Presentation_on_the_Least_Cost_Energy_Plan,_LEDS,_November_2014.pptx
PPTX presentation 824 KB Posted
- Attached to
- Market Liberalization & Electricity Trade Program (MLET) Federal contract opportunity
- Solicitation number
- SOL-111-17-000003
- Issued by
- US Agency for International Development
About this file
7.8 Presentation on the Least Cost Energy Plan, LEDS, November 2014
View the file
Other files for this federal contract opportunity
Show all 20
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Prepared by: USAID/LEDS/Tetra Tech, USAID/SRIE
28 November 2014 Armenia Least Cost Energy Development Program
Content Project Description MARKAL Model Structure Objectives Primary data Macroeconomic development data Technical/technology data Reference scenario Considered sensitivity scenarios Results Conclusions
Project Description
| The Project was developed within the scope of the USAID projects “Low Emissions Strategies and Clean Energy Development in E&E” led by Tetra Tech and USAID grant “Support to National and Regional Energy Planning and Capacity Building at the Scientific Research Institute of Energy“. |
| The MARKAL-Armenia model has been applied therein. The model was developed as a result of four-year research efforts of the SRIE team assisted by the USAID. |
MARKAL model structure
Demand Sectors
Industry Commercial Residential Agriculture
National Model
Energy Service Demand Projections
Energy Balance
Planning Horizon & System Settings
Fuel and Market Share Limits Supply Sector Secondary Energy Resources Primary Local & Imported Resources
Transport*
Future Resource Supply and Technologies
Start with an initial energy balance along with the complete suite of existing power plants and an estimate of the current device stock.
Future resource supply and technology options are assembled by the model to meet demand projections at least cost Reflects anticipated economic and demographic activity, and environmental and policy constraints.
Selection of least-cost generation capacities till 2036, considering the following:
The principles specified in the officially approved documents, including:
Ensuring reasonable level of energy security and independence of the country Reliable supply of energy carriers to the local market consumers at the lowest price possible Realization of energy efficiency and renewable energy potential Expansion of regional cooperation Generation and consumption technologies available in the market Infrastructural and technological restrictions Sensitivity analysis Objectives
Official documents reflecting the RoA energy strategy:
The RoA Long-term Development Strategy Program for 2014-2025, the GoA, March 27, 2014 Energy Security Concept of the RoA, approved by the RoA President on October 29, 2013 Financial Cooperation Agreement between the GoA and Germany Renewable Energy Roadmap for Armenia, Renewable Resources and Energy Efficiency Fund, May 2011 Sustainable Development Program, approved by the GoA on October 30, 2008 Action Plan of the RoA Ministry of Energy stipulated by the RoA National Security Strategy provisions, the RoA Ministry of Energy, the GoA, November 01, 2007 The RoA Energy Efficiency and Renewable Energy National Program, the GoA, January 18, 2007 Energy Sector Development Strategy within the Context of the RoA Economy Development, the GoA, June 23, 2005 Iran-Armenia Electricity-Gas Exchange Inter-State Agreements Memorandum of Partnership between the Ministries of Energy of Armenia, Iran and Georgia, September 29, 2006
Primary Data (Strategic Documents)
Macroeconomic data
| Annual growth | 2015 | 2018 | 2021 | 2024 | 2027 | 2030 | 2033 | 2036 | Source |
| GDP | 5.70% | 5.70% | 5.70% | 5.70% | 3.00% | 3.00% | 3.00% | 3.00% | World Bank |
| Population | 0.175% | 0.024% | 0.024% | -0.215% | -0.215% | -0.215% | -0.275% | -0.275% | GoA |
| Residential | 203% (3.0%) |
| Commercial | 201% (2.9%) |
| Industry | 245% (3.8%) |
| Agriculture | 173% (2.3%) |
Transport
| Passenger | 161% (2.0%) |
| Freight | 254% (4.0%) |
Useful energy demand growth for whole planning period Change in Household conditions during planning period (24 years)
| Number of persons per dwelling | -14% (3.76 –> 3.24) | |
| Number of dwellings | +12% |
Macroeconomic indicators
Residential 2012 2015 2018 2021 2024 2027 2030 2033 2036 20.918733870352703 23.553480827500159 26.274929294900989 29.367893093567574 32.768812497064587 35.019598671988788 37.313661407328041 39.751237755692138 42.373851945520435 Commercial 2012 2015 2018 2021 2024 2027 2030 2033 2036 9.816509895504554 11.143412396609953 12.657280071783866 14.376569745591242 16.017323828184004 16.960240817957033 17.859532648037241 18.774035884505139 19.706532765664129 Industry 2012 2015 2018 2021 2024 2027 2030 2033 2036 11.274998562051838 13.063411024484983 15.135497060638214 17.53625227310178 20.317809355968468 21.944160108925129 23.700693044680282 25.597828671040908 27.646821611363688 Agriculture 2012 2015 2018 2021 2024 2027 2030 2033 2036 1.8047336637239497 1.9789819466194121 2.1700540216911488 2.3795742377045372 2.6093237754212115 2.7285134453313198 2.8531475056797033 2.9834746473744587 3.1197549211202187
PJ
Technical/Technological Data
| Swap levels | 2015 | 2018 | 2021 | 2024 | 2027 | 2030 | 2033 | 2036 |
| Electricity export (GWh) | 1,200 | 6,000 | 6,900 | 6,900 | 6,900 | 6,900 | 6,900 | 6,900 |
| Natural gas import (mln. cm) | 405 | 2,000 | 2,300 | 2,300 | 2,300 | 2,300 | 2,300 | 2,300 |
Iran – Armenia Electricity - gas swap
| Gas pipeline | Daily maximum capacity, mln. cm | Annual maximum capacity, bln. cm |
| North-South pipeline | 10 | 3.65 |
| Iran-Armenia pipeline | 8 | 2.30 |
| Total | 18 | 5.95 |
European gas prices are based on World energy outlook 2013
Russian gas price stated according to Russian-Armenian Intergovernmental Agreement, which assumes 65% Russian wholesale gas price, and 35% CPI-U
Capacities of gas pipelines of RA
Natural Gas Import Prices, $/1000 cub.m European
| 2012 | 2015 | 2018 | 2021 | 2024 | 2027 | 2030 | 2033 | 2036 | 189 | 189 | 189 | 324 | 460 | 471 | 481 | 495 | 508 | Russian |
| 2012 | 2015 | 2018 | 2021 | 2024 | 2027 | 2030 | 2033 | 2036 | 189 | 189 | 189 | 243 | 274 | 297 | 315 | 335 | 355 |
| Season/Time of day | Day | Night | Peak |
| Winter | 0.047 | 0.030 | 0.047 |
| Spring | 0.023 | 0.011 | 0.023 |
| Summer | 0.044 | 0.023 | 0.044 |
| Fall | 0.047 | 0.030 | 0.047 |
| Season | 24 hour |
| Winter | 0.053 |
| Spring | 0.034 |
| Summer | 0.045 |
| Fall | 0.055 |
Import price(EUR/kWh) Export price(EUR/kWh) Armenia-Georgia electricity exchange prices, 2012 Note:
Import prices are growing 2% annually.
Export prices are constant till 2021, afterwards 2% growth for each three years.
| Indicator | PWR-1000 | CANDU-6 | SMR | ANPP life extension |
| Investment, Million € | 4,073.19 | 1,622.21 | 1,633.20 | 227.38 |
| Efficiency | 0.342 | 0.332 | 0.340 | 0.300 |
| Fixed O&M cost, Million €/year | 54.70 | 38.46 | 24.83 | 25.44 |
| Fresh fuel cost, €/MWh | 5.23 | 2.21 | 5.88 | 8.97 |
| Spent fuel cost, €/MWh | 1.34 | 4.05 | 0.78 | 0.52 |
| Variable O&M cost, €/MWh | 0.51 | 0.55 | 0.66 | 0.43 |
| Total variable O&M cost, €/MWh | 1.85 | 4.60 | 1.44 | 0.94 |
| Unit capacity, MW | 1028 | 670 | 360 | 385 |
| Specific investment cost per kW, €/kW | 3,962.24 | 2,421.21 | 4,536.68 | 590.59 |
| Specific fixed cost per kW, €/kW/year | 53.21 | 57.41 | 68.97 | 66.08 |
| Annual maximum generation, GWh/year | 8,105 | 5,282 | 2,838 | 2,277 |
| Construction period, years | 6 | 6 | 4 | 1 |
Nuclear technologies
| Indicator | Meghri HPP | Loriberd HPP | Shnokh HPP | Small HPPs |
| Capacity, MW | 130 | 66 | 70 | 148 |
| Efficiency | 0.88 | 0.88 | 0.875 | 0.9 |
| Specific investment cost, €/kW | 0 | 1,620 | 1,810 | 910 (1,137 after 2021) |
| Specific fixed cost, €/kW/year | 28.32 | 12.52 | 15.03 | 18.87 (23.59 after 2021) |
| Variable cost, €/MWh | 0.57 | 0.433 | 0.433 | 0.2 |
| Construction period, years | 5 | 4 | 4 | 2 |
| Annual maximum generation, GWh/year | 800 | 212 | 270 | 527 |
| Investment, Million € | 0 | 106.9 | 126.7 | 134.7 - 168.2 |
Hydro technologies
| Indicator | Geothermal | Solar PV | Wind |
| Maximum capacity, MW | 30 | up to 70 | up to 200 |
| Specific investment cost per kW, €/kW | 2,335 | 2,037 [1000] | 1,960 [1,400] |
| Specific fixed cost per kW, €/kW/year | 194 | 29 | 40 |
| Variable O&M cost, €/MWh | 1.2 | 0 | 0 |
| Annual maximum generation, GWh/year | 194 | 145 | 527 |
| Investment, Million € | 70.1 | 153.6 | 392 |
Alternative technologies
| Indicator | Natural gas CCGT |
| Unit capacity, MW | 220/400 |
| Efficiency | 0.49 |
| Specific investment cost per kW, €/kW | 780 |
| Specific fixed cost per kW, €/kW/year | 30 |
| Variable O&M cost, €/MWh | 1.53 |
| Annual maximum generation, GWh/year | 1,760/3,200 |
| Investment, Million € | 171.6/312 |
Decommissioning of Hrazdan TPP’s 1-4 units in 2019 is planned according to “Action Plan” based on the “Concept of Ensuring Energy Security of RA”. Hrazdan 5 unit will remain in operation.
Thermal technologies
Reference Scenario
SWAP
Electricity import from Georgia
Nuclear
ANPP life time extension through 2026, construction of new nuclear unit in 2027
Reference
Gas price SWAP
International gas price
Forced till 2027 according to agreement, optional after 2027
Up to 2 billion kWh of power flow
CANDU - Excluded from Further Considerations Initial runs of Markal model demonstrate that CANDU 670 MW reactors are the least-cost option in all scenarios where the nuclear technology is selected.
However, the CANDU reactor is excluded from further consideration, since it is deemed technologically inacceptable for Armenia.
Main Results
| Indicator | 2012 | 2036 | Annual growth (%) | Total growth (%) |
| Primary energy (ktoe) | 3141 | 6116 | 2.81% | 94.67% |
| Import (ktoe) | 2930 | 5449 | 2.62% | 85.96% |
| Primary energy consumption (ktoe) | 1932 | 3534 | 2.55% | 82.88% |
| Electricity consumption, GWh | 5118 | 8317 | 2.04% | 63.51% |
| Generation capacity (MW) | 2589 | 3767 | 1.57% | 45.46% |
| CO2 emissions (Gg) | 5194 | 6919 | 1.20% | 33.21% |
| GDP energy intensity (toe/€000 GDP) | 0.25 | 0.16 | -1.72% | -34.05% |
| Energy consumption per capita (toe/person) | 0.59 | 1.12 | 2.71% | 90.04% |
Reference scenario
Final Energy Consumption Energy final consumption by energy carriers Energy final consumption by sectors
Biofuels 2012 2015 2018 2021 2024 2027 2030 2033 2036 Reference 0 28.183142659246652 32.102510210418188 35.969332919343607 54.617975112851923 57.271489646277558 99.001647997324838 116.30323150779795 134.3858224462011 Biomass 2012 2015 2018 2021 2024 2027 2030 2033 2036 Reference 11.9420096013757 11.9420096013757 11.9420096013757 11.9420096013757 11.9420096013757 11.9420096013757 11.9420096013757 11.9420096013757 11.9420096013757 Bunker Fuel 2012 2015 2018 2021 2024 2027 2030 2033 2036 Reference 31.990255320165222 38.567914208602964 48.059423439776324 59.796030476008411 74.317514151281273 83.450763094413404 93.634908882466505 105.00370202297621 117.6956698273184 Coal 2012 2015 2018 2021 2024 2027 2030 2033 2036 Reference 1.8701187035754345 1.4712555828894858 0.84549427977739955 0.56366285318493303 0.28183142659246652 0 0 0 0 Diesel 2012 2015 2018 2021 2024 2027 2030 2033 2036 Reference 118.87076357209365 162.65733597649793 207.45659079509858 254.28121044209286 288.2466741503257 311.09890372351805 290.06902481549548 338.06873820726463 386.46253791587958 Electricity 2012 2015 2018 2021 2024 2027 2030 2033 2036 Reference 440.03916979149164 462.99171224533563 501.10821849100665 541.82808282977771 589.59850963720112 618.40502519763891 643.17514151281318 672.44261864386397 715.09708853805841 Gas 2012 2015 2018 2021 2024 2027 2030 2033 2036 Reference 1115.5676037163516 1209.9644128113846 1301.237192194701 1411.2278774272118 1514.574028517515 1573.7753469153754 1658.4203109699274 1710.4373163916 1763.3428073276143 Gasoline 2012 2015 2018 2021 2024 2027 2030 2033 2036 Reference 190.75210776469441 189.41937949318071 211.79870548615875 233.64064104707501 253.83457928300135 266.83226253313887 308.4286703766503 354.64424753397458 404.46869999283399 Heat 2012 2015 2018 2021 2024 2027 2030 2033 2036 Reference 10.258186247581726 8.1181781270151898 5.9757816045283993 3.8286082782010493 1.6838233537939729 0 0 0 0 LPG 2012 2015 2018 2021 2024 2027 2030 2033 2036 Reference 10.941269196780413 7.2750722491580762 4.1582077431990188 1.0389548353196858 0 0 0 0 0 Oil (HFO, KER, AVF) 2012 2015 2018 2021 2024 2027 2030 2033 2036 Reference 0 0 0 0 0 0 0 0 0 Renewables (SOL, GEO) 2012 2015 2018 2021 2024 2027 2030 2033 2036 Reference 0 5.8688910649884091E-5 2.8734669922854571E-2 5.7434605244930576E-2 8.6137648212281065E-2 0.11479652934151752 0.14344946377988477 0.17210804557070841 0.20077216348611118 ktoe
Agriculture 2012 2015 2018 2021 2024 2027 2030 2033 2036 Reference 55.222240798681511 61.209964412811296 67.694475626358283 74.857292985263484 82.758126537533556 87.238768539969726 91.922424705629311 96.854474670997476 102.04686044567568 Commercial 2012 2015 2018 2021 2024 2027 2030 2033 2036 Reference 239.73584274761717 266.71556153999336 296.31854653760473 331.26751060357253 363.97710122448524 381.4349518737007 397.06704244190149 414.61663860037191 431.20208268647372 Industrial 2012 2015 2018 2021 2024 2027 2030 2033 2036 Reference 356.09400749958144 412.75375868145818 477.67147888853253 552.15486346074567 624.75916301571419 674.63441028739555 728.9402144947793 788.40439858470347 855.2556784255637 Residential 2012 2015 2018 2021 2024 2027 2030 2033 2036 Reference 632.73685787167051 687.05089975050657 739.18031936542422 793.47650764204889 849.48275740597876 895.1925101736831 913.73403972695655 952.99624430826941 1003.6513666776121 Territories Electricity Demand 2012 2015 2018 2021 2024 2027 2030 2033 2036 Reference 0 0 0 0 0 0 0 0 0 Transportation 2012 2015 2018 2021 2024 2027 2030 2033 2036 Reference 648.47978217774414 692.86284636408686 744.04885175903303 802.52215242780926 868.19842843153504 884.37985144139952 973.10898277962099 1056.1369987341452 1141.4531037282943 ktoe
Energy Intensity of GDP In 2036 by energy intensity of GDP Armenia will reach current levels of such countries as Czech Republic, Brazil, Poland, etc.
Reference 2012 2015 2018 2021 2024 2027 2030 2033 2036 0.24959437824375066 0.23195281159478576 0.21533973829308359 0.20033674164352275 0.1852436285049594 0.17765065383371387 0.17269266395766045 0.16843421601916106 0.16460356342999577 ktoe/ M 2012Euro
Natural Gas Consumption Transmission capacity of existing gas pipelines is sufficient
Natural Gas Import
Availability of 1000 MW ANNU and Iran-Armenia electricity-gas swap brings to the drastic reduction of gas import from Russia The RoA Energy Sector significantly reduces gas price risks
Generation Capacities by Power Plant
| Power plant, MW | 2012 | 2015 | 2018 | 2021 | 2024 | 2027 | 2030 | 2033 | 2036 |
| Armenian NPP | 385 | 385 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| Lifetime extension of existing plant | 0 | 0 | 385 | 385 | 385 | 0 | 0 | 0 | 0 |
| Geothermal power plant | 0 | 0 | 0 | 30 | 30 | 30 | 30 | 30 | 30 |
| Hrazdan 5 - CCGT | 440 | 440 | 440 | 440 | 440 | 440 | 440 | 440 | 440 |
| Hrazdan TPP | 370 | 370 | 370 | 0 | 0 | 0 | 0 | 0 | 0 |
| Lori Wind Farm | 2.6 | 2.6 | 2.6 | 2.6 | 2.6 | 2.6 | 2.6 | 2.6 | 2.6 |
| Loriberd HPP | 0 | 0 | 0 | 66 | 66 | 66 | 66 | 66 | 66 |
| Meghri HPP | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 130 | 130 |
| New gas-fired power plant 220 MW | 0 | 0 | 0 | 220 | 220 | 220 | 220 | 220 | 220 |
| New gas-fired power plant 400 MW | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| New Small HPPs | 0 | 60 | 120 | 148.1 | 148.1 | 148.1 | 148.1 | 148.1 | 148.1 |
| New Wind Farms | 0 | 0 | 50 | 100 | 150 | 200 | 200 | 200 | 200 |
| New NPP VVER 1000, AES-92 | 0 | 0 | 0 | 0 | 0 | 1028 | 1028 | 1028 | 1028 |
| Sevan-Hrazdan HPP cascade | 550 | 550 | 550 | 550 | 550 | 550 | 550 | 550 | 550 |
| Shnokh HPP | 0 | 0 | 0 | 70 | 70 | 70 | 70 | 70 | 70 |
| Small HPPs | 221.8 | 221.8 | 221.8 | 221.8 | 221.8 | 221.8 | 221.8 | 221.8 | 221.8 |
| Solar PV | 0 | 0 | 20 | 40 | 40 | 40 | 40 | 40 | 40 |
| Vorotan HPP cascade | 400 | 400 | 400 | 400 | 400 | 400 | 400 | 400 | 400 |
| Yerevan CCGT | 220 | 220 | 220 | 220 | 220 | 220 | 220 | 220 | 220 |
| Total | 2589 | 2649 | 2779 | 2894 | 2944 | 3637 | 3637 | 3767 | 3767 |
| El. Import from Georgia (2 billion kWh) | 11 | 125 | 250 | 250 | 250 | 250 | 250 | 250 | 250 |
Electricity Generation by Power Plant
| Power plant, GWh | 2012 | 2015 | 2018 | 2021 | 2024 | 2027 | 2030 | 2033 | 2036 |
| Electricity exports | -1696 | -1201 | -6004 | -6905 | -6905 | -6905 | -6905 | -6905 | -6905 |
| Electricity imports | 98 | 1098 | 2190 | 2190 | 2190 | 2190 | 2190 | 2190 | 2190 |
| Hrazdan 5 - CCGT | 892 | 299 | 3276 | 2833 | 3307 | ||||
| Hrazdan TPP | 722 | 839 | |||||||
| New CCGT 220 MW | 1754 | 1754 | |||||||
| Yerevan CCGT | 1614 | 1638 | 1638 | 1638 | 1638 | 1143 | 1434 | 1062 | 1582 |
| Loriberd HPP | 212 | 212 | 212 | 212 | 212 | 212 | |||
| Meghri HPP | 720 | 720 | |||||||
| New Small HPPs | 220 | 441 | 544 | 544 | 544 | 544 | 544 | 544 | |
| Sevan-Hrazdan HPP cascade | 633 | 472 | 472 | 472 | 472 | 472 | 472 | 472 | 472 |
| Shnokh HPP | 270 | 270 | 270 | 270 | 270 | 270 | |||
| Small HPPs | 558 | 558 | 558 | 558 | 558 | 558 | 558 | 558 | 558 |
| Vorotan HPP cascade | 1119 | 1119 | 1119 | 1119 | 1119 | 1119 | 1119 | 1119 | 1119 |
| Armenian NPP | 2123 | 2123 | |||||||
| Lifetime extension of ANPP | 2123 | 2123 | 2123 | ||||||
| New NPP PWR 1000 | 7895 | 7895 | 7895 | 7895 | |||||
| Geothermal power plant | 194 | 194 | 194 | 194 | 194 | 194 | |||
| Lori Wind Farm | 3 | 3 | 3 | 3 | 3 | 3 | 3 | 3 | 3 |
| New Wind Farms | 132 | 264 | 395 | 527 | 527 | 527 | 527 | ||
| Solar PV | 41 | 83 | 83 | 83 | 83 | 83 | 83 | ||
| Total | 6067 | 6331 | 6830 | 7354 | 7959 | 8307 | 8598 | 8946 | 9466 |
Electricity Generation by Power Plant Type
Power Generation Structure During the period of observation the RoA Energy Sector changed from being mostly thermal (42%) to nuclear (48%)
Electricity Exports under the Swap Agreement Electricity exports to Georgia are not realized due to economic reasons Forced Proposed by model
Electricity exports 2012 2015 2018 2021 2024 2027 2030 2033 2036 1696.1539325037584 1200.8046526069388 6003.8843774630304 6904.5017554754004 6904.4739783610676 6904.4739783610676 6904.5017554754004 6904.4462012467357 6904.4739783610676 GWh
| Years | CCGT 220 | PWR 1000 | ANPP lifetime extension | Hydro | Renewables | Total |
| mln Euro | ||||||
| 2014 | 50.0 | 50.0 | ||||
| 2015 | 70.0 | 56.6 | 126.6 | |||
| 2016 | 107.4 | 107.4 | ||||
| 2017 | 0.0 | |||||
| 2018 | 39.2 | 195.4 | 234.5 | |||
| 2019 | 52.0 | 78.4 | 130.4 | |||
| 2020 | 103.3 | 91.4 | 194.8 | |||
| 2021 | 16.6 | 52.2 | 249.3 | 318.1 | ||
| 2022 | 737.7 | 737.7 | ||||
| 2023 | 398.9 | 398.9 | ||||
| 2024 | 1011.5 | 98.0 | 1109.5 | |||
| 2025 | 1229.1 | 1229.1 | ||||
| 2026 | 820.4 | 820.4 | ||||
| 2027 | 720.2 | 98.0 | 818.2 | |||
| Total | 172.0 | 4917.7 | 227.4 | 261.2 | 697.2 | 6275.5 |
For realization of the Least-Cost Strategy the country should invest € 6,275,500,000 within 13 years including the interest during construction (IDC) Investment requirements
Scenario Options EE promotion – Energy efficiency promotion via Hurdle rates
EE target – Target of final energy consumption reduction by 8 % in 2027
EE & RE
EE promotion
EE target of 8%
Gas price
Electricity imports from Georgia
Nuclear
No life extension of existing ANPP in 2017
No new nuclear unit
SWAP
Optional till 2036
No Swap after 2027
Russian low price
Limit up to 1000 GWh
No imports
RE promotion
Scenario Features
| Scenario | ||||||||
| Sensitivity | No Swap after 2027 | Flexible swap | No new NPP | No ANPP LTE | Russian gas | Limited imports | No imports | EE & RE Promotion |
| Reference | ||||||||
| Flexible Swap | √ | |||||||
| Flex Swap and no ANPP life ext. | √ | √ | ||||||
| Flex Swap and less import | √ | √ | ||||||
| Flex Swap and no imports | √ | √ | ||||||
| No Swap after 2027 | √ | |||||||
| No Swap after 2027 and no ANPP life ext | √ | √ | ||||||
| No New NPP | √ | |||||||
| No ANPP life extension | √ | |||||||
| No New NPP and no ANPP life extension | √ | √ | ||||||
| No New NPP and flex Swap | √ | √ | ||||||
| No New NPP, no ANPP Life Ext and flexible swap | √ | √ | √ | |||||
| Less electricity imports | √ | |||||||
| No electricity imports | √ | |||||||
| No imports and no ANPP life extension | √ | √ |
Scenario Features
| Scenario | ||||||||
| Sensitivity | No Swap after 2027 | Flexible swap | No new NPP | No ANPP LTE | Russian gas | Limited imports | No imports | EE & RE Promotion |
| Russian gas at lower price | √ | |||||||
| Russian gas and less imports | √ | √ | ||||||
| Russian gas with less imports and flex Swap | √ | √ | √ | |||||
| Russian gas and no swap after 2027 | √ | √ | ||||||
| Russian gas and no imports | √ | √ | ||||||
| Russian gas and no imports and flex Swap | √ | √ | √ | |||||
| No ANPP life ext. with Russian gas | √ | √ | ||||||
| No New NPP with flex Swap and Russian gas | √ | √ | √ | |||||
| No New NPP, no ANPP Life Ext and Russian Gas | √ | √ | √ | |||||
| No New NPP, no ANPP Life Ext, flex Swap and Russian gas | √ | √ | √ | √ | ||||
| EE Promotion | √ | |||||||
| EE Target | √ | |||||||
| EE Target+ Promotion | √ | |||||||
| RE Promotion | √ |
| EU Gas Price | ||||
| Total energy system cost, M€ | Total electricity production cost, M€ | New generation investment requirements, M€ | Average generation cost, €/MWh | |
| Reference | 33,666 | 17,850 | 6,275 | 56.3 |
| Reference with flexible Swap | 33,552 | 16,089 | 6,104 | 54.3 |
| No ANPP Life extension (LTE) | 34,229 | 19,212 | 6,391 | 60.6 |
| No New NPP | 34,734 | 21,699 | 1,742 | 68.4 |
| No ANPP LTE, No New NPP | 35,179 | 22,584 | 1,545 | 71.2 |
| No ANPP LTE, No import | 34,951 | 24,201 | 6,572 | 66.0 |
| No New NPP, No import | 35,506 | 26,886 | 1,944 | 73.4 |
| No ANPP LTE, No New NPP, No import | 35,928 | 27,573 | 1,655 | 75.4 |
| No ANPP LTE, No New NPP, No import, No swap after 2027 | 36,203 | 21,123 | 1,655 | 69.6 |
| No ANPP LTE, No New NPP, No import, flexible swap | 35,732 | 24,894 | 1,655 | 76.0 |
| No import | 34,478 | 22,831 | 6,690 | 62.3 |
Scenario Results
| Russian Gas Price | ||||
| Total energy system cost, M€ | Total electricity production cost, M€ | New generation investment requirements, M€ | Average generation cost, €/MWh | |
| Reference | 33,666 | 17,850 | 6,275 | 56.3 |
| Reference with Russian gas | 33,202 | 16,971 | 6,275 | 52.4 |
| No ANPP LTE | 33,617 | 17,895 | 6,262 | 55.4 |
| No New NPP | 33,552 | 18,141 | 1,669 | 56.8 |
| No ANPP LTE, No New NPP | 33,854 | 18,420 | 1,473 | 57.4 |
| No ANPP LTE, No import | 34,004 | 21,636 | 6,489 | 58.6 |
| No New NPP, No import | 33,979 | 21,771 | 1,841 | 59.2 |
| No ANPP LTE, No New NPP, No import | 34,258 | 22,284 | 1,614 | 60.6 |
Scenario Results
Capacity Changes Reference vs Scenarios
REFERENCE
CCGT_220
VVER_1000
Capacity Changes Reference vs Scenarios
CCGT_220
VVER_1000
Generation Cost Impacts by Scenarios
Generation cost Reference 2012 2015 2018 2021 2024 2027 2030 2033 2036 37.299999999999997 33.5 43.8 57.2 70.7 60.7 62.6 59.2 60.4 No ANPP LTE 2012 2015 2018 2021 2024 2027 2030 2033 2036 37.299999999999997 33.5 47.7 64.400000000000006 82.5 63.9 65.7 62.3 63.3 No new NPP 2012 2015 2018 2021 2024 2027 2030 2033 2036 37.299999999999997 33.5 43.8 57.2 70.599999999999994 83.8 85.5 82.4 84.7 No import 2012 2015 2018 2021 2024 2027 2030 2033 2036 37.299999999999997 35.700000000000003 46.7 61 76.8 69.099999999999994 70.099999999999994 67 68.599999999999994 €/MWh
Generation Cost Impacts by Technologies
Cost of ANPP & TPPs Generation
New Nuclear Unit Development Schedule
Start date Lining up Financing & Investors Selection of Technology & EPC Contractors Tendering & Selection of Suppliers Licensing & Permitting EPC Construction Schedule Commissioning & Startup Testing 2018.5 2018.5 2019.5 2020 2021 2024 Duration Lining up Financing & Investors Selection of Technology & EPC Contractors Tendering & Selection of Suppliers Licensing & Permitting EPC Construction Schedule Commissioning & Startup Testing 1 1 1 1.5 6.5 5 Start date Lining up Financing & Investors Selection of Technology & EPC Contractors Tendering & Selection of Suppliers Licensing & Permitting EPC Construction Schedule Commissioning & Startup Testing 2018.5 2018.5 2019.5 2020 2021 2024 Lining up Financing & Investors Selection of Technology & EPC Contractors Tendering & Selection of Suppliers Licensing & Permitting EPC Construction Schedule Commissioning & Startup Testing 1 1 1 1.5 6.5 5
Conclusions There is no economically justified alternative to the existing ANPP Life Time Extension (LTE). The ANPP’s generating capacity can be replaced with new thermal generation capacity; however, this approach would result in higher overall costs and higher gas price risk;
In case if the ANPP Life Time is not extended and electricity-gas exchange agreements (swap agreements) are maintained the aggregate system costs for the entire period of planning will increase by €563 mil. mainly due to construction and operation of new 400 MW thermal capacities operated on natural gas;
Maintaining swap agreement after 2027 will result in additional cost savings;
Development of new 1000 MW PWR nuclear unit in 2027 is cost-effective in all scenarios, except for scenario “no SWAP after 2027 and Russian gas”. In this case the cost-effective option is construction of SMR-360 MW in 2027;
Conclusions (cont-ed) Development of new HPPs (Shnokh, Loriberd, Meghri and Small HPPs) is cost-effective option in all considered scenarios;
Development of wind and geothermal energy sources is cost-effective in all scenarios. Solar energy can be developed only under stimulus measures.
To cover the current swap requirements there is a need for installation of 220 MW of additional thermal capacity in 2021. Considering the limited import levels from Georgia, additional 440 MW thermal capacities will be required;
Energy Efficiency Promotion demonstrates fuel and economic savings, but does not result in structural changes in the power sector;
Conclusions (cont-ed) To implement the Least Cost-Resource Strategy Armenia will have to invest EUR 6,275,000,000 over the next 13 years, including investments into the new nuclear unit;
To implement the strategy, Armenia will have to make important decisions and implement the identified steps in a timely manner:
ANPP Life Time Extension Implementation of Iran-Armenia Agreement and extension of the Agreement in 1:3 proportion. Construction of 400 kV Armenia-Iran line Reliable power flows with Georgia; construction of a 400 kV line and a B2B converter Construction of new CCGT Promotion of medium-size HPPs Development of alternative energy within a reasonable scope Ensuring consistency in the ANNU development process Otherwise an alternative strategy would have to be implemented and this will result in cost increase;
We recommend to analyze the CANDU suitability to Armenia.
image1.png oleObject1.bin image2.emf image3.emf image4.png image5.emf image6.emf image7.png image8.png image9.png oleObject2.bin image10.png
Microsoft_Excel_Worksheet1.xlsx Sheet1
Project Implementation Schedule
Task Start date Duration End date
Lining up Financing & Investors 2018.5 1.0 2019
Selection of Technology & EPC Contractors 2018.5 1.0 2019
Tendering & Selection of Suppliers 2019.5 1.0 2020
Licensing & Permitting 2020 1.5 2021
EPC Construction Schedule 2021 6.5 2027
Commissioning & Startup Testing 2024 5.0 2027
Task Start date Duration End date
Lining up Financing & Investors 2018 1.0 2019
Selection of Technology & EPC Contractors 2018 1.0 2019
Tendering & Selection of Suppliers 2019 1.0 2020
Licensing & Permitting 2019 1.5 2021
Project Execution 2020.5 6.5 2027
EPC Construction Schedule 2020.5 6.5 2027
Commissioning & Startup Testing 2022 5.0 2027
Project Implementation Schedule
Start date Lining up Financing & Investors Selection of Technology & EPC Contractors Tendering & Selection of Suppliers Licensing & Permitting EPC Construction Schedule Commissioning & Startup Testing 2018.5 2018.5 2019.5 2020 2021 2024 Duration Lining up Financing & Investors Selection of Technology & EPC Contractors Tendering & Selection of Suppliers Licensing & Permitting EPC Construction Schedule Commissioning & Startup Testing 1 1 1 1.5 6.5 5 Start date Lining up Financing & Investors Selection of Technology & EPC Contractors Tendering & Selection of Suppliers Licensing & Permitting EPC Construction Schedule Commissioning & Startup Testing 2018.5 2018.5 2019.5 2020 2021 2024 Lining up Financing & Investors Selection of Technology & EPC Contractors Tendering & Selection of Suppliers Licensing & Permitting EPC Construction Schedule Commissioning & Startup Testing 1 1 1 1.5 6.5 5
Ծրագրի իրականացման ժամանակացույց
Start date Lining up Financing & Investors Selection of Technology & EPC Contractors Tendering & Selection of Suppliers Licensing & Permitting EPC Construction Schedule Commissioning & Startup Testing 2018.5 2018.5 2019.5 2020 2021 2024 Duration Lining up Financing & Investors Selection of Technology & EPC Contractors Tendering & Selection of Suppliers Licensing & Permitting EPC Construction Schedule Commissioning & Startup Testing 1 1 1 1.5 6.5 5 Start date Lining up Financing & Investors Selection of Technology & EPC Contractors Tendering & Selection of Suppliers Licensing & Permitting EPC Construction Schedule Commissioning & Startup Testing 2018.5 2018.5 2019.5 2020 2021 2024 Lining up Financing & Investors Selection of Technology & EPC Contractors Tendering & Selection of Suppliers Licensing & Permitting EPC Construction Schedule Commissioning & Startup Testing 1 1 1 1.5 6.5 5
File details come from the government source that posted it. Updated .