This is a Statement of Work issued by the Texas Department of Public Safety (TXDPS) for the replacement of the Autoclave system and Nitro Generator at HQ Building U Laboratory in Austin, Texas. The project involves replacing the existing lab autoclave system with two new autoclaves from Consolidated Sterilizer Systems, replacing the nitrogen generator, and temporarily removing/replacing drywall sections as needed for equipment removal and installation. The work will be performed at 5800 Guadalupe Street, Building U, and must be completed no later than August 31, 2025. The project requires coordination with the Contract Monitor Chris Henderson and adherence to strict facility access protocols, with all site visits and construction phases requiring advance scheduling.
The contract includes detailed requirements for project execution, quality control, administrative procedures, and facility protection measures. The contractor must submit comprehensive operation and maintenance documentation, provide staff training, and record all training sessions on DVD. Key requirements include maintaining facility operations during construction, protecting existing infrastructure, proper waste management, and obtaining all necessary permits. The contractor must carry appropriate insurance, provide warranty coverage for one year from substantial completion, and comply with HUB (Historically Underutilized Business) requirements. The work must follow specific safety protocols including background checks for personnel, restrictions on hazardous materials, and compliance with NFPA standards.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TEXAS DEPARTMENT OF PUBLIC SAFETY SCOPE OF WORK
The Texas Department of Public Safety (TXDPS) is requesting Bid Solicitations for the replacement of the Autoclave system and Nitro Generator at HQ Building U Laboratory. See the attached scope of work, drawings, and specifications for more information.
Services to Include:
• Austin Department of Public Safety Headquarters Building U.
• Replacement of the Lab Autoclave system and Nitro Generator
• Must meet all requirements as listed in the Statement of Work and Specifications.
Project Location Department of Public Safety 5800 Guadalupe Street, Building U.
Austin, Texas 78752
Department of Public Safety
Contract Monitor:
Chris Henderson Construction Manager Austin, HQ
PH: 512-839-9135
christopher.henderson2@dps.texas.gov
Department of Public Safety
Site Contact:
Chris Henderson Construction Manager Austin, HQ
PH: 512-839-9135
christopher.henderson2@dps.texas.gov
NOTE: Building contacts will be identified to the bidders for the respective locations for site visits and future access. Access times for each phase of construction must be scheduled ahead of actual work.
Table of Contents - Specification Sections Section 0110 00 Summary Section 0111 00 Summary of Work Section 01 20 00 Price and Payment Procedures Section 01 23 00 Alternates Section 01 25 00 Substitution Procedures Section 01 30 00 Administration Procedures RFI Form AIA Document C106-2022 Digital Data
Licensing Agreement Section 01 33 00 Section 01 40 00 Section 01 50 00 Section 01 60 00 Section 01/70 00 Section 01 78 23 Section 01 78 39 Section 01 74 00 Section 01 79 00
Submittal Procedures Quality Requirements Temp Facilities and Controls Product Requirements Execution and Closeout Requirements Operation and maintenance Data Project Record Documents Cleaning and Waste Management Demonstration and Training
Building U Equipment Replacement
Issued for Proposals
Austin, Texas
June 2024
Parkhill
SUMMARY
0110 00 - 2
1.6 ACCESS TO SITE
A. General: Contractor shall have limited use of Project site for construction operations as indicated on Drawings by the Contract limits and as indicated by requirements of this Section.
B. Use of Site: Limit use of Project site to areas within the Contract limits indicated. Do not disturb portions of the Project site beyond areas in which the Work is indicated.
1. Limits: Confine construction operations to the Building U at the DPS
Headquarters Campus located at 5800 Guadalupe Street, Austin, Texas.
2. Driveways, Walkways, and Entrances: Keep driveways and entrances serving premises clear and available to Owner, Owner's employees, and emergency vehicles at all times. Do not use these areas for parking or for storage of materials.
a. Schedule deliveries to minimize use of driveways and entrances by construction operations.
b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
C. Condition of Existing Building: Maintain portions of existing building affected by construction operations in a weathertight condition throughout construction period.
Repair damage caused by construction operations.
D. Condition of Existing Grounds: Maintain portions of existing grounds, landscaping, and hardscaping affected by construction operations throughout construction period. Repair damage caused by construction operations.
1.7 COORDINATION WITH OCCUPANTS
A. Partial Owner Occupancy: Owner will occupy the premises during the entire construction period, with the exception of areas under construction. Cooperate with Owner during construction operations to minimize conflicts and facilitate Owner usage. Perform the Work so as not to interfere with Owner's operations. Maintain existing exits unless otherwise indicated.
1. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Owner and authorities having jurisdiction.
2. Provide not less than 72 hours' notice to Owner of activities that will affect Owner's operations.
1.8 WORK RESTRICTIONS
A. Work Restrictions, General: Comply with restrictions on construction operations.
1. Comply with limitations on use of public streets and with other requirements of authorities having jurisdiction.
SECTION 01 11 00 – SUMMARY OF WORK
SECTION 1.0 GENERAL
1.01 SCOPE OF WORK
This section outlines the scope of work included in the project. Refer to the appropriate drawings and specification sections for further information about installation, preparation methods and components to be provided. The contractor is responsible for including all means and methods necessary to complete this portion of the project. The contract Documents, otherwise referred to as drawings, shall serve as a part of this scope of work showing more detail on the intent of this project. The Contractor is responsible for including all means and methods necessary to complete this project. In general, the work includes, but is not limited to, the following items:
1. See Contract Drawings for complete understanding of demolition and construction scope. This list is generic in nature for major items and intended only to give an overview of general project scope.
2. Replace the existing Autoclave with two newer models from Consolidated Sterilizer systems, see drawings and notes for specifications.
3. Temporarily remove a portion of the drywall in the autoclave room to the extent needed in order to remove the old unit from the space. This drywall opening will need to be infilled after the new autoclaves are installed.
4. Replace the existing nitrogen generator, see drawings for notes and specifications. High pressure clean all lines prior to connecting the new nitrogen generator.
5. Provide turnkey project as indicated on the drawings and as required for complete project. Contractor bid must include labor and material for the autoclaves and generator.
1.02 QUALITY CONTROL
1. Contractor is responsible for properly disposing of all trash, or construction debris associated with this project. Removal shall not utilize TXDPS dumpster or equipment unless authorized by TXDPS.
2. TXDPS will identify an exterior staging area/ entry for use by the contractor. This temporary storage must be maintained in a neat orderly manner and restored to original condition upon completion.
3. Any container used as part of this contract is subject to inspection upon being located on TXDPS property.
4. Contractor shall efficiently schedule all work to ensure work will be done in as few calendar days as possible for optimum installation to meet the manufacturer’s warranty requirements. All work shall be continuous to insure the facility impact is minimal with limited disruptions. Every effort shall be made to eliminate down time and get the TXDPS operations back in service as quickly and safely as possible. The exact dates will be coordinated once the bid award is made.
5. All work will be performed by qualified craft persons with a minimum of (3) three years of experience in the field. It shall be the contractor’s responsibility to provide only skilled qualified workers for this project.
6. The new work shall comply with the state and local codes and ordinances.
7. Attached contract drawings may include other trade work for reference and coordination.
1.03 PERFORMANCE REQUIREMENTS
1. The Work requirements of the Contract are summarized by reference to the Bidding Requirements, the
Contract forms, the Conditions of the Contract, the Specification, the Drawings, and Addenda and Contract Modifications, including, but not limited to, the printed matter referenced in these requirements. It is recognized that the Work is affected or influenced by governing regulations, natural phenomenon (including weather conditions), unforeseen conditions uncovered by the Work, and other forces outside of the Contract Documents.
2. All work shall be considered new unless otherwise indicated.
3. All workmanship and materials shall be of the best construction practice. Should a conflict arise between the specification requirements and those of the referenced publications, the better quality or more stringent requirement will prevail. Specification requirements that exceed the minimum requirements of the manufacturer shall be compiled with by the Contractor.
4. The Contractor shall check and verify all dimensions, notes, conditions in the installation area on site before any construction work is started. All discrepancies shall be reported to TXDPS in writing. No extra charge of compensation will be allowed on account of any difference between actual measurements and measurements or dimensions supplied by TXDPS, either verbally or in written form.
5. The Contractor shall assume full responsibility for the accuracy, fit and stability of all parts of the work.
6. All labor, materials and installations must comply with the codes, rules and regulations of local, state and federal authorities having jurisdiction. Any discrepancy which exists between the requirements by the plans, specifications, said codes, rules and regulations, shall be immediately brought to the attention of TXDPS Facilities Department, in writing for resolution.
7. Applicable publications: Publications listed herein form a part of this Specification to the extent referenced and are indicated in the text by basic designation only. Applicable publications referenced shall be those that were issued and in use at the time of the Bid Submission.
8. The Contractor shall provide all necessary protection of existing work and newly added work.
9. The Contractor shall be responsible for adequately bracing and protecting all work during construction against damage, breakage, collapse, distortion and misalignment according to applicable codes and standards.
10. Working hours will be between 7:00 am and 5:00 pm during the week and as approved during the weekend if necessary. TXDPS needs to be clean and ready for work as soon as work is complete. If additional time is necessary for the specified products, schedule must be coordinated with TXDPS before any work begins.
11. The Contractor shall repair and restore to its original condition all work and items damaged as a result of building operations and shall leave the work completed to the true intent of the drawings and specifications and to the satisfaction of TXDPS.
12. Any disturbance or damage to the existing building, site or utilities resulting from either directly or indirectly from the building operations shall be promptly repaired, restored or replaced to the satisfaction of TXDPS at no additional cost to TXDPS.
13. All materials and construction to be incorporated in the work shall be in strict accordance with the latest editions of IBC and shall conform to the standards and recommendations of the various trade institutes where applicable.
14. The Contractor shall coordinate the work of any and all Sub-Contractors and also coordinate with TXDPS on portions of the work done by TXDPS employees or sub-contractors.
15. Manufacturer's Instructions:
a. Require compliance with instructions in full detail, including each step in sequence. Do not omit preparatory steps or installation procedures unless specifically modified or exempted by the SOW.
b. Should instruction conflict with Contract Documents, request clarification from TXDPS Contact before proceeding.
16. Manufacturer's Certificates:
a. When required in individual specifications section, submit manufacturer's certificate, in duplicate, certifying that products meet or exceed specified requirements, executed by responsible officer.
1.04 PROJECT CONDITIONS
1. The building will be occupied and in use during construction, take necessary precautions to create as little disturbance or disruption to the building and its occupants as possible during work hours.
2. Supply, install, and maintain barriers, protection, warning lines, lighting, and personnel required to segregate the work area(s) from pedestrian or vehicular traffic, as well as to prevent damage to the building, its occupants, and the surrounding landscaped and paved areas. The Contractor shall observe all applicable OSHA requirements.
3. Schedule and execute work without exposing the building interior to the effects of inclement weather.
Protect the building and its occupants against such risks and repair/replace work related damage to TXDPS’s satisfaction.
1.05 PRECONSTRUCTION CONFERENCE
1. A preconstruction conference may be held with TXDPS Staff as required, Contractor, and involved trades to discuss all aspects of the project. The Contractor's foreman or field representative will attend this conference.
2. TXDPS shall reserve the right to require an alternate superintendent and/or foreman.
3. Delivery of materials and commencement of construction shall not proceed until the preconstruction conference is held unless authorized by the TXDPS Contract Monitor.
4. Provide a line item breakdown of construction labor and materials costs for each Specification Section included in these Contract Documents.
1.06 EMERGENCY RESPONSE
1. The Contractor shall provide TXDPS with after-hours (24 hour) emergency telephone numbers of the
Contractor’s superintendent and foreman.
2. The Contractor must respond to emergency situations or calls within two (2) hours.
1.07 SUBMITTALS
1. Provide:
a. Manufacturer’s technical data.
b. Application or installation instructions.
c. Substitution Request Form, if necessary.
2. Provide schedule of installation as part of this requirement.
3. Provide samples and manufacturer’s literature for all products used on this project.
4. Provide certificates signed by the manufacturer certifying that installers comply with specified requirements.
5. All bidders shall submit information of not less than three (3) projects of similar size and complexity to include:
a. Project name and location.
b. Products installed.
c. Date of completion.
d. Owner’s contact name and telephone number.
6. Provide maintenance data for O&M (Operations and Maintenance) Manuals.
7. Provide warranty information to be turned over to the Owner at Substantial Completion.
8. All submittals, samples and documentation required should be sent to TXDPS Contract Monitor.
1.08 SCHEDULING
1. All field work installations at the listed location shall be scheduled to facilitate continued facility usage as required by TXDPS.
2. Prior approval must be received from local TXDPS staff if scheduled project tasks may impact regular
TXDPS facility operational schedule.
3. Proper coordination of all aspects of the work by the Contractor and any sub-trades is critical to ensure proper installation and performance of the work. The Contractor’s Construction Schedule shall clearly outline the coordination between job tasks of all involved disciplines. Subject to review and acceptance by the TXDPS, this Schedule will be strictly adhered to by the Contractor and sub-trades.
4. TXDPS shall review the Contractor’s Construction Schedule prior to the start of any work. After defining the location(s) of the work progress, TXDPS shall arrange to control occupancy in the building to the greatest extent possible. It shall be the responsibility of the Contractor to supply TXDPS with written notice, 72 hours in advance, if his work location(s) for a workday is different from the schedule. The Contractor shall update his Construction Schedule weekly and submit a copy to TXDPS for review.
1.09 SPECIAL CONSIDERATIONS
1. Even if it is not anticipated, the contractor may be required to shut down operations during the project for an unforeseen State of Texas emergency. In this event, the contractor will be required to finish any open work, secure the site staging area, and evacuate his/her personnel as safely but as quickly as possible from the property. Notification to return to work will be issued as soon as possible from authorized TXDPS personnel.
2. Any Propane tanks, gas cylinders or other flammable/hazardous materials must be secured and stored in a safe industry acceptable manner when in use or when they are being stored for future use at this or any TXDPS facility. Storage locations and quantities are to be identified to the affected Building Manager for the duration of the contract.
3. Contractor vehicles used for transport of personnel or materials shall be locked with the emergency brake set and the ignition key removed when left unattended. Parking or storage must be located only in approved areas determined by the local building manager. The Department of Public Safety shall not be responsible for damage by others to contract or Personal vehicles left on the project site. Any vehicle or equipment without an ignition key starter shall be rendered inoperable if left overnight. Also, any Vehicle or large equipment with a common industrial type of ignition source shall be rendered inoperable if left overnight. Security and safety of tools or equipment shall be the responsibility of the contractor during work and after regular business hours. Items such as ladders must be removed and secured prohibiting unauthorized access to the facility.
4. The facility shall not be left open by removal of any building component without prior knowledge of the TXDPS Building Manager. All removed openings are to be left secure with new products at the end of each work day or reasonably secured with 3/4” plywood or industry standard plugs. Temporary fillers must be cut to size and screwed securely into the opening in the event new component material need to be altered if the first attempt fails to fit an opening.
5. Contractor will be required to provide operation demonstration to the identified staff for future maintenance needs along with other information on warranty, maintenance manuals or other related details. Warranty information is subject to approval by Department of Public Safety’s Legal Section. Counsel may advise as to the warranty details that are not in compliance to state law or must be changed not to violate agency policy.
1.10 DEFINITIONS
1. TXDPS: Texas Department of Public Safety = Owner.
2. Contractor: Primary party responsible for coordination of their own employees or their respective sub-contractor groups to complete the contract project to meet these specifications.
3. Installer/Applicator/Erector: Entity engaged by Construction Manager as an employee, Subcontractor, or
Sub- subcontractor, to perform a particular construction operation, including installation, erection, application, and similar operations.
4. TXDPS Contact/Contract Monitor: Owner’s primary representative for this project having authority to communicate project details and accept or deny final installation completion.
5. TDLR-TAS: Texas Department of Licensing and Regulation – Texas Accessibility Standards.
1.11 PREFERRED PRODUCTS
1. Pursuant to Texas Government Code 2155.444 and 2155.4441, when quality, availability, and price of materials are comparable, provide those produced within the following distances from the Project site (listed in order of preference): 1. Within the State of Texas and within 500 miles; 2. Within the State of Texas and greater than 500 miles; 3. Within the United States and within 500 miles; 4. Within the United States and greater than 500 miles; 5. Outside the United States and within 500 miles; 6. Outside the United States and greater than 500 miles.
1.12 CONTRACT METHOD
1. Project may be constructed under a single prime contract at the discretion of TXDPS.
2. Contractor is mandated to make a scheduled site visit prior to sending in their bid proposal.
3. TXDPS reserves the right to reduce Scope of Work. In such cases, TXDPS will send out a revised Scope of Work to bidders for a revised bid.
1.13 WARRANTY
1. Installer shall furnish a single, written warranty covering 100% of the new material and labor costs protecting the owner, for a period of one (1) years from date of Substantial Completion.
2. In the event of component damage from the use of incompatible materials, or during installation any accident, mishandling, improper transportation methods or negligence on part of the Contractor or Sub- Contractor forces, the Primary Contractor shall be responsible for replacement at no cost the TXDPS.
3. Refer to specific sections of the specification for systems and product warranty requirements. Verify with Manufacturer of proposed systems and products that specified warranty requirements are acceptable, without exception, prior to selecting materials for use on this project.
4. Submit a full Contractor's Guarantee of the Work to be free from defect in materials and workmanship upon Substantial Completion, and prior to final payment. This Guarantee shall be for a period of one (1) years from the date of Substantial Completion, and shall be signed by a Principal of the Contractor’s firm, and sealed if a corporation.
5. If requested by TXDPS, submit a letter from the manufacturer acknowledging that completed Work is acceptable and that warranty remains in effect.
1.14 FINAL INSPECTION AND PAYMENT
1. Inspections: TXDPS will conduct inspections of the project to verify work is in general compliance with the project intent, Contract Documents, and specifications prior to issuing payments to the Contractor. Inspections will be done by TXDPS Contract Monitor or designated representative and may be conducted at any time, prior to payments and at a minimum prior to any payments to the Contractor.
2. Final Inspection: The Contractor and the TXDPS Contract Monitor or designated representative shall provide a comprehensive final inspection after completion of the project. All application errors shall be addressed and final punch list items completed prior to rendering any final payments.
3. Prior to TXDPS final acceptance of the project and completion of receiving reports for applications for payment, the contractor shall return all security badges, issued to the contractor and sub-contractors for access to TXDPS facilities, to the Contract Monitor.
1.15 PERMITS
1. The Contractor will obtain and pay for any and all permits required to perform the work.
1.16 PRE-JOB DAMAGE SURVEY OF FACILITY
1. Perform a thorough pre-job survey of property and all affected and adjacent areas of the building with TXDPS prior to starting the work in order to document existing damage. Damaged items identified during the survey will not be the responsibility of Contractor unless further damaged by the Contractor during execution of the project.
2. Documentation recorded during this meeting (pictures and videos) will be sent to TXDPS in order to review at the end of the project. It is the responsibility of the contractor to provide this documentation.
PART 3 - EXECUTION
3.0 EXAMINATION
1. Contractor shall check and verify all dimensions, notes, conditions and location of existing poles, cables or equipment in the installation area on site before any construction work starts. All discrepancies shall be reported to TXDPS Contact. No extra charge of compensation will be allowed on account of any difference between actual measurements and measurements or dimensions supplied by TXDPS, either verbally or in written form.
2. Examine substrates and conditions under which Work is to be performed. Do not commence work over unsatisfactory conditions detrimental to proper and timely execution of Work.
3. Do not proceed with Work until unsatisfactory conditions have been corrected.
4. Commencement of installation constitutes acceptance of conditions and cost of any corrective measures are the responsibility of the Contractor.
5. The Contractor is responsible for notifying the TXDPS Contact should there be a discovery of asbestos during the demolition process. In such cases, Work will cease until there is a resolution and permission from TXDPS Contract Monitor to commence work.
6. Ensure preparatory works are correctly done prior to main work.
END OF SUMMARY OF WORK
Building U Equipment
Replacement Issued for Proposals
Austin, Texas
June 2024
Parkhill
DEMONSTRATION AND TRAINING
017900 -1
SECTION 01 79 00 - DEMONSTRATION AND TRAINING
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes administrative and procedural requirements for instructing Owner's personnel, including the following:
1. Demonstration of operation of systems, subsystems, and equipment when indicated in specific Specification Sections.
2. Training in operation and maintenance of systems, subsystems, and equipment for the following, but not limited to:
a. Items specified in specific Specification Sections.
B. Related Requirements:
1. Other Division 01 Specification Sections apply to Work of this Section.
1.2 SUBMITTALS
A. Training Manuals: Submit manufacturer's training materials.
1. Include necessary sections of the O&M documents.
2. Include additional documents necessary to supplement the O&M documents.
3. Provide two copies of training manuals.
B. Qualification Data: For instructor.
C. Training Reports:
1. Attendance Record: For each training module, submit date, time, length of instruction time, and a list of participants.
D. Evaluations: For each participant and for each training module, submit results and documentation of performance-based test.
1.3 QUALITY ASSURANCE
A. Instructor Qualifications: A factory-authorized service representative, complying with requirements in Section 01 40 00 "Quality Requirements," experienced in operation and maintenance procedures and training.
B. Preconstruction Conference: Conduct conference at Project Site. Review methods and procedures related to demonstration and training including, but not limited to, the following:
1. Inspect and discuss locations and other facilities required for instruction.
2. Review and finalize instruction schedule and verify availability of educational materials, instructors' personnel, audiovisual equipment, and facilities needed to avoid delays.
3. Review required content of instruction.
4. For instruction that must occur outside, review weather and forecasted weather conditions and procedures to follow if conditions are unfavorable.
Replacement Issued for Proposals
Austin, Texas
June 2024
Parkhill
DEMONSTRATION AND TRAINING
017900 -2
1.4 COORDINATION
A. Coordinate instruction schedule with Owner's operations. Adjust schedule as required to minimize disrupting Owner's operations and to ensure availability of Owner's personnel.
B. Coordinate instructors, including providing notification of dates, times, length of instruction time, and course content.
C. Coordinate content of training modules with content of approved emergency, operation, and maintenance manuals. Do not submit instruction program until operation and maintenance data has been reviewed and approved by Architect.
PART 2 - PRODUCTS
2.1 INSTRUCTION PROGRAM
A. Program Structure: Develop an instruction program that includes individual training modules for each system and for equipment not part of a system, as required by individual Specification Sections.
B. Training Modules: Develop a learning objective and teaching outline for each module. Include a description of specific skills and knowledge that participant is expected to master. For each module, include instruction for the following as applicable to the system, equipment, or component:
1. Basis of System Design, Operational Requirements, and Criteria: Include the following:
a. System, subsystem, and equipment descriptions.
b. Performance and design criteria if Contractor is delegated design responsibility.
c. Operating standards.
d. Regulatory requirements.
e. Equipment function.
f. Operating characteristics.
g. Limiting conditions.
h. Performance curves.
2. Documentation: Review the following items in detail:
a. Emergency manuals.
b. Operations manuals.
c. Maintenance manuals.
d. Project Record Documents.
e. Identification systems.
f. Warranties and bonds.
g. Maintenance service agreements and similar continuing commitments.
3. Emergencies: Include the following, as applicable:
a. Instructions on meaning of warnings, trouble indications, and error messages.
b. Instructions on stopping.
c. Shutdown instructions for each type of emergency.
Replacement Issued for Proposals
Austin, Texas
June 2024
Parkhill
DEMONSTRATION AND TRAINING
017900 -3
d. Operating instructions for conditions outside of normal operating limits.
e. Sequences for electric or electronic systems.
f. Special operating instructions and procedures.
4. Operations: Include the following, as applicable:
a. Startup procedures.
b. Equipment or system break-in procedures.
c. Routine and normal operating instructions.
d. Regulation and control procedures.
e. Control sequences.
f. Safety procedures.
g. Instructions on stopping.
h. Normal shutdown instructions.
i. Operating procedures for emergencies.
j. Operating procedures for system, subsystem, or equipment failure.
k. Seasonal and weekend operating instructions.
I. Required sequences for electric or electronic systems.
m. Special operating instructions and procedures.
5. Adjustments: Include the following:
a. Alignments.
b. Checking adjustments.
c. Noise and vibration adjustments.
d. Economy and efficiency adjustments.
6. Troubleshooting: Include the following:
a. Diagnostic instructions.
b. Test and inspection procedures.
7. Maintenance: Include the following:
a. Inspection procedures.
b. Types of cleaning agents to be used and methods of cleaning.
c. List of cleaning agents and methods of cleaning detrimental to product.
d. Procedures for routine cleaning.
e. Procedures for preventive maintenance.
f. Procedures for routine maintenance.
g. Instruction on use of special tools.
8. Repairs: Include the following:
a. Diagnosis instructions.
b. Repair instructions.
c. Disassembly; component removal, repair, and replacement; and reassembly instructions.
d. Instructions for identifying parts and components.
e. Review of spare parts needed for operation and maintenance.
C. All instructional programs and training modules are to be recorded to DVD video.
Provide Owner with three DVDs labeled according to training module and recorded date.
PART 3 - EXECUTION (NOT USED)
END OF SECTION
SECTION 01 74 00 - CLEANING AND WASTE MANAGEMENT
PART 1 - GENERAL
1.1 SUMMARY
A. Provisions as established in the General Requirements of the Scope of Work.
B. Section Includes:
1. Cleaning during construction.
2. Final cleaning of project and related site work.
1.2 CLEANING DURING CONSTRUCTION
A. Control accumulation of waste materials and rubbish; dispose of off-site daily.
B. Keep site and construction areas clean on a daily basis.
C. Maintain areas free of dust and other contaminants during finishing operations.
1.3 FINAL CLEANING
A. Execute cleaning prior to inspection for Substantial Completion of the Work.
PART 2 - PRODUCTS
2.1 CLEANING MATERIALS
A. Use materials which will not create hazards to health or property, and which will not damage surfaces.
B. Use only materials and methods recommended by manufacturer of material being cleaned.
PART 3 - EXECUTION
3.1 CLEANING
A. In addition to removal of debris and cleaning specified in other sections, clean exposed-to-view surfaces.
B. Remove waste, foreign matter, and debris from access ways.
C. Maintain cleaning until Final Completion.
D. Final Cleaning: In addition to cleaning during construction, prior to Substantial Completion provide the following:
1. Remove temporary protection and labels not required to remain.
2. Remove waste, debris, and surplus materials from site daily. Clean grounds; remove stains, spills, and foreign substances from paved areas and sweep clean. Rake clean other exterior surfaces.
END OF SECTION
| page 1 |
| SOL_EXH_F.8_24R0022034A_Statement of Work |
| SOL_EXH_F.8_24R0022034A_Statement of Work |
| SOLICIEXH_F.8_24R0022034_Statement of Work |
| SOLICIEXH_F.8_24R0022034_Statement of Work |
| 01 11 00 Summary of Work |
| SOL_EXH_F.8_24R0022034A_Statement of Work |
| SOL_EXH_F.8_24R0022034A_Statement of Work |
| SOW_24R0022034 PAGE 1.6 |
| SOL_EXH_F.8_24R0022034A_Statement of Work |
| SOLICIEXH_F.8_24R0022034_Statement of Work |
| SOLICIEXH_F.8_24R0022034_Statement of Work |
| SOLICIEXH_F.8_24R0022034_Statement of Work |
| SOW_24R0022034 PAGE 67-70 |
| 1.3 QUALITY ASSURANCE |
| 1.4 COORDINATION |
| 2.1 INSTRUCTION PROGRAM |
| END OF SECTION |