This is a Memorandum for the Record documenting the justification for using other than full and open competition for a simplified acquisition threshold procurement by the Department of Defense (DOC 5182-1350).

The memorandum justifies the award to a single source based on restrictive rights and proprietary capabilities. The selected vendor is approved to work on SUBSAFE equipment and has undergone facility inspection by Puget Sound Naval Shipyard (PSNS). The vendor has served as PSNS's sole provider for this particular service since at least 2010, consistently delivering excellent service in a timely manner with costs that have remained aligned with inflation. The determination is made under FAR 13.106-1(b)(1)(i), which permits single-source solicitation when circumstances deem only one source reasonably available for acquisitions not exceeding the simplified acquisition threshold. The memorandum requires technical certification that facts are complete and accurate, though specific item descriptions, delivery dates, and signatory information are not fully detailed in the provided document sections.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MEMORANDUM FOR THE RECORD

(This is only applicable to acquisitions under the Simplified Acquisition Threshold. Acquisition using FAR Subpart 13.5 shall follow the special documentation requirements at FAR 13.501.)

Subj: USE OF OTHER THAN FULL AND OPEN COMPETITION FOR AN

ACQUISITION UNDER THE SIMPLIFIED ACQUISITION THRESHOLD

I. BACKGROUND:

1. FAR 13.106-1(b)(1)(i) states for purchases not exceeding the simplified acquisition threshold, Contracting Officers may solicit from one source if the Contracting Officer determines that the circumstances of the contract action deem only one source reasonably available (e.g., urgency, exclusive licensing agreements, brand-name or industrial mobilization).

2. As required by FAR 13.106-3(b)(3)(i), this memorandum explains the absence of competition for this acquisition, as only one source will be solicited for this requirement (or for a portion of the requirement) and the requirement is not expected to exceed the simplified acquisition threshold.

II. DESCRIPTION OF ITEM OR SERVICE:

Provide a description of the item or service required, to include its intended use, the name of the required source or brand name, and the required delivery date/period of performance.

III. THE DETERMINATION FOR USE OF OTHER THAN FULL AND OPEN

COMPETITION IS BASED ON THE FOLLOWING (select all that apply):

A. _X__ ONLY ONE RESPONSIBLE SOURCE (select all that apply):

1. _X__ RESTRICTIVE RIGHTS. The source has established proprietary rights, limited rights in data, patent rights, copyrights or secret processes in the item or service required.

The suggested source is approved to work on SUBSAFE equipment and has had their facility inspected by PSNS. This is the closest vendor that can accomplish this work even without the requirements for SUBSAFE. PSNS has used this vendor solely as far back as 2010 for this particular service. This vendor has a history of providing excellent service in a timely manner at a cost that has stayed consistent with inflation for all of the years of service.

2. ___ EXCLUSIVE LICENSING AGREEMENTS. The item or service is only available from the Original Equipment Manufacturer (OEM), or there is only one authorized distributor or technical representative for the OEM.

Identify the OEM and explain the circumstances surrounding why the item or service is only available from the OEM.

OR

Identify the distributor(s)/authorized technical representative(s) for the item or service. Provide evidence of the exclusive licensing agreement as an attachment to this document. NOTE: If there is more than one distributor/authorized technical representative for an OEM part, then Part B, BRAND NAME SOLE SOURCE, is applicable, and Part A, ONLY ONE RESPONSIBLE SOURCE, should be left blank).

3. ___ OTHER REASONS. Other reason not identified above. Provide details on mission impact if requirement is not solicited from only one source.

B. ___ BRAND NAME. Item required must be a brand name product, or feature of a product, particular to one manufacturer. Discuss why you are precluding consideration of a product manufactured by another company. Describe how the particular brand name, product, or feature is essential to the Government’s requirements and why a “brand name or equal” purchase description cannot be used (see FAR 11.104). Describe how market research indicates other companies’ similar products or products lacking the particular feature do not meet, or cannot be modified to meet, the agency’s needs.

C. ___UNUSUAL AND COMPELLING URGENCY. The supplies or services are of such unusual and compelling urgency that the Government would be seriously injured unless the agency is permitted to limit the number of sources from which it solicits bids or proposals.

Urgent requirements are supplies or services that will result in a work stoppage, or are mission critical and the routine processing time would result in injury to the Government. The determination that the procurement for the above item/service is an urgent and compelling requirement is based on the following:

1. Date on which the requirement was first identified:

2. Required delivery date/period of performance:

3. Explanation of why delivery/commencement of services by the date mentioned above is required: Explain the impact to the mission if the date above is not met, any special circumstances or conditions that exist which validate the requirement as “urgent,” estimated production lead time for the item, etc.

4. If appropriate, include any additional pertinent information.

IV. CERTIFICATIONS/APPROVALS:

A. Technical / Requirements Certification: I certify that the facts and representation under my cognizance which are included in this justification are complete and accurate to the best of my knowledge and belief.