Sol_SOL-DC-14-00041.pdf
PDF 620 KB Posted
- Solicitation number
- SOL-DC-14-00041
About this file
SOL-DC-14-00041
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment_1_Solicitation_Clauses.docx | DOCX document | |
| Sol_SOL-DC-14-00041_Amd_000002.pdf | ||
| Attachment_4_Technical_Proposal_Instructions.docx | DOCX document | |
| Sol_SOL-DC-14-00041_Amd_000001.pdf | ||
| Solicitation_Questions.docx | DOCX document | |
| Attachment_1_SOW.docx | DOCX document | |
| Attachment__2_PP_Questionnaire.doc | DOC document | |
| Attachment_3_Client_Authorization.docx | DOCX document | |
| Attachment_4_Technical_Proposal_Instructions.docx | DOCX document | |
| Attachment_3_Client_Authorization.docx | DOCX document | |
| Attachment_6_HSPD_12.doc | DOC document | |
| Attachment_5_Invoice.docx | DOCX document | |
| Attachment__2_PP_Questionnaire.doc | DOC document | |
| Attachment_1_SOW.docx | DOCX document |
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOL-DC-14-00041
SOLICITATION, OFFER AND AWARD
4. TYPE OF SOLICITATION2. CONTRACT NUMBER 3. SOLICITATION NUMBER
7. ISSUED BY CODE 8. ADDRESS OFFER TO (If other than Item 7)
ORDER UNDER DPAS (15 CFR 700)
6. REQUISITION/PURCHASE NUMBER
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
NEGOTIATED (RFP)
SEALED BID (IFB)
5. DATE ISSUED
1. THIS CONTRACT IS A RATED RATING PAGE OF PAGES
1 72
C. E-MAIL ADDRESS
EXT.NUMBERAREA CODE
B. TELEPHONE (NO COLLECT CALLS)A. NAME
10. FOR
INFORMATION
CALL:
CAUTION: LATE Submissions, Modifications, and Withdrawals: See Section L, Provision No. 52.214-7 or 52.215-1. All offers are subject to all terms and conditions contained in this solicitation.
(Date)(Hour) local timeuntildepository located in copies for furnishing the supplies or services in the Schedule will be received at the place specified in Item 8, or if hand carried, in the
SOLICITATION
9. Sealed offers in original and
PART IV - REPRESENTATIONS AND INSTRUCTIONS
OTHER STATEMENTS OF OFFERORS
EVALUATION FACTORS FOR AWARD
INSTRS., CONDS., AND NOTICES TO OFFERORS
REPRESENTATIONS, CERTIFICATIONS AND
LIST OF ATTACHMENTS
CONTRACT CLAUSES
PART III - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACH.
I
J
K
L
M SPECIAL CONTRACT REQUIREMENTS
CONTRACT ADMINISTRATION DATA
DELIVERIES OR PERFORMANCE
INSPECTION AND ACCEPTANCE
PACKAGING AND MARKING
DESCRIPTION/SPECS./WORK STATEMENT
SUPPLIES OR SERVICES AND PRICES/COSTS
SOLICITATION/CONTRACT FORM
PART II - CONTRACT CLAUSESPART I - THE SCHEDULE
H
G
F
E
D
C
B
A
SEC. DESCRIPTION PAGE(S) (X) DESCRIPTION SEC. (X)
11. TABLE OF CONTENTS
18. OFFER DATE17. SIGNATURE
SUCH ADDRESS IN SCHEDULE.
IS DIFFERENT FROM ABOVE - ENTER
15C. CHECK IF REMITTANCE ADDRESS
EXT.NUMBERAREA CODE
15B. TELEPHONE NUMBER
(Type or print)AND
ADDRESS
OF
OFFEROR
CODE FACILITY
16. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER15A. NAME
DATEAMENDMENT NO.DATEAMENDMENT NO.
and related documents numbered and dated):
amendments to the SOLICITATION for offerors
(The offeror acknowledges receipt of
14. ACKNOWLEDGEMENT OF AMENDMENTS
CALENDAR DAYS (%)30 CALENDAR DAYS (%)20 CALENDAR DAYS (%)10 CALENDAR DAYS (%)
(See Section I, Clause No. 52.232.8)
13. DISCOUNT FOR PROMPT PAYMENT
designated point(s), within the time specified in the schedule.
by the offeror) from the date for receipt of offers specified above, to furnish any or all items upon which prices are offered at the price set opposite each item, delivered at the
12. In compliance with the above, the undersigned agrees, if this offer is accepted within ______________ calendar days (60 calendar days unless a different period is inserted
NOTE: Item 12 does not apply if the solicitation includes the provisions at 52.214-16, Minimum Bid Acceptance Period.
OFFER (Must be fully completed by offeror)
IMPORTANT - Award will be made on this Form, or on Standard Form 26, or by other authorized official written notice.
28. AWARD DATE
(Signature of Contracting Officer)
27. UNITED STATES OF AMERICA
25. PAYMENT WILL BE MADE BY
26. NAME OF CONTRACTING OFFICER (Type or print)
CODE 24. ADMINISTERED BY (If other than Item 7)
ITEM
(4 copies unless otherwise specified)
23. SUBMIT INVOICES TO ADDRESS SHOWN IN
41 U.S.C. 253 (c) ( 10 U.S.C. 2304 (c) (
22. AUTHORITY FOR USING OTHER THAN FULL AND OPEN COMPETITION:
21. ACCOUNTING AND APPROPRIATION20. AMOUNT19. ACCEPTED AS TO ITEMS NUMBERED
AWARD (To be completed by government)
CODE
09/15/2015 X
HPOD
HPOD
US Environmental Protection Agency William Jefferson Clinton Building 1200 Pennsylvania Avenue, N. W.
Mail Code: 3803R Washington DC 20460
1630 ES 10/15/2015
Christine Edwards 202 Edwards.Christine@epa.gov
564-2182
PAGE(S)
Christine Edwards
AUTHORIZED FOR LOCAL REPRODUCTION
Previous edition is unusable
STANDARD FORM 33 (Rev. 9-97)
Prescribed by GSA - FAR (48 CFR) 53.214(c)
SECTION A - Solicitation/Contract Form
SECTION B - Supplies or Services/Prices
B-1 EPAAR 1552.211-73 LEVEL OF EFFORT-COST-REIMBURSEMENT TERM CONTRACT
(APR 1984)
B-2 EPAAR 1552.211-74 WORK ASSIGNMENTS. (APR 1984) - ALTERNATE I (APR 1984)
B-3 LOCAL CLAUSES EPA-B-16-102 ESTIMATED COST AND FIXED FEE
B-4 LOCAL CLAUSES EPA-B-31-101 OTHER DIRECT COSTS
B-5 LOCAL CLAUSES EPA-B-32-101 LIMITATION OF FUNDS NOTICE
SECTION C - Description/Specifications
C-1 EPAAR 1552.211-79 COMPLIANCE WITH EPA POLICIES FOR INFORMATION
RESOURCES MANAGEMENT (JAN 2012)
C-2 LOCAL CLAUSES EPA-C-10-101 STATEMENT OF WORK/PERFORMANCE WORK
STATEMENT/SPECIFICATIONS
SECTION D - Packaging and Marking
SECTION E - Inspection and Acceptance
E-1 FAR 52.246-5 INSPECTION OF SERVICES --COST REIMBURSEMENT (APR 1984)………11
E-2 FAR 52.246-11 HIGHER-LEVEL CONTRACT QUALITY REQUIREMENT (DEC 2014)
SECTION F - Deliveries or Performance
F-1 FAR 52.242-15 STOP-WORK ORDER (AUG 1989) - ALTERNATE I (APR 1984)……….……13
F-2 EPAAR 1552.211-70 REPORTS OF WORK (OCT 2000)
F-3 EPAAR 1552.211-72 MONTHLY PROGRESS REPORT (JUN 1996)
F-4 EPAAR 1552.211-75 WORKING FILES (APR 1984)………………………………………….… 14
F-5 EPAAR 1552.211-78 MANAGEMENT CONSULTING SERVICES (APR 1985) ………..……15
F-6 LOCAL CLAUSES EPA-F-12-101 PERIOD OF PERFORMANCE
SECTION G - Contract Administration Data
G-1 EPAAR 1552.216-74 PAYMENT OF FEE (MAY 1991)
G-2 EPAAR 1552.232-70 SUBMISSION OF INVOICES (JUN 1996)
G-3 EPAAR 1552.242-70 INDIRECT COSTS (APR 1984)
G-4 EPAAR 1552.245-70 GOVERNMENT-FURNISHED PROPERTY (SEP 2009)
G-5 LOCAL CLAUSES EPA-G-42-101 CONTRACT ADMINISTRATION REPRESENTATIVES22
SECTION H - Special Contract Requirements
H-1 EPAAR 1552.203-71 DISPLAY OF EPA OFFICE OF INSPECTOR GENERAL HOTLINE
POSTER. (AUG 2000) …………..………………………………………………………………………. 24
H-2 EPAAR 1552.208-70 PRINTING (SEP 2012)……………………………………...…………..…
H-3 EPAAR 1552.209-71 ORGANIZATIONAL CONFLICTS OF INTEREST. (MAY 1994)
H-4 EPAAR 1552.209-73 NOTIFICATION OF CONFLICTS OF INTEREST REGARDING
PERSONNEL. (MAY 1994)
H-5 EPAAR 1552.217-71 OPTION TO EXTEND THE TERM OF THE CONTRACT-COST-TYPE
CONTRACT (APR 1984)
H-6 EPAAR 1552.217-73 OPTION FOR INCREASED QUANTITY-COST-TYPE CONTRACT
(JUN 1997)
H-7 EPAAR 1552.227-76 PROJECT EMPLOYEE CONFIDENTIALITY AGREEMENT (MAY
1994)………………………………………………………………………………………………………...29
H-8 EPAAR 1552.228-70 INSURANCE LIABILITY TO THIRD PERSONS (OCT 2000)
H-9 EPAAR 1552.235-70 SCREENING BUSINESS INFORMATION FOR CLAIMS OF
CONFIDENTIALITY (APR 1984) ……………………………………………………………………
H-10-EPAAR1552.235-71 TREATMENT OF CONFIDENTIAL BUSINESS INFORMATION. (APR
1984) ……………………………………………………………………………………………………..…30
H-11 EPAAR 1552.235-75 ACCESS TO TOXIC SUBSTANCES CONTROL ACT CONFIDENTIAL
BUSINESS INFORMATION (APR 1996) ……………………………………………………………
H-12 EPAAR 1552.235-76 TREATMENT OF CONFIDENTIAL BUSINESS INFORMATION (APR
1996)
H-13 EPAAR 1552.235-78 DATA SECURITY FOR TOXIC SUBSTANCES CONTROL ACT
CONFIDENTIAL BUSINESS INFORMATION (DEC 1997)…………………………………..….…..32
H-14 EPAAR 1552.235-79 RELEASE OF CONTRACTOR CONFIDENTIAL BUSINESS
INFORMATION (APR 1996) ………………………………………...…………………………….…….33
H-15 EPAAR 1552.237-71 TECHNICAL DIRECTION (AUG 2009)………………………………….34
H-16 EPAAR 1552.237-72 KEY PERSONNEL (APR 1984)
H-17 EPAAR 1552.237-75 PAPERWORK REDUCTION ACT (APR 1984) ………………………...36
H-18 EPAAR 1552.237-76 GOVERNMENT-CONTRACTOR RELATIONS (JUN 1999)
H-19 LOCAL CLAUSES EPA-H-07-103 NOTICE REGARDING PROHIBITED CONTRACTOR
ACTIVITIES ON ENVIRONMENTAL PROTECTION AGENCY
H-20 LOCAL CLAUSES EPA-H-09-107 UNPAID FEDERAL TAX LIABILITY & FELONY
CRIMINAL VIOLATION CERTIFICATION (APR 2012)
SECTION I - Contract Clauses
I-1 FAR 52.202-1 DEFINITIONS (NOV 2013) …………………………………………………………39
I-2 FAR 52.203-3 GRATUITIES (APR 1984) ………………………………………….………………..39
I-3 FAR 52.203-5 COVENANT AGAINST CONTINGENT FEES (MAY 2014) …………………..39
I-4 FAR 52.203-6 RESTRICTIONS ON SUBCONTRACTOR SALES TO THE GOVERNMENT
(SEP 2006) …………………………………………………………………………………………………39
I-5 FAR 52.203-7 ANTI-KICKBACK PROCEDURES (MAY 2014) …………………………………39
I-6 FAR 52.203-8 CANCELLATION, RESCISSION, AND RECOVERY OF FUNDS FOR
ILLEGAL OR IMPROPER ACTIVITY (MAY 2014) …………………………………………………39
I-7 FAR 52.203-10 PRICE OR FEE ADJUSTMENT FOR ILLEGAL OR IMPROPER ACTIVITY
(MAY 2014) ……………………………………………………………………………………………...39
I-8 FAR 52.203-12 LIMITATION ON PAYMENTS TO INFLUENCE CERTAIN FEDERAL
TRANSACTIONS (OCT 2010) ………………………………………………………………..…………39
I-9 FAR 52.203-13 CONTRACTOR CODE OF BUSINESS ETHICS AND CONDUCT (APR 2010)
…………………………………………………………………………………………………...……….…39
I-10 FAR 52.203-14 DISPLAY OF HOTLINE POSTER(S) (DEC 2007) …………………………...39
I-11 FAR 52.203-17 CONTRACTOR EMPLOYEE WHISTLEBLOWER RIGHTS AND
REQUIREMENT TO INFORM EMPLOYEES OF WHISTLEBLOWER RIGHTS (APR 2014)
I-12 FAR 52.204-4 PRINTED OR COPIED DOUBLE-SIDED ON POSTCONSUMER FIBER
CONTENT PAPER (MAY 2011) ………………………………………………………………………...40
I-13 FAR 52.204-9 PERSONAL IDENTITY VERIFICATION OF CONTRACTOR PERSONNEL
(JAN 2011) ………………………………………………………………………………………………
I-14 FAR 52.204-10 REPORTING EXECUTIVE COMPENSATION AND FIRST-TIER
SUBCONTRACT AWARDS (JUL 2013) ………………………………………………………………..40
I-15 FAR 52.204-13 SYSTEM FOR AWARD MANAGEMENT MAINTENANCE (JUL 2013) …..40
I-16 FAR 52.209-6 PROTECTING THE GOVERNMENT'S INTEREST WHEN
SUBCONTRACTING WITH CONTRACTORS DEBARRED, SUSPENDED, OR PROPOSED FOR
DEBARMENT (AUG 2013) ………………………………………………………………………….…...40
I-17 FAR 52.209-9 UPDATES OF PUBLICLY AVAILABLE INFORMATION REGARDING
RESPONSIBILITY MATTERS (JUL 2013) …………………………………………………………
I-18 FAR 52.210-1 MARKET RESEARCH (APR 2011) ……………………………………………….40
I-19 FAR 52.215-2 AUDIT AND RECORDS - NEGOTIATION (OCT 2010) ………………………..40
I-20 FAR 52.215-8 ORDER OF PRECEDENCE - UNIFORM CONTRACT
FORMAT (OCT 1997) ……………………………………………………………………………….…...40
I-21 FAR 52.215-23 LIMITATIONS ON PASS-THROUGH CHARGES (OCT 2009) ……………...40
I-22 FAR 52.216-7 ALLOWABLE COST AND PAYMENT (JUN 2013)
I-23 FAR 52.216-8 FIXED FEE (JUN 2011) …………………………………………………………….46
I-24 FAR 52.217-8 OPTION TO EXTEND SERVICES (NOV 1999)
I-25 FAR 52.217-9 OPTION TO EXTEND THE TERM OF THE CONTRACT (MAR 2000)
I-26 FAR 52.219-8 UTILIZATION OF SMALL BUSINESS CONCERNS (OCT 2014) …………….46
I-27 FAR 52.219-9 SMALL BUSINESS SUBCONTRACTING PLAN (JUL 2013) - ALTERNATE II
(OCT 2001) …………………………………………..…………………………………….………………46
I-28 FAR 52.219-16 LIQUIDATED DAMAGES - SUBCONTRACTING PLAN …..………………..47
I-29 FAR 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION
(JUL 2013)
I-30 FAR 52.222-3 CONVICT LABOR (JUN 2003) ………………………………………………….. 48
I-31 FAR 52.222-21 PROHIBITION OF SEGREGATED FACILITIES (APR 2015) ………………48
I-32 FAR 52.222-26 EQUAL OPPORTUNITY (APR 2015) ..…………………………………………48
I-33 FAR 52.222-35 EQUAL OPPORTUNITY FOR VETERANS (JUL 2014) ……………………..48
I-34 FAR 52.222-36 EQUAL OPPORTUNITY FOR WORKERS WITH DISABILITIES (JUL 2014)
…………………………………………………………………………………………….……………….. 48
I-35 FAR 52.222-37 EMPLOYMENT REPORTS ON VETERANS (JUL 2014) ……………………48
I-36 FAR 52.222-40 NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE NATIONAL
LABOR RELATIONS ACT (DEC 2010) ……………………………………………………………….48
I-37 FAR 52.222-50 COMBATING TRAFFICKING IN PERSONS (MAR 2015) ………………….48
I-38 FAR 52.222-54 EMPLOYMENT ELIGIBILITY VERIFICATION (AUG 2013) ...……………48
I-39 FAR 52.223-6 DRUG-FREE WORKPLACE (MAY 2001) …...………………………………….48
I-40 FAR 52.223-18 ENCOURAGING CONTRACTOR POLICIES TO BAN TEXT MESSAGING
WHILE DRIVING (AUG 2011) ……..…………………………………………………………………..48
I-41 FAR 52.225-13 RESTRICTIONS ON CERTAIN FOREIGN PURCHASES (JUN 2008) .…….48
I-42 FAR 52.227-14 RIGHTS IN DATA-GENERAL (MAY 2014) …………………………………...48
I-43 FAR 52.228-7 INSURANCE - LIABILITY TO THIRD PERSONS (MAR 1996) ……………...48
I-44 FAR 52.230-2 COST ACCOUNTING STANDARDS (MAY 2014) ……………………………..48
I-45 FAR 52.230-3 DISCLOSURE AND CONSISTENCY OF COST ACCOUNTING PRACTICES
(MAY 2014) ……………………………………………………………………………………………..…48
I-46 FAR 52.230-6 ADMINISTRATION OF COST ACCOUNTING STANDARDS (JUN 2010) …49
I-47 FAR 52.232-17 INTEREST (MAY 2014) …………………………………………………………49
I-48 FAR 52.232-22 LIMITATION OF FUNDS (APR 1984) ………………………………………….49
I-49 FAR 52.232-23 ASSIGNMENT OF CLAIMS (MAY 2014) ……………………………………...49
I-50 FAR 52.232-25 PROMPT PAYMENT (JUL 2013) - ALTERNATE I (FEB 2002) ……………..49
I-51 FAR 52.232-33 PAYMENT BY ELECTRONIC FUNDS TRANSFER - SYSTEM FOR AWARD
MANAGEMENT (JUL 2013) …………………………………………………………………………
I-52 FAR 52.232-39 UNENFORCEABILITY OF UNAUTHORIZED OBLIGATIONS
(JUN 2013) …………………………………………………………………………………………………49
I-53 FAR 52.233-1 DISPUTES (MAY 2014)……………………………………………………………..49
I-54 FAR 52.233-3 PROTEST AFTER AWARD (AUG 1996) ………………………………………...49
I-55 FAR 52.233-4 APPLICABLE LAW FOR BREACH OF CONTRACT CLAIM (OCT 2004) ...49
I-56 FAR 52.237-3 CONTINUITY OF SERVICES (JAN 1991) ………………………………………49
I-57 FAR 52.242-1 NOTICE OF INTENT TO DISALLOW COSTS (APR 1984) …………………..49
I-58 FAR 52.242-3 PENALTIES FOR UNALLOWABLE COSTS (MAY 2014) ……………………49
I-59 FAR 52.242-4 CERTIFICATION OF FINAL INDIRECT COSTS (JAN 1997)
I-60 FAR 52.242-13 BANKRUPTCY (JUL 1995) ………………………………………….…………..50
I-61 FAR 52.243-2 CHANGES - COST-REIMBURSEMENT (AUG 1987) - ALTERNATE I (APR
1984) ………………………………………………………………………………………………………..50
I-62 FAR 52.244-2 SUBCONTRACTS (OCT 2010) - ALTERNATE I (JUN 2007)
I-63 FAR 52.244-5 COMPETITION IN SUBCONTRACTING (DEC 1996) …...……………………52
I-64 FAR 52.244-6 SUBCONTRACTS FOR COMMERCIAL ITEMS (APR 2015) ….……………..52
I-65 FAR 52.245-1 GOVERNMENT PROPERTY (APR 2012) .……………………………………..52
I-66 FAR 52.245-9 USE AND CHARGES (APR 2012) ……….………………………………………..52
I-67 FAR 52.246-25 LIMITATION OF LIABILITY - SERVICES (FEB 1997) ……………………..52
I-68 FAR 52.249-6 TERMINATION (COST-REIMBURSEMENT). (MAY 2004) …………………..52
I-69 FAR 52.249-14 EXCUSABLE DELAYS (APR 1984) …………………………………………….52
I-70 FAR 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
I-71 FAR 52.252-6 AUTHORIZED DEVIATIONS IN CLAUSES (APR 1984)
I-72 FAR 52.253-1 COMPUTER GENERATED FORMS (JAN 1991) ……………………...……….53
SECTION J - List of Documents, Exhibits and Other Attachments
SECTION K - Representations, Certifications, and Other Statements of Bidders
K-1 FAR 52.203-11 CERTIFICATION AND DISCLOSURE REGARDING PAYMENTS TO
INFLUENCE CERTAIN FEDERAL TRANSACTIONS (SEP 2007) ………………………………..55
K-2 FAR 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (JAN 2014)
K-3 FAR 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (JUL 2013) ...58
K-4 FAR52.225-25 PROHIBITION ON CONTRACTING WITH ENTITIES ENGAGING IN
CERTAIN ACTIVITIES RELATING TO IRAN-REPRESENTATION AND CERTIFICATIONS
(DEC 2012) ………………………………………………………………...………………………………59
K-5 EPAAR 1552.209-72 ORGANIZATIONAL CONFLICT OF INTEREST CERTIFICATION
(APR 1984)
K-6 EPAAR 1552.224-70 SOCIAL SECURITY NUMBERS OF CONSULTANTS AND CERTAIN
SOLE PROPRIETORS AND PRIVACY ACT STATEMENT (APR 1984)
SECTION L - Instructions,Conditions, and Notices to Bidders
L-1 FAR 52.204-7 SYSTEM FOR AWARD MANAGEMENT (JUL 2013) ……………..…….……..61
L-2 FAR 52.215-1 INSTRUCTIONS TO OFFERORS - COMPETITIVE ACQUISITION
(JAN 2004) ………………………………………………………………………………………………
L-3 FAR 52.215-16 FACILITIES CAPITAL COST OF MONEY (JUN 2003) ..…………………….61
L-4 FAR 52.215-20 REQUIREMENTS FOR CERTIFIED COST OR PRICING DATA OR DATA
OTHER THAN COST OR PRICING DATA (OCT 2010) - ALTERNATE IV (OCT 2010)
L-5 FAR 52.215-22 LIMITATIONS ON PASS-THROUGH CHARGES--IDENTIFICATION OF
SUBCONTRACT EFFORT (OCT 2009) ……………………………………………………………
L-6 FAR 52.216-1 TYPE OF CONTRACT (APR 1984)
L-7 FAR 52.222-46 EVALUATION OF COMPENSATION FOR PROFESSIONAL EMPLOYEES
(FEB 1993)
L-8 FAR 52.233-2 SERVICE OF PROTEST (SEP 2006)
L-9 FAR 52.237-10 IDENTIFICATION OF UNCOMPENSATED OVERTIME (MAR 201) .…
L-10 FAR 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB
1998)
L-11 FAR 52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (APR 1984)
L-12 EPAAR 1552.209-70 ORGANIZATIONAL CONFLICT OF INTEREST NOTIFICATION
(APR 1984) ...………………………………………………………………………………………………66
L-13 EPAAR 1552.215-75 PAST PERFORMANCE INFORMATION (OCT 2000)
L-14 EPAAR 1552.219-71 PROCEDURES FOR PARTICIPATION IN THE EPA MENTOR-
PROTÉGÉ PROGRAM (OCT 2000) ………………………………………………….……………….68
L-15 EPAAR 1552.233-70 NOTICE OF FILING REQUIREMENTS FOR AGENCY PROTESTS
(JUL 1999) …………………………………………………………………………………………………68
L-16 LOCAL CLAUSES EPA-L-12-101 PROPOSED CONTRACTOR START DATE
L-17 LOCAL CLAUSES EPA-L-15-102 TECHNICAL QUESTIONS
L-18 LOCAL CLAUSES EPA-L-15-104 ELECTRONIC SUMBISSION OF
PROPOSALS/BIDS/OFFERS/QUOTES
SECTION M - Evaluation Factors for Award
M-1 EPAAR 1552.215-70 EPA SOURCE EVALUATION AND SELECTION PROCEDURES-
NEGOTIATED PROCUREMENTS (AUG 1999) ..……………………………...……………………..69
M-2 EPAAR 1552.215-71 EVALUATION FACTORS FOR AWARD (AUG 1999) ...……………….69
M-3 EPAAR 1552.217-70 EVALUATION OF CONTRACT OPTIONS (APR 1984) ..……………..71
SECTION A - Solicitation/Contract Form
See Cover Page (SF 1447).
SECTION B - Supplies or Services/Prices
B-1 EPAAR 1552.211-73 LEVEL OF EFFORT-COST-REIMBURSEMENT TERM CONTRACT
(APR 1984)
(a) The Contractor shall perform all work and provide all required reports within the level of effort specified below. The Government hereby orders 25,000 direct labor hours for the base period, which represents the Government's best estimate of the level of effort to fulfill these requirements.
(b) Direct labor includes personnel such as engineers, scientists, draftsmen, technicians, statisticians, and programmers and not support personnel such as company management, typists, and key punch operators even though such support personnel are normally treated as direct labor by the Contractor. The level of effort specified in paragraph (a) includes Contractor, subcontractor, and consultant labor hours.
(c) If the Contractor provides less than 90 percent of the level of effort specified for the base period or any optional period ordered, an equitable downward adjustment of the fixed fee, if any, for that period will be made. The Government may require the Contractor to provide additional effort up to 110 percent of the level of effort for any period until the estimated cost for that period has been reached. However, this additional effort shall not result in any increase in the fixed fee, if any. If this is a cost-plus-incentive-fee (CPIF) contract, the term "fee" in this paragraph means "base fee and incentive fee." If this is a cost-plus-award-fee (CPAF) contract, the term "fee" in this paragraph means "base fee and award fee."
(d) If the level of effort specified to be ordered during a given base or option period is not ordered during that period, that level of effort may not be accumulated and ordered during a subsequent period.
(e) These terms and conditions do not supersede the requirements of either the "Limitation of Cost" or "Limitation of Funds" clauses.
B-2 EPAAR 1552.211-74 WORK ASSIGNMENTS (APR 1984) - ALTERNATE I (APR 1984)
(a) The contractor shall perform work under this contract as specified in written work assignments issued by the Contracting Officer.
(b) Each work assignment will include (1) a numerical designation, (2) the estimate of required labor hours,
(3) the period of performance and schedule of deliverables, and (4) the description of the work.
(c) The Contractor shall acknowledge receipt of each work assignment by returning to the Contracting Officer a signed copy of the work assignment within five (5) calendar days after its receipt. The Contractor shall begin work immediately upon receipt of a work assignment. Within 15 calendar days after receipt of a work assignment, the Contractor shall submit one (1) copies of a work plan to the Contracting Officer's Representative and one (1) copies to the Contracting Officer. The work plan shall include a detailed technical and staffing plan and a detailed cost estimate. Within 45 calendar days after receipt of the work plan, the Contracting Officer will provide written approval or disapproval of it to the Contractor. If the Contractor has not received approval on a work plan within 45 calendar days after its submission, the Contractor shall stop work on that work assignment. Also, if the Contracting Officer disapproves a work plan, the Contractor shall stop work until the problem causing the disapproval is resolved. In either case, the Contractor shall resume work only when the Contracting Officer finally approves the work plan.
(d) This clause does not change the requirements of the "Level of Effort" clause, nor the notification requirements of either the "Limitation of Cost" or "Limitation of Funds" clauses.
(e) Work assignments shall not allow for any change to the terms or conditions of the contract. Where any language in the work assignment may suggest a change to the terms or conditions, the Contractor shall immediately notify the Contracting Officer.
(f) Within 20 days of receipt of the work assignment or similar tasking document, the Contractor shall provide a conflict of interest certification. Where work assignments or similar tasking documents are issued under this contract for work on or directly related to a site, the Contractor is only required to provide a conflict of interest certification for the first work assignment issued for that site. For all subsequent work on that site under this contract, the Contractor has a continuing obligation to search and report any actual or potential conflicts of interest, but no additional conflict of interest certifications are required.
Before submitting the conflict of interest certification, the contractor shall search its records accumulated, at a minimum, over the past three years immediately prior to the receipt of the work assignment or similar tasking document. In the COI certification, the Contractor must certify to the best of the Contractor's knowledge and belief that all actual or potential organizational conflicts of interest have been reported to the Contracting Officer or that to the best of the Contractor's knowledge and belief, no actual or potential organizational conflicts of interest exist. In addition, the Contractor must certify that its personnel who perform work under this work assignment or relating to this work assignment have been informed of their obligation to report personal and organizational conflicts of interest to the Contractor. The certification shall also include a statement that the Contractor recognizes its continuing obligation to identify and report any actual or potential conflicts of interest arising during performance of this work assignment or other work related to this site.
B-3 LOCAL CLAUSES EPA-B-16-102 ESTIMATED COST AND FIXED FEE
(a) The estimated cost of this contract is To Be Determined (TBD).
(b) The fixed fee is TBD.
(c) The total estimated cost and fixed fee is TBD.
B-4 LOCAL CLAUSES EPA-B-31-101 OTHER DIRECT COSTS
For the categories listed below, Other Direct Costs in excess of the following are not allowable as a charge to this contract without the prior written approval of the Contracting Officer:
Base Period - TBD.
B-5 LOCAL CLAUSES EPA-B-32-101 LIMITATION OF FUNDS NOTICE
(a) Pursuant to the Limitation of Funds clause, incremental funding in the amount of $TBD is allotted to cover estimated cost. Funding in the amount of $TBD is provided to cover the corresponding increment of fixed fee. The amount allotted for costs is estimated to cover the contractor's performance through TBD.
(b) When the contract is fully funded as specified in the Estimated Cost and Fixed Fee Clause (EPA-B-16- 102), the Limitation of Cost clause shall become applicable.
(c) Recapitulation of Funds
Funding Action Estimated Cost Fixed Fee Total Cost Plus Fixed Fee
(CPFF)
Previous Amount TBD TBD TBD This Modification TBD TBD TBD Total Funded TBD TBD TBD Total Per Contract TBD TBD TBD
SECTION C - Description/Specifications
C-1 EPAAR 1552.211-79 COMPLIANCE WITH EPA POLICIES FOR INFORMATION
RESOURCES MANAGEMENT (JAN 2012)
(a) Definition. Information Resources Management (IRM) is defined as any planning, budgeting, organizing, directing, training, promoting, controlling, and managing activities associated with the burden, collection, creation, use and dissemination of information. IRM includes both information itself and the management of information and related resources such as personnel, equipment, funds, and technology.
Examples of these services include but are not limited to the following:
(1) The acquisition, creation, or modification of a computer program or automated data base for delivery to EPA or use by EPA or contractors operating EPA programs.
(2) The analysis of requirements for, study of the feasibility of, evaluation of alternatives for, or design and development of a computer program or automated data base for use by EPA or contractors operating EPA programs.
(3) Services that provide EPA personnel access to or use of computer or word processing equipment, software, or related services.
(4) Services that provide EPA personnel access to or use of: Data communications; electronic messaging services or capabilities; electronic bulletin boards, or other forms of electronic information dissemination;
electronic record-keeping; or any other automated information services.
(b) General. The Contractor shall perform any IRM-related work under this contract in accordance with the IRM policies, standards, and procedures set forth on the Office of Environmental Information policy Web site. Upon receipt of a work request (i.e. delivery order, task order, or work assignment), the Contractor shall check this listing of directives. The applicable directives for performance of the work request are those in effect on the date of issuance of the work request. The 2100 Series (2100-2199) of the Agency's Directive System contains the majority of the Agency's IRM policies, standards, and procedures.
(c) Section 508 requirements (accessibility). Contract deliverables are required to be compliant with Section 508 requirements (accessibility for people with disabilities). The Environmental Protection Agency policy for 508 compliance can be found at www.epa.gov/accessibility.
(d) Electronic access. A complete listing, including full text, of documents included in the 2100 Series of the Agency's Directive System is maintained on the EPA Public Access Server on the Internet at http://epa.gov/docs/irmpoli8/policies/index.html''.
C-2 LOCAL CLAUSES EPA-C-10-101 STATEMENT OF WORK/PERFORMANCE WORK
STATEMENT/SPECIFICATIONS
The Contractor shall furnish the necessary personnel, material, equipment, services, and facilities (except as otherwise specified), to perform the Statement of Work included in Attachment 1.
http://www.epa.gov/accessibility http://epa.gov/docs/irmpoli8/policies/index.html''
SECTION D - Packaging and Marking
SECTION E - Inspection and Acceptance
E-1 FAR 52.246-5 INSPECTION OF SERVICES - COST REIMBURSEMENT (APR 1984)
E-2 FAR 52.246-11 HIGHER-LEVEL CONTRACT QUALITY REQUIREMENT (DEC 2014)
(a) The contractor shall comply with the higher-level quality standard selected below:
Title Numbering Date Tailoring Specifications and Guidelines for Quality Systems and Environmental Data Collection and Environmental Technology Programs
ANSI/ASQC E4 2014 See below
As authorized by FAR 52.246-11, the higher-level quality standard ANSI/ASQC E4 is tailored as follows:
The solicitation and contract require the offeror/contractor to demonstrate conformance to ANSI/ASQC E4 by submitting the quality documentation described below.
In addition, after award of the contract, the Contractor shall revise, when applicable, quality documentation submitted before award to address specific comments provided by EPA and submit the revised documentation to the Contracting Officer’s Representative.
After award of the contract, the Contractor shall also implement all quality documentation approved by the Government.
A. Pre-award Documentation: The offeror must submit the following quality system documentation as a separate and identifiable part of its technical proposal: (CO, select one or more)
This documentation will be prepared in accordance with the specifications identified above, or equivalent specifications defined by EPA, Project Officer. The offeror shall describe their plan for covering the costs associated with the required documentation. Work involving environmental data generation or use shall not commence until the Government has approved this documentation and incorporated it into the contract.
B. Post-award Documentation: The Contractor shall submit the following quality system documentation to the Contracting Officer’s Representative at the time frames identified below: (CO, select one or more)
CO Documentation Specification Due After
CO
Select
Documentation Specifications
X Quality Management Plan EPA Requirements for Quality Management Plans (QA/R-2) [dated 03/20/01]
Joint Quality Management Plan/Quality Assurance Project Plan for the contract
EPA Requirements for Quality Management Plans (QA/R-2) [dated 03/20/01] and EPA Requirements for Quality Assurance Project Plans (QA/R) [dated 03/20/01]
Programmatic Quality Assurance Project Plan for the entire program (contract)
EPA Requirements for Quality Assurance Project Plans (QA/R-5) [dated 03/20/01]
Other Equivalent:
Select
Quality Management Plan EPA Requirements for Quality Management Plans (QA/R-2) [dated 03/20/01]
Award of contract
Joint Quality Management Plan/Quality Assurance Project Plan for the contract
EPA Requirements for Quality Management Plans (QA/R-2) [dated 03/20/01] and EPA Requirements for Quality Assurance Project Plans (QA/R) [dated 03/20/01]
Award of contract
Quality Assurance Project Plan for the contract
EPA Requirements for Quality Assurance Project Plans (QA/R-5) [dated 03/20/11]
Award of contract
Programmatic Quality Assurance Project Plan for the entire program (contract)
EPA Requirements for Quality Assurance Project Plans (QA/R-5) [dated 03/20/01]
Award of contract
X Quality Assurance Project Plan for each applicable project
EPA Requirements for Quality Assurance Project Plans (QA/R-5) [dated 03/20/01]
Issuance of Statement of Work for the project
Project-specific supplement to Programmatic Quality Assurance Project Plan for each applicable project
EPA Requirements for Quality Assurance Project Plans (QA/R-5) [dated 03/20/01]
Issuance of Statement of Work for the project
Other Equivalent:
This documentation will be prepared in accordance with the specifications identified above or equivalent specifications defined by the EPA Contracting Officer’s Representative. The offeror shall describe their plan for covering the costs associated with the required documentation.
The Government will review and return the quality documentation, with comments, and indicating approval or disapproval. If necessary, the contractor shall revise the documentation to address all comments and shall submit the revised documentation to the government for approval.
The Contractor shall not commence work involving environmental data generation or use until the Government has approved the quality documentation.
(Note: Statement of work includes statements of work to perform projects under work assignments, task orders, delivery orders, etc.)
(b) The contractor shall include applicable requirements of the higher-level quality standard(s) listing in paragraph (a) of this clause and the requirement to flow down such standards, as applicable, to lower-tier subcontracts, in—
(1) Any subcontract for critical and complex items (see 46.203(b) and (c)); or
(2) When the technical requirements of a subcontract require—
(i) Control of such things as design, work operations, in-process control, testing and inspection; or
(ii) Attention to such factors as organization, planning, work instruction, documentation control, and advanced metrology.
SECTION F - Deliveries or Performance
F-1 FAR 52.242-15 STOP-WORK ORDER. (AUG 1989) - ALTERNATE I (APR 1984)
F-2 EPAAR 1552.211-70 REPORTS OF WORK (OCT 2000)
The Contractor shall prepare and deliver reports, including plans, evaluations, studies, analyses and manuals in accordance with the requirements detailed in individual work assignments. Each report shall cite the contract number, identify the U.S. Environmental Protection Agency as the sponsoring agency, and identify the name of the Contractor preparing the report.
The OMB clearance number for progress reports delivered under this contract is 2030-0005.
F-3 EPAAR 1552.211-72 MONTHLY PROGRESS REPORT (SEP 2013)
(a) The Contractor shall furnish one (1) copy of the combined monthly technical and financial progress report stating the progress made, including the percentage of the project completed, and a description of the work accomplished to support the cost. If the work is ordered using work assignments or delivery orders, include the estimated percentage of task completed during the reporting period for each work assignment or delivery order.
(b) Specific discussions shall include difficulties encountered and remedial action taken during the reporting period, and anticipated activity with a schedule of deliverables for the subsequent reporting period.
(c) The Contractor shall provide a list of outstanding actions awaiting Contracting Officer authorization, noted with the corresponding work assignment, such as subcontractor/consultant consents, overtime approvals, and work plan approvals.
(d) The report shall specify financial status at the contract level as follows:
(1) For the current reporting period, display the amount claimed.
(2) For the cumulative period and the cumulative contract life display: the amount obligated, amount originally invoiced, amount paid, amount suspended, amount disallowed, and remaining approved amount.
The remaining approved amount is defined as the total obligated amount, less the total amount originally invoiced, plus total amount disallowed.
(3) Labor hours.
(i) A list of employees, their labor categories, and the numbers of hours worked for the reporting period.
(ii) For the current reporting period, display the expended direct labor hours and costs broken out by EPA contract labor hour category for the prime contractor and each subcontractor and consultant.
(iii) For the cumulative contract period and the cumulative contract life display: the negotiated, expended and remaining direct labor hours and costs broken out by EPA contract labor hour category for the prime contractor, and each subcontractor and consultant.
(iv) Display the estimated direct labor hours and costs to be expended during the next reporting period.
(4) Display the current dollar ceilings in the contract, net amount invoiced, and remaining amounts for the following categories: Direct labor hours, total estimated cost, award fee pool (if applicable), subcontracts by individual subcontractor, travel, program management, and Other Direct Costs (ODCs).
(5) Unbilled allowable costs. Display the total costs incurred but unbilled for the current reporting period and cumulative for the contract.
(6) Average cost of direct labor. Compare the actual average cost per hour to date with the average cost per hour of the approved work plans for the current contract period.
(e) The report shall specify financial status at the work assignment or delivery order level as follows:
(1) For the current period, display the amount claimed.
(2) For the cumulative period display: amount shown on workplan, or latest work assignment/delivery order amendment amount (whichever is later); amount currently claimed; amount paid; amount suspended;
amount disallowed; and remaining approved amount. The remaining approved amount is defined as: the workplan amount or latest work assignment or delivery order amount (whichever is later), less total amounts originally invoiced, plus total amount disallowed.
(3) Labor hours.
(i) A list of employees, their labor categories, and the number of hours worked for the reporting period.
(ii) For the current reporting period, display the expended direct labor hours and costs broken out by EPA contract labor hour category for the prime contractor and each subcontractor and consultant.
(iii) For the current reporting period, cumulative contract period, and the cumulative contract life display:
the negotiated, expended and remaining direct labor hours and costs broken out by EPA contract labor hour category for the prime contractor and each subcontractor and consultant.
(iv) Display the estimated direct labor hours and costs to be expended during the next reporting period.
(v) Display the estimates of remaining direct labor hours and costs required to complete the work assignment or delivery order.
(4) Unbilled allowable costs. Display the total costs incurred but unbilled for the current reporting period and cumulative for the work assignment.
(5) Average cost of direct labor. Display the actual average cost per hour with the cost per hour estimated in the workplan.
(6) A list of deliverables for each work assignment or delivery order during the reporting period.
(f) This submission does not change the notification requirements of the "Limitation of Cost" or "Limitation of Funds" clauses requiring separate written notice to the Contracting Officer.
(g) The reports shall be submitted to the following addresses on or before the 15th of each month following the first complete reporting period of the contract. See EPAAR 1552.232-70, Submission of Invoices, paragraph (e), for details on the timing of submittals. Distribute reports as follows:
The monthly report shall be emailed to the individuals listed in the section G provision entitled, Contract Administration Officials.
F-4 EPAAR 1552.211-75 WORKING FILES (APR 1984)
The Contractor shall maintain accurate working files (by task or work assignment) on all work documentation including calculations, assumptions, interpretations of regulations, sources of information, and other raw data required in the performance of this contract. The Contractor shall provide the information contained in its working files upon request of the Contracting Officer.
F-5 EPAAR 1552.211-78 MANAGEMENT CONSULTING SERVICES (APR 1985)
All reports containing recommendations to the Environmental Protection Agency shall include the following information on the cover of each report: (a) Name and business address of the contractor; (b) contract number; (c) contract dollar amount; (d) whether the contract was subject to full and open competition or a sole source acquisition; (e) name of the EPA Project Officer and the EPA Project Officer's office identification and location; and (f) date of report.
F-6 LOCAL CLAUSES EPA-F-12-101 PERIOD OF PERFORMANCE
The period of performance of this contract shall be from date of award through 12 months plus four (4) one-year option periods exclusive of all required reports.
SECTION G - Contract Administration Data
G-1 EPAAR 1552.216-74 PAYMENT OF FEE (MAY 1991)
(a) The term fee in this clause refers to either the fixed fee under a cost-plus-fixed-fee type contract, or the base fee under a cost-plus-award-fee type contract.
(b) The Government will make provisional fee payments on the basis of percentage of work completed.
Percentage of work completed is the ratio of direct labor hours performed to the direct labor hours set forth in clause 1552.211-73, Level of Effort-Cost-Reimbursement Term Contract.
G-2 EPAAR 1552.232-70 SUBMISSION OF INVOICES (JUN 1996)
In order to be considered properly submitted, an invoice or request for contract financing payment must meet the following contract requirements in addition to the requirements of FAR 32.905:
(a) Unless otherwise specified in the contract, an invoice or request for contract financing payment shall be submitted as an original and five copies. The Contractor shall submit the invoice or request for contract financing payment to the following offices/individuals designated in the contract: the original and two copies to the Accounting Operations Office shown in Block 25 on the cover of the contract; two copies to the Contracting Officer's Representative (the Contracting Officer's Representative may direct one of these copies to a separate address); and one copy to the Contracting Officer.
(b) The Contractor shall prepare its invoice or request for contract financing payment on the prescribed Government forms. Standard Forms Number 1034, Public Voucher for Purchases and Services other than Personal, shall be used by contractors to show the amount claimed for reimbursement. Standard Form 1035, Public Voucher for Purchases and Services other than Personal-Continuation Sheet, shall be used to furnish the necessary supporting detail or additional information required by the Contracting Officer. The Contractor may submit self-designed forms which contain the required information.
(c)(1) The Contractor shall prepare a contract level invoice or request for contract financing payment in accordance with the invoice preparation instructions identified as a separate attachment in Section J of the contract. If contract work is authorized by individual work assignments, the invoice or request for contract financing payment shall also include a summary of the current and cumulative amounts claimed by cost element for each work assignment and for the contract total, as well as any supporting data for each work assignment as identified in the instructions.
(2) The invoice or request for contract financing payment shall include current and cumulative charges by major cost element such as direct labor, overhead, travel, equipment, and other direct costs. For current costs, each major cost element shall include the appropriate supporting schedule identified in the invoice preparation instructions.
Cumulative charges represent the net sum of current charges by cost element for the contract period.
(3) The charges for subcontracts shall be further detailed in a supporting schedule showing the major cost elements for each subcontract. The degree of detail for any subcontract exceeding $5,000 is to be the same as that set forth under (c)(2).
(4) The charges for consultants shall be further detailed in the supporting schedule showing the major cost elements of each consultant. For current costs, each major cost element of the consulting agreement shall also include the supporting schedule identified in the invoice preparation instructions.
(d) Invoices or requests for contract financing payment must clearly indicate the period of performance for which payment is requested. Separate invoices or requests for contract financing payment are required for charges applicable to the basic contract and each option period.
(e)(1) Notwithstanding the provisions of the clause of this contract at FAR 52.216-7, Allowable Cost and Payment, invoices or requests for contract financing payment shall be submitted once per month unless there has been a demonstrated need and Contracting Officer approval for more frequent billings. When submitted on a monthly basis, the period covered by invoices or requests for contractor financing payments shall be the same as the period for monthly progress reports required under this contract.
(2) If the Contracting Officer allows submissions more frequently than monthly, one submittal each month shall have the same ending period of performance as the monthly progress report.
(3) Where cumulative amounts on the monthly progress report differ from the aggregate amounts claimed in the invoice(s) or request(s) for contract financing payments covering the same period, the contractor shall provide a reconciliation of the difference as part of the payment request.
G-3 EPAAR 1552.242-70 INDIRECT COSTS (APR 1984)
(a) In accordance with paragraph (d) of the "Allowable Cost and Payment" clause, the final indirect cost rates applicable to this contract shall be established between the Contractor and the appropriate Government representative (EPA, other Government agency, or auditor), as provided by FAR 42.703-1(a).
EPA's procedures require a Contracting Officer determination of indirect cost rates for its contracts. In those cases where EPA is the cognizant agency (see FAR 42.705-1), the final rate proposal shall be submitted to the cognizant audit activity and to the following designated Contracting Officer:
Environmental Protection Agency, Chief, Cost Policy and Rate Negotiation Branch (3804F), Cost Advisory and Financial Analysis Division, Washington, DC 20460.
Where EPA is not the cognizant agency, the final rate proposal shall be submitted to the above-cited address, to the cognizant audit agency, and to the designated Contracting Officer of the cognizant agency.
Upon establishment of the final indirect cost rates, the Contractor shall submit an executed Certificate of Current Cost or Pricing Data (see FAR 15.406-2) applicable to the data furnished in connection with the final rates to the cognizant audit agency. The final rates shall be contained in a written understanding between the Contractor and the appropriate Government representative. Pursuant to the "Allowable Cost and Payment" clause, the allowable indirect costs under this contract shall be obtained by applying the final agreed upon rate(s) to the appropriate bases.
(b) Until final annual indirect cost rates are established for any period, the Government shall reimburse the contractor at billing rates established by the appropriate Government representative in accordance with FAR 42.704, subject to adjustment when the final rates are established. The established billing rates are currently as follows:
Cost center TBD Period TBD Rate TBD Base TBD
These billing rates may be prospectively or retroactively revised by mutual agreement, at the request of either the Government or the Contractor, to prevent substantial overpayment or underpayment.
(c) Notwithstanding the provisions of paragraphs (a) and (b) of this clause, ceilings are hereby established on indirect costs reimbursable under this contract. The Government shall not be obligated to pay the Contractor any additional amount on account of indirect costs in excess of the ceiling rates listed below:
Cost center TBD Period TBD Rate TBD Base TBD
G-4 EPAAR 1552.245-70 GOVERNMENT PROPERTY (SEP 2009)
(a) The contractor shall not fabricate or acquire, on behalf of the Government, either directly or indirectly through a subcontract, any item of property without prior written approval from the Contracting Officer. If the Contracting Officer authorizes the contractor to acquire and/or fabricate equipment for use in the performance of this contract, the equipment shall be subject to the provisions of the ``Government Property'' clause and listed on the contract via contract modification.
(b) If the Government provides item(s) of Government property to the contractor for use in the performance of this contract, this property shall be used and maintained by the contractor in accordance with the provisions of the ``Government Property'' clause.
The ``EPA Contract Property Administration Requirements'' provided below apply to this contract.
U.S. Environmental Protection Agency
Contract Property Administration Requirements
1. Purpose. This document sets forth the requirements for the U.S. Environmental Protection Agency (EPA) contractors performing Government property management responsibilities under EPA contracts.
These requirements supplement those contained in the Government Property clause(s) and Part 45 Government Property of the Federal Acquisition Regulation (FAR).
2. Contract Property Administration (CPAR)
a. EPA Delegation. EPA delegates all contract property administration to the EPA Contract Property Coordinator (CPC). The delegations apply to all EPA contracts issued with or that have the potential to receive, purchase or acquire Government Property or include the Government Property clauses. In addition to administering all contract property, the CPC provides technical expertise and assistance to the Contracting Officer (CO) and Contracting Officer Technical Representative (COTR) relative to Government Property.
b. DCMA Re-delegation. The CPC may request support for contract property management oversight, including property administration and plant clearance, from the Defense Contract Management Agency (DCMA). If DCMA agrees to provide support, DCMA will notify the contractor of the assigned property administrator (PA) and plant clearance officer (PLCO). The DCMA PA is available to the contractor for assistance in all matters of property administration. Notwithstanding the delegation, as necessary, the contractor may contact the EPA CO. In the event of a disagreement between the contractor and the DCMA PA, the contractor should seek resolution from the CO. Unless, otherwise directed in the contract, or this document, all originals of written information or reports, except direct correspondence between the contractor and the DCMA PA, relative to Government property, should be forwarded to the administrative CO assigned to this contract and the CPC.
c. Disagreements. Notwithstanding the delegation(s), as necessary, the contractor may contact the CO. In the event of a disagreement between the contractor and the PA or the CPC the contractor should seek resolution from the CO.
3. Requests for Government Property.
In accordance with FAR 45.102, the contractor shall furnish all property required for performing Government contracts. If a contractor believes that Government property is required for performance of the contract, the contractor shall submit a written request to the CO. At a minimum, the request shall contain the following elements:
a. Contract number for which the property is required.
b. An item(s) description, quantity and estimated cost.
c. Certification that no like contractor property exists which could be utilized.
d. A detailed description of the task-related purpose of the property.
e. Explanation of negative impact if property is not provided by the Government.
f. Lease versus purchase analysis shall be furnished with the request to acquire property on behalf of the Government, with the exception of requests for material purchases. The contractor may not proceed with acquisition of property on behalf of the Government until receipt of written authorization from the Contracting Officer.
4. Transfer of Government Property. The Contracting Officer initiates the transfer of the government property via a contract modification. The transferor (EPA or another contractor) shall provide to the transferee, the receiving contractor, the information needed to establish and maintain the property records required of FAR 52.245-1, as well as all of the applicable data elements required by Attachment 1 of this clause.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .