Solicitation Summary
This is a Request for Proposal (RFP) for potable and wastewater treatment plant operations at Flight 93 National Memorial in Stoystown, Pennsylvania, issued by the National Park Service (NPS). The solicitation number is 140P4226R0020, with proposals due by 12:00 PM Eastern Time on September 2, 2026. This is a Women-Owned Small Business (WOSB) set-aside for commercial services under FAR Part 12, utilizing a Lowest Price Technically Acceptable evaluation methodology.
The contractor shall provide comprehensive operations and maintenance for both potable and wastewater treatment plants, including daily inspections, routine maintenance, operational testing, laboratory analysis, and monthly compliance reporting in accordance with NPDES permit PA0255009 and potable water permit PWSID 4560361. Key requirements include providing on-site personnel holding Pennsylvania Department of Environmental Protection (PADEP) Class D and Sub-class 1 wastewater operator licenses plus potable water licenses; furnishing testing chemicals and equipment; preparing monthly discharge monitoring reports; and maintaining emergency response availability 24/7 with two-hour on-site response time. The contract runs for five years comprising a 12-month base period (September 20, 2026 to September 19, 2027) and four optional 12-month periods. Proposals must include technical capability documentation demonstrating relevant experience, copies of operator licenses, a Quality Control Plan, a Safety Plan, relevant project experience (three similar projects), and sealed pricing. The Government will furnish major equipment, mechanical/electrical systems, and bulk chemicals (chlorine, AQUA MAG), while the contractor provides testing chemicals, supplies, personnel, supervision, and all other consumables. All proposals must be submitted electronically via email to Deborah_Coles@ios.doi.gov with firm-fixed pricing for each service line item.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment_1_Quote_Submission_Package_140P4226R0020.docx | DOCX document | |
| Attachment_3_-_Limitations_on_Subcontracting_Worksheet.docx | DOCX document | |
| Attachment_2_-_Wage_Determination_WD_15-5793_Rev_32_Somerset_County.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
WOMEN-OWNED SMALL
BUSINESS (WOSB)
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES
1. REQUISITION NUMBER PAGE 1 OF
2. CONTRACT NUMBER 3.AWARD/EFFECTIVE
DATE
4. ORDER NUMBER 5. SOLICITATION NUMBER 6. SOLICITATION ISSUE
DATE
7. FOR SOLICITATION
INFORMATION CALL:
a. NAME b. TELEPHONE NUMBER (No collect calls)
8. OFFER DUE DATE/
LOCAL TIME
9. ISSUED BY
13b. RATING
14. METHOD OF SOLICITATION
CODE
15. DELIVER TO 16. ADMINISTERED BY CODE
18a. PAYMENT WILL BE MADE BY CODE17a. CONTRACTOR/
OFFEROR
CODE
FACILITY
CODE
CODE
TELEPHONE NUMBER
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN
OFFER
18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK
BELOW IS CHECKED
REQUEST
FOR QUOTE
(RFQ)
INVITATION
FOR BID
(IFB)
REQUEST
FOR
PROPOSAL
(RFP)
SEE ADDENDUM
19.
ITEM NO.
20.
SCHEDULE OF SUPPLIES/SERVICES
21.
QUANTITY
22.
UNIT
23.
UNIT PRICE
24.
AMOUNT
(Use Reverse and/or Attach Additional Sheets as Necessary)
25. ACCOUNTING AND APPROPRIATION DATA 26. TOTAL AWARD AMOUNT (For Government Use Only)
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN 29. AWARD OF CONTRACT: REFERENCE
. YOUR OFFER ON SOLICITATION
(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE
SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:
30a. SIGNATURE OF OFFEROR/CONTRACTOR
30b. NAME AND TITLE OF SIGNER (Type or print) 30c. DATE SIGNED
31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER)
31b. NAME OF CONTRACTING OFFICER (Type or print) 31c. DATE SIGNED
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
STANDARD FORM 1449 (REV. 11/2021)
Prescribed by GSA - FAR (48 CFR) 53.212
10. THIS ACQUISITION IS UNRESTRICTED OR
NORTH AMERICAN
INDUSTRY CLASSIFICATION
STANDARD (NAICS):
SIZE STANDARD:
13a. THIS CONTRACT IS A
RATED ORDER UNDER
THE DEFENSE PRIORITIES
AND ALLOCATIONS
SYSTEM - DPAS (15 CFR 700)
SET ASIDE: % FOR:
11. DELIVERY FOR FREE ON
BOARD (FOB) DESTINATION
UNLESS BLOCK IS MARKED
SEE SCHEDULE
12. DISCOUNT TERMS
ARE ARE NOT ATTACHED
ARE ARE NOT ATTACHED
27a. SOLICITATION INCORPORATES BY REFERENCE (FEDERAL ACQUISITION REGULATION) FAR 52.212-1, 52.212-4.
FAR 52.212-3 AND 52.212-5 ARE ATTACHED.
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED.
8(A)
ECONOMICALLY
DISADVANTAGED
WOMEN-OWNED SMALL
BUSINESS (EDWOSB)
SERVICE-DISABLED
VETERAN-OWNED
SMALL BUSINESS
(SDVOSB)
HUBZONE SMALL
BUSINESS
SMALL BUSINESS
NOTE: OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30.
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH
AND DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND
ON ANY ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS
SPECIFIED
DATED.
OFFER
ADDENDA
ADDENDA
140P4226R0020
See Schedule See Schedule
DOI, NPS, NERO & NER SOUTH MABO
National Park Service Northeast Regional Contracting South/Philadelphia MABO 1234 Market Street, 20th Floor Philadelphia PA 19107
09/02/2026 1200 ED
0044037344
Deborah Coles 5406770325
PNC 100.00
PNC
Deborah Coles
221310
$41
07/29/2026
0011282840
ADMINISTERED BY:
DOI, NPS, NERO & NER SOUTH MABO
National Park Service
Northeast Regional Contracting
South/Philadelphia MABO
1234 Market Street, 20th Floor
Continued...
STOCK RECORD (S/R)
STANDARD FORM 1449 (REV. 11/2021) BACK
19.
ITEM NO.
20.
SCHEDULE OF SUPPLIES/SERVICES
21.
QUANTITY
22.
UNIT
23.
UNIT PRICE
24.
AMOUNT
32a. QUANTITY IN COLUMN 21 HAS BEEN
RECEIVED INSPECTED AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED:
41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT
32b. SIGNATURE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32c. DATE
41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE
42a. RECEIVED BY (Print)
42b. RECEIVED AT (Location)
42c. DATE RECEIVED (MM/DD/YYYY) 42d. TOTAL CONTAINERS
40. PAID BY
32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f. TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE
32g. EMAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE
33. SHIP NUMBER 34. VOUCHER NUMBER 35. AMOUNT VERIFIED
CORRECT FOR
PARTIAL FINAL
37. CHECK NUMBER
38. S/R ACCOUNT NUMBER 39. S/R VOUCHER NUMBER
36. PAYMENT
COMPLETE PARTIAL FINAL
ACCEPTED,
Philadelphia PA 19107 US
DELIVER TO:
NPS, Flight 93 NM
892 Skyline Rd
Stoystown PA 15563 US
Request for firm fixed price proposal for potable and wastewater treatment plant operations at Flight 93 National Memorial in
Stoystown, Pennsylvania as described in the attached Statement of Work.
Questions must be sent to the Contracting
Officer at Deborah_Coles@ios.doi.gov by 12:00PM
Eastern Time on August 24, 2026.
Proposals must be sent to the Contracting
Officer at Deborah_Coles@ios.doi.gov by 12:00PM
Eastern Time on September 2, 2026 with
"140P4226R0020 FLNI Water Operations" in the subject line.
Contractor must have an active SAM registration at the time of award. www.SAM.gov
Please contact Brad Thomas, Brad_Thomas@nps.gov, 724-610-7484 if you are interested in a site visit.
Period of Performance: 09/20/2026 to
09/19/2031
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
NSN 7540-01-152-8067
00010 Wastewater Operator
Product/Service Code: H345
Product/Service Description: INSPECTION-
PLUMBING, HEATING, AND WASTE DISPOSAL
EQUIPMENT
Delivery: 09/19/2027
Period of Performance: 09/20/2026 to
09/19/2027
00020 Potable Water Operator
Product/Service Code: H345
Product/Service Description: INSPECTION-
PLUMBING, HEATING, AND WASTE DISPOSAL
EQUIPMENT
Delivery: 09/19/2027
Period of Performance: 09/20/2026 to
09/19/2027
00030 Wastewater Operator - Option Period One
(Option Line Item)
Anticipated Exercise Date 09/20/2027
Product/Service Code: H345
Product/Service Description: INSPECTION-
PLUMBING, HEATING, AND WASTE DISPOSAL
EQUIPMENT
Period of Performance: 09/20/2027 to
09/19/2028
00040 Potable Water Operator - Option Period One
(Option Line Item)
Anticipated Exercise Date 09/20/2027
Product/Service Code: H345
Product/Service Description: INSPECTION-
PLUMBING, HEATING, AND WASTE DISPOSAL
EQUIPMENT
Period of Performance: 09/20/2027 to
09/19/2028
00050 Wastewater Operator - Option Period Two
(Option Line Item)
Anticipated Exercise Date 09/20/2028
Product/Service Code: H345
Product/Service Description: INSPECTION-
PLUMBING, HEATING, AND WASTE DISPOSAL
EQUIPMENT
Period of Performance: 09/20/2028 to
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
09/19/2029
00060 Potable Water Operator - Option Period Two
(Option Line Item)
Anticipated Exercise Date 09/20/2028
Product/Service Code: H345
Product/Service Description: INSPECTION-
PLUMBING, HEATING, AND WASTE DISPOSAL
EQUIPMENT
Period of Performance: 09/20/2028 to
09/19/2029
00070 Wastewater Operator - Option Period Three
(Option Line Item)
Anticipated Exercise Date 09/20/2029
Product/Service Code: H345
Product/Service Description: INSPECTION-
PLUMBING, HEATING, AND WASTE DISPOSAL
EQUIPMENT
Period of Performance: 09/20/2029 to
09/19/2030
00080 Potable Water Operator - Option Period Three
(Option Line Item)
Anticipated Exercise Date 09/20/2029
Product/Service Code: H345
Product/Service Description: INSPECTION-
PLUMBING, HEATING, AND WASTE DISPOSAL
EQUIPMENT
Period of Performance: 09/20/2029 to
09/19/2030
00090 Wastewater Operator - Option Period Four
(Option Line Item)
Anticipated Exercise Date 09/20/2030
Product/Service Code: H345
Product/Service Description: INSPECTION-
PLUMBING, HEATING, AND WASTE DISPOSAL
EQUIPMENT
Period of Performance: 09/20/2030 to
09/19/2031
00100 Potable Water Operator - Option Period Four
(Option Line Item)
Anticipated Exercise Date 09/20/2030
Product/Service Code: H345
Product/Service Description: INSPECTION-
PLUMBING, HEATING, AND WASTE DISPOSAL
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
EQUIPMENT
Period of Performance: 09/20/2030 to
09/19/2031
REFERENCE NO. OF DOCUMENT BEING CONTINUED
140P4226R0020
PAGE OF
SECTION A - TABLE OF CONTENTS
SECTION DESCRIPTION PAGE
PART I – The Schedule A Solicitation/Contract Form 1 B Schedule of Items 7 C Description/specifications/requirements 9 D Packaging and Marking 26 E Inspection and Acceptance 25 F Deliveries or Performance 26 G Contract Administration Data 27 H Special Contract Requirements 33
PART II – Contract Clauses I Contract Clauses 36
PART III – List of Documents, Exhibits, and Other Attachments J List of Attachments 48
PART IV – Representations and Instructions K Representations, Certifications, and Other Statements of Offerors 49 L Instructions, Conditions, and Notices to Offerors 58 M Evaluation Factors for Award 66
140P4226R0020
SECTION B - SCHEDULE OF SERVICES
19.
ITEM
NO.
20.
SCHEDULE OF SERVICES
21.
QTY
22.
UNIT OF
MEASURE
23.
UNIT
PRICE
24.
TOTAL
Base Items
00010 Base Period – Provide Wastewater Treatment Plant Operation Services
1 Each $ $
00020 Base Period – Provide Potable Water Treatment Plant Operation Services
1 Each $ $
Base Total $ Optional Item
00030 Optional Period One (1) - Provide Wastewater Treatment Plant Operation Services (Subject to the Availability of Funding)
1 Each $ $
00040 Optional Period One (1) - Provide Potable Water Treatment Plant Operation Services (Subject to the Availability of Funding)
1 Each $ $
00050 Optional Period Two (2) – Provide Wastewater Treatment Plant Operation Services (Subject to the Availability of Funding)
1 Each $ $
00060 Optional Period Two (2) - Provide Potable Water Treatment Plant Operation Services (Subject to the Availability of Funding)
1 Each $ $
00070 Optional Period Three (3) – Provide Wastewater Treatment Plant Operation Services (Subject to the Availability of Funding)
1 Each $ $
00080 Optional Period Three (3) - Provide Potable Water Treatment Plant Operation Services (Subject to the Availability of Funding)
1 Each $ $
00090 Optional Period Four (4) - Provide Wastewater Treatment Plant Operation Services (Subject to the Availability of Funding)
1 Each $ $
140P4226R0020
00100 Optional Period Four (4) - Provide Potable Water Treatment Plant Operation Services (Subject to the Availability of Funding)
1 Each $ $
Optional Item Total $ Base and Optional Item Total $
NOTE: This acquisition utilizes Revolutionary FAR Updates (RFO) FAR 12 Acquisition of Commercial Products and Commercial Services – Specifically RFO FAR 12.201-1 – Simplified Procedures.
The contract includes the FAR Clause 52.217-8 – Option to Extend Services for up to six (6) months. If the Government elects to exercise FAR 52.217-8 – Option to Extend Services after the base period, the contractor is hereby notified that the Government will require continued performance of any services within the limits and at the unit prices specified in the Schedule of Services above, unless any of the unit prices require adjustment per revisions to the prevailing labor rates provided by the Secretary of Labor. The prices under this clause are hereby considered to be evaluated at the time of award of the base contract.
140P4226R0020
SECTION C – Description/Specification/Requirements
Flight 93 National Memorial (FLNI) – Potable and Wastewater Treatment Plant Operations
C.0 NATIONAL PARK SERVICE
The National Park Service (NPS) is a bureau of the U.S. Department of the Interior (DOI) that has been entrusted with the care of our national parks since 1916. The National Park System currently has 433 units (often referred to as parks), covering more than 85 million acres in all 50 states, the District of Columbia, and US territories.
The NPS also has more than 150 related areas that are linked in importance and purpose to places managed directly by the National Park Service by preserving important segments of the nation's natural and cultural heritage. They are designated by acts of Congress or by the Secretary of the Interior (affiliated areas). The majority of related areas are not units of the National Park Service and are managed by other government agencies or non-government organizations and landowners. The National Park Service is involved in related areas by directly managing the entire or sections of a related area, or by providing technical or financial assistance.
The NPS preserves unimpaired natural and cultural resources, and values of the National Park System for the enjoyment, education, and inspiration of this and future generations. The NPS cooperates with partners to extend the benefits of natural and cultural resource conservation and outdoor recreation throughout this country and the world.
The NPS – Business Service Contracting Division (BSCD) – Contracting Operations – Northeast Region – Philadephia MABO. The NPS – BSCD-Northeast issues contracts through the Federal Acquisition Regulation’s (FAR) for supplies, services, construction, A&E for Northeast Regional Parks only.
C.1 FLIGHT 92 NATIONAL MEMORIAL (FLNI
On Tuesday morning, September 11, 2001, the U.S. came under attack when four commercial airliners were hijacked and used to strike targets on the ground. Nearly 3,000 people tragically lost their lives. Because of the actions of the 40 passengers and crew aboard one of the planes, Flight 93, the attack on the U.S. Capitol was thwarted.
The flight data recorder that was recovered from the crash site revealed that the terrorists had reprogrammed the aircraft's autopilot system for a new destination - Washington, D.C. Recovered evidence and responses to interrogations revealed that the terrorists' intended target was most likely the United States Capitol Building, where the nation's legislators were in session. Flight 93 crashed only 20 minutes flying-time from Washington, D.C. Because of the quick and determined actions of the passengers and crew, Flight 93 was the only one of the four hijacked aircraft that failed to reach the terrorists' intended target that day. The passengers and crew showed unity, courage, and defiance in the face of adversity. Today the National Park Service, volunteers, and partners work to honor their actions, and understand fully the legacy of Flight 93 and the events of September 11, 2001.
For more information, please visit FLNI’s website at: Flight 93 National Memorial (U.S. National Park Service)
C.2 BACKGROUND
The National Park Service at Flight 93 National Memorial (FLNI) has a requirement for a contractor to provide potable and wastewater treatment plant operations.
C.3 SUMMARY OF WORK
The Contractor shall provide personnel, supervision, transportation, operation, testing, training, monitoring and reporting, and other items or services (except as stated herein) necessary to perform wastewater & potable water treatment plant services to maintain a safe, clean and healthy environment for all the Memorial visitors, staff, volunteers and members of the general public. To accomplish these goals, it is essential that the properties and facilities of the Flight 93 National Memorial specified herein have qualified wastewater & potable water treatment plant services as required.
C.4 OBJECTIVES/TASKS
1. Routine operations and maintenance services, daily operations testing; submitting samples for laboratory analysis;
preparation of monthly operations reports in accordance with the National Pollutant Discharge Elimination System (NPDES) permit No. PA0255009 and the Potable water permit No. PWSID: 4560361 for NPS signatures.
https://www.nps.gov/flni/index.htm
140P4226R0020
2. Provide training and guidance to designated NPS staff limited to: recognizing and reporting abnormal plant conditions;
routine visual monitoring, reading of instrumentation, and assisting with sample collection under the certified operator’s direction; emergency shutdown and life-safety procedures; interim protective actions (e.g., restroom closure, area access restriction); and assembly of a comprehensive Safety Data Sheet (SDS) binder for all contractor- and NPS-provided chemicals. NPS staff shall not make process control decisions as defined in 25 Pa. Code Chapter 302, and the Contractor’s certified operator shall remain the operator in responsible charge, retaining responsibility for all process control decisions, for permit compliance, and for the validity of compliance monitoring data, including where NPS staff assist with monitoring or sampling.
3. The Contractor shall be on-site each service day for the time necessary to complete all required routine operations, maintenance, and daily testing, and the Contractor’s certified operator shall at all other times serve as the available operator (on-site or reachable to make process control decisions in a timely manner) as defined in 25 Pa. Code §
302.101. Emergency response is governed by Section C.6, and coverage during operator absences by Section C.10 and 7.2(d). The Government is not responsible for plant operation or process control decisions at any time during the term of this contract.
4. The contractor shall prepare for the NPS signature and submission, the monthly reports on facility operation in accordance with the NPDES permit PA0255009 and PWSID: 4560361 permit no later than the 5th of each month.
5. Daily inspections, operational maintenance and monitoring to comply with the provisions of the NPDES permit PA025500 and permit PWSID: 4560361, PADEP requirements, and the manufacturer’s recommendations found in the equipment operations and maintenance manuals.
6. Prepare the Discharge Monitoring Report for NPS signature and submission as stated in the respective NPDES permit No. PA0255009 and prepare the monthly water samples and submission as stated in the respective permit PWSID:
4560361. The Contractor shall notify the COR by telephone immediately, and in writing (email) within two (2) hours, upon receiving or determining any noncompliant effluent test result or any condition that is causing or may cause a permit violation. For any total coliform result, the Contractor shall so notify both the COR and the FLNI Work Maintenance Supervisor on the same immediate basis. “Immediately” means without delay upon receipt or determination of the result and shall not be contingent on prior COR approval. Upon any such result or condition, the Contractor’s certified operator shall promptly inspect the affected facilities and processes, determine the probable cause, take any corrective operational measures within the normal scope of this contract to restore compliance, and report findings to the COR within twenty-four (24) hours, stating whether the corrective action is (a) within normal contract operations; (b) outside the contract scope but within the Contractor’s capability, with a proposed approach and rough order-of-magnitude cost; or (c) beyond the Contractor’s scope and capability such that a separate corrective project is warranted.
The Contractor shall also recommend any interim protective measures the Government may take (e.g., restroom closure, area access restriction). The Contractor shall copy or notify the COR on all communications with regulatory agencies;
nothing in this paragraph relieves the Contractor or its certified operator of any independent mandatory reporting obligation under the permit or applicable law, and the Contractor shall not delay any such mandatory report pending COR notification.
7. Provide necessary laboratory analysis monthly to comply with NPDES testing requirements and perform and provide guidance in the performance by NPS staff of daily operating test as required as well as compliance with PA DEP Potable water testing requirements.
8. Provide routine operations and maintenance services, daily operations testing, submitting samples for laboratory analysis and preparation of monthly operations reports to NPS Work Maintenance Supervisor. One maintenance staff member will be assigned to a communicate needs of the contracting operator and two (2) NPS maintenance staff members will be assigned to a shadow detail throughout the term of the contract receive instruction and guidance on the above tasks.
9. The service requirements and performance objectives relate directly to the essential items as identified in the SOW, the National Pollutant Discharge Elimination System (NPDES) permit No. PA0255009 and the PWSID: 4560361 issued by the Pennsylvania Department of Environmental Protection (PADEP), and the Contractor’s Quality Control Plan (QCP) providing for the highest level of service delivery performance critical to operation success. The contractor shall use the SOW, NPDES permit No. PA0255009, DEP permit No. PWSID: 4560361, as well as the approved QCP to accomplish the functions/tasks generated for this effort.
140P4226R0020
C.5 OTHER INCIDENTAL WORK
Furnishing of Supplies, Material and Chemicals by the Contractor, and Accessibility to Government- Furnished Equipment.
1. The NPS shall furnish all necessary supplies and consumable materials necessary for the operation of the Wastewater and Potable Water plants, including chlorine and de-chlorination tablets and AQUA MAG Sequestrant agent. The Contractor shall provide a minimum of 45 days regarding quantities and types of these supplies needed.
2. The Contractor shall furnish all the necessary chemicals to conduct the required testing at the wastewater treatment plant (to include, but not limited to: Buffer Reagent for PH, 4.00, 7.00, and 10.0. Total Chlorine Reagent, Total Alkalinity Reagent) and to conduct the required testing for Potable Water (to include but not limited to: Chlorimator- or a daily Chlorine test kit.
Chlorine levels monitored and held to a 1.0-1.75. Contractor shall always keep to the Potable Water standard and always stay within compliance of a .04-4.0.
3. Before commencing work, the contractor shall submit to the COR for approval, a list providing the name of the manufacturer and brand name of all chemicals to be used in accomplishment of the work and an SDS for each.
4. The Contractor shall provide testing equipment necessary for the performance of the contract (to include, but not limited to:
PH Meter, DO Meter, Alkalinity test it, and Chlorine test kit.
5. The Government is responsible for all the mechanical and electrical equipment required to operate the Wastewater and Potable water treatment plant.
6. Except for those items specifically stated as Government–furnished property, the contractor shall furnish any other items and service necessary to provide and accomplish the required performance of this contract.
7. The Government will provide a designated area for the storage of the contractors’ supplies, materials and chemicals. The contractor shall be responsible for the maintaining of this area, to be kept clean and in an organized manner.
8. The contractor shall identify and make recommendations to the COR of all facilities or equipment requiring repairs that are the responsibility of the Government so that a work order may be placed to complete the work in timely manner so as not to negatively impact facility effectiveness.
9. The Contractor shall actively participate in NPS energy conservation activities. The contractor shall comply with and enforce all local NPS policies and directives regarding energy management. Contract employees shall be instructed in utilities conservation practices and shall be required to operate under conditions that prevent waste or misuse of Government-owned utilities.
C.6 PLACE OF PERFORMANCE AND HOURS OF OPERATION
Flight 93 National Memorial 892 Skyline Road Stoystown, PA 15562
Hours of Operation: Services shall be provided daily from Sunday through Saturday, unless specifically stated otherwise by the CO.
Site access is available 24 hours a day / 7 days a week. The contractor shall remain on-site for a sufficient amount of time to meet the requirements of routine operations, notify the NPS staff regarding maintenance, and daily testing services.
Service Call / Emergency Response Time: Contractor shall be available to respond to emergency situations 24 hours per day, 7 days per week. Response time to an emergency will require the contractor to be on-site within two (2) hours of notification.
Period of Performance: The contract will be for a total of five (5) years consisting of a 12-month base period and four (4) 12-month option periods. The option periods are subject to the availability of funds and will be exercised at the discretion of the National Park Service. The estimated period of performance dates are:
140P4226R0020
Base Period: September 20, 2026 – September 19, 2027 Option Period One: September 20, 2027 – September 19, 2028 Option Period Two: September 20, 2028 – September 19, 2029 Option Period Three: September 20, 2029 – September 19, 2030 Option Period four: September 20, 2030 – September 19, 2031
C.7 SCHEDULING AND COORDINATION
The COR will be responsible for acting on behalf of the Contracting Officer (CO) on all matters of work within the scope of the contract. Approval of all work beyond the scope of the contract is reserved for the CO. The contractor is responsible for notifying the COR in writing all work that is beyond the scope of the contract.
C.8 SPECIFIC LOCATION REQUIREMENTS
1. This procurement consists of locations within the boundaries of the Flight 93 National Memorial regarding the operation of a Potable water plant. The FLNI Potable Water Plant System consists of a 2 gallon a minute producing well which pumps into a small building, (Well House/Potable Water Building) The raw water starts to be converted to potable water in this building by first injecting AQUA MAG into the raw water line which flows through a static mixer and about 10 ft of waterline to a chlorine injection pump. Also, in this building an AQUA Scout Panel controls and monitors the well and level of a holding tank at a higher location. When the well pump turns on it pumps through the Well house /Potable water building to the higher elevation into a 5,000 gallon underground holding tank. The Holding tank services the detention time needed for chlorine contact and gravity feeds the FLNI Learning Center and Visitor center. The water comes into the Learning Center in a 2-inch line at 25-31 psi and then is boosted by a pump to a pressure of 45-50 lbs. After the booster pump the water line is plumbed into a dirt media filter that back washes daily. All finished and water samples are taken beyond this point.
2. This procurement consists of locations within the boundaries of the Flight 93 National Memorial regarding the operation of a Class D, Sub-class 1 wastewater treatment plant; including a 5000 gallon per day Extended Aeration Treatment Plant (package plant), that is comprised of four Jet 1250 1500 Series Bat Media Plants. The associated plant equipment includes a 5,000 gal.
septic tank, three 5,000 gal. equalization tanks, dosing tank and pumps, as well as 2" effluent pressure line which extends to the point of discharge.
3. The government is responsible for the environmentally acceptable removal and disposal of the sludge generated through the sewage treatment process.
C.9 GENERAL CONTRACTOR RESPONSIBLITIES
Monitoring and Analytical Services The contractor shall perform, and provide instruction and guidance to NPS staff for, specific monitoring and analytical services, and be responsible for the completion of the Discharge Monitoring Report, as well as any other reports required by permit with the Pennsylvania Department of Environmental Protection. Specific monitoring and analytical requirements are as follows:
Effluent Limitations Monitoring Requirements Mass Units (lbs/day} 11'
Concentrations (mg/L) Minimum {2) Measurement Frequency
Required Sample Type
Parameter Average Monthly Minimum Average Monthly
Daily Maximum
Instant.
Maximum
Flow (MGD) Report XXX XXX XXX XXX XXX 2/month Measured pH (S.U.) XXX XXX 6.0 XXX XXX 9.0 1/day Grab
140P4226R0020
Dissolved Oxygen
XXX XXX 4.0 XXX XXX XXX 1/day Grab
Total Residual Chlorine
XXX XXX XXX 0.5 XXX 1.6 1/day Grab
CBOD5 XXX XXX XXX 25 XXX 50 2/month Grab
Total Suspended Solids
XXX XXX XXX 30 XXX 60 2/month Grab
Fecal Coliform (CFU/100 ml) May 1- Sep 30
XXX XXX XXX 200
Geo Mean
XXX 1,000 2/month Grab
Fecal Coliform (CFU/100 ml) Oct 1 -Apr 30
XXX XXX XXX 2,000
Geo Mean
XXX 10,000 2/month Grab
Total Nitrogen XXX XXX XXX XXX Report XXX 1/year Grab
Effluent Limitations Monitoring Requirements
Parameter ' Mass Units (lbs/day) Concentrations (mg/L) Minimum Measurem ent Frequency
Required Sample Type
Average Monthly
Minimum Average Monthly
Daily Maximum
Instant Maximum
Ammonia- Nitrogen May 1 -Oct
XXX XXX XXX 25 XXX 50 2/month Grab
Ammonia- Nitrogen Nov 1 -Apr
XXX XXX XXX Report XXX Report 2/month Grab
Total Phosphorus
XXX XXX XXX XXX Report XXX 1/year Grab
Total Aluminum
XXX XXX XXX XXX Report XXX 1/year Grab
Total Iron XXX XXX XXX XXX Report XXX 1/year Grab Total Manganese
XXX XXX XXX XXX Report XXX 1/year Grab
C.10 CONTRACTOR/EMPLOYEE QUALIFICATIONS
1. General: The contractor shall manage the total work effort associated with the services required to assure fully adequate and timely completion of these services. Such management includes, but is not limited to, planning, scheduling, report preparation, establishing and maintaining records and quality control. The contractor shall provide staff with the necessary management expertise to assure the performance of the required work; and trained and experienced personnel who meet established standards to effectively perform the services required and who exhibit capability to perform with minimum supervision. The contractor shall submit copies of the employee’s licenses proposed to operate the plant in accordance with the Pennsylvania Department of Environmental Protection. Removal or dismissal of employees, who are not fully able to perform the normally assigned duties or violate any security or health requirement, does not relieve the contractor
140P4226R0020 of the requirement to provide sufficient personnel to adequately perform services required. The contractor shall provide contingencies for employees who are absent during their regular work hours; and shall have in place a suitable replacement for the absentee employee within two hours of initial notification by the COR.
2. Personnel Requirements:
a. On-site Wastewater and Potable Water Treatment Plant Operator(s). The contractor’s onsite personnel must have a minimum of a Class D License and a Sub-class 1 (Activated Sludge) License assigned by the Pennsylvania Department of Environmental Protection (PADEP) and a Potable Water License issued in PA assigned by the Pennsylvania Department of Environmental Protection (PADEP).
b. The contractor shall provide copies of employee’s licenses proposed to operate the plant. These persons must be approved by the state prior to any service performance under this contract. If the Contractor intends to use an operator certified in another state, Pennsylvania certification through reciprocity (25 Pa. Code § 302.304) shall be obtained and in effect before the operational start date; the Contractor is responsible for allowing sufficient lead time for State Board processing, which occurs on a scheduled board-meeting cycle.
c. The contractor’s Project Manager shall have an intimate knowledge of the wastewater and potable water treatment duties and shall be able to both properly train and direct personnel. At the time of hiring, all personnel for these tasks shall comply with all rules, regulations and laws, both federal and state (Commonwealth of Pennsylvania) applicable.
d. The Contractor shall designate in writing and provide licenses for On-site Operator(s) to include any alternates or replacement, with the authorization to act on behalf of the Contractor to be available at all times for contract work is in progress.
e. The Project Manager shall be the central point of contact with the Government for performance of all work required:
Shall stay apprised of facilities conditions to ensure conformity with the SOW, the approved Contractors Quality Control Plan, permit PWSID: 4560361, NPDES permit No. PA0255009: and, shall be fully capable of supervising all other contractor employees and be responsible for ensuring the completion of all work assignments and required services as specified and/or directed under the terms of the contract.
f. In addition, the contractor’s project manager shall conduct overall management coordination; shall have the authority to act for the Contractor on a day to day basis to accept and sign notices regarding deficiencies, inspection reports and other routine correspondence from the Contracting Officer or his representative; and, shall be available to meet with the COR and/or other Government personnel to discuss problem areas. The Project Manager’s authority under this paragraph is limited to contract administration and correspondence and does not extend to process control decisions or to certifying regulatory submissions, which remain the responsibility of the certified operator and/or the permittee’s authorized signatory under 40 CFR 122.22. The Contractor’s representative shall be available to discuss contract matters with the COR, during the hours of 7:00 a.m. to 4:30 p.m., Monday through Friday. This can be accomplished in person, or by telephone, depending on the circumstances.
g. The Contractor shall comply with all applicable federal, state, local and municipal laws, regulations and requirements;
all industry standards/references; and all Government and NPS Regulations. The contractor shall instruct and guide its employees regarding any directives provided by the NPS.
h. The Contractor shall utilize safe products and equipment and qualified personnel to ensure the health and safety of all are following Environmental Protection Agency (EPA) and Occupational Safety Hazard Administration (OSHA) regulations. The Contractor shall obtain and submit all necessary licenses and permits required for the execution of the services; and shall maintain such licensing through the term of the contract.
i. Conduct of Personnel: The contractor shall require their employees to comply with the instructions pertaining to conduct, safety and health regulations forming a part of this contract. Contractor personnel shall not smoke or consume food or drink while performing work on this contract. During breaks, eating or smoking is permitted in designated areas only. Each contractor employee is expected to adhere to standards of conduct that reflect credit on themselves, their employer, the NPS, and the Federal Government. The Government reserves the right to direct the contractor to remove an employee from the work site for failure to comply with the standards of conduct. To maintain continuity of services, the contractor shall initiate immediate action to replace such an employee, at no additional cost to the Government.
140P4226R0020
j. The Contractor shall provide adequately trained and instructed employees and recurring training for all contractor personnel in the areas of safety, security, environmental, health, and in fire prevention in accordance with established Federal, State, and Local requirements, to include applicable NPS regulations (available upon request). The Contractor shall ensure that all employees have been properly trained, certified, and licensed to perform wastewater and potable water treatment operations required by this SOW. The Contractor shall maintain records of all training, qualifications and certifications and ensure they are available for Government review upon request.
k. The contractor or qualified representative on site must be able to read, write, speak, and understand the English language. They must be able to fulfill, completely and clearly, the reporting requirements of the contract.
C.11 SAFETY
1. The Contractor shall be responsible for the safe conduct of all operations, shall adhere to applicable OSHA standards (29 CFR 1910.266), and be subject to inspection by NPS Safety Officer.
2. During the execution of this contract, the Contractor must conform to the rules and regulations, as amended and as set forth by:
• 29 CFR 1910 – OSHA General Industry Regulations & Standards.
• National Park Service Occupational Safety and Health Program – Reference Manual 50B - Reference Manual 50B: NPS
Occupational Safety and Health Program
• Most Recent Superintendents Compendiums as amended:
o FLNI- Superintendent's Compendium - Flight 93 National Memorial (U.S. National Park Service)
• All Contractor or employee conduct is subject to park rules and regulations concerning: littering, wildlife harassment, collecting, resource damage and other topics as specified for the NPS in the Code of Federal Regulations title 36 (eCFR :: 36 CFR Part 2 -- Resource Protection, Public Use and Recreation).
• All operations under this contract shall be conducted in accordance with ANSI Z133.1-2006 Tree Care Safety Standards, and all federal OSHA, state and local safety requirements. Where OSHA regulations and ANSI standards conflict, OSHA regulations will take precedence.
• Work area shall always be maintained in a clean and safe condition.
• All personnel providing service on-site shall have pictured identification and uniform displaying the name of the company (if appliable).
• All on-site vehicles will also be marked with the company name (if applicable).
• Smoking of any kind will not be permitted on premises. The COR/POC may authorize the use of a designated smoking if requested.
• Contract employees shall not possess, distribute, consume, use or cause to be used any controlled substance or alcohol on the job site on Government property. Any employee using a controlled substance prescribed by a physician shall get written permission from the Contracting Officer to continue performance of assigned duties for this contract. Any contractor or contractor employee found to be in violation of this section will be permanently prohibited from the NPS property. Actions taken under this section shall not relieve the contractor of the requirement to provide sufficient personnel to perform adequate and timely service as required in this contract.
3. Contractor and operators shall follow all OSHA regulations which apply to the work activities. OSHA Regulations for tree removal operations can be found at http://www.osha.gov/pls/oshaweb/owadisp.show_document?p_table=STANDARDS&p_id =9862
4. The contractor shall maintain the ability to contact 911 or FLNI within 15 minutes in case of an emergency.
5. The Contractor shall ensure that any Contractor employee shall be in good health and free of any communicable disease prior to commencing work at this facility. The Contractor shall maintain and follow an exposure control plan for bloodborne pathogens in accordance with OSHA standard 29 CFR 1910.1030. Any necessary medical certificates, exams and treatments are at the expense of the Contractor.
C.12 PERSONAL PROTECTIVE EQUIPMENT (PPE)
https://www.nps.gov/subjects/policy/upload/RM-50B_Contents.pdf?msclkid=621da23cc59111ec9bbf5daecf70f928 https://www.nps.gov/subjects/policy/upload/RM-50B_Contents.pdf?msclkid=621da23cc59111ec9bbf5daecf70f928 https://www.nps.gov/flni/learn/management/superintendent-s-compendium.htm https://www.ecfr.gov/current/title-36/chapter-I/part-2 https://www.ecfr.gov/current/title-36/chapter-I/part-2 http://www.osha.gov/pls/oshaweb/owadisp.show_document?p_table=STANDARDS&p_id
140P4226R0020
1. The Contractor shall furnish personal protective equipment (PPE) to crew members respective of the type of work being completed.
2. The contractor shall train workers in the safe operation and use of equipment that they will be using to accomplish the work under this contract. Occupation Safety & Health Administration (OSHA) standards PPE shall be followed; information can be found at OSHA PPE Standards.
3. PPE, including personal protective equipment for eyes, face, head, and extremities shall be provided, used, and maintained in a sanitary and reliable condition wherever it is necessary by reason of hazards or processes encountered in a manner capable of causing injury or impairment in the function of any part of the body.
4. Defective or damaged PPE shall not be used and shall be either repaired or replaced.
C.13 SAFETY PLAN
The Contractor shall provide a copy of their safety plan at the pre-work meeting. The Safety Plan shall be available to all employees and subcontractors working on the contract and subsequent task orders. The Safety Plan should cover at a minimum:
1. Name or responsible party to ensure program compliance.
2. Safety briefings covering the area working in, equipment being used, and any special considerations for the work under the contract.
3. Personal Protective Equipment required for the work under the contract.
4. Appropriate OSHA requirements for the type of work under the contract.
5. Weather considerations for the time of year of the contract.
6. Communication issues and locations of the nearest medical facilities to the job site.
7. Emergency numbers to contact if an accident happens.
8. Outline of the methods proposed to ensure property protection and safety of the public, National Park Service personnel, and
Contractor’s employees.
C.14 ACCIDENT REPORTING
1. Accident Reporting: Reportable Accidents: A reportable accident is defined as death, occupational disease, traumatic injury to employees or the public, property damage by accident in excess of $100, and fires. Within 7 days of a reportable accident, send a report of the accident to the Contracting Officer.
2. All Other Accidents: The Contractor shall report all other accidents to the Contracting Officer as soon as possible and assist the Contracting Officer and other officials as required in the investigation of the accident.
3. The COR will provide the numbers for the rescue services to the contractor upon award.
C.15 FIRE PREVENTION AND PROTECTION
• Any accidental fire starts shall be reported immediately to COR and/or FLNI Fire Management Fire Management. Should the fire exceed the size of a campfire and threaten workers safety, the contractor should depart the area and call 911 or FLNI Fire Management Fire Management immediately.
• Hazard Control: Take all necessary precautions to prevent fire during construction. Keep flammable substances or materials at a safe distance from use of volatile or noxious substances.
• Smoking is prohibited in the work areas in sites designated for the contractor’s use. Designate a space away from the work area be used for smoking. Cigarette butts must be disposed of properly.
C.16 SECURITY
1. The contractor’s employees shall have personal identification on their person at all times while working at this project.
Employees working after normal working hours must check in with the on-duty NPS Law Enforcement Officer.
2. Any contractor-owned vehicle(s) used must meet established Pennsylvania Department of Transportation and NPS regulations (e.g. safety, insurance, etc.). All vehicles will be identified with the contractor’s logo to facilitate easy
140P4226R0020 identification.
3. The contractor is responsible for safeguarding all Government property that they come in contact with during the performance of this contract. The contractor shall also be expressly responsible for safeguarding their property. At the close of each workday, facilities, equipment and supplies shall be secured.
4. The contractor shall be responsible for restoring any damaged property or equipment caused by the contractor. The restoration shall be to its original condition at no additional charge to the Government.
5. The Contractor, or any representative, and all contractor employees entering the Government reservation, shall abide by all security regulations of this installation which may be in effect during the contract period; and shall be subject to such checks as may be deemed necessary to insure that no violations occur. All contractor personnel shall follow any instructions given by the COR, and NPS Law Enforcement personnel in case of fire, hurricane or any other emergencies.
6. All Contractor personnel shall wear attire appropriate for the specific task. Clothing not to be worn tank tops, shorts, sandals, or other inappropriate clothing as determined by the Contracting Officer’s Technical Representative (COR). The contractor shall ensure that each employee or representative of the Contractor shall present a clean and professional appearance.
C.17 DRONES/UNMANNED AERIAL VEHICLE (UAV) USAGE
The use of drones and/or UAVs are not authorized at any NPS location during performance of this contract.
C.18 PROHIBITION OF WEAPONS/FIREARMS
18 USC 930 is Federal law that supersedes Section 512 of Public Law 111-24 and prohibits the possession of a firearm or other dangerous weapon in a Federal facility. Federal facilities are buildings or parts thereof owned or leased by the Federal Government, where Federal employees are regularly present for the purpose of performing official duties. No weapon or firearms are authorized within FLNI at any time.
C.19 GENERAL COMMUNICATION REQUIREMENTS
• Contractor shall furnish a serviceable cellular telephone, radio, or other NPS-approved device while on- site to communicate with the National Park Service and to provide for the safety of the contract employees.
• If the Contractor’s employees do not speak English, the Contractor’s job site supervisor shall be fluent and conversant in both English and the language of their non-English speaking employees.
• The Contractor shall contact the COR/POC with project progress notifications prior to completion. The time frame for these progress notifications shall be coordinated in writing between COR/POC and Contractor, and maybe either daily, weekly, etc.
As the Contractor near the completion of the specified work, a site visit will be scheduled with the COR/POC to determine if the work has been successfully completed.
C.20 PROJECT MEETINGS
Contractor Conference: At least 10 days before contract start date, the Contractor shall meet in conference with the Contracting Officer and COR to discuss and develop mutual understanding relative to scheduling and administration of work performed under this contract.
• Correspondence procedures
• Designation of responsible personnel
• Labor standards provisions
• Changes
• Payments to Contractor
• Subcontractors
• National Park Service regulations
• Accident prevention program (including name of responsible Supervisor)
• Accident reporting
• Documents required under the contract
140P4226R0020
• Park rules and regulations
• Park Access
• Working hours and days
• Safety program (compliance with the "Accident Prevention" clause of the General Provisions)
• Tentative work schedule.
C.21 RESOURCE DAMAGE
All conduct outside of the specified work is subject to park rules and regulations concerning littering, wildlife harassment, collecting, resource damage and other topics as specified for the NPS in the Code of Federal Regulations title 36, which can be found at http://www.gpoaccess.gov/ecfr/
C.22 IDENTIFICATION OF CONTRACTOR EMPLOYEES
All contract personnel attending meetings, answering Government telephones, and working in other situations where their contractor status is not obvious to third parties are required to identify themselves as such to avoid creating an impression in the minds of members of the public that they are Government officials. They must also ensure that all documents or reports produced by contractors are suitably marked as contractor products or that contractor participation is appropriately disclosed. Contractor personnel not required to obtain and wear badges in the performance of this service.
In accordance with AP&P 1443.37-1 the following requirements will be applicable to any and all on-site contractor personnel:
a) Contractor personnel should not in any way represent themselves as government employees. Contractor personnel shall wear badges clearly identifying them as contractors when working outside of government office space. Badging should be visible at all times. In addition, contractor personnel shall dress in clothing appropriate to the office/environment in which they are working.
b) Government office space occupied by contractor personnel shall be clearly labeled with the individual’s name and/or company affiliation.
c) Contractor personnel shall be clearly identified as “contractors” in printed material such as telephone directories, etc. They shall be listed separately on organization charts or any other document that shows direct lines of supervision.
d) Contractors shall provide proper identification when making phone calls or speaking to others during performance of their scope of services. This means they shall indicate to the other party that they are a contractor, rather than a government employee.
e) Contractor personnel shall complete all necessary computer and security training/documentation before receiving access to the NPS computer network.
f) Contractor personnel shall not receive "all-employee" e-mail or other communications intended for NPS employees, unless it relates directly to the work the contractor is doing for the NPS or involves health or safety issues, for example security alerts or severe weather conditions. They shall not have access to internal NPS web pages, unless it relates directly to the work the contract employee is doing for the NPS.
g) Contractor personnel may use NPS e-mail systems when it is required to perform the work the contractor is doing for the NPS. The e-mail addresses of the contractor must include a label that identifies their contractor status (e.g. John Doe contractor would have an e-mail address john_doe@contractor.nps.gov). In addition, contractor personnel shall indicate in their e-mail signature block that they are a contractor and the contractor for whom they work. Doing so clearly identifies this individual each time they send an e-mail message using the NPS system, and it identifies their status as a contractor employee in the e-mail directory.
h) Unless stipulated in the contract, contractor personnel shall not drive government vehicles.
i) Contractor personnel are not authorized to purchase property and supplies with government funds.
j) Generally, all Government-furnished property shall be set forth in the contract or agreement; however, when it is not, use of additional property must be…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .