project area and properly disposed of. All waste materials generated and equipment used on the project site shall be removed prior to the completion of the project.
0003 Work Report: Completed at the end of field 1 EA operations and describes the actions taken, results and recommendations for future work (if any). Shall include field notes and photographs of the completed portal closure.
Work Report ¿ Prepare a concise technical memo summarizing:
a. Equipment and materials used.
b. Brief description of work performed, including dates of work performance.
c. Photographs and field notes.
d. Recommendations for future work (if any)
The "Submit Invoice-to" address for USDA orders is the Department of Treasury's Invoice
Processing Platform (IPP), https://www.ipp.gov.
If the contractor lacks an IPP account, USDA will automatically initiate the enrollment process with Treasury using the contractor's SAM.gov
Accounts Receivable POC as the IPP account holder. Once the enrollment process is complete, the IPP account holder will receive notification and can being invoicing. More information about
IPP can be found at: https://www.ipp.gov
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
12363N26Q4188 Bear Gulch Post-Fire – Adit Safety Closure Page 5 of 27
SEE Attachments for Project Supplement to include Maps, and Wage Determination
Schedule of Items:
Item No.
Description Quantity Order Unit
Unit Price Amount
01 Project Workplan 1 Lump Sum
02 Portal Closure 1 Lump Sum
03 Work Report 1 Lump Sum
Description Of Work:
1.01 GENERAL SCOPE OF THE PROJECT
A. This Statement of Work defines the following Base Items:
1.Project Workplan: Must include a description of all equipment and materials to be used, work methods, fire prevention procedures, and a project schedule. Shall include a Health & Safety Plan (HASP). The Site is in a remote location near Lake Cushman, WA in area within a Post-Wildfire burn scar and having sporadic cell phone coverage. The HASP shall address alternative forms of emergency communication for on-site personnel as well the mitigation of physical hazards that may be encountered. The Health & Safety Plan shall address safety concerns with performing work underground.
2.Portal Closure: Install a bat-friendly wildlife gate at the historical adit adjacent to the Copper Creek trail #876. Adequate closure of the adit would consist of installing “bat friendly” steel gate that is permanently anchored to the bedrock and restricts public access yet allowing ingress and egress for bats and other wildlife species that inhabit the mine feature. There is no design requirement to facilitate human entry with this historical adit closure.
3.Work Report: Completed at the end of field operations and describes the actions taken, results and recommendations for future work (if any). Shall include field notes and photographs of the completed portal closure.
Project Background:
On July 6, a human-caused fire was reported in Olympic National Forest near the Mt. Rose Trailhead along the Lake Cushman Corridor. The fire – named the Bear Gulch Fire – burned on a steep, rocky slope north of Lake Cushman in the Olympic National Forest and near the Staircase area of Olympic National Park. During a Post-Fire Assessment conducted by a USFS BAER Team, specialists identified a damaged wildlife-friendly bat gate designed to mitigate public access to a historical mine adit located adjacent to and easily accessible by trail users on the Copper Creek #876, the USFS BAER Team recommended that repairs be completed to prevent unauthorized public entry to preserve human life and safety.
12363N26Q4188 Bear Gulch Post-Fire – Adit Safety Closure Page 6 of 27
Specific Work Requirement:
A. Line Item 01 – Project Workplan - Prepare a Workplan that includes, at a minimum:
1. Description of workers conducting field work and their certifications (relevant to this work), equipment and materials to be used, work methods, and proposed project schedule.
2. A Health & Safety Plan (HASP) shall be prepared prior to conducting field operations.
A. The HASP shall describe, at minimum, certifications for personnel conducting field work (e.g. Hazwoper), a job hazard analysis to identify and mitigate potential hazards at the site (including work conducted inside the portals), personnel protective equipment (PPE) to be utilized, an emergency evacuation plan, and alternative forms of emergency communication for on-site personnel.
B. Line Item 02 – Portal Closure Adequate closure of the adit shall consist of installing a “bat friendly” steel non-functioning gate that restricts public access and human entry into the adit, yet allows ingress and egress for bats.
The gate must have a minimum spacing of 5 ¾” inches, utilizing ¾” X ¾” square steel tube, 1/8” or 3/16” thickness. All waste material and equipment shall be removed at the end of project. The portal dimensions are approximately 10’ by 10’ (Height x Width at entrance), however, dimensions will vary
Project Location Driving Directions: From Hoodsport, WA turn onto State Route 119 off of Highway 101. Follow State Route 119 for 9.0 miles to the junction with Forest Road 24. Turn left and travel 6 miles to Forest Service Road 2451. Turn left at the causeway immediately prior to the Bear Gulch Day Use area. Drive over the causeway bridge and continue about ½ mile on Forest Road 2451 to the Copper Creek # 876 trailhead located on the left.
Walking Directions: Access to the portal closure project site is via the Copper Creek #876 trail near Lake Cushman, WA. Approximately 0.25 mi from the Copper Creek #876 trailhead is the historical site identified as the Brown Mule manganese mine site located before the first footbridge crossing the stream named Copper Creek. The mine feature while visible from the trail and requires crossing Copper Creek channel to reach the mine portal.
Approximate Lat/Long (DDS): 47.503° N / 123.325° W
Definitization of Equitable Adjustments for Change Orders 36.101-1 Acquisition Strategy.
(a) The contracting officer will only use sealed bid procedures (see part 14) for a construction contract if the conditions in part 6 for use of sealed bidding are met. However, the contracting officer should not use sealed bidding if the contract will be performed outside the United States and its outlying areas.
(b) The following must be considered when determining the contract type and pricing structure and must be addressed in the acquisition plan.
12363N26Q4188 Bear Gulch Post-Fire – Adit Safety Closure Page 7 of 27
(1) Generally, firm-fixed-price contracts must be used to acquire construction. They may be priced—
(i) on a lump-sum basis (when a lump sum is paid for the total work or defined parts of the work),
(ii) on a unit-price basis (when a unit price is paid for a specified quantity of work units), or
(iii) using a combination of the two methods.
(2) Lump-sum pricing must be used in preference to unit pricing except when—
(i) Large quantities of work such as grading, paving, building outside utilities, or site preparation are involved;
(ii) Quantities of work, such as excavation, cannot be estimated with sufficient confidence to permit a lump-sum offer without a substantial contingency;
(iii) Estimated quantities of work required may change significantly during construction; or
(iv) Offerors would have to expend unusual effort to develop adequate estimates.
Pursuant to FAR 36.101-4(b), information regarding USDA’s definitization of equitable adjustments for change orders under construction contracts may be found at Contracting with USDA under “Federal Acquisition Regulation 36.101-4”. USDA’s procedures that apply to the definitization of equitable adjustments for change orders under construction contracts may be found in AGAR
443.304 -70.
Federal Acquisition Regulation (FAR) and United States Department of Agriculture Acquisition Regulation (AGAR) Clauses and Provisions The clauses and provisions contained herein are applicable to any order awarded as a result of this solicitation. The terms and conditions set forth herein supersede all other terms and conditions.
Acceptance of the order in accordance with (IAW) FAR 12.201-1(b)(2) constitutes acceptance of all terms and conditions contained herein.
As part of the Revolutionary FAR Overhaul (RFO), system updates may lag policy updates. The System for Award Management (SAM) may continue to require entities to complete representations based on provisions that are not included in this solicitation. Contracting officers will rely on representations from offers based on provisions in the solicitation. Entities are not required to, nor are they able to, update their entity registration to remove these representations in SAM.
52.252-2 Clauses Incorporated by Reference Feb 1998 This solicitation incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also the full text of the clause may be accessed electronically at Internet address https://www.acquisition.gov/far-overhaul/far-part-deviation-guide/far-overhaul-part-52
52.212-4 Terms and Conditions—Commercial Products and Commercial Services (Nov 2025) ☐ Alternate I (Nov 2025) of 52.212-4
This is a commercial construction acquisition. FAR 52.212-4 is amended as follows:
(b) Inspection/Acceptance. Inspection and Acceptance will be conducted in accordance with FAR 52.246-12, Inspection of Construction (Aug 1996).
12363N26Q4188 Bear Gulch Post-Fire – Adit Safety Closure Page 8 of 27 https://www.usda.gov/about-usda/general-information/staff-offices/departmental-administration/office-contracting-and-procurement-ocp/policies-regulations https://www.acquisition.gov/far-overhaul/far-part-deviation-guide/far-overhaul-part-52
(d) Changes. Changes will be handled in accordance with the following FAR clause(s):
☐ FAR 52.243-4, Changes (Nov 2025) ☒ FAR 52.243-5, Changes and Changed Conditions (Nov 2025)
52.203-17 Contractor Employee Whistleblower Rights (Nov 2023) 52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (Jan 2017) 52.222-50 Combating Trafficking in Persons (Nov 2025)
☐ Alternate I (Nov 2025) of 52.222-50 52.226-8 Encouraging Contractor Policies to Ban Text Messaging While Driving (May 2024) 52.232-39 Unenforceability of Unauthorized Obligations (Jun 2013) 52.232-40 Providing Accelerated Payments to Small Business Subcontractors (Mar 2023) 52.233-3 Protest After Award (Sep 2025) 52.233-4 Applicable Law for Breach of Contract Claim (Sep 2025) 52.240-91 Security Prohibitions and Exclusions (Nov 2025)
☐ Alternate I (Nov 2025) of 52.240-91 52.244-6 Subcontracts for Commercial Products and Commercial Services (Nov 2025)
The following clauses are applicable if checked:
☐ 52.203-6 Restrictions on Subcontractor Sales to the Government (Jun 2020) with Alternate I (Nov 2021) of 52.203-6 ☐ 52.203-13 Contractor Code of Business Ethics and Conduct (Nov 2021) ☐ 52.204-9 Personal Identity Verification of Contractor Personnel Jan 2011 ☒ 52.204-13 System for Award Management—Maintenance (Nov 2025) ☐ 52.204-91 Contractor identification (Nov 2025) ☐ 52.209-6 Protecting the Government’s Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (Sep 2025) ☐ 52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters (Sep 2025) ☒ 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (Sep 2025) ☐ 52.219-4 Notice of Price Evaluation Preference for HUBZone Small Business Concerns (Nov 2025) ☒ 52.219-6 Notice of Total Small Business Aside (Nov 2025)
☐ Alternate I (Mar 2020).
☐ 52.219-8 Utilization of Small Business Concerns (Nov 2025) ☐ 52.219-9 Small Business Subcontracting Plan (Nov 2025)
☐ Alternate III (Nov 2025) of 52.219-9.
☐ Alternate IV (Nov 2025) of 52.219-9
☒ 52.219-14 Limitations on Subcontracting (Nov 2025) ☐ 52.219-16 Liquidated Damages—Subcontracting Plan (Nov 2025) ☐ 52.219-33 Nonmanufacturer Rule (Nov 2025) ☒ 52.222-3 Convict Labor (June 2003) ☒ 52.222-19 Child Labor—Cooperation with Authorities and Remedies (Nov 2025)
12363N26Q4188 Bear Gulch Post-Fire – Adit Safety Closure Page 9 of 27
☐ 52.222-35 Equal Opportunity for Veterans (Nov 2025) ☐ Alternate I (Jul 2014) of 52.222-35
☒ 52.222-36 Equal Opportunity for Workers with Disabilities (Nov 2025) ☐ Alternate I (Jul 2014) of 52.222-36
☐ 52.222-37 Employment Reports on Veterans (Nov 2025) ☒ 52.222-40 Notification of Employee Rights Under the National Labor Relations Act (Dec 2010) ☐ 52.222-41 Service Contract Labor Standards (Aug 2018) ☐ 52.222-42 Statement of Equivalent Rates for Federal Hires (May 2014)
This Statement is for Information Only:
It is not a Wage Determination
Employee Class Monetary Wage -- Fringe Benefits Aircraft Mechanic $XX.XX
☐ 52.222-43 Fair Labor Standards Act and Service Contract Labor Standards -- Price Adjustment (Multiple Year and Option Contracts) (Aug 2018) ☐ 52.222-44 Fair Labor Standards Act and Service Contract Labor Standards -- Price Adjustment (May 2014) ☒ 52.222-51 Exemption from Application of the Service Contract Labor Standards to Contracts for Maintenance, Calibration, or Repair of Certain Equipment-Requirements (May 2014) ☒ 52.222-53 Exemption from Application of the Service Contract Labor Standards to Contracts for Certain Services-Requirements (Nov 2025) ☐ 52.222-54 Employment Eligibility Verification (Nov 2025) ☒ 52.222-62 Paid Sick Leave Under Executive Order 13706 (Jan 2022) ☒ 52.222-90 Addressing DEI Discrimination by Federal Contractors (Apr 2026) ☒ 52.223-2 Reporting of Biobased Products Under Service and Construction Contracts (Nov 2025) ☐ 52.223-9 Estimate of Percentage of Recovered Material Content for EPA-Designated Items (May 2008)
☐ Alternate I (May 2008) of 52.223-9 ☒ 52.223-11 Ozone-Depleting Substances and High Global Warming Potential Hydrofluorocarbons (Nov 2025) ☐ 52.223-12 Maintenance, Service, Repair, or Disposal of Refrigeration Equipment and Air Conditioners (Nov 2025) ☐ 52.223-23 Sustainable Products and Services (Nov 2025) ☐ 52.224-3 Privacy Training (Jan 2017)
☐ Alternate I (Jan 2017) of 52.224-3 ☒ 52.225-1 Buy American-Supplies (Nov 2025)
☐ Alternate I (Oct 2022) of 52.225-1 ☐ 52.225-3 Buy American--Free Trade Agreements--Israeli Trade Act (Nov 2025)
12363N26Q4188 Bear Gulch Post-Fire – Adit Safety Closure Page 10 of 27
☐ Alternate II (Nov 2025) of 52.225-3.
☐ Alternate III (Nov 2025) of 52.225-3.
☐ Alternate IV (Oct 2022) of 52.225-3
☐ 52.225-5 Trade Agreements (Nov 2023) ☐ 52.225-19 Contractor Personnel in a Designated Operational Area or Supporting a Diplomatic or Consular Mission outside the United States (May 2020) ☐ 52.225-26 Contractors Performing Private Security Functions Outside the United States (Oct 2016) ☐ 52.226-4 Notice of Disaster or Emergency Area Set-Aside (Nov 2007) ☐ 52.226-5 Restrictions on Subcontracting Outside Disaster or Emergency Area (Aug 2025) ☐ 52.229-12 Tax on Certain Foreign Procurements ☐ 52.232-29 Terms for Financing of Purchases of Commercial Products and Commercial Services (Nov 2021) ☐ 52.232-30 Installment Payments for Commercial Products and Commercial Services (Nov 2021) ☒ 52.232-33 Payment by Electronic Funds Transfer— System for Award Management (Oct 2018) ☐ 52.232-34 Payment by Electronic Funds Transfer—Other Than System for Award Management (Jul 2013) ☐ 52.232-36 Payment by Third Party (Nov 2025) ☐ 52.240-92 Security Requirements (Nov 2025)
☐ Alternate II (Nov 2025) of 52.240-92 ☐ 52.240-93 Basic Safeguarding of Covered Contractor Information Systems (Nov 2025) ☐ 52.242-13 Bankruptcy (July 1995) ☒ 52.246-21 Warranty of Construction (Mar 1994) ☐ 52.247-64 Preference for Privately Owned U.S.-Flag Commercial Vessels (Nov 2025)
☐ Alternate I (Apr 2023) of 52.247-64.
☐ Alternate II (Nov 2021) of 52.247-64
The Contractor shall comply with the following FAR Clauses for Commercial Construction.
52.222-6 Construction Wage Rate Requirements 52.222-7 Withholding of Funds 52.222-8 Payrolls and Basic Records 52.222-9 Apprentices and Trainees 52.222-10 Compliance with Copeland Act Requirements 52.222-11 Subcontracts (Labor Standards) 52.222-12 Contract Termination-Debarment 52.222-14 Disputes Concerning Labor Standards 52.222-15 Certificate of Eligibility 52.236-5 Material and Workmanship
12363N26Q4188 Bear Gulch Post-Fire – Adit Safety Closure Page 11 of 27
The following clauses are applicable when checked:
☒ 52.222-30 Construction Wage Rate Requirements-Price Adjustment (None or Separately Specified Pricing Method (Aug 2018) ☒ 52.222-31 Construction Wage Rate Requirements-Price Adjustment (Percentage Method) (Aug 2018) ☒ 52.222-32 Construction Wage Rate Requirements-Price Adjustment (Actual Method) (Nov 2025) ☒ 52.225-9 Buy American-Construction Materials (Nov 2025) ☐ Alternate I (Oct 2022) of 52.25-9 ☐ 52.225-11 Notice of Buy American Requirement-Construction Materials under Trade Agreements (Nov 2025) ☐ Alternate I (Nov 2025) (of 52.225-11 ☐ Alternate II (Oct 2022) of 52.225-11 ☐ 52.228-2 Additional Bond Security (Oct 1997) ☐ 52.228-5 Insurance-Work on Government Installation (Jan 1997) ☐ 52.228-11 Individual Surety-Pledge of Assets (Feb 2021) ☐ 52.228-13 Alternative Payment Protections (Jul 2020) ☐ 52.228-14 Irrevocable Letter of Credit (Nov 2014) ☐ 52.228-15 Performance and Payment Bonds-Construction (Jun 2020) ☐ 52.228-17 Individual Surety-Pledge of Assets (Bid Guarantee) (Feb 2021) ☐ 52.236-2 Differing Site Conditions (Jul 2025) ☐ 52.236-3 Site Investigation and Conditions Affecting the Work (Jul 2025) ☐ 52.236-6 Superintendent by the Contractor (Jul 2025) ☒ 52.236-7 Permits and Responsibilities (Jul 2025) ☐ 52.236-8 Other Contracts (Jul 2025) ☒ 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements (Jul 2025) ☐ 52.336-10 Operations and Storage Areas (Jul 2025) ☒ 52.236-11 Use and Possession Prior to Completion (Jul 2025) ☒ 52.236-12 Cleaning Up (Jul 2025) ☒ 52.236-13 Accident Prevention (Jul 2025) ☒ Alternate I (Nov 1991) of 52.236-13 ☒ 52.236-14 Availability and Use of Utility Services (Jul 2025) ☒ 52.236-15 Schedules for Construction Contracts (Jul 2025) ☒ 52.236-16 Quantity Surveys (Jul 2025) ☐ Alternate I (Apr 1984) of 52.236-16 ☒ 52.236-17 Layout of Work (Jul 2025) ☐ 52.236-21 Specifications and Drawings for Construction (Jul 2025) ☐ Alternate I (Apr 1984) of 52.236-21 ☐ Alternate II (Apr 1984) of 52.236-21 ☒ 52.242-14 Suspension of Work (Apr 1984)
12363N26Q4188 Bear Gulch Post-Fire – Adit Safety Closure Page 12 of 27
☐ 52.248-3 Value Engineering (Oct 2025) ☐ Alternate I (Apr 1984) of 52.248-3
Other Applicable Clauses
52.216-18 Ordering (Aug 2020) 52.216-19 Delivery – Order Limitations (Oct 1995) 52.216-21 Requirements (Nov 2025) ☐ Alternate I (Apr 1984) of 52.216-21 52.216-22 Indefinite Quantity (Nov 2025) 52.217-8 Option to Extend Services (Nov 1999) 30 calendar days prior to contract expiration 52.217-9 Option to Extend the Term of the Contract (Mar 2000)
(a) 30 Calendar days prior to contract expiration and 60 days
(c) five years and 6 months.
52.232-90 Fast Payment Procedures (Nov 2025) 52.245-1 Government Property (Sep 2021) ☐ Alternate I (Sep 2021) of 52.245-1 52.245-9 Use and Charges (Apr 2012) 52.246-21 Warranty of Construction 452.236-71 Prohibition Against the Use of Lead-Based Paint.
452.236-72 Use of Premises.
452.236-73 Archeological or Historic Sites 452.236-74 Control of Erosion, Sedimentation, and Pollution 452.236-76 Samples and Certificates 452.236-77 Emergency Response
AGAR Clauses 452.203-71 Anti-Discrimination and Diversity, Equity, and Inclusion (DEI) Compliance (Dec 2025)
(a) By entering into this contract, the contractor certifies that:
(1) It is compliant with all applicable Federal anti-discrimination laws and the Equal Protection principles of the U.S. Constitution, and it will remain compliant for the duration of the contract.
(2) Neither it nor any subcontractor or teaming partner operates or funds any program, policy, or initiative that promotes DEI in a manner that violates any applicable Federal anti-discrimination laws, including but not limited to Title VI and VII of the Civil Rights Act of 1964, or the Equal Protection principles of the U.S. Constitution, and the contractor and any subcontractor or teaming partner will not do so for the duration of the contract.
(b) If the contractor participates in, facilitates, or funds programs that implicate Title VI of the Civil Rights Act of 1964 or Title IX of the Education Amendments of 1972, as amended, including but not
12363N26Q4188 Bear Gulch Post-Fire – Adit Safety Closure Page 13 of 27 limited to grants to or for schools, colleges, universities, 4-H programs, non-governmental organization (NGO) programs, sports programs, and education-related grants to prisons or other detention facilities, the contractor certifies that it will remain compliant with those laws, including the requirements set forth in Executive Order 14168, Defending Women from Gender Ideology Extremism and Restoring Biological Truth to the Federal Government, and Executive Order 14173, Ending Illegal Discrimination and Restoring Merit-Based Opportunity.
(c) The contractor affirms that the above requirements are conditions of payment that go to the essence of the contract and are therefore material terms of the contract. Payments under the contract are predicated on compliance with the above requirements, and therefore the contractor is not eligible for funding under the contract or to retain any funding under the contract absent compliance with the above requirements.
(d) This certification reflects a change in the Government’s position regarding the materiality of the foregoing requirements and therefore any prior payment of similar claims does not reflect the materiality of the foregoing requirements to this contract.
(e) Submission of a knowing false statement relating to contractor’s compliance with the above requirements and/or eligibility for the contract may subject the contractor to liability under the False Claims Act, 31 U.S.C. § 3729, and/or criminal liability, including under 18 U.S.C. §§ 287 and 1001.
(f) The contractor must include the provisions of this clause in all subcontract solicitations.
(g) Failure on the part of the contractor or its subcontractors to comply with the terms of this clause may be grounds for the Contracting Officer to terminate this contract for default.
(End of Clause)
AGAR 452.203-72 Unenforceable Supplier Terms (MAY 2026)
(a) Definitions.
Supplier terms mean provisions customarily drafted by vendors of supplies or services and intended to create a binding legal obligation on the end user. The term applies:
(1) Regardless of the format or style of the document. For example, supplier terms may appear in standard terms of sale or lease, Terms of Service (TOS), End User License Agreement (EULA), or another similar legal instrument or agreement, and may be presented as part of a proposal or quotation responding to a solicitation for a contract or order or otherwise become effective after the contract date.
(2) Regardless of the media or delivery mechanism used. For example, supplier terms may be presented as one or more paper documents or may appear on a computer or other electronic device screen during a purchase, software installation, other product delivery, registration for a service, or another transaction.
(b) Applicability. When any supply or service acquired under this contract is subject to supplier terms, the supplier terms are deemed part of the contract only to the extent they are consistent with this clause. Supplier terms that conflict with any part of this clause, the contract, or Federal law are void and will not be considered incorporated into a contract, even if they are physically present in a
12363N26Q4188 Bear Gulch Post-Fire – Adit Safety Closure Page 14 of 27 contract documentation or systems. In the event of any inconsistency between supplier terms and this contract, this clause and the terms of the Government contract must govern and supersede any supplier terms in all cases.
(c) Authorization Required. Notwithstanding any other provision, no supplier terms must be binding on the Government unless the term is expressly authorized on the USDA Supplier Terms Authorization Form signed by the Contracting Officer, and the completed Authorization Form has been incorporated into the contract.
(d) Unenforceable Terms. Any supplier terms that impose obligations or restrictions inconsistent with applicable Federal law are unenforceable against the Government and deemed stricken from the agreement. This includes, but is not limited to, any clause that:
(1) Requires the Government to pay future fees, penalties, interest, legal costs, early‑termination fees, cancellation fees, minimum purchase commitments, true‑up payments, seat‑count minimums, usage minimums, continued‑use charges, or any other financial obligation not expressly authorized by the contract.
(2) Requires the Government to indemnify the contractor or any other entity.
(3) Restricts the Government’s ability to obtain similar supplies or services from another source.
(4) Imposes any penalty, financial or otherwise, based on the Government’s decision not to exercise an option.
(5) Subjects the United States Government to the laws of any U.S. state, territory, district, municipality, or foreign nation, except where Federal law expressly permits such application.
(6) Requires dispute resolution in a forum or venue other than one prescribed by applicable Federal law.
(7) Establishes a period of limitations for bringing an action that differs from that provided by applicable Federal law.
(8) Grants the contractor rights to use, mine, access, aggregate, analyze, or otherwise exploit Government data, usage data, or metadata.
(9) Deems the Government to have accepted initial or revised terms based on silence, continued performance, or failure to object.
(10) Grants the supplier the right to audit Government facilities, systems, records, or use of the product or service, except as expressly authorized by the contract and applicable Federal law.
(11) Requires the Government to accept supplier security requirements, network access requirements, monitoring, penetration testing, or other technical or security measures.
(12) Permits the supplier to suspend, degrade, or terminate access to products or services based on alleged non‑payment, alleged breach, automated security triggers.
12363N26Q4188 Bear Gulch Post-Fire – Adit Safety Closure Page 15 of 27
(13) Limits the Government’s right to use, install, access, test, evaluate, or transfer the licensed product or service in any manner consistent with the contract and Federal law.
(14) Requires the Government to store, process, maintain, or transmit data in a particular geographic location, or permits the supplier to transfer Government data outside the United States, except as expressly authorized by applicable Federal law.
(15) Authorizes the supplier to use the Government’s name, seal, trademark, logo, or any reference to the Government as an end user or customer for marketing, publicity, promotional activities, press releases, or similar purposes.
(16) Incorporates by reference, or requires the Government to accept, terms or conditions imposed by any third party, subcontractor, or upstream service provider, unless such terms are expressly incorporated into the contract by bilateral modification.
(17) Limits, conditions, or negates the contractor’s performance obligations, service levels, or remedies through a supplier‑provided service level agreement (SLA).
(18) Uses Government data, usage data, metadata, prompts, content, or interactions to train, fine‑tune, improve, or derive any artificial intelligence, machine learning, or automated decision‑making model.
(19) Subjects the Government to automated decision‑making, automated risk scoring, automated content moderation, or any algorithmic process that may affect access, performance, or rights under the contract.
(20) Utilizes artificial intelligence or algorithmic tools that produce decisions, recommendations, or outputs affecting contract performance without providing transparency, explainability, auditability, and bias‑mitigation consistent with applicable Federal law and policy.
(21) Profiles, tracks, or analyzes Government user behavior, preferences, communications, or interactions for personalization, marketing, or algorithmic optimization purposes.
(e) Non-binding Actions. Neither the Government nor any Government authorized end user is deemed to have consented to any term, condition, or clause by virtue of its inclusion in the supplier agreement or through the use of clickwrap, browsewrap, “I agree” mechanisms, or similar means.
Execution of such mechanisms does not bind the Government or its authorized end users to any unenforceable terms.
(f) End user. The supplier agreement must bind the ordering activity as the end user to the extent it does not conflict with the terms of this clause, but it must not bind or impose personal liability on any Government employee or any person acting on behalf of the Government in their personal capacity.
(g) Law and disputes. The supplier agreement is governed by Federal law.
(h) Statutory exception. This clause does not apply to indemnification or any other payment by the Government that is expressly authorized by statute and specifically authorized under applicable agency regulations and procedures.
12363N26Q4188 Bear Gulch Post-Fire – Adit Safety Closure Page 16 of 27
(i) Continued performance. The supplier or licensor must not unilaterally revoke, terminate, or suspend any rights granted to the Government except as allowed by the contract. If the supplier or licensor believes the ordering activity to be in breach of the supplier agreement, it must pursue its rights under the Contract Disputes Act or other applicable Federal statute while proceeding diligently with performance, pending final resolution of any dispute in accordance with the Disputes Clause at FAR 52.212‑4(d) or FAR 52.233‑1, as applicable.
(j) Arbitration. Binding arbitration must not be used unless specifically authorized by agency guidance.
(k) Equitable or injunctive relief. Equitable or injunctive relief, including the award of attorney fees, costs, or interest, may be awarded against the United States Government only when explicitly provided by statute (e.g., the Prompt Payment Act or the Equal Access to Justice Act).
(l) Revisions to supplier agreements. Any revisions to the supplier agreement must be incorporated into the contract using a bilateral modification. Unilateral revisions are not binding on the Government.
(m) No automatic renewals. If any license or service tied to periodic payment is provided under the supplier agreement (e.g., annual software maintenance or annual lease term), such license or service must not renew automatically upon expiration of its current term without prior express written consent from an authorized Government representative.
(n) Indemnification. Any clause of the supplier agreement requiring the supplier or licensor to defend or indemnify the end user is amended to provide that the U.S. Department of Justice has the sole right to represent the United States in any such action, in accordance with 28 U.S.C. 516.
(o) Taxes or surcharges. Any taxes or surcharges which the supplier or licensor seeks to pass along to the Government as end user will be governed by the terms of the associated Government contract or order and must be submitted to the Contracting Officer for a determination of applicability prior to invoicing unless specifically agreed otherwise.
(p) Non‑assignment. The supplier agreement may not be assigned, nor may any rights or obligations thereunder be delegated, without the Government’s prior approval, except as expressly permitted by FAR 52.212-4(b) or FAR 52.232-23, as applicable.
(q) Confidential information. If the supplier agreement includes a confidentiality clause, such clause is amended to state that neither the agreement nor the contract price list, as applicable, must be deemed “confidential information.” Issues regarding release of “unit pricing” will be resolved consistent with the Freedom of Information Act. Notwithstanding anything in the supplier agreement to the contrary, the Government may retain any confidential information as required by law, regulation, or its internal document retention procedures for legal, regulatory, or compliance purposes; provided, however, that all such retained confidential information will continue to be subject to the confidentiality obligations of the supplier agreement.
(r) Conflict with Federal law. If any other language, provision, or clause of the supplier agreement conflicts or is inconsistent with Federal law or the terms and conditions of this contract, such language, provisions, or clauses will be considered null and void and will not be binding on the United States Government.
12363N26Q4188 Bear Gulch Post-Fire – Adit Safety Closure Page 17 of 27
(End of Clause)
452.204–70 Modification for Contract Closeout (Apr 2026)
(a) If unliquidated funds in the amount of $1000 or less remain on the contract, the Contracting Officer (Contracting Officer) may issue a unilateral modification for deobligation. The contractor will receive a copy of the modification but is not required to provide a signature. The Contracting Officer will immediately proceed with contract closeout upon completion of the period of performance, receipt and acceptance of supplies or services, and final payment.
(b) For commercial contracts not exceeding the simplified acquisition procedure threshold under FAR 12.001(c), if more than $1,000 in unliquidated funds remain at closeout, the Contracting Officer will issue a bilateral deobligation modification. Only the modification requires the contractor’s signature, though a Release of Claims may be requested. If the required documents are not returned within 60 days, the Contracting Officer will issue a unilateral modification and proceed with closeout once performance is complete, acceptance is confirmed, and final payment is made.
(c) For all other non-commercial or non–cost‑reimbursement contracts, if more than $1,000 in unliquidated funds remain at closeout, the Contracting Officer will issue a bilateral deobligation modification and a Release of Claims, both requiring contractor signature. If these documents are not returned within 120 days, the Contracting Officer will issue a unilateral modification u and proceed with closeout upon completion of performance, acceptance, and final payment.
(End of Clause)
452.232-71 Progress Payments for Commercial Construction Contracts (May 2026)
(a) Contractor entitlement to progress payments. The contractor may request progress payments monthly as the work proceeds, or at more frequent intervals as determined by the Contracting Officer, on estimates of work accomplished that meets the standards of quality established under the contract, as approved by the Contracting Officer.
(b) Computation of amounts. Progress payments will be authorized when the payment requested is properly due in accordance with this contract; the work will be performed in accordance with the contract; and there has been no impairment or diminution of the Government’s security under this contract. The Contracting Officer may authorize consideration of:
(1) Materials delivered on site and preparatory work;
(2) Materials delivered to the contractor at locations other than the site, if:
i. Specifically authorized by the contract; and
ii. The contractor provides satisfactory evidence of title and intended use in the contract.
(c) Contractor request for progress payments. The contractor’s request for progress payments must include the following:
(1) An itemization of the amounts requested, related to the various elements of work required by the contract;
(2) A listing of the amount included for work performed by each subcontractor;
12363N26Q4188 Bear Gulch Post-Fire – Adit Safety Closure Page 18 of 27
(3) A listing of the total amount of each subcontract;
(4) A listing of the amounts previously paid to each subcontractor; and
(5) Additional supporting data in a form and detail required by the Contracting Officer.
(d) Contractor Certification. Each request for progress payment must be accompanied by the following certification:
I hereby certify, to the best of my knowledge and belief, that—
(1) The amounts requested are only for performance in accordance with the specifications, terms, and conditions of the contract;
(2) All payments due to subcontractors and suppliers from previous payments received under the contract have been made, and timely payments will be made from the proceeds of the payment covered by this certification, in accordance with subcontract agreements and the requirements of Chapter 39 of Title 31, United States Code;
(3) This request for progress payments does not include any amounts which the prime contractor intends to withhold or retain from a subcontractor or supplier in accordance with the terms and conditions of the subcontract; and
(4) This certification is not to be construed as final acceptance of a subcontractor’s performance.
________________________________________________(name)
________________________________________________(title)
________________________________________________(date)
(e) Access for verification of payment entitlement. To verify the contractor’s entitlement to progress payments under this contract, the contractor must provide the Government, upon request and during normal business hours, access to the following:
(1) Records and Documentation:
i. Certified progress payment requests and supporting documentation;
ii. Subcontractor and supplier invoices, payment records, and lien waivers;
iii. Updated schedule of values and progress schedules;
iv. Quality assurance and inspection reports;
v. Payroll records, if applicable under labor provisions.
(2) Facilities and Worksite Access:
i. Physical access to the construction site for inspection of work progress;
ii. Access to off-site storage locations for materials billed but not yet incorporated into the work; or
iii. Access to any fabrication facilities where contract-related work is being performed.
12363N26Q4188 Bear Gulch Post-Fire – Adit Safety Closure Page 19 of 27
(3) Access to electronic invoicing or project management systems used to track progress and payments, if such systems are used in contract performance.
(f) Dates for payment. A progress payment under this clause is a contract progress payment under the Prompt Payment clause of this contract, and except as provided in paragraph (g) of this clause, approved requests must be paid within 30 days of submitting a proper request for payment.
(g) Liquidation of progress payments. Progress payments must be liquidated by deducting from the payment of each item the total unliquidated amount of progress payments made for that separately priced unit of that line item. The liquidation amounts for each line item must be clearly delineated in each request for progress payment submitted by the contractor.
(h) Security for progress payments. In the event that the contractor fails to provide adequate security as required in this contract, no progress payment must be made under this contract. Upon receipt of adequate security, progress payments must be made, including all previous payments to which the contractor is entitled, in accordance with the terms of the contract. If at any time the Contracting Officer determines that the security provided by the contractor is insufficient, the contractor must promptly provide such additional security as the Contracting Officer determines necessary. In the event the contractor fails to provide such additional security, the Contracting Officer may collect or liquidate such security that has been provided, and suspend further payments to the contractor; the contractor must repay to the Government the amount of unliquidated progress payments as the Contracting Officer at his sole discretion deems repayable.
(i) Special terms regarding termination for cause. If this contract is terminated for cause, the contractor must, on demand, repay the Government the amount of unliquidated progress payments.
The Government must be liable for no…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .