SOL W911N2-22-Q-0049.pdf

PDF 1 MB Posted

Attached to
CNC tube bender Federal contract opportunity
Solicitation number
w911n222q0049
Issued by
Department of the Army Materiel Command Contracting Command Redstone Arsenal

View the file

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SEE ADDENDUM

(No Collect Calls)

W911N222Q0049 22-Jul-2022

b. TELEPHONE NUMBER

717-267-9481

8. OFFER DUE DATE/LOCAL TIME

02:30 PM 22 Aug 2022

5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

STANDARD FORM 1449 (REV. 2/2012)

Prescribed by GSA – FAR (48 CFR) 53.212

(TYPE OR PRINT)

(SIGNATURE OF CONTRACTING OFFICER)

ADDENDA ARE

26. TOTAL AWARD AMOUNT (For Gov t. Use Only )

23.

CODE 10. THIS ACQUISITION IS

SUCH ADDRESS IN OFFER

17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT

BELOW IS CHECKED

TELEPHONE NO.

W911N29. ISSUED BY

18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a. UNLESS BLOCK

7. FOR SOLICITATION

INFORMATION CALL:

a. NAME

SCOTT A. COY

2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NUMBER

(TYPE OR PRINT)

30b. NAME AND TITLE OF SIGNER 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER

30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a.UNITED STATES OF AMERICA

0 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1. 52.212-4. FAR 52.212-3. 52.212-5 ARE ATTACHED.

25. ACCOUNTING AND APPROPRIATION DATA

1. REQUISITION NUMBER

20.

ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.

OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS

W25G1Q216601E9

ARE NOT ATTACHED

27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED

(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE

SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:

. YOUR OFFER ON SOLICITATION

28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN

% FOR:SET ASIDE:UNRESTRICTED ORX

SMALL BUSINESS

17a.CONTRACTOR/ CODE FACILITY

OFFEROR CODE

LETTERKENNY ARMY DEPOT

LETTERKENNY CONTRACTING OFFICE - ACC-RSA-LEAD

1 OVERCASH AVENUE, ATTN: CCAM-MLK, BLDG 2S

CHAMBERSBURG PA 17201-4150

18a. PAYMENT WILL BE MADE BY CODE

RATED ORDER UNDER

DPAS (15 CFR 700)

13a. THIS CONTRACT IS A

13b. RATING

CODE15. DELIVER TO CODE W25G1Q 16. ADMINISTERED BY

12. DISCOUNT TERMS11. DELIVERY FOR FOB DESTINA-

TION UNLESS BLOCK IS

MARKED

SEE SCHEDULE

14. METHOD OF SOLICITATION

RFQ IFB RFPX

OFFICE OF STRATEGIC MANAGEMENT

BLDG 370 ASRS DOOR 18 AMLD-PLX

LETTERKENNY ARMY DEPOT

CHAMBERSBURG PA 17201-4150

TEL: FAX:

717-2679834FAX:

TEL: SERVICE-DISABLED

VETERAN-OWNED

SMALL BUSINESS

8(A)

HUBZONE SMALL

BUSINESS

SIZE STANDARD:

NAICS:

333517

X

OFFER DATED

29. AWARD OF CONTRACT: REF.

DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY

COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND

EMAIL:

TEL:

31c. DATE SIGNED

SEE SCHEDULE

SCHEDULE OF SUPPLIES/ SERVICESITEM NO. QUANTITY UNIT UNIT PRICE AMOUNT

24.22.21.19.

WOMEN-OWNED SMALL BUSINESS (WOSB)

ELIGIBLE UNDER THE WOMEN-OWNED

SMALL BUSINESS PROGRAM

EDWOSB

32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS

(CONTINUED)

PAGE 2 OF41

ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED: ______________________________________________________

32a. QUANTITY IN COLUMN 21 HAS BEEN

RECEIVED INSPECTED

32b. SIGNATURE OF AUTHORIZED GOVERNMENT

REPRESENTATIVE

32c. DATE 32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT

REPRESENTATIVE

32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f . TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE

37. CHECK NUMBER

FINALPARTIALCOMPLETE

36. PAYMENT35. AMOUNT VERIFIED

CORRECT FOR

34. VOUCHER NUMBER

FINAL

33. SHIP NUMBER

PARTIAL

38. S/R ACCOUNT NUMBER 39. S/R VOUCHER NUMBER 40. PAID BY

41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT

41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE

42a. RECEIVED BY (Print)

42b. RECEIVED AT (Location)

42c. DATE REC'D (YY/MM/DD) 42d. TOTAL CONTAINERS

STANDARD FORM 1449 (REV. 2/2012) BACK

Prescribed by GSA – FAR (48 CFR) 53.212

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

SEE SCHEDULE

20.

SCHEDULE OF SUPPLIES/ SERVICES

21.

QUANTITY UNIT

22. 23.

UNIT PRICE

24.

AMOUNT

19.

ITEM NO.

W911N222Q0049

Section SF 1449 - CONTINUATION SHEET

SOLICITATION NOTES

1. System for Award Management (SAM): In accordance with FAR 4.1102 Policy, Offerors shall be registered in the SAM database in order to be eligible for contract award. No award will be made to an Offeror not registered.

Registration can be accomplished at https://sam.gov/content/entity-registration. Registration in this database shall remain active. There has been a recent SAM requirement for submission of notarized letters for all new vendor registrants, and for renewals of existing registrations. Please check your SAM registration and if the registration is due for renewal in the next few months, it is important to start that process immediately. For additional information on notarized letters, visit https://www.fsd.gov/gsafsd_sp?id=kb_article_view&sysparm_article=KB0016652&sys_kb_id=8cfe46491b1cb8909 ac5ddb6bc4bcbbb&spa=1.

2. Annual Representations and Certifications: In accordance with FAR 4.1201 Policy, Offerors shall complete electronic annual representations and certifications within SAM as part of required registration. Registration in this database shall remain active and can be accessed at https://sam.gov/content/entity-registration.

3. Questions: Questions regarding this solicitation shall be submitted to the Contracting Officer, in writing, at least 10 calendar days prior to the closing date. Questions submitted after this time will be answered at the discretion of the Contracting Officer. The Contracting Officer for this action is Randy Allison, randy.s.allison.civ@army.mil .

Contract specialist for this action is Scott Coy, scott.a.coy2.civ@army .mil.

4. Award without Discussions: The Government intends to award without discussions, offerors should submit their best prices in their initial offer. If FAR Provision 52.212-2 Evaluation-Commercial Products and Commercial Services, is included, Offerors must submit all information requested therein in order for the Government to determine technical acceptability.

5. Amendments: The Offeror shall submit to the Contracting Officer signed copies of all amendments issued to this solicitation. Failure to comply may cause your proposal to be rejected.

6. Payment: Payment for this action will be made by Electronic Funds Transfer (EFT) through the Defense Finance and Accounting Services (DFAS) utilizing Wide Area Work Flow (WAWF). See DFARS 252.232-7006 Wide Area WorkFlow Payment Instructions for more information.

7. Period for Acceptance of Offers: The Offeror agrees to hold the prices in its offer firm for 60 calendar days from the date specified for receipt of offers.

8. FOB Destination: Unless otherwise stated in the solicitation, Offerors shall provide FOB Destination prices.

PURCHASE DESCRIPTION

LETTERKENNY ARMY DEPOT

PURCHASE DESCRIPTION

CNC TUBING BENDER

1.0 General Information:

1.1 Scope:

Request the purchase of one (1) CNC ROTARY-DRAW TUBE BENDER which is capable of bending 1/4” to 2.00” OD x 0.109” wall or greater, mild steel; 1/4” to 2.00”OD x 0.065” wall or greater, stainless steel; 1/4” to 2.00” OD x.120” wall or greater, aluminum; and 1/4” to 2.125” OD x 0.083” wall or greater, copper. The tubing bender shall be setup and started up in accordance with Original Equipment Manufacturer specification and standards. The CNC tubing bender shall include equipment specified in Section 4.0. Other requirements within the specification are training and complete turnkey installation, all required equipment calibration, Operating and Maintenance (O&M) manuals, and shipping to Letterkenny Army Depot (LEAD), Chambersburg, Pennsylvania in accordance with (IAW) the following specifications. This specification establishes the minimum requirements for the purchase of a government installed CNC tubing bender at Letterkenny Army Depot (LEAD). The contractor shall provide all professional architectural, engineering and construction services for the preparation of all necessary drawings, specifications, calculations, cost estimates and related design, permits, fabrication, construction, installation and testing services for the completion of this project. The tubing bender specifications are based upon commercially available products and shall meet or exceed the minimum requirements specified in section 4.0 Specifications. The contractor must address the requirements listed in this purchase description and disclose where in their proposal they address the requirements.

1.2 Place and Performance of Installation: All work shall be performed in building

350 Annex between the hours of 6:00 AM and 3:30 PM, Monday thru Thursday, exclusive of Federal Holidays and special depot closures (typically the Monday before or Thursday after Federal Holidays that fall on a Saturday, Sunday, Tuesday or Thursday). Other hours, weekend, and holiday work will be considered separately as requested by the contractor with adequate advanced notice and approved by the Contracting Officer.

1.3 Security Requirements: Contractor and all associated sub-contractor’s employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Risk Management or Security Office. Contractor workforce shall comply with all personal identity verification requirements as directed by DOD, HQDA and/or local policy. Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes.

The contractor and all associated subcontractor employees shall also comply with adjudication standards and processes using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

1.3.1 Security, Safety and Fire Protection: All work shall comply with LEAD Regulation

385-1 and Pamphlet 385-4. The equipment and the installation shall also meet all the safety criteria set forth in OSHA 1926.501 and ANSI/ASSE Z359.

1.3.2 Media Devices: All pictures shall be taken by LEAD representative and approved before release.

1.3.3 AT Level I Awareness Training: This standard language is for contractor employees with an area of performance within an Army controlled installation, facility or area. All contractor employees, to include subcontractor employees, requiring access to Army installations, facilities and controlled access areas shall complete AT Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee to the COR or to the contracting officer, if a COR is not assigned, within 30 calendar days after completion of training by all employees and subcontractor personnel. AT level I awareness training is available at the following website.

https://jkodirect.jten.mil/Atlas2/page/login/Login.jsf

1.3.4 Physical Security: The contractor shall safeguard all Government property provided for contractor use.

1.3.5 iWATCH Training: This standard language is for contractor employees with an area of performance within an Army controlled installation, facility or area. The contractor and all associated subcontractors shall brief all employees on the local iWATCH program (training standards provided by the requiring activity ATO).

This local developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the CO. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the COR NLT 30 calendar days after contract award.

Training website: http://www.letterkenny.army.mil/iwatch.html

1.3.6 OPSEC Training: Per AR 530-1, the contractor employees must complete Level I

OPSEC Awareness training. New employees must be trained with 30 calendar days of their reporting for duty and annually thereafter.

http://www.letterkenny.army.mil/iwatch.html (PDF, certificate at the end)

2.0 Government Responsibilities:

2.1 Government Furnished Property and Materials: The Government will provide the facilities, equipment, materials and/or services listed below:

2.1.1 Facilities: The Government will provide clear access to all working areas necessary for the contractor to perform the setup and start up, during the specified hours listed in section 1.2.

2.1.2 Equipment: none

2.1.3 Materials: Stock material for testing.

2.1.4 Services: none

2.2 Site Preparation: Letterkenny Army Depot will provide a clear area for installation of the tubing bender.

2.3 Utilities: LEAD will provide adequate utilities to the equipment in disconnect(s) for the installation and operation of the machines. LEAD will also provide temporary utilities for the operation of equipment required for the installation of the industrial equipment.

2.4 Utility Installation: Utilities will be run overhead. The Government will connect all utilities (power, air, water, etc.).

2.5 Delivery and Storage: The Government will unload and locate tubing bender to final location. The equipment will be setup and started by the contractor during agreed upon time with the Government. Startup will be scheduled to be done in a timely manner.

3.0 Contractor Responsibilities: The contractor shall be responsible to inform all of his workers, direct or contracted, and ensure they follow the information within this specification. The contractor shall also have a representative onsite to perform the setup, startup, testing, training, and be the point of contact (POC) to communicate and coordinate with Letterkenny’s POC.

3.1 Post Processor: None.

3.2 Project Schedule: A project schedule shall be submitted by the contractor, within

30 days after receipt of the purchase order, to include a timeline for material delivery, installation, testing and training.

3.3 Utility Requirements: The contractor shall provide certified utility requirements within 15 days after receipt of the purchase order. They shall include type, number of connections, and requirements.

3.4 Field Verification: It shall be the responsibility of the contractor to verify, in the field, all measurements, locations of structures and utilities, and any other physical conditions which would affect the progress, or quantity of work. Any errors by the contractor, due to omission of field verification, shall not be the basis for any increase in contract price. Where existing utilities or other obstructions interfere with the progress of the contract, the contractor shall provide all materials and labor to relocate all obstructions as required and approved by the Contracting Officer.

3.5 Special Foundation: None.

3.6 Disposal Of Materials And Equipment: All salvageable materials and equipment removed by the contractor shall be delivered to the Depot Property Disposal Yard, Facilities Engineering Division warehouse, or other sites as directed by the Contracting Officer, or his representative and shall remain the property of the Government. Delivery shall be made during normal operating hours of the receiving activity. No Government materials or equipment shall be removed from the reservation by the contractor. All packing, packaging, and scrap material accumulated during the performance of the contract shall be removed and disposed of properly by the contractor.

3.7 Dust Control: Since the containers will be located outside the building, dust control isn’t a concern. Use of water will not be permitted when it will result in, or create, hazardous or objectionable conditions such as ice, flooding or pollution.

3.8 Protection of Existing Structures and Equipment: The contractor shall take all necessary precautions to insure against damage to existing structures and equipment to remain in place.

3.9 Installation of New Equipment: The contractor shall be perform the setup, startup, testing, debugging, troubleshooting, and training for the equipment provided under this contract.

3.10 Wiring: All electrical work and materials shall be in compliance with the National

Electrical Code and National Electrical Manufacturers Association. All electrical installations shall be inspected and accepted by a certified electrician. All work shall be subject to inspection by LEAD electricians.

3.11 Compressed Air and Water: Schedule 40 (minimum) black steel pipe, valves, and all materials necessary, shall be supplied and installed to provide the equipment with required adequate air and water supplies.

3.12 Fluids: The contractor shall provide all necessary fluids and chemical additives required for the start-up and proper operation of the equipment. The contractor shall supply LEAD with MSDSs for all the necessary fluids within 30 days after award of contract.

3.13 Permits/Insurance/licensing/bonding: Not applicable. However, any hot work

(welding, burning, etc.) the contractor will do, the contractor is required to contact the Letterkenny fire department (717-267-8108) at least 24 hours in advance of the hot work to be performed.

4.0 Requirements:

4.1 Machine Features: The CNC tubing bender shall have the following minimum features.

Hydraulic Powered Clamp, Pressure Die & Pressure Die Assist Drop-Away Style Clamp Die Holder Closed-loop Feedback Control of “L” (Length),”R” (Rotation), and “A” (Bend

Angle) Swing Arm Safety Guards CW (RH) Bend Arm Rotation Remote Dual Palm Anti-Tie Down Cycle Switches and Safety Mat for Safe

Machine Operation.

Servo Controlled Carriage with Gripper for Part Length Positioning and Rotation.

Automatic Part Program Cycle.

Programmable auto Springback Compensation Hydraulic Mandrel Extractor Automatic Mandrel Lube- to pump lube automatically through hollow Mandrel

Rod to Mandrel.

Wiper Die Holder- used for Tight Radius Bending of thin wall material Step File Converter , ISO 10303 Standard 3D Step files into LRA bender data;

Step files from ProE, Solid Works, Solid Edge, and AutoCAD Inventor X,Y,Z to L,R,A Conversion Automatic axis zeroing when initializing Manual and automatic bend cycle modes Ability to Pause a Part in Auto or Manual Mode.

Three (3) Axis CNC Control Operating From A Windows ® PC and stand Unlimited Part Program Storage, disk space and network server Hydraulic Powered Bend Head, adjustable speed control and programmable Last Bend Carriage Release, programmable Hitch Feed, unlimited Part Length

4.1.1 PC, INTERFACE & DISPLAY:

If PC is required then it shall be a PC with Windows 10 and Ethernet connection for part program backup to server.

The program control panel, shall be High Resolution Color Display The CNC Control software shall operate all three axis for complete machine control Must have the ability to store unlimited number of programs Electric Servo Powered Rotation & Feed Axis – all programmable

Displays and Rotates Part in 3D Graphics based on LRA Bend Data Onboard Self Diagnostics provides for real time system feedback

(2) E Stop Switches for Safe Machine Operation – (1) on PC control stand and

(1) on remote stand Remote PC stand - This option takes the standard laptop stand that is attached to the main frame and moves it to a remote stand on wheels.

Single Step Mode Partial Bending Regrip

4.1.2 PC CONTROL SYSTEM:

Windows® 10 Operating System Bright, high resolution color display Hard Drive for unlimited part storage Supports both X,Y,Z or L,R,A data input with auto conversion bend data editor includes add, insert and delete commands machine sequences and interferences moves programmable Programmable mandrel mode function with auto lube and early extraction Production parts counter with set limits Password protection for part data input or changes Maintenance screen with graphic representations of bender operating status, limit switch states and axis positions in real time.

store notes with part program High resolution encoders on all axis for precise position and feedback information Automatic axis zeroing when initializing.

Unlimited hitch feed moves Manual and automatic bend cycle modes Ability to Pause during a part program BEND ARM (A Axis) Standard hydraulic cylinder drive system. Power supply is air cooled.

FEED (L Axis) has brushless AC Servo Drive Motor with linear bearings.

ROTATION (R Axis) 360° bi-directional rotation with brushless AC Servo Drive

Motor

4.1.3 TUBING BENDER DIES: The Rotary-Draw Tube Bender will use supplied Winton dies to bend the following materials:

1” O.D. x 1/8” wall, mild steel and aluminum with a radius of 3.0”.

½” O.D. x 1/16” wall, mild steel and aluminum with a radius of 3.0” 5/8 O.D. x 1/16” wall, mild steel and aluminum with a radius of 3.0” ¾” O.D. x 1/16” wall, mild steel and aluminum with a radius of 3.0” 7/8” O.D. x 1/8” wall, mild steel and aluminum with a radius of 3.5” 1 ¼” O.D. x 1/8” wall, mild steel and aluminum with a radius of 3.5’ 1 ½” O.D. x 1/8” wall, mild steel and aluminum with a radius of 3.5”

1 ¾” O.D. x 1/8” wall, mild steel and aluminum with a radius of 3.5”

4.1.4 UTILITY REQUIREMENTS: The Rotary-Draw Tube Bender shall operate with

480 VAC, 60Hz, Three Phase power and 70-90 psi shop air.

4.1.5 FOOTPRINT: The Rotary-Draw Tube Bender shall occupy a footprint no greater than 175”L x51”W x 61” H

4.1.6 MACHINE CAPACITY: the Rotary-Draw Tube Bender shall be capable of bending:

¼” to 2.00”OD x 0.120” (50mm x 2.75mm) wall or greater, mild steel.

¼”to 2.00”OD x 0.075” (50mm x 1.65mm) wall or greater, stainless steel.

¼”to 2.00”OD x 0.2” (50 mm x 3.00 mm) wall or greater, aluminum.

¼”to 1.00”OD (25.4mm) or greater, solid mild steel bar.

Machine Length repeatability of ± 0.002” Machine Rotation repeatability (R motion) of ± 0.10⁰ Machine Angle repeatability ( A motion) of ± 0.10⁰ Have a Bend Arm Rotation of 190 Degree or greater Have a Maximum Bend Radius of 10” Centerline Radius or greater Have a Minimum Bend Radius of 1.5 x material diameter Have Tube Length of 120” end chuck, 144” Over Mandrel or greater.

Have a Bend Speed of 75 Degree per Second or greater.

At least three zone design to provide rotational limits in three zones of operation.

Zones will have adjustable elevation trips and adjustable rotation limit trips.

4.2 General Requirements:

4.2.1 Documentation: Two sets (each) of paper and one (each) CD of operator instruction manuals, maintenance service manuals, and parts listing manuals shall be provided for the furnished systems. These manuals shall be written in the English language.

4.2.2 Preservation, Packaging and Delivery: The contractor shall utilize standard commercial methods for preservation and packaging appropriate for each unit and acceptable to commercial carriers. As a minimum, all areas susceptible to damage from exposure to the elements shall be preserved and/or packed to prevent damage. The contractor shall be responsible for ensuring the equipment is delivered to LEAD in good condition.

4.2.3 Warranty: The contractor shall furnish with the equipment a standard commercial warranty or full one year warranty (parts, labor, and shipping, at minimum), whichever is greater. The contractor shall provide commercial warranties for any subcontracted components that will be underwritten. The contractor shall supply all corresponding warranty contact names and phone numbers before the end of the project. The warranty shall be effective beginning immediately after final acceptance of the equipment and not before that time.

4.2.4 Inspection and Acceptance: The equipment shall be examined for design, construction, materials, components, and workmanship to determine compliance with the contract and this specification. Any deviation from these requirements shall be cause for rejection.

4.2.5 Painting: All surfaces to be painted shall be cleaned of all foreign matter. The equipment shall be painted IAW standard commercial practice that shall not be less than one coat of primer and one coat of finish color.

4.2.6 Lubrication: Means shall be provided to ensure adequate lubrication to all moving parts. All oil holes, grease fittings and filler caps shall be easily accessible.

4.2.7 Power Requirements: All power requirements shall be 480V 3ph. If any requirement is not, the contractor shall supply all required transformers.

4.2.8 Lubrication: If the equipment does not include an automatic centralized lubrication system, the equipment must have adequate and proper lubrication points to provide lubricant to critical components. All lubrication points must be obviously marked.

4.2.9 Energy Efficiency: All equipment that directly consumes energy in normal operation shall be designed and constructed for the highest degree of energy efficiency as governed by the latest developments available within industry.

4.3 Safety and Environmental Requirements:

The contractor is reminded that LEAD maintains a Safety Management System (SMS) and is ISO 45001 certified.

LEAD’s safety policy and safety program (LEAD-R 385-1) can be requested at usarmy.letterkenny.usamc.list.lead-safety-office@army.mil

It is the contractor’s responsibility to be familiar with these documents and to comply with their contents.

Any and all on site work at LEAD shall be completed in accordance with applicable OSHA, DoD, DOT, Army, and LEAD Safety requirements. As a federal installation, additional requirements other than OSHA apply to contractors performing work at LEAD. Examples include full conformance to all applicable NFPA standards, ANSI standards, and other consensus standards for the industry covered by the subject contract. It is the responsibility of the contractor to be familiar with all applicable standards prior to starting work.

If contractor personnel determine a procedure is unsafe, they shall discontinue work immediately and contact their Program Manager who shall notify safety personnel and the COR. As soon as LEAD Safety Office personnel determine that the unsafe conditions have been corrected, the COR will notify the contractor Program Manager that personnel may resume work.

Additionally, all contractor supervisors and employees shall read and be knowledgeable of the governing SOP(s) prior to signing the SOP(s) and starting the operation.

All contractor personnel shall wear the appropriate PPE when in the following work areas:

industrial buildings, at construction sites, test sites and test facilities. Failure to wear/use PPE may cause removal from the job site and/or seizure of non-compliant equipment/items.

The contractor shall comply with reporting requirements of 29 CFR Part 1904, AR 385-40 and

APGR 385-4, and shall report accidents resulting in injury or death and accidents resulting in damage to Government property, supplies, and equipment to the COR promptly of the occurrence.

In case of injury/accident, the contractor shall complete an injury/accident investigation report and submit it to the COR Office with a copy to the LEAD Safety Office.

All shipped material shall include a current product Safety Data Sheet (SDS) for any chemical products being shipped other than residue. This includes items like engine oil.

All safety messages or recalls related to the safe use of products produced by the contractor will be provided to the COR for the Contract within 5 days of contractor’s awareness of the message or notice.

As part of the applicability of engineering controls, all equipment with rotating and moving parts at point of operation shall comply with LEAD 385-1 Chapter 17-3- Policies: One or more methods of machine guarding shall be provided to protect the operator and other employees in the machine area from hazards such as those created by point of operation, nip/pinch points, rotating parts, flying chips, and sparks. Examples of guarding methods are: physical barrier guards, electronic safety devices, guarding by distance, and physical restraints. The point of operation of machines whose operations exposes an employee to injury shall be guarded. The guarding device shall be in conformity with any appropriate standard (OSHA, ANSI, Equipment Owner’s Manual). In the absence of applicable specific standards guarding shall be designed and constructed as to prevent the operator, or any employees who may come in contact, from having any part of his/her body in the danger zone during operation. All machines designed for fixed locations shall be securely anchored to prevent walking or moving during operation.

4.3.1 Equipment Hazards: All hazards inside the machinery shall be guarded against unauthorized access. Clearly visible signs and symbols shall warn personnel in the area, and interlocks, safety mats and redundant deactivation systems shall guard against accidental access to the tooling and moving parts. Guards shall be easily removable to facilitate inspection, maintenance, or repair.

4.3.2 Mercury Restriction: The equipment shall not contain mercury compounds nor be exposed to free mercury during manufacture.

4.3.3 Asbestos Restriction: Asbestos and materials containing asbestos shall not be used in or on the equipment.

4.3.4 PCB Restriction: Equipment and materials containing Polychlorinated Biphenyl

(PCB) shall not be shipped to Letterkenny Army Depot.

4.4 Installation Requirements:

4.4.1 Design and Installation: The contractor shall provide all parts, labor, and services for the design, fabrication and installation of the tubing bender. The contractor shall provide competent English speaking personnel to place the system in operation and to conduct the acceptance tests and training of depot personnel.

The contractor, through his service personnel, shall be fully responsible for the offloading, installation, activation, and testing of the system and the service personnel shall remain until system activation and testing has successfully been completed. Under no circumstances should the contractor plan on gratuitous Depot assistance during installation, activation, and testing such as diagnosis, troubleshooting, or repair of the system.

4.4.2 Badges: Identification badges will be issued for admittance of personnel before performing work or service on this contract. The identification badge is the property of the US Government and must be returned upon termination or demand. The contractor/vendor agrees that he will ensure all badges issued to employees are returned to the Badge and Identification Section, Security Division, Letterkenny Army Depot promptly on termination of need or on expiration, which occurs first. The badge room is located in Bldg 2, phone # 717- 267-5301. Hours of operation are 7:30 AM to 3:30 PM, Monday thru Friday, exclusive of Federal Holidays.

4.4.3 Fire Extinguishers: The LEAD R 385-1 designates the type and number of fire extinguishers required to perform the contracted work. The LEAD Fire Department will not provide any extinguisher support. The contractor can gain the above information through a pre-construction conference, visiting the fire department, or phone 717-267-7108.

4.4.4 Use of Portable Gas or Arc Equipment: The contractor shall obtain a permit, from the LEAD Fire Department, to use portable gas or arc equipment for cutting, welding or open flame operations. The Fire Department will require one day advance notice to permit necessary inspection before actually starting work, and notification when work is finished to allow for re-inspection. The Fire Department can be notified by calling ext. 717-267-7108. The contractor shall take necessary precautions to prevent fires IAW NFPA Standard No. 51B and LEAD R 420-13.

4.4.5 Spills: Any spills or releases of materials or wastes must be reported immediately to the site supervisor, the LEAD Fire Department, and the LEAD Environmental Office per the LEAD Installation spill Contingency Plan (ISCP).

Any such spills or releases generated by the contractor shall be contained, cleaned and disposed of by the contractor per the direction of the LEAD on-scene coordinator.

5.0 Applicable Documents:

OSHA Safety and Health Standards 29 CFR 1910 Occupational Safety and Health Standards (copies may be obtained at http://www.osha.gov)

Letterkenny Army Depot (LEAD) Publications:

LEAD Regulation 385-1: LEAD Safety and Occupational Health Program LEAD Pamphlet 385-4 – Safety Requirements for Security, Safety, and Fire Prevention for Contractors Performing Work on LEAD (Copies may be obtained at LEAD Directorate of Contracting, Bldg 2)

National Fire Protection Association NFPA Standard 70 – National Electric Code NFPA Standard 79 – Electrical Standard for Industrial Machinery (copies may be obtained from http://www.nfpa.org/)

Unified Facilities Criteria UFC 3-600-01 - Fire Protection Engineering For Facilities (copies may be obtained from http://www.nfpa.org/)

6.0 Quality Assurance:

6.1 Quality Conformance Inspection: The tubing bender and all accessory components shall be subject to a quality conformance inspection, performed by a designated Depot representative, to determine compliance with this specification.

6.2 Tests:

6.2.1 Accuracy: If an accuracy test was performed by the OEM before the machine was shipped, the contractor shall repeat the accuracy test at LEAD after complete installation. The results of the test performed at LEAD shall be compared to those from the test at the factory. If no accuracy test was performed at the factory, the contractor shall be responsible for developing test procedures to demonstrate the accuracy and operation of the machine to be in compliance with the requirements of this specification. All test procedures shall be submitted to and approved by Depot Technical Point of Contact (TPOC) prior to the start of testing. To support the testing procedures, LEAD will provide a supply of mild steel material of various thicknesses for use during the performance tests and training. If mild steel is not available, other readily available materials may be used. The contractor shall prove out all problems.

6.2.2 Post Processing Verification: None.

6.3 Technical Instruction: The contractor shall be responsible for providing technical instruction of four (4) Depot personnel in the operation of the equipment and software and four (4) Depot personnel in the maintenance of the equipment supplied under this contract. The training will be onsite for at least one day. All instructions, oral and written, shall be in the English language. The project LEAD

TPOC will coordinate with individuals to be trained upon successful completion of all installation and test specifications.

7.0 Information Technology (IT) Industrial System Requirements:

7.1 Operating System (OS) Specifications:

7.1.1 If applicable, the system’s OS must be Microsoft Windows 10, Windows Server

2012R2, or Red Hat Linux v6.X. Any OS supplied with the system must contain all service packs, updated patches, and hot fixes. All patching and fixes will be current as of a predefined date agreed upon by the vendor and the government.

7.1.2 Defense Information System Agency (DISA) Security Technical Implementation

Guides (STIGS) are configuration standards for the Department of Defense and contain technical guidance to lock down information systems and software applications that might otherwise be vulnerable to malicious attacks. The contractor shall be responsible for ensuring all appropriate STIGs are implemented and their software runs acceptably while secure.

7.1.3 The Army Golden Master (AGM) is a collection of security settings for Microsoft

Operating systems which must be applied to all Army computer systems. LEAD will supply the AGM to the contractor who shall ensure their software functions as intended, when installed on top of the AGM.

7.2 Programmable Logic Controllers (PLC): If a PLC is to be installed within the system, it shall be manufactured by a government approved source and shall provide an Ethernet adapter to allow for connection to the Industrial Network if required. If an Ethernet connection is used to interconnect the PLC to peripheral equipment, an additional Ethernet port shall be provided.

7.3 System Software Specifications:

7.3.1 Software Installations: If installing application code at LEAD, the contractor shall install the code within a standard container (E.g., Program Files) and located in a volume separate from the standard System Files. Interactive applications are required to run as services and daemons and any time WEB services are used, file types (E.g., XML and HTML) must be separated.

7.3.2 Software Licensing: When installed, the software licensing for computers, control units and other IT systems will be surrendered to the Information Technology Configuration Manager and will become the property of the Government upon acceptance of the system.

7.3.3 If software has been customized for LEAD’s use or is any software other than

Commercial Off The Shelf (COTS); the contractor shall provide copies of all source code, firmware and software used in the system, as well as one set of backup and configuration software for PLC’s, control and communication computers, and data acquisition. All programs shall be tested and fully operational before acceptance. All acceptance testing will adhere to common User Acceptance Testing (UAT) standards as defined by the government.

7.3.4 If any special programming software or programming software interface devices such as hardware "keys", dongles or "PIC" modules, are required to access software, these programs and devices shall be provided to LEAD along with the necessary registration information. If custom application software was written and provided, a copy of the required compiler and compiler license shall also be provided. At acceptance, all items shall become property of the government.

Software and hardware purchased for this project shall be registered to Commander, Letterkenny Army Depot, Chambersburg, PA 17201.

7.4 System Environment Specifications:

7.4.1 All supplied software must be capable of operating in a multi-user environment and data which contains permissions information shall be hidden from view and inaccessible to those with less than administrator level access. Shared accounts shall not be used, and users shall only be authorized the minimum security rights to operate the application software. Users will not have access to system or software configuration items (e.g., Control Panel, software and hardware installation). Under no circumstances will the intended end user log in using the Administrator or Root account for routine operation of the equipment. The use of these accounts will be restricted to only administrative activities which will be carried out by LEAD Information Technology personnel. All software products shall employ a minimum of three permission based levels of access.

7.4.1.1 Administrator - Full control at root level, restricted to LEAD IT personnel and when required, the Contractor.

7.4.1.2 Maintenance - Mid-level control required to perform maintenance and alter control parameters as needed.

7.4.1.3 Operator - Minimum control necessary to perform the routine operation of software. The Operator shall not be able to alter the programming of software, make changes to executable files, or modify control parameters.

7.4.2 Application Interoperability: If an application will interfere with the operation of the industrial system, E.g., (McAfee Anti-Virus), the Contractor shall provide a written statement to the LEAD IT Directorate explaining the technical restrictions placed upon them.

7.4.3 Auditing: If applicable, the contractor shall enable audit files and data logs for access by LEAD Cybersecurity personnel to audit access and actions on the equipment.

7.4.4 User Acceptance Testing (UAT): LEAD Cyber Security Personnel will have the ability to conduct validation testing with approved security tools prior to equipment being introduced to the shop floor. This testing will also satisfy any UAT requirements. A UAT Plan will be furnished prior to testing and all equipment documentation will be made available for review during the test. If discrepancies are discovered the contractor shall remediate identified issues prior to government acceptance.

7.5 Documentation Requirements:

7.5.1 A complete set of instruction manuals containing all of the information necessary to operate, maintain, and reinstall all software and hardware contained within the system shall be provided by the Contractor. These manuals shall include step-by-step instructions which facilitate the rebuilding of the system in the event of a fatal system crash.

7.5.2 If networked, the Contractor shall provide the system’s network design drawings to the Information Technology Directorate. These drawings should include complete directional data flow diagrams that include all ports and protocols in use.

7.5.3 The Contractor shall provide to Industrial Automation at least two electronic copies of all control unit programs. These copies should include description files of the ladder logic and any cabling required to connect to the control systems. No control units will be password protected and no other form of lockout measure shall be implemented by anyone other than LEAD IT employees. The Contractor shall also provide electrical wiring diagrams for all installed control systems to this LEAD Industrial Automation group.

7.5.4 Certificate of Networthiness: Certificate of Networthiness (CoN) certification ensures Automated Information Systems (AIS) utilizing the Army Network are developed in compliance with the Clinger Cohen Act and are secure, supportable, sustainable, and compatible with the Army Enterprise Infrastructure (AEI) (as defined in AR 25-1). All new AIS capabilities and all capability modifications and upgrades must be assessed to validate their Networthiness (network security, network impact, compatibility with the infrastructure, infrastructure requirements, spectrum support, security policy compliance, Joint Technical Architecture –Army (JTA-A) standards compliance, communications and information manpower, training, logistics support, schedule, and funding). If software is installed within the system, the Contractor shall work with LEAD Directorate of Information Management (DOIM) personnel to check for CoN availability and when not available, ensure a CoN is requested and all documentation is submitted.

7.6 Proposal Deviations:

7.6.1 Proposals or specifications that deviate from those described herein shall be coordinated for specific approval or rejection by the LEAD Information Technology representatives prior to shipment, installation, or acceptance of the equipment.

8.0 Final Acceptance: Once all conditions of this contract are met, final acceptance will be after 100 hours of continuous operation without a breakdown or failure, or 14 days, whichever comes first. If the machine has a failure or breakdown and it is determined that is the fault of the machine hardware or software, the operating time and 14 days timeframe start over each time this happens. After the 100-hour operating time or 14 days have been met, final payment of this contract will be made.

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Each

CNC TUBING BENDER

FFP

Part Number: RD50 NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

FOB: Destination

NSN: RD50:384B5

MILSTRIP: W25G1Q216601E9

MFR PART NR: RD50

PURCHASE REQUEST NUMBER: W25G1Q216601E9

PSC CD: 3441

NET AMT

INSPECTION AND ACCEPTANCE TERMS

Supplies/services will be inspected/accepted at:

CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY

0001 Destination Government Destination Government

DELIVERY INFORMATION

CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /

CAGE

0001 60 dys. ADC 1 OFFICE OF STRATEGIC MANAGEMENT

BLDG 370 ASRS DOOR 18 AMLD-PLX

LETTERKENNY ARMY DEPOT

CHAMBERSBURG PA 17201-4150

FOB: Destination

W25G1Q

CLAUSES INCORPORATED BY REFERENCE

52.203-18 Prohibition on Contracting With Entities That Require Certain

Internal Confidentiality Agreements or Statements-- Representation

JAN 2017

52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements

JAN 2017

52.204-7 System for Award Management OCT 2018 52.204-9 Personal Identity Verification of Contractor Personnel JAN 2011 52.204-10 Reporting Executive Compensation and First-Tier

Subcontract Awards

JUN 2020

52.204-13 System for Award Management Maintenance OCT 2018 52.204-16 Commercial and Government Entity Code Reporting AUG 2020 52.204-18 Commercial and Government Entity Code Maintenance AUG 2020 52.204-19 Incorporation by Reference of Representations and

Certifications.

DEC 2014

52.204-21 Basic Safeguarding of Covered Contractor Information Systems

NOV 2021

52.204-22 Alternative Line Item Proposal JAN 2017 52.204-23 Prohibition on Contracting for Hardware, Software, and

Services Developed or Provided by Kaspersky Lab and Other Covered Entities

NOV 2021

52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment

NOV 2021

52.209-6 Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, or Proposed for Debarment

NOV 2021

52.209-10 Prohibition on Contracting With Inverted Domestic Corporations

NOV 2015

52.212-1 Instructions to Offerors--Commercial Products and Commercial Services

NOV 2021

52.212-3 Alt I Offeror Representations and Certifications--Commercial Products and Commercial Services (MAY 2022) Alternate I

OCT 2014

52.212-4 Contract Terms and Conditions--Commercial Products and Commercial Services

NOV 2021

52.214-34 Submission Of Offers In The English Language APR 1991 52.214-35 Submission Of Offers In U.S. Currency APR 1991 52.215-1 Instructions to Offerors--Competitive Acquisition NOV 2021 52.222-3 Convict Labor JUN 2003 52.222-19 Child Labor -- Cooperation with Authorities and Remedies JAN 2022 52.222-21 Prohibition Of Segregated Facilities APR 2015 52.222-26 Equal Opportunity SEP 2016 52.222-36 Equal Opportunity for Workers with Disabilities JUN 2020 52.222-50 Combating Trafficking in Persons NOV 2021 52.223-18 Encouraging Contractor Policies To Ban Text Messaging

While Driving

JUN 2020

52.225-1 Buy American--Supplies NOV 2021 52.225-13 Restrictions on Certain Foreign Purchases FEB 2021 52.232-33 Payment by Electronic Funds Transfer--System for Award

Management

OCT 2018

52.232-39 Unenforceability of Unauthorized Obligations JUN 2013 52.232-40 Providing Accelerated Payments to Small Business

Subcontractors

NOV 2021

52.233-1 Disputes MAY 2014 52.233-3 Protest After Award AUG 1996 52.233-4 Applicable Law for Breach of Contract Claim OCT 2004 52.242-17 Government Delay Of Work APR 1984 52.246-2 Inspection Of Supplies--Fixed Price AUG 1996 52.247-34 F.O.B. Destination NOV 1991 252.203-7000 Requirements Relating to Compensation of Former DoD

Officials

SEP 2011

252.203-7002 Requirement to Inform Employees of Whistleblower Rights SEP 2013 252.203-7005 Representation Relating to Compensation of Former DoD

Officials

NOV 2011

252.204-7003 Control Of Government Personnel Work Product APR 1992 252.204-7012 Safeguarding Covered Defense Information and Cyber

Incident Reporting

DEC 2019

252.204-7015 Notice of Authorized Disclosure of Information for Litigation Support

MAY 2016

252.204-7016 Covered Defense Telecommunications Equipment or Services -- Representation

DEC 2019

252.204-7017 Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services -- Representation

MAY 2021

252.204-7022 Expediting Contract Closeout MAY 2021 252.223-7006 Prohibition On Storage, Treatment, and Disposal of Toxic or

Hazardous Materials

SEP 2014

252.223-7008 Prohibition of Hexavalent Chromium JUN 2013 252.232-7003 Electronic Submission of Payment Requests and Receiving

Reports

DEC 2018

252.232-7010 Levies on Contract Payments DEC 2006 252.232-7017 Accelerating Payments to Small Business Subcontractors--

Prohibition on Fees and Consideration

APR 2020

252.243-7001 Pricing Of Contract Modifications DEC 1991 252.244-7000 Subcontracts for Commercial Items JAN 2021 252.247-7023 Transportation of Supplies by Sea FEB 2019

CLAUSES INCORPORATED BY FULL TEXT

52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO

SURVEILLANCE SERVICES OR EQUIPMENT (NOV 2021)

The Offeror shall not complete the representation at paragraph (d)(1) of this provision if the Offeror has represented that it "does not provide covered telecommunications equipment or services as a part of its offered products or services to the Government in the performance of any contract, subcontract, or other contractual instrument" in paragraph (c)(1) in the provision at 52.204-26, Covered Telecommunications Equipment or Services-- Representation, or in paragraph (v)(2)(i) of the provision at 52.212-3, Offeror Representations and Certifications- Commercial Products and Commercial Services. The Offeror shall not complete the representation in paragraph (d)(2) of this provision if the Offeror has represented that it "does not use covered telecommunications equipment or services, or any equipment, system, or service that uses covered telecommunications equipment or services" in paragraph (c)(2) of the provision at 52.204-26, or in paragraph (v)(2)(ii) of the provision at 52.212-3.

(a) Definitions. As used in this provision-

Backhaul, covered telecommunications equipment or services, critical technology, interconnection arrangements, reasonable inquiry, roaming, and substantial or essential component have the meanings provided in the clause 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment.

(b) Prohibition.

(1) Section 889(a)(1)(A) of the John S. McCain National Defense Authorization Act for…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .